Appendix 2: Facility Status Update () This section describes the current status of facilities that were applied for, are under construction or have been placed on-stream since the 2012 Annual Plan was issued on 14, 2012. Periodic updates are being provided based on the level of activity occurring with respect to facilities. Facilities with (AP) after the project name refer to ATCO Pipelines footprint projects. Service Date Status Reference Aitken Creek Compressor 15 MW April 2019 Nov. 8 October 22, 72 Alces River Compressor Modifications Flow Proposed October 22, 10 Banff Loop Extension at Canmore (AP) 7 km NPS 6 4 th qtr. Dec. 11 July 10, 2012 11.4 Bonanza Meter Upgrade 2-1284U Ultrasonic Meter February Oct. 15 Oct. 1, 3.0 Bootis Hill Lateral Loop 5 km NPS 20 Feb. Project Feb. 14/May 16 2012 Cancelled 2 24.3 April Bootis Hill Meter Modifications 2-1280-4U Feb. Project Cancelled February 14, 2012 2.2 April Cardinal Lake Compressor Units 1, 2 & 3 2 0.8 MW units 1 1.2 MW unit January Filed 26, 12, 1.6 Cavendish Compressor Units 1 & 2 1 1.3 MW unit 1 3 MW unit Q2 Proposed October 22, 1.8 Chinchaga Lateral Loop No. 3 33 km NPS 48 April Under construction July 12/Sept 13, 2011 140.7 Clarkson Valley Compressor Cutbank River Lateral Loop No. 2 (Kakwa Didsbury Compressor Units 5 & 6 1 15.1 MW unit Q1 Proposed October 22, 12 km NPS 24 April Proposed October 22, 2 0.7 MW unit Q2 Proposed October 22, 2.6 24.0 0.8 Divest Brazeau East Lateral & Pembina West Meter 3.8 km NPS 8 Sale Finalized Jan. 14 June 12, 2012 January Divest Hackett Lateral, Hackett Lateral Loop and Hackett Meter 2 6.5 km NPS 4 Sale Finalized Nov. 21 July 15, 0.4 1 is the applied for cost or the forecast cost to complete for facilities in-service. 2 Bootis Hill Lateral Loop and Bootis Hill Meter Modifications were applied for in a single NEB Section 58 application. 1
Appendix 2: Facility Status Update () Service Date Status Reference Decommission Alberta System Meter s and Associated Laterals Flatbush Edwand South Fourth Creek South Owlseye Oyen 3 rd qtr. Completed October 8, June 7, 2012 1.7 Decommission Alces River Compressor A Plant 3.3 MW July Completed July 31, June 10, 1.3 September Decommission Beaver Creek Compressor Units 1, 2, & 3 3 1 MW units September Completed September 18, July 26, 1.8 Decommission Bens Lake A Compressor Units 1, 2, 3 & 7 4 1 MW units October Completed October 27, September 6, 2.4 Decommission Nine NGTL System Meter s and Associated Laterals Caslan Crossfield West Fawcett River Flat Lake North Keho Lake Meyer A & Meyer B Virginia Hills East Webster North 4 th qtr. Approved Sept 19 May 8, 2.2 Decommission Princess Compressor A Units 1, 2, 3, 4 & 5 3 2.7 MW units 2 4.5 MW units Completed 25, August 12, 2.2 Denning Lake Compressor 3.5 MW Approved Sept 25 20, 2012 June 7, 34.7 East Calgary Connector (AP) 11 km NPS 30 Proposed July 12, 2011 41.8 Grey Owl Creek Meter 660 Orifice Meter Oct. 31 May 3, 1.5 (less 0.2 CIAC) Groundbirch Compressor 30 MW Nov. 8 October 22, 103 Hangingstone Sales Meter 2-1280T Turbine Meter February Variance Application Nov. 1, Aug. 20, 2012 2.7 Hanmore Lake Compressor Units A1 & A2 2 0.5 MW units Completed 28, October 7, 1.5 Hidden Lake North Compressor Horn River Mainline (HRML) Loop (Kyklo Creek 15 MW March Mar. 19 29.1 km NPS 42 April Mar. 30 2010 Annual Plan 66.6 April 2010 Annual Plan 97.4 April 2
Appendix 2: Facility Status Update () HRML (Komie North & Fortune Creek M.S. HRML Loop (Townsoitoi Service Date Status Reference 100 km NPS 36 April NEB recommends Certificate should not be approved Jan 30 July 12/Sept 13, 2011 27 km NPS 42 TBD Proposed July 12/Sept 13, 2011 227.3 2.5 77.5 February Inland Looping (AP) 18 km NPS 20 Proposed October 22, 29.0 Leismer to Kettle River Crossover 79 km NPS 30 April Apr. 26 2010 and May 10, 2011 149.9 June Leming Lake Sales Lateral Loop 37 km NPS 20 April Under construction 20, 2012 61.0 Little Sundance Meter Upgrade 660-2 Orifice Meter September Sep. 11 July 10, 1.5 MacKay Sales Meter 2-860T Turbine Meter Approved Dec 11 June 10, 1.6 Marten Hills Extension 40 km NPS 20 Q3 Proposed October 22, 3.0 Medicine Hat Area Capacity Expansion EASML NPS 48 Loop #4 Modifications Proposed October 22, 15.2 Foothills Control Valve at Empress Tie-in / Control Valve / 2-1610 Minnehik Buck Lake & Minnehik Buck Lake B Meter Modifications and Minnehik Buck Lake Lateral Modifications Sour Bottle & Sour Monitoring and shut-in facility May May 25 April 5, 1.5 Mitchell Creek Meter 2-1064U Approved Sept 13 May 3, 2.2 September Mitsue Lateral Loop 13 km NPS 10 26 km NPS 8 Proposed October 22, 3.1 Moody Creek Compressor 15 MW January Jan. 28 2010 Annual Plan 54.6 March Moosa Crossover 5 km NPS 20 April Approved October 29 20, 2012 12.6 Musreau Lake Lateral Loop No. 3 16 km NPS 24 April Proposed October 22, 31.0 Musreau Lake West Meter 2-1284U February Approved 5 August 6, 3.2 3
