DCP Midstream Contractor Covered Task List Last updated 7/11/2018

Similar documents
Columbia Pipeline Group Contractor Covered Task List Last updated 1/8/2018

Southern Star Central Gas Pipeline Contractor Covered Task List Last updated 8/15/2018

Williams Contractor Covered Task List Last updated 11/7/2017

Northern Natural Gas Contractor Covered Task List Last updated 4/26/2018

Enbridge Gas Transmission and Midstream and Enbridge Liquid Pipelines (Express-Platte) Contractor Covered Task List Last updated 8/30/2018

Boardwalk Pipeline Partners, LP Contractor Covered Task List Last updated 9/17/2018

EnLink Midstream Contractor Covered Task List Last updated 11/8/2017

Energy Transfer Partners LP Contractor Covered Task List Last updated 12/10/2018

Energy Transfer Partners LP Contractor Covered Task List Last updated 3/2/2018

TransCanada US Contractor Covered Task List Last updated 9/27/2018

Saddle Butte Rockies Midstream LLC Contractor Covered Task List Last updated 12/6/2017

Dominion Energy Questar Pipeline LLC Contractor Covered Task List Last updated 10/3/2017

Epic Consolidated Operations LLC Contractor Covered Task List Last updated 9/6/2018

Howard Midstream Energy Partners LLC Contractor Covered Task List Last updated 10/11/2013

Noble Energy Contractor Covered Task List Last updated 2/20/2019

Black Hills Energy Contractor Covered Task List Last updated 10/10/2018

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 8/24/2018

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 12/12/2017

Appendix A Kinder Morgan Operator Qualification Program List of Covered Tasks - Natural Gas - Part 192 Revised 12/13/2017

ASMECourseCatalog.

Florida City Gas Contractor Covered Task List

COVERED TASK Conduct Cathodic Protection Surveys 1 DESCRIPTION ELEMENTS OF TASK 4 PART QUESTION NOTES ABNORMAL OPERATING CONDITIONS

Operator Qualification (OQ) Report

PIPELINE CORROSION CONTROL

PIGGING PRODUCTS. Capex supply. PIG LAUNCHER and RECEIVER

PHMSA Office of Pipeline Safety Dave Mulligan Western Region

HDPE FUSIBLE VALVES EXPECT INNOVATION

This article discusses a tank

New UST Installation Inspection Checklist

The Implementation of a Storage Facility Inspection Program. Presented By: John R. Rueckel PCA Engineering, Inc.

Monthly Checklist For Depot

LINE STOPPING. Extending and modifying your existing pressurized system while it s under full operating conditions.

Pipe Support The Fast, Economical Solution for Low Pressure Pipeline Repair

GUIDELINE FOR GLOVEBOXES THIRD EDITION AGS-G001 February 2007

INSTALLATION, OPERATION, & MAINTENANCE MANUAL Models # MM-30, MM-30HT, MM-50, MM-50HT, & MM-50 EXL with Special HP Tool and Special HP EXL Tool

Highway Crossings - Cased or Uncased

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER SAMPLE / INJECTION PUMP

No Infrared Refrigerant Leak Detector

INSTALLATION INSTRUCTIONS

PROCEDURE EXTRUDED HOT TAP & LINE STOP TEES DESIGN & MANUFACTURING VALIDATION

Methane to Markets Partnership Expo. Remote Sensing - Aerial Leak Detection and Measurement. ANGEL Service Airborne Natural Gas Emission Lidar

Monitoring Cathodic Protection of Natural Gas Pipelines

This publication is copyrighted and intended for the sole use of General Industries - 07/07/2016

Inspector's Initials: Tank Owner or Agent Signature: Title: Date:

ESTABLISHMENT OF ULTRASONIC TESTING IN UNIQUE DESIGNED PARTIAL PENETRATION END PLUG OF HEADER IN BOILERS.

