SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update

Similar documents
STAFF REPORT INFORMATION ONLY

TORONTO TRANSIT COMMISSION REPORT NO.

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

TORONTO TRANSIT COMMISSION REPORT NO.

Energy Performance Information Request Timeline

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED

TORONTO TRANSIT COMMISSION REPORT NO.

Welcome to Open House #5 Scarborough Rapid Transit

Department of Market Quality and Renewable Integration November 2016

METRO CNG Program Phase I Update. Customer Service Committee April 2014

STAFF REPORT ACTION REQUIRED

ANNUAL SUMMARY REPORT FY 2005 PERFORMANCE REPORT SUMMARY COMPARATIVE ANALYSIS

Sound Transit Operations July 2016 Service Performance Report. Ridership

Up and Down Months of the Stock Market

Dawn Storage Pricing Summary last updated April 1, 2018

Electrovaya Provides Business Update

Too Good to Throw Away Implementation Strategy

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017

Action Requested From AMWG

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

Total Production by Month (Acre Feet)

The Peoples Gas Light and Coke Company

TORONTO TRANSIT COMMISSION REPORT NO.

STAFF REPORT ACTION REQUIRED

Date Event or Holiday :Sun, 2:Mon North Orchard Delong Preschool North Orchard Delong Preschool

TECHNICAL SERVICE BULLETIN

Bulk Storage Containers

Florida Courts E-Filing Authority Board. Service Desk Report October 2018

Price Category Breakdown - February 2010

Inventory Levels - All Prices. Inventory Levels - By Price Range

Hospitality & Tourism Management January 2015 Calendar Sunday Monday Tuesday Wednesday Thursday Friday Saturday 1 2 3

Algebra II Pacing Guide

November 2018 Customer Switching Report for the Electricity and Gas Retail Markets

Electric Vehicle Program

Precision Station Stopping Progress Update

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

Automated Occupancy Detection October 2015 (Phase I) Demonstration Results Presented by Kathy McCune

Developing Toronto s Transit Network Plan to 2031

STAFF REPORT ACTION REQUIRED

Late Starter. Tuesday, November 6, 2018

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014

increase of over four per cent compared to the average of $409,058 reported in January 2010.

Inventory Levels - All Prices. Inventory Levels - By Price Range

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Glendale Water & Power Smart Grid Project

Foothill Transit Battery Electric Bus Performance Results

LRT vs. Subway. Scarborough RT and Sheppard

System Status Briefing

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses

Transit Project Delivery Status Report. Significant Issues

The Use of GPS to Optimize the Mobile Fleet. We provide the right equipment at the right place and the right time.

STRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR 2015 THROUGH QUARTER 4 (JULY 2014 THROUGH JUNE 2015)

IOWA MOLD TOOLING CO., INC. BOX 189, GARNER, IA TEL: IMT PART NUMBER

NJ Solar Market Update

New McNicoll Bus Garage Public Open House

Government of Canada Hopper Car Fleet

Florida Courts E-Filing Authority Board. Service Desk Report December 2018

STATISTICS BOTSWANA ELECTRICITY GENERATION & DISTRIBUTION 2016/2 STATS BRIEF, FIRST QUARTER Copyrights Statistics Botswana 2016

Predict Future Failures From Your Maintenance Records

Toronto Police Service Annual Report: Parking Enforcement Unit 2017 Parking Ticket Issuance. Andy Pringle, Chair, Toronto Police Services Board

TORONTO TRANSIT COMMISSION REPORT NO.

FOR IMMEDIATE RELEASE

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

Scarborough Subway Extension. Stakeholder Advisory Meeting February 28, 2017

TORONTO TRANSIT COMMISSION REPORT NO.

Operational Opportunities to Minimize Renewables Curtailments

Report for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer

ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT

Washington Metropolitan Area Transit Authority

Sprinkler System Waiver Application Packet

Mobility Management: Caltrain

Residential Load Profiles

MARKET RATES UPDATE Paula Gold-Williams Cory Kuchinsky

AEP Utilities Presentation

Inventory Levels - All Prices. Inventory Levels - By Price Range

Digitized for FRASER Federal Reserve Bank of St. Louis. Per cent. P Total reported (000) ^D-)>oCL

7 Habits of Highly Effec3ve Product Development

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

IMPORTANT UPDATE. The most recent update will be highlighted with a red box.

