Appendix Item Addendum

Similar documents
Marina Bay Sands Guidelines for Electrical and Wiring Service

ibusiness Banking Application Form Welcome to ibusiness Banking Need help completing this form? Adding an Additional Company to an existing Group

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw

FOR PROPOSED TOWNSHIPS ESTER PARK X36, X 37 IRENE EXTENSION 193

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

WELLINGTON, NEW ZEALAND. PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998

Construction and Connection of Street Light Assets

Connecting your business diesel generation

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Net +Plus Connection Code

CHAPTER 2 HOW TO APPLY FOR ELECTRICITY

Terms of Reference (ToR) Trade & Traceability Standing Committee (T&T SC)

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

MAIN ELECTRICAL SYSTEM. Co-X/FMD/SOP05

AGREEMENT. (Revision 2, including the amendments entered into force on 16 October 1995) Addendum 102: Regulation No. 103

33kV Connection up to 90MVA

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

Assisted School Travel Program. Eligible Service Provider Request for Increased Run Capacity

WELLINGTON, NEW ZEALAND. PURSUANT to section 152 of the Land Transport Act Land Transport Rule: Vehicle Standards Compliance 2002

Noble County Rural Electric Membership Corporation

NPS/001/017 Technical Specification for Low Voltage and High Voltage Current Limiting Fuse Links

2019 Regulations. A: General i Where specified in the Supplementary, Technical and/or Championship Regulations, the following shall apply:

A General i Where specified in the Supplementary, Technical and/or Championship Regulations, the following shall apply:

Umatilla Electric Cooperative Net Metering Rules

Note: it is a criminal offence to give false information in this application.

SECTION 1 SCOPE, SPECIFIC TECHNICAL REQUIREMENT AND QUANTITIES

MANAGING NEW CONNECTIONS FOR YOUR BUSINESS

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Wholesale Developer Services Charges

Application for release of capital subsidy on installation of Grid Connected Solar Power Plant

Fuel Oil Conversions. Association of Energy Engineers (AEE) September 20, 2011

56-SDMS-07 REV. 01 SPECIFICATIONS FOR

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

Application for Net Export Rebate

ANNEX MOTOR VEHICLES AND MOTOR VEHICLES' PARTS. Article 1. General Provisions

ST. VINCENT AND THE GRENADINES

Ministry of New and Renewable Energy (Jawaharlal Nehru National Solar Mission) Form B for Project Proposals for

Large Embedded Generation User Guide A

Land Transport Rule: Vehicle Standards Compliance 2002 Rule 35001/1 Rule requirements...2

Risk Management of Rail Vehicle Axle Bearings

CITY OF HAMILTON BY-LAW NO

MINIBUS SAFETY POLICY STANDARD & PROCEDURES

Municipality Generator Interconnection Application Single Meter Application Part I

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

Proforma undertaking letter from remaining shareholders of acquiree company under Practice Note 2.9.6

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Jemena Electricity Networks (Vic) Ltd

Transposition of GTR15 (WLTP) into EU Legislation and UN Regulations

Acceptance of Trams and Light Rail or Metro Vehicles for Shared Running on Railtrack Controlled Infrastructure

ANNEX 3. RESOLUTION MEPC.278(70) (Adopted on 28 October 2016)

Schedule No.: 13. Diesel Engine Driven Monoset Pumps for Agricultural Purposes

IMO fuel oil consumption data collection system

NIT No.:-10/WEX/MCR/HYD. PRESS/2-303/ /Dt

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

E/ECE/324/Rev.2/Add.102/Rev.1 E/ECE/TRANS/505/Rev.2/Add.102/Rev.1

To complete the process for a net metering interconnection, please follow the steps below:

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

RESOLUTION MEPC.278(70) (Adopted on 28 October 2016) AMENDMENTS TO THE ANNEX OF THE PROTOCOL OF 1997 TO AMEND THE INTERNATIONAL CONVENTION FOR THE

Toyota Fleet. Policies & Procedures. Toyota Executive Delivery Program. Toyota Division. Fleet Sales

/ I S S : / S T S I

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Abu Dhabi Department of Transport Application Form Non Objection Certificate (NOC)

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM

SECONDARY FUEL TESTING ARRANGEMENTS

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS. International Competitive Bidding (ICB)

SCHEDULE NO. ACG33 NET METERING SERVICE

CHAPTER 4 PROTECTION REQUIREMENTS

COUNCIL OF THE EUROPEAN UNION. Brussels, 11 December /3/06 REV 3 ADD 1. Interinstitutional File: 2003/ 0153(COD) ENT 84 CODEC 561

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW)

IRISH COAST GUARD. ADMINISTRATION OF IRCG VEHICLES Procedure No. VS&T04 IRCG Division: VS&T