Appendix 2: Facility Status Update () Service Date Status Reference Norma Transmission (AP) 38 km NPS 20 Oct. 24 July 10, 2012 52.0 Norma Transmission (NGTL) 3 km NPS 20 Oct. 22 20, 2012 8.7 North Branch Replacement (AP) 3 km NPS 16 Proposed October 22, 7.0 North Montney Mainline 180.9 km NPS 42 April 2016 (Aitken Creek 3 Nov. 8 October 22, 762 North Montney Mainline (Kahta 125 km NPS 42 Nov. 8 October 22, 530 North Montney Mainline Meter s Nov. 8 October 22, 66 Receipt Meter s: Kahta Creek Kahta Creek North Buckinghorse River Mason Creek Beatton River Lily Halfway River Blair Creek Aitken Creek West Aitken Creek East Gundy Kobes Altares 2-1064U Ultrasonic Meters April 2018 April 2016 April 2016 Storage Meter : Aitken Creek Interconnect 2-3020U Ultrasonic Meter April 2016 Delivery Meter : Mackie Creek Interconnection 2-3020U Ultrasonic Meter Northeast Calgary Connector (AP) 17 km NPS 24 Proposed 2011 Annual Plan 43.7 Northwest Mainline Loop 49.8 km NPS 48 April (Timberwolf 4 Apr. 30 2010 Annual Plan 202.2 June NWML Loop (Pyramid 30 km NPS 48 TBD Proposed July 12/Sept 13, 2011 92.5 3 The North Montney Project was filed as a Section 52 application comprised of the following facilities: North Montney Mainline (Aitken Creek, North Montney Mainline (Kahta, Aitken Creek Compressor, Saturn Compressor, Groundbirch Compressor, 13 receipt meter stations, a bi-directional storage meter station (Aitken Creek Interconnect) and a delivery meter station (Mackie Creek Interconnection). 4 The 2010 Annual Plan Chapter 2 included two sections of Northwest Mainline called Timberwolf and Sabbath sections. Since these were to be constructed together, both were combined under a single name Timberwolf Section. 4
Appendix 2: Facility Status Update () Otter Lake Compressor 28 MW Service Date Status Reference Dec. 18 October 22, 100 Peace River Mainline / Abandonment (Meikle River to Valleyview section) 266 km NPS 20 2.3 km NPS 4 Q3 Proposed October 22, 13.7 Peigan Trail Pipeline (AP) 8 km NPS 20 2016 Proposed July 10, 2012 32.5 Pelican Lake Compressor Unit 2 1 3.3 MW unit Q1 Proposed October 22, 2.4 Resthaven Meter Upgrade 2-1280-4U August 4 Oct. 21, 2.2 Saddle Hills Compressor Modifications Flow Proposed October 22, 10 Saddle Lake Lateral Loop 12.1 km NPS 16 April Nov. 28 20, 2012 20.4 Saturn Compressor 15 MW Nov. 8 October 22, 70 Saturn Compressor Unit 2 15 MW April 2019 Nov. 8 October 22, 63 Shepard Energy Centre Extension (AP) 15.8 km NPS 20, associated Delivery (2-1612T Turbine Meter) and associated system modifications July Approved Aug. 14 (AUC) 20, 2012 71.8 September Slave Lake Compressor Unit 1 1 1 MW unit Q1 Proposed October 22, 1.7 Snipe Hills Compressor 3.5 MW Proposed October 22, 45 South Lateral Princess Control Valve Pressure control valve station Nov. 16 August 1, 5.9 Southeast Calgary Connector (AP) 11 km NPS 24 July 12, 2011 29.4 Southwest Edmonton Connector (AP) 20 km NPS 20 Proposed July 10, 2012 42.0 Sunday Creek South Lateral Loop No. 3 12.8 km NPS 24 April Under construction 20, 2012 31.0 Sunday Creek South Sales Meter 2-1280U 2012 Dec. 11 2012 October 18, 2012 2.5 January Tanghe Creek Lateral Loop No. 2 (Cranberry 32.3 km NPS 48 April Apr. 2 2010 Annual Plan 117.7 April 5
Appendix 2: Facility Status Update () Thunder Creek Compressor Service Date Status Reference 1 3.5 MW unit January Proposed 6, 2.7 Upgrade Indus Pipeline System (AP) 20 km NPS 4 4 th qtr. Dec. 23 July 10, 2012 9.3 Valleyview Compressor 1 3 MW unit Q2 Proposed October 22, 1.8 Vermillion Compressor (AP) 3.0 MW Proposed October 22, 14.0 Wapasu Creek Sales Meter 2-1280U April Apr. 1 May 10, 2012 2.9 Wildhay River Meter Modifications Sour Conversion and NPS 20 PTI June Aug. 8 May 3, 1.5 (100% CIAC) September Wolverine River Lateral Loop 62 km NPS 20 April 2016 Project Filed 15, October 22, 128.0 6