NJ Solar Market Update As of 6/30/15

RE: Advice Schedule 45 Public DC Fast Charger Delivery Service Optional Transitional Rate REPLACEMENT PAGES

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case

2013 / 2014 Revenue Comparison: OCTOBER

George Carter III Dept. of Enterprise Services Olympia Washington

Audit Follow-up. Fleet Fuel Operations (Report #0801, Issued October 18, 2007) As of March 31, Summary. Report #0811 June 20, 2008

TORONTO TRANSIT COMMISSION REPORT NO.

November 2017 Customer Switching Report for the Electricity and Gas Retail Markets

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

MEMORANDUM. TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit. Date: May 24, Summary

The Regional Municipality of York. Purchase of Six Battery Electric Buses

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]

August 2018 MLS Statistical Report

TORONTO TRANSIT COMMISSION REPORT NO.

FOR IMMEDIATE RELEASE

ANCR CRU Statistics February 2007 to December 2007

Alfred & Plantagenet Multi-Residential Cart Recycling Program CIF Project Number # Final Report October 1, 2016

Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items

Transcription:

MEETING DATE: August 31, 2005 SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update RECOMMENDATION It is recommended that the Commission: i) Receive for information the updated Due Diligence Checklist relating to the Russell Hill Subway Train Accident of August 11, 1995, which provides a status report on the progress toward closing the Coroner's Jury Recommendations and the TTC's Internal Team Recommendations. ii) Forward this report to the Chief Coroner of Ontario, the City of Toronto, and the Province of Ontario for information. BACKGROUND Fifteen previous Due Diligence Checklist updates were submitted to the Commission at its meetings of April 2, 1996, May 28, 1996, July 9, 1996, December 10, 1996, March 4, 1997, December 16, 1997, June 17, 1998, December 2, 1998, September 1, 1999, December 8, 1999, September 5, 2000, August 29, 2001, August 28, 2002, August 27, 2003 and September 22, 2004. The following definitions have been provided to staff to clarify their meaning within the Due Diligence Checklists: Closed means that every aspect of the recommendation has been addressed and completed. There is documentation supporting the closure. For example: a signed-off written procedure is complete and currently being followed, the equipment is purchased and in use, or a memo is on file detailing the reason the TTC has non-concurred. The person responsible has signed-off on the Due Diligence Sign-off Report. Closed by TTC means that every possible step has been taken by the TTC, and the completion of the recommendation rests with an outside agency. This applies only to Coroner's Jury Recommendations. The person responsible has signed-off on the Due Diligence Sign-Off Report. Open indicates that the implementation of the recommendation is underway. SUMMARY OF JURY AND TTC INTERNAL TEAMS RECOMMENDATIONS Three recommendations have closed since the last update on September 22, 2004. The TTC has closed 229 of the 236 recommendations from both the Coroner's Jury Recommendations and the Internal Teams' Recommendations. Of the remaining seven recommendations, five relate to the completion of the new Transit Control Centre. Two of these recommendations are scheduled to close in December 2005, and the remaining three will be considered closed upon the signing of the final Transit Control Centre Safety Certification Certificate, also scheduled for December 2005. Two other recommendations relate to the implementation of speed control, and are scheduled for completion in 2007. The following table provides a summary of the current status of recommendations. CATEGORY September 22, 2004 August 31, 2005 TOTAL