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members

AGREEMENT. done at Vienna on 13 November Addendum 1: Rule No. 1. Revision 1

COMMISSION REGULATION (EU) / of XXX

Service & Installation Rules

Economic and Social Council

WP2 - CFD Private Network Meter Commissioning, Proving and Calibration Tests

UWA Electrical Safety Procedure

Request for Quotation (RFQ) for the provision of electrical construction services to the CSIR CSIR RFQ:

REFERENCE CP_TSSPEC_138 0 DATE: JUNE 2006 PAGE: 1 OF 17 TITLE SPECIFICATION FOR POLE- MOUNTED AUTO-RECLOSERS TABLE OF CONTENTS

CITY AND COUNTY OF SAN FRANCISCO. SPECIFICATION FOR Copier Lease Agreement Last revision 03/03/2016

Technical Specification for 12kV and 24kV Powder Filled Current Limiting Fuse Links for Use in Switchgear (In Air)

QUOTATION REQUEST (QR) Quotation Request #: SI OA BILL OF QUANTITIES & PRICING

WELLINGTON, NEW ZEALAND

12042/16 MGT/NC/ra DGE 2

WHO Region: WPRO / New Zealand Speed Legislation Submitted to GSRRS 2008 WELLINGTON, NEW ZEALAND

TABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS...

RSPO Membership Rules

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Towing Administration Introduction Towing Operations Weak Links Aerotow Pilot (ATP) Certification

شركة كهرباء محافظة القدس المساهمة المحدودة

SAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT AGRICULTURAL PUMP ENGINE COMPONENT

Transcription:

Addendum to ESAH Version 3 Supply Application Appendix Item Addendum 1 Electrical System Item 1.4.5 Short Circuit Ratings Addendum for type of short circuit rating for system voltage of 275kV. 2 Types of Supply Item 1.5.1 Supply Application Based on Load Addendum for type of supply is to elaborate more on type of connection. 3 Electricity Supply Application For Load Up To 100 kva Item 2.2 What The Applicant Should Do 4 5 Electricity Supply Application For Load Up To 100 kva Item 2.2 - What The Electrical Contractor Should Do Electricity Supply Application For Load Exceeding 100 kva Item 3.3 - Applicant Parts Part B - TNB Application Process (Technical & Financial Approval) Addendum is to suit the new individual supply application process. 6 Electricity Supply Application For Load Exceeding 100 kva Item 3.4 - What The Applicant Should Do

Appendix 1 1.4.5 Short Circuit Ratings All equipment proposed to be installed and connected to TNB supply must comply with the following short circuit ratings: Systems Short Circuit Rating i. 500kV 50 ka, 1s ii. 275kV 40 ka, 3s for bulk station (50kA, 1s for Power Substation and 275kV within 500kV substation) iii. 132kV 31.5 ka, 3s (40kA, 3s for substation adjacent to Power Station, or within 500/275kV substation) iv. 33kV 25 ka, 3s v. 22kV 20 ka, 3s vi. 11kV 20 ka, 3s vii. 6.6kV 20 ka, 3s viii. 400/230 V 31.5 ka, 3s

Appendix 2 1.5 Types of Supply 1.5.1 Supply Application Based on Load All new applications and upgrade of supply requirement can be classified into two (2) types of supply applications. 1) Supply Application For Load Up To 100 KVA Supply from existing supply mains or Establishment of new supply mains or Establishment of new substation/substations Submission of applications to TNB by Electrical Contractor registered with the Energy Commission 2) Supply Application For Load Exceeding 100 KVA Supply from existing supply mains or Establishment of new supply mains or Establishment of new substation/substations Submission of applications to TNB by Electrical Consultant Engineer registered with the Board of Engineers Malaysia Note: Establishment of new supply system may require the construction of a new substation/substations and its related ancillaries.

Appendix 3 2.2 What The Applicant Should Do The applicant should take the following steps to apply for supply of electricity up to 100KVA for a single (1) phase and three (3) phase low voltage system. Steps Action Reference 1 Appoint an Electrical Contractor who will act on their behalf and submit the electricity supply application for the applicant using the Electricity Supply Application Form available at TNB web page http://www.tnb.com.my. Visit our web page: www.tnb.com.my The Electrical Contractor must be registered with the Energy Commission 2 Settle connection charges billed by TNB (notice of connection charges) & Deposit a sum of money equivalent to 2 months bill (as reviewed from time to time) upon receiving the notice of deposit. For deposit of more than RM2,000, the applicant are encourage to settle via Bank Guarantee in order for TNB to start electricity infrastructure works.