HOT TAPPING & PLUGGING SOLUTIONS

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

Client Success Story Sheri Baucom Senior Advisor II

ANNUAL UST SYSTEM INSPECTION CHECKLIST

CASE STUDY ON PIPELINE UNDER-PROTECTION ALONG WITH MITIGATION METHODS. Vipul Vilas Sawant. Mahanagar Gas Ltd, Mumbai, India

LACT MEASUREMENT. Total Head = Or PSI = S.G. 2.31

An Introduction to Constructing and Maintaining Cathodic Protection Systems

CONTENTS. Foreword...iii. 1. Introduction...1

CHAPTER 115 LEAK DETECTION AND REPAIR (LDAR) PROGRAM CHANGES

KENNEDY VALVE Plant and Industrial Group 1021 East Water Street Elmira, New York Telephone (607) Fax (607)

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER AUTOMATIC INSERTION PROBE

Inline Ultrasonic Flowmeter

SECTION FACILITY FUEL - NATURAL GAS PIPING AND SYSTEMS

Report of the Pipeline Safety Department. Home Explosion January 2, Whispering Hollow Drive Oklahoma City, Oklahoma

Rolls -Royce M250--C47M OPERATION AND MAINTENANCE

OIL HANDLING SYSTEMS

Broetje-Automation Company Standard Structural component specification for welded parts

September 2012 / M&H C502 / Model 129

Algeria, November 2016

Val-Matic Extended Bonnet Assembly Instructions

Cathodic Protection for AST s. Why is Cathodic Protection Important?

THE APPLICATION OF LONG RANGE GUIDED ULTRASONICS FOR THE INSPECTION OF RISER PIPES

Asset Protection Cathodic Protection Testing of Insulating Joints. Work Instruction No.:

The Gradient Control Mat (GCM)

Atmos Energy DOT Report-Distribution Leaks Cause of Leak WTX LA MS CO KS KY M-TX TN VA Total

Station 130 (Maple) Compressor Upgrade Project

Hand Expansion Valves Built Stronger to Last Longer Sizes: 6mm (¼ ) to 305mm (4 )

Processing Plant Enters. the Pipeline World. A Case Study of a Chemically Welded Anomaly Repair. By Randy Vaughn. R&F Pipecon Resources

Ignition energy enough for igniting the mixture is available, such as sparkles generated by friction and impaction, electric arc or hot surfaces.

Application for Permit to Install Underground Storage Tanks (Petroleum or Hazardous Substances) 1. Owner Information 2. Installation Site Information

VRX Plunger. Advanced Control Valve

SITRANS AS 100. Instruction Manual September 2001 ITRANS AS 100

MUELLER GAS. Shur StopTM Unit 812 PE Line Stopping. System 8" 12" SDR Reliable Connections. General Information 2

Oil & Gas Custody Transfer Data Sheet

Pipeline Safety Information. for public officials

Baumann Sanitary Diaphragm Angle and Inline Control Valve

GAS DISTRIBUTION PRODUCTS METER RISERS

DESIGN, OPERATION & MAINTENANCE OF L.A.C.T. UNITS

SECTION PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY

OIL-FREE, ROTARY SCREW AIR COMPRESSORS Two-stage, Air-cooled and Water-cooled Fixed Speed or VFD

Provides the perfect seal, protects flanges, valves and pipelines against corrosion whilst improving safety and reducing the risk of fire.

GF Piping Systems. SurTap System Operation with VersaTap Fittings Manual

Annex to the Accreditation Certificate D-PL according to DIN EN ISO/IEC 17025:2005

Application Engineering

A new approach to the results of internal inspection

Biogas safety control equipment

FISC Puget Sound Manchester Fuel Department. Maintenance, Leak Detection in Large Underground Storage Tanks. Glenn E. Schmitt, P.E.

Report for CSP Joint Venture Click to edit Master text styles Second level Third level. Fifth level

Geomembrane Test Methods

PIPELINE INTEGRITY CONFERENCE BHR GROUP 5th-7th NOVEMBER 2008 SCHIPOL, THE NETHERLANDS PIPPELINE IN INDIA

Type B (Extruded Branch) Sizes 4 through 30

Rosemount 402 and 402VP

DONKIN ASSET PROTECTION SYSTEM WARRANTY UP TO 20 YEARS* DONKIN ASSET PROTECTION SYSTEM

BCV30 DN20 - Blowdown Control Valve Installation and Maintenance Instructions

Mitigation of External Corrosion on Buried Carbon Steel Pipeline Systems July/2018

Transcription:

001 Provide Security for Pipeline Facilities 195.436 Oral 007 Operate Valves 008 Measurement of Wall Thickness with Ultrasonic Device 009 Movement and/or Relocation of Liquid Pipelines 195.424 011 Inspect, Test and Maintain Computational Pipeline Monitoring (CPM) Sensing Devices 012 Inspect, Test and Maintain Liquid Leak Detection Flow Computers 014 Maintain/Prove Flow Meters for CPM Hazardous Liquid Leak Detection 015 Inspect, Test and Maintain Gravitometers/Densitometers for CPM Hazardous Liquid Leak Detection 195.444 195.444 195.444 195.444 016 Purging - Hazardous Liquids 195.402(c)(10) 020 Pump Stations/Units - Startup, Operation and Shutdown 195.402(c)(7) 195.402(c)(8) 201 Abnormal Operating Conditions Related to Welding on Pipelines 192.225 192.227 192.715 192.717 192.713 192.245 202 Monitoring of Welding Process 192.241(a) 192.241(c) 192.231 192.235 192.245 204 Non-Destructive Testing (Dye Penetrant) 192.243 205 Non-Destructive Testing (Mag Particle) 192.243 206 Non-Destructive Testing (Ultrasonic) 192.243 207 Non-Destructive Testing (X-Ray) 192.243 208 Plastic Pipe Joining: Butt Fusion 192.281 192.283 192.285 192.287 195.222 195.214 195.230 195.224 195.226 195.204 195.224 195.228 195.234 Oral Oral No 1:0 1 Page 1 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 25

210 Plastic Pipe Joining: Electrofusion Joining 192.281 192.283 192.285 192.287 No 1:0 1 211 Perform Plastic Fusion Inspection 192.287 Oral 213 Joining of Metal Pipe and Components by means other than Welding - Threaded and Flanged Connections 192.271 216 Joining of Metal Pipe - Compression Couplings 192.271 217 Small Diameter Metal Tubing and Fitting Installation 192.271 401 of Buried Pipelines When Exposed 192.459 404 Protection of Coating When Backfilling and From Below Ground Supports 192.461(d) 192.614(c)(6) 192.461( c ) 192.319(b) 195.126 195.569 Oral 195.252 195.422 405 Protection of Coatings From Above Ground Structures 192.461(d) 406 Conduct Test to Determine Cathodic Protection Current Requirements 192.465(a) 407 Perform Cathodic Protection Survey 192.465(a) 192.465(e) 192.328(e) Oral 195.571 408 Inspect Cathodic Protection Rectifier 192.465(b) 195.573( c ) 409 Inspect Interference Bonds 192.465(c) 195.573( c ) 410 Clear Shorted Casing 192.467(c) 195.401(b)(1) 195.575(a) 411 Inspect/Test to Assure Electrical Isolation is Adequate 192.467(d) 195.575 412 Install CP Leads on Pipeline Using Exothermic Weld 192.471 195.567 414 Inspect for Internal Corrosion Whenever Pipe is Removed 192.475(b)(1) 415 Monitoring for Internal Corrosion with Probes and Coupons 192.477 192.620(d)(5) 416 Monitoring for Internal Corrosion with Gas Samples 192.477 195.579(c) 195.579(b) 417 Atmospheric Corrosion Monitoring 192.481 Page 2 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 25

418 General and Localized Corrosion Measurement (Remedial Measures) 192.485(a)(b) 419 Cathodic Protection Potential Measurement 192.465(a) 192.620(d)(8) 195.585(b) 195.587 420 Soil Resistivity 421 Measurement of Depth of Pitting with Pit Gage 192.485 195.569 195.585 422 Assessment of Pipeline Segments Using Long Range Guided Wave UT 423 Perform Direct Current Voltage Gradient (DCVG) Survey 192.490 192.620(d)(7) 424 Perform AC Current Attenuation (ACCA) Survey 192.490 192.328(e) 192.620(d)(7) 426 Inspect Pipe Coating with Holiday Detector 192.455(a) 192.457(a) 192.461 192.479 195.588 195.588 195.561 195.569 427 Inspection of Above or Below Ground Coatings Oral 436 Perform Close Survey 192.328(e) 192.465(e) & (7) 480 Apply Approved Coating by Hand Application 192.461(a) 195.557 482 Apply Approved Coatings by Mechanical Spray and Hand Application Methods 192.461(a) 195.557 484 Apply Approved Coatings by Wrap Application 192.461(a) 195.557 501 Conduct a Pressure Test 192.505 192.507 192.513 192.328(d) 502 Conduct Pressure Test on Pipe that is to be Operated at a Pressure <100 psig 601 Start-up/Shut-down of Pipeline to Assure Operation Within MAOP / MOP 192.509 192.511 192.513(b) 192.605(b)(5) 602 Monitoring Pipeline Pressure 192.605(b)(5) 192.619 603 Compressor Units: Startup, Operation, Shutdown and Purging Before Returning to Service 192.605(b)(7) 192.605(b)(6) 195.304 195.305 195.306 195.402 195.406 195.402( c )(9) 195.406 Oral Page 3 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 25