OPEN CLOSED OPEN CLOSED Training 0 50 0 50 50 Track 0 31 0 31 31 Transit Control 2 37 2 37 39 Vehicles 0 32 0 32 32 Signals Design 5 27 3 29 32 Signals Maintenance 0 34 0 34 34 Coroner's Jury 3 15 2 16 18 TOTAL 10 226 7 229 236 ONGOING STEPS The next updated Due Diligence Checklist, which is scheduled to be presented at the Commission Meeting in August 2006, will also be forwarded to the Office of the Chief Coroner of Ontario, to ensure that the Chief Coroner is apprised of our progress with respect to the resolution of all of the recommendations stemming from the Russell Hill Subway Train Accident. The status of the recommendations are also summarized and reported in the TTC s monthly Chief General Manager's report. The TTC will continue to present publicly to the Commission each year in August, until closure of all recommendations, and will outline the status of all recommendations and any outstanding issues or deficiencies. - - - - - - - - - - - - - - August 8, 2005 13.8.8 Attachment: Due Diligence Checklist #16 Russell Hill Subway Train Accident of August 11, 1995 P:\Common\Glenn Pringle\Russell Hill\RH-Aug 2005\COM Aug 2005.doc

Due Diligence Checklist #16 Update re: Recommendations Open as of September 22, 2003 Russell Hill Subway Train Accident of August 11, 1995 INDEX Page Summary Implementation of TTC & Coroner s Jury Recommendations i Coroner s Jury Recommendations 1 Transit Control Incident Management and Emergency Response 6 Signals Design 7 Note: This updated checklist contains updates to recommendations that were open as of the last update in Due Diligence Checklist #15, dated September 22, 2004. Disposition of the recommendations closed on that date may be referenced in previous Due Diligence Checklists. August 31, 2005 Russell Hill Subway Train Accident Due Diligence Checklist SUMMARY Recommendations Open as of September 22, 2004 # Category R: Revised Responsibility Summary of Recommendation Updated Change 1 Jury #7 December 2006 R: December 2007 D. Finn 7 (i) & (v) Speed Control To be operational on Sheppard Line by 1st Quarter of 2006, and balance of subway by the end of 2007.

# Category R: Revised Responsibility Summary of Recommendation Updated Change December 2004 R: December 2005 D. Finn 7 (vi) IPHC New Train Control system in service on B-D & YUS since May 2004. This recommendation will be considered closed upon the signing of the final Safety Certification Certificate, scheduled for December 2005. 2 Jury #8 Closed D. Finn 2 trip arms Completed December 2004. 3 Jury #11 December 2004 R: December 2005 D. Finn New TCC Train operation began in new TCC in May 2004. Will close upon the signing of Safety Certification Certificate. 4 T.C. #15 5 T.C. #39 6 Sig D. #6 7 Sig D. #16 December 2004 R: December 2005 December 2004 R: December 2005 April 2005 R: December 2005 December 2006 R: December 2007 D. Finn Plotting Incident Responses D. Finn New TCC D. Finn 8 Sig D. #22 Closed D. Finn 9 Sig D. #28 Closed D. Finn 10 Sig D. #30 Aug 31 2005 Update April 2005 R: December 2005 Signal Violation Alarms at TCC D. Finn Speed Control System D. Finn Raised trip arms in blind curves Raised trip arms in blind curves Signal Violation Alarms at TCC Train operation began in new TCC in May 2004. Will close upon the signing of Safety Certification Certificate. Train operation began in new TCC in May 2004. Will close upon the signing of Safety Certification Certificate. Operational as of March 2005 for interlocking signals. Deficiencies with automatic signals to be completed by December 2005. To be operational on Sheppard Line by 1st Quarter of 2006, and balance of subway by the end of 2007. Completed December 2004. Completed December 2004. Operational as of March 2005 for interlocking signals. Deficiencies with automatic signals to be completed by December 2005. August 23, 2005

Coroner s Jury Recommendations 7(i, v, vi), 8 & 11(vii) (7) We strongly recommend the TTC conduct a comprehensive review and reexamination of the existing signal system with comparison to other Transit Authorities in North America. Attention should be focused on a human factors analysis with particular attention to signal interpretation. Action must be taken on the following items where deemed appropriate to improve safety. Report: S: Oct. 31/96 Report Presentation (Internal): Nov.22/96 (Commission): Dec.10/96 M. Reidak All of the recommendations below were addressed through the comprehensive Strategic Signal Plan which was presented to the Commission on December 10, 1996.

