Expo Line Project Westside/Central Metro Service Council November 2014
2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily Riders by 2030 Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes Estimated Cost: $1.5 billion Final design in now complete Project is 75% complete Major construction started in 2012
3 Construction Progress Expo Phase 2 Construction Progress at a Glance 2014 Construction Highlights: Station construction is more than 68% complete All 7 bridges have been completed All 7 stations are under construction Track installation to be completed by fall Roadway widening work and final paving continues
4 ROW Construction Progress Construction Update Venice Boulevard Median Construction Rail Welding at the I-10 Box OCS Pole Installation at Northvale Trench Sidewalk Concrete Pour at Overland Avenue
5 Palms Station Street view from Exposition Boulevard looking west
6 Westwood/Rancho Park Station Street view from Exposition Boulevard looking east
7 Expo/Sepulveda Station Street view from Exposition Boulevard looking west
8 Expo/Bundy Station Street view from Exposition Boulevard looking east
9 26 th Street/Bergamot Station Street view from looking east
10 17 th Street/SMC Station Street view looking east
11 Downtown Santa Monica Station Street view from Colorado Avenue looking east
12 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion On-going electrical, train control systems installation Canopy and archway installation Expo/ Bundy Palms Station Platform Paver Installation
13 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Electrical and train control systems installation on-going Canopy installation Expo/ Bundy Westwood Rancho Park Station Platform Pavers
14 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion Electrical and train control systems installation Canopy and Archway installation Utility Room construction Expo/ Bundy Sepulveda Station Plaza Progress
15 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion Electrical and train control systems installation Canopy and Archway installation Utility Room construction Expo/ Bundy Bundy Station Elevator Installation Progress
16 Construction Activities thru December 2014 Los Angeles Venice Blvd to Motor Ave Venice bridge track installation completed Venice Blvd roadway improvements continue on the north side Traffic signal and street light installation Motor Ave to Military Ave Complete roadway improvements at Overland Ave and Westwood Blvd Traffic signal and street light installation Construction Progress Pico Roadway Improvements Lane closures on Pico Blvd Scheduled to begin: Friday, December 5, 2014 Military Ave to Centinela Ave On-going track installation on ROW Roadway improvements at Pico Blvd and Barrington Ave Traffic signal and street light installation Westwood Boulevard Bus Pad Construction
17 Construction Update Expo Right-of-Way (ROW) Construction Progress Santa Monica Rail Installation at 19 th Street Maintenance Facility Building Progress Downtown Santa Monica Station Concrete Pour TPSS Installation at Olympic and Cloverfield
18 Construction Progress Station Progress thru December 2014 26 th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica Foundation work nearing completion On-going electrical and systems installation Canopy and archway installation Platform paver installation has been completed Track installation was completed in June 26 th Street /Bergamot Station Paver Installation
19 Construction Progress Station Progress thru December 2014 26th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica On-going electrical and systems installation Canopy and archway installation Paver installation has been completed Foundation work is complete Track installation was completed in July 17 th Street /SMC Station Tactile Warning Paver Installation
20 Construction Progress Station Progress thru December 2014 26th Street/ Bergamot 17th Street/ SMC Downtown Santa Monica Foundation work on-going Utility work on-going Electrical Systems Installation Platform paver installation to start in November Track installation to be completed in October Downtown Santa Monica Station Concrete Pour
21 Construction Progress Ongoing Construction Activities thru December 2014 Santa Monica Centinela Ave to 4th Street Continue with track installation on ROW Traffic signal, street light and train control systems installation Final street improvements Sidewalk installation between Stewart and Cloverfield Irrigation and permanent fence installation OCS Pole and Catenary Wire installation 6th Street Track Installation 6th Street is the only remaining Expo 2 track crossing Scheduled to begin: Wednesday, November 12, 2014 Olympic Bridge Rail Installation Progress
22 Bikeway and Maintenance Facility Expo Bikeway Design/Construction Soil removal and grading Irrigation, drainage systems, and curb and gutter Electrical and lighting conduits Maintenance Facility On-going installation of building pre-cast panels Typical Bike Path Design Installation of Main building interior utilities and walls On-site rail installation to start in mid-october Foundation construction for secondary and third buildings continues Maintenance Facility Building Foundation Progress
23 Construction Timeline Construction Progress and Timeline Construction Timeline 2011 Pre-Construction Activities 2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls 2013 2014 2015 Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations
24 Contacts How to Reach Us Project Website: www.buildexpo.org Sign-up on our homepage to be added to the project database and receive notices via email. Project Hotline: 213-922-EXPO (3976) Email: info@buildexpo.org Community Relations Contacts: Torri Hill SRJV Community Relations Manager 310-500-1485 or torri.hill@skanska.com Heather Rozman SRJV Community Relations Coordinator 310-500-1487 or heather.rozman@skanska.com Social Media: www.facebook.com/expoline www.twitter.com/expoline