604 Locate, Mark, and Remediate Exposed Pipelines in the Gulf of Mexico 192.612(b) 195.413 605 Locate Line/Install Temporary Marking of Buried Pipeline 192.614(c)(5) 195.442(c)(5) 606 Locate and Mark Submerged Pipelines 192.614(c)(5) 607 Damage Prevention: Observation of Excavating and Backfilling 192.614(c)(6) 192.319(b) 195.252 195.442(c)(6) 608 Damage Prevention for Blasting Near a Pipeline 192.614(c)(6) 195.442(c)(6) Oral 609 Inspect and Maintain Odorization Equipment 192.625(e) 610 Monitor Odorant Concentration 192.625(f) 611 Hot Tap (Steel Pipe) 192.627 612 Hot Tap (Plastic Pipe) 192.627 613 Purge Pipeline Facilities With Gas 192.629(a) 614 Purge Pipeline Facilities With Air or Inert Gas 192.629(b) 195.422 195.402(c)(10) Oral 616 Atmospheric Monitoring during Hot Work Operations 195.402( c )(11) 619 Damage Prevention during Vacuum Excavation and Backfilling Activities 701 Patrolling Pipeline and Leakage Survey without Instrument 192.705 192.613 192.706 192.620(d)(4) 192.721 192.614(c)(6) 195.442(c)(6) Oral 195.412(a) Oral 702 Leakage Survey with Leak Detection Device 192.706 703 Placing/Maintaining Line Markers 192.707 195.410(a) 195.410(c) 704 Permanent Field Repair by Grinding 192.713 195.226 195.230 705 Permanent Field Repair Using Composite Materials (Clockspring) 192.713 195.422(a) 707 Permanent Field Repair Using Bolt-On Clamp/Sleeve 192.717 195.422(a) 708 Permanent Field Repair Using Full Encirclement Weld Sleeve 192.717 195.422(a) Oral Yes 1:3 1 Page 4 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 25

709 Inspection and Testing of Relief Devices (Compressor Stations, Meter Stations, Regulating Stations) 710 Inspect/Test Compressor Station Remote Shutdown Devices (ESD/EBD) 192.731(a) 192.731(b) 192.743 195.428 192.731(c) 711 Inspect, Test, and Maintain Systems 192.731(c) 195.408(b)(1) 195.408(b)(1) 712 Programmable Logic lers 192.731(c) 195.408(b)(1) 195.428(a) 713 Test/Maintain Gas Detection and Alarm Systems 192.736(c) 714 Inspect and Maintain Pressure ing and Regulating Devices 715 Test and Maintain Pressure Switches and Transmitters in Pressure ing and Regulating Service 192.743(a) 192.619(b) 192.743(a) 192.619(b) 716 Inspect, Maintain, and Operate Valves 192.745 192.747 718 Monitoring for Internal Corrosion with Liquid Samples 192.477 192.620 719 Permanent Field Repair Using Composite Materials (Wrapmaster) 721 Permanent Field Repair Using Composite Materials (Black Diamond) 195.428 195.428 195.420(a) 195.420(b) 192.713 195.422(a) 192.713 195.422(a) 195.579 723 Leakage Survey with Remote Laser Leak Detection Device 192.706 195.412(a) 725 Aerial Leakage Survey: Transmission 192.706 728 Aerial Leakage Survey: Transmission (UV/IR) 192.706 738 Valve (Electric) Actuator/Operator Inspection, Testing and Maintenance 192.745 192.747 765 Inspection and Repair of Rupture Pin Devices 192.619(b) 192.621(b) 192.623 195.420(a) 195.420(b) 195.428 Yes 1:3 1 Page 5 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 25