7 (i) the use of lunar white aspect in conjunction with red aspect. Red is to be seen as absolute. Study:Oct 31/96 Work:Dec 31/98 R: Jan 1999 S: Dec 31/2001 R: Dec 31/2003 R: Dec 31/2005 R: Mar 31/2002 R: Dec 31/2006 R: Dec 31/2007 Subsection Closed May 31/99 M. Reidak Study Budgeted in CP 2.4 D. Finn Flashing Red Signals completed May 31, 1999. Medium Term - A speed control system will eliminate all lunar white aspects. for completion December 31, 2006. This will be done in accordance with the Strategic Signal Plan, which was presented on November 22, 1996. Update July 2002 Contract awarded December 2001. Work has begun. Update July 2003 Vehicle and wayside design ongoing. T 1 prototype approved. Update July 2004 T-1 installation began in April 2004. Wayside design being finalized. Update August 2005 To be operational on Sheppard Line by 1 st Quarter of 2006, and balance of subway by the end of 2007.

7 (v) progressive speed control. Study - Oct. 31/96 Installation - S: Dec. 1/2001 R: Dec. 1/2003 R: Dec. 1/2005 R: Dec 31/2006 D. Finn CP 2.4 A speed control system will be installed. of installation is scheduled for December 31, 2006. Update July 2002 Contract awarded December 2001. Work has begun. Update July 2003 Vehicle and wayside design ongoing. T 1 prototype approved. R: Dec 31/2007 Update July 2004 T-1 installation began in April 2004. Wayside design being finalized. Update August 2005 To be operational on Sheppard Line by 1 st Quarter of 2006, and balance of subway by the end of 2007.

7 (vi) Expansion of the existing TTC Intermediate Point Headway Control system to identify headway and train separation. Study - Oct. 31/96 Installation - Dec.31/2001 R: July 2000 R: July 2002 R: Oct 2002 R: July 2003 R: Oct 2003 R: Dec 2004 R: Dec 2005 D. Finn Included in CP 30A The IPHC system will not be expanded. The new Transit Control Centre's signal system scheduled for October will identify headway and train separation in accordance with Jury Recommendation #15 and the Strategic Signal Plan presented November 22, 1996. Update July 2003 In-service testing is ongoing. The revised date is October 2003. Update August 2004 New Train Control System in place May 2004. This recommendation will be considered closed upon the signing of the final Safety Certification Certificate, scheduled for December 2004. Update August 2005 Signing of the final Safety Certification Certificate scheduled for December 2005.

(8) We recommend the TTC eliminate the automatic key-by ability to allow trip arms to be raised behind trains occupying long track blocks. Test - June 30/96 Study - Oct 31/96 Work - Dec.31/98 R: Dec.31/00 R: Mar 1/2001 R: June 2002 R: June 2003 R: Nov 2003 R: Oct 2004 June 30/96 Nov.22/96 CLOSED Dec 2004 D. Finn CP 2.4 Two trip arms will be raised behind trains in long signal blocks with blind curves. The work is scheduled for completion Dec. 31/98. The automatic key-by ability will not be removed. Locations identified as having similar characteristics as the accident site will be completed in 1998. A comprehensive system-wide program has been included in the 1999 Capital Budget submission. Update July 2003 Final completion of this work has been delayed due to the heavy resource demands of the Sheppard Line. Design has resumed for the remaining locations and completion is scheduled for November 2003. Update August 2004 Project delayed due to operational emergencies (B2 relays, SRT unsafe door openings). Update August 2005 Completed.