Appendix 4 2.3 What The Electrical Contractor Should Do The Electrical Contractor appointed by the applicant should take the following action: Steps Action Reference 1 Submit electricity supply application for the applicant using the Electricity Supply Application Form available at TNB web page http://www.tnb.com.my. All information in the Electricity Supply Application Form must be completed. All documents in checklist must be completed, duly endorsed by the appropriate competent person(s) of the appropriate category and attached with the application. Appendix 1 Submission Checklist 2 Ensure all internal wirings: Completed according wiring diagram & specification Submit G and H form certifying the internal installations

Appendix 5 3.3 Application Parts PART B : TNB Application Process (Technical & Financial Approval) Part B process is the TNB Application Process for Electricity Supply above 100 KVA as outlined in Appendix 4. The process starts after the completion of Part A (Authorities Approval Process). The Process in Part B can be summarised as follows: Stage Description 1 Submit Application The Electrical Consultant Engineer (registered with Board of Engineers Malaysia) on behalf of the developer/consumer submits application for the Electricity Supply Application to the nearest Kedai Tenaga using the reference of the approved Development Order Plan. Complete details as in Appendix 5 must be submitted with the application. TNB will issue an acknowledgement letter to the Electrical Consultant Engineer. 2 Documentation Check And System Study TNB will check on the documentation and carry out system studies and shall advise on the necessary amendments (if any) to the consultant by letter. The Electrical Consultant Engineer is to ensure that all the amendments are done and resubmitted to TNB. If the study shows connection of low voltage (LV) supply mains without involving establishment of new substation or upgrading of existing substation, go straight to stage 8 3 Joint Meeting TNB will restudy the amendments and arrange for a joint meeting with the Electrical Consultant Engineer and Applicant for final acceptance of the technical requirements including substation details, cable/overhead line route, metering system requirements and meter location. Activities of both parties will be recorded in the Joint Meeting Action Log. TNB shall forward in writing the final proposal on the above agreed technical requirements to the Electrical Consultant/Applicant. Electrical Consultant on behalf of the Applicant shall in writing confirm acceptance of the final proposal to TNB.

Stage Description 4 Connection Charges TNB will issue a Notice of Connection Charges to the Electrical Consultant Engineer based on the accepted final proposal. The Electrical Consultant / Applicant shall make the payments for the Connection Charge. Relevant documents (such as Form A (Borang hal tanah) etc.) related to substation site to be submitted during the payment of Connection Charge. 5 Electricity Infrastructure Agreement (Optional) The applicant / TNB may decide to enter into an Electricity Infrastructure Agreement (mainly for large development) with regard to scope of work, charges, timely connection and their respective obligations. 6 Discussion And Preparation Of Site Work After payment of Connection Charges, the Electrical Consultant Engineer will arrange for pre start work discussion. 7 Construction Completion And Substation Energising The substation site and the construction of the substation building shall be completed (in accordance to TNB specification and requirement) and hand over to TNB. TNB will install the electrical equipment including its ancillaries and shall be responsible for the commissioning of substation. The energising of supply by TNB will normally be done at the same time as the installation of the meters. For HV / MV supply, the supply shall be energised in the presence of the Electrical Testing Engineer and for LV consumers in the presence of the Electrical Contractor. 8 Supply Application By The Electrical Contractor The Electrical Consultant Engineer shall advise the Electrical Contractor (Appointed by the Applicant) to submit supply application. The process is similar as outline in Section 2.

Appendix 6 3.4 What The Applicant Should Do The Applicant should take the following action in applying for electricity supply application for load exceeding 100KVA. Steps Action Reference 1 Appoint one (1) Electrical Consultant Engineer for each electricity supply application Submit an appointment letter of the Electrical Consultant Engineer allowing him to act on behalf of the applicant. Appendix 6 Sample of Appointment Letter of Electrical Consultantt 2 After approval from Local Authority / One Stop Centre and TNB completion of work plan, the applicant settles Connection Charges to TNB at any Kedai Tenaga or via Online Payment Channel. The Applicant may decide to enter into an Electricity Infrastructure Agreement with TNB with regard to scope of work, charges, timely connection and their respective obligations. 3 Provide the substation(s) land and building(s) to TNB by: Transfer the substation land at a nominal value of RM10.00 to TNB or; Leasing the substation land at a nominal value of RM10.00 to TNB. The Certificate of Completion and Compliance (CCC) of the substation building/compartment shall be handed to TNB. The transfer of the land title should be finalised prior to the handing over of site. In the absence of the land title, the applicant is to prepare a Bank Guarantee for TNB for the period of twelve (12) months and shall be renewed until the land title is transferred to TNB or registration of lease to TNB. Delay in title transfer may affect project implementation.

Steps Action Reference TNB have the right to use the substation to supply electricity to other consumers. 4 Applicants are required to: Deposit a sum of money equivalent to 2 months bill (as reviewed from time to time) upon receiving the notice of deposit. For deposit of more than RM2,000, the applicant are encourage to settle via Bank Guarantee.