(11) We support the TTC initiative to build a new Transit Control Centre (TCC) scheduled for completion in the year 2000. In the interest of public safety, we recommend interim improvements be made to the existing TCC facility and its operation: Fall 2000 R: Aug 2001 R: Dec 2001 R: Mar 2002 R: July 2002 R: Oct 2002 R: July 2003 R: Dec 2003 R: Dec 2004 R: Dec 2005 D. Finn CP Update June 2003 - The new Transit Control Centre began cutover in March 2003, and will be fully operational by December 2003. Update August 2004 This recommendation will be considered closed upon the signing of the final Safety Certification Certificate. Update August 2005 Signing of the final Safety Certification Certificate scheduled for December 2005.

vii) use of signals expert on staff in TCC to interpret reported faults. Trouble Desk in new Transit Control Centre Subsection Closed August 2004 D. Finn Operating (labour) $465,000 (1996$ s) Partially agree - A control desk will be provided in close proximity to the new TCC, to handle all Signals/Electrical/Communications issues. S: Fall 2000 R: Aug 2001 R: Dec 2001 R: Oct 2002 R: July 2003 R: Dec 2003 R: Dec 2005 Transit Control Daily Log review now in effect. Update July 2002 - There are no current plans to have a Signals/Electrical/Communications staff member in Transit Control. This will be reviewed in conjunction with the opening of the new Transit Control Centre. Update June 2003 No change. Update August 2004 Event playback capability is now operational and has been used successfully to interpret faults. Signals experts are available 24/7 to interpret these as required. It is not considered necessary that staff be physically located in the TCC to perform this function. Consideration is also being given to having a Signal Foreperson physically in the TCC during rush hour service. Update August 2005 Signing of the final Safety Certification Certificate scheduled for December 2005. Transit Control Recommendations 15 & 39

(15) The Transit Control Centre shall develop a method of plotting the incident response activities so that everyone in Control can see a picture of the incident & response developing. SR Dec.31/2000 R: Dec 2001 R: Mar 2002 R: July 2002 R: Oct 2002 R: July 2003 R: Dec 2003 R: Dec 2004 R: Dec 2005 D. Finn CP New "state of the art" technology, mimic boards, etc. available upon completion of the new Transit Control Centre (December 2001) will address these issues. The rear projection screen technology planned for the new Transit Control Centre will provide the level of tracking detail to allow the Controllers to plot the trains at an incident scene. In the interim there are two solutions to the recommendation. The first involves the plotting of an incident on the back of a message slip and the second, which should be implemented this year is the introduction of a more accurate train tracking system which will replace the current CTDI system. New call taking software being pursued. Demonstration to be done by December 1998. MIS was requested to provide budget funds for call taking software in their 1999 budget. Update June 2003 The new Transit Control Centre began cutover in March 2003, and will be fully operational by December 2003. Update August 2004 Train Operation began in the new Transit Control Centre in May 2004. This recommendation will be considered closed upon the signing of the final Safety Certification Certificate, scheduled for December 2004. Update August 2005 Signing of the final Safety Certification Certificate scheduled for December 2005. See Coroners' Jury Recommendation #11.

(39) Provide Transit Control staff with the technology required to better monitor systems and control trains. RT S: Fall 2000 R: Aug 2001 R: Dec 2001 R: Mar 2002 R: July 2002 R: Oct 2002 R: July 2003 R: Dec 2003 R: Dec 2004 R: Dec 2005 D. Finn The new Transit Control Centre will provide the train control capabilities to monitor and control train movements. Transit Control project is in progress. See Coroner's Jury Recommendation #11. Update June 2003 - The new Transit Control Centre began cutover in March 2003, and will be fully operational by December 2003. Update August 2004 Train Operation began in the new Transit Control Centre in May 2004. This recommendation will be considered closed upon the signing of the final Safety Certification Certificate, scheduled for December 2004. Update August 2005 Signing of the final Safety Certification Certificate scheduled for December 2005. Signals Design Recommendations 6, 16, 22, 28, 30

(6) Consider the installation of alarms at Transit Control which will annunciate whenever a signal is violated. S: Dec 31/00 R: Aug. 2001 R: Dec 2001 R: Mar 2002 R: July 2002 R: Oct 2002 R: July 2003 R: Dec 2003 R: Apr 2005 R: Dec 2005 D. Finn Included in CP 30A The comprehensive review of the Signal System in the Strategic Signal Plan presented November 22, 1996 addressed this issue. The new Transit Control Signal System will include monitoring of red signal overruns at interlockings only. Update June 2003 - The new Transit Control Centre began cutover in March 2003, and will be fully operational by December 2003. Update August 2004 Train Operation began in the new Transit Control Centre in May 2004. Red Signal overrun not fully implemented. Update August 2005 Operational as of March 2005 for interlocking signals. Deficiencies with automatic signals to be completed by December 2005.

(16) Analyze signal design in older section of subway where signals are located within stations and determine if modifications are feasible without affecting system design adversely. RT RT S: Jun. 30/97 R: Dec. 31/01 R: Dec. 31/03 R: Dec. 31/05 R: Dec. 31/06 R: Dec. 31/07 D. Finn CP 2.4 This is not cost effective in the short term with the existing signal system. This will be addressed when a speed control system is installed. A decision has been made to proceed with a speed control system for completion December 2006. Update July 2003 Design ongoing. Installation to begin in the 4 th quarter of 2003. Update July 2004 T-1 installation began in April 2004. Wayside design being finalized. Update August 2005 To be operational on Sheppard Line by 1 st Quarter of 2006, and balance of subway by the end of 2007.

(22) Raise trip arm immediately behind train. RT S: Dec 31/98 R: Dec. 31/00 R: Mar 31/01 R: June 2002 R: June 2003 R: Nov 2003 R: Oct 2004 CLOSED Dec 2004 D. Finn CP 2.4 Test & evaluation program initiated in October 1, 1995, both ways between Dupont and Eglinton West. Operations does not concur for system wide, only for long blocks with blind curves. Strategic signal plan presented Nov. 22/96 recommended raising two trip arms behind trains in long signal blocks with blind curves. A comprehensive system-wide program has been included in the 1999 Capital Budget submission. Update July 2003 Final completion of this work has been delayed due to the heavy resource demands of the Sheppard Line. Design has resumed for the remaining locations and completion is scheduled for November 2003. Update August 2004 Project delayed due to operational emergencies (B2 relays, SRT unsafe door openings). Update August 2005 Completed. See recommendations #28 from the Signals Design Due Diligence Checklist.

(28) Modify the signal system to implement the double Trip. RT S: Dec 31/98 R: Dec 31/00 R: Mar 31/01 R: June 2002 R: June 2003 R: Nov 2003 R: Oct 2004 CLOSED Dec 2004 D. Finn CP 2.4 A comprehensive system-wide program has been included in the 1999 Capital Budget submission. Update July 2003 Final completion of this work has been delayed due to the heavy resource demands of the Sheppard Line. Design has resumed for the remaining locations and completion is scheduled for November 2003. Update August 2004 Project delayed due to operational emergencies (B2 relays, SRT unsafe door openings). Update August 2005 Completed. Refer to Signals Design Recommendations #22.

(30) Explore the feasibility of real time monitoring of trains violating red signals and the provision of resulting alarms at Transit Control. RT S: Dec 31/00 R: Aug 2001 R: Dec 2001 R: Mar 2002 R: July 2002 R: Oct 2002 R: July 2003 R: Dec 2003 R: Apr 2005 R: Dec 2005 D. Finn Included in CP 30A The new Transit Control signal system will record / monitor trains violating red interlocking signals in real time and annunciate the alarms in accordance with the Strategic Signal Plan presented November 22, 1996. Update June 2003 - The new Transit Control Centre will be fully operational by December 2003. Update August 2004 Train Operation began in the new Transit Control Centre in May 2004. Red Signal overrun not fully implemented. Update August 2005 Operational as of March 2005 for interlocking signals. Deficiencies with automatic signals to be completed by December 2005. For 72% of the active fleet, whenever a signal is violated or a trip valve is activated, the event is recorded on the vehicle event logger. The information is automatically recorded on SMS. In addition, there is an alarm activated at ECD (Equipment Control Desk). When Speed Control is implemented, H5 vehicles will be included, bringing the total to 91% of the active fleet. H4 vehicles will not be included. See Recommendations #6 of the Signals Design Due Diligence Checklist.

P:\Common\Glenn Pringle\Russell Hill\RH-Aug 2005\Checklist 16.doc