Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Similar documents
Business Advisory Committee. November 3, 2015

Business Advisory Committee. July 7, 2015

Committee Report. Transportation Committee. Business Item No

Community Advisory Committee. October 5, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015

Tracking the Blue Line Extension

Tracking the Blue Line Extension

Extending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process

SWLRT Business Advisory Committee. October 10, 2012

Meeting Summary. 1 August 3, 2015 CAC Meeting Summary

Operating & Maintenance Cost Results Report

Extending TRACKS. Peer reviews, advanced design next for Southwest LRT

Policy Advisory Committee Meeting November 13, 2013

Meeting Summary. 1 October 6, 2015 BAC Meeting Summary

Alternatives Analysis Summary Report

Regional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013

CEDAR AVENUE TRANSITWAY Implementation Plan Update

Draft Results and Open House

FREQUENTLY ASKED QUESTIONS

Corridor Management Committee. March 7, 2012

ACTION TRANSMITTAL No

Harlem Avenue between 63 rd and 65 th

Recommended Transportation. Capital Improvement Program

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Draft Results and Recommendations

Peninsula Corridor Electrification Project (PCEP)

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

Peninsula Corridor Electrification Project Cost / Schedule Update

Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2

Transitways. Chapter 4

FREQUENTLY ASKED QUESTIONS

Letter EL652 City of Mercer Island. Page 1. No comments n/a

C LINE: LONG-TERM GLENWOOD REALIGNMENT STUDY

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Mobility Corridor Updates. Transit & Active Transportation Projects

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Transit Project Delivery Status Report. Significant Issues

7000 Series Railcar Program Overview

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

2019 Bond Program. Bond Advisory Committee Rankings. November 12, 2018

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

Peninsula Corridor Electrification Project (PCEP)

A Presentation to: Project Advisory Group Meeting #10

Alternatives Analysis Findings Report

I-394 Corridor Performance

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

CROSSING RAIL PROJECT (P4) RAIL

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

REVISED AGENDA. Special Southwest LRT Corridor Management Committee Meeting

Waco Rapid Transit Corridor (RTC) Feasibility Study

Business Item No

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Harlem Avenue between 63 rd and 65 th

Public Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP)

Transportation Infrastructure Investment Program moving

Recommended C Line Station Plan

Mobility Corridor Updates. Transit & Active Transportation Projects

5. OPPORTUNITIES AND NEXT STEPS

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

D Line Station Plan: Table of Contents

Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project

To Infill or Not to Infill?

Utility work, road construction substantially done on Fourth Street

Restoration of Historic Streetcar Services in Downtown Los Angeles

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

West Broadway Transit Study. Community Advisory Committee September 17, 2015

Task Force Meeting January 15, 2009

Public Information Workshop

Restoration of Historic Streetcar Services in Downtown Los Angeles

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016

Valley Metro: Past, Present and Future. September 11, 2014

DART Priorities Overview

METRO Orange Line BRT American Boulevard Station Options

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Recommended Station Plan

Rapid Transit Implementation Working Group #4 February 9, 2017

Key Project Elements Status Report

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]

Transportation Improvement Program (TIP) Candidate Project List for Public Review

I-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018

FREQUENTLY ASKED QUESTIONS

SAN RAFAEL CITY COUNCIL AGENDA REPORT

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling.

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7

CTA Blue Line Study Area

Federal Way Link Extension

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

Metro Green Line to LAX Alternatives Analysis. March 2012

Draft Station Plan. Tuesday, November 17th

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Sales and Use Transportation Tax Implementation Plan

Transit Access to the National Harbor

I-35W & Lake Street Station

Transcription:

Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1

Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2

3 Revised Project Scope

Project Scope Refinement During Project Development Resolves issues identified by Technical Advisory Group during DEIS Reflects input and coordination: DEIS: 1,231+ public comments City/County/Agency: 105+ Issue Resolution Team meetings Advisory Committees: TPAC, BAC, CAC, CMC Public: 14 public open houses (1,600+ attendees; 530+ public comments) and 112+ community meetings Establishes scope for Municipal Consent Plans and Final Environmental Impact Statement Provides context for continued discussions with stakeholders 4

5

Project Scope Target Field Station connection 7 th St at-grade traffic signal crossing I-94 bridge rehabilitation to accommodate LRT Olson Memorial Highway reconstruction * Van White Station and Penn Ave Station Westbound OMH (TH 55) bridge reconstruction Plymouth Ave Station and vertical circulation * Golden Valley Rd Station and vertical circulation Golden Valley Rd Station surface park and ride facility, trail connections and intersection reconstruction * * New scope requirement, not in DEIS cost estimate 6

Project Scope Grimes Pond and Golden Valley Pond LRT structures * Roadway bridge reconstruction * Plymouth Ave Theodore Wirth Pkwy Golden Valley Rd 36 th Ave Robbinsdale Station and park and ride structure LRT bridge construction over TH 100 LRT bridge construction over CP Rail Bass Lk Rd Station and surface park and ride facility * * New scope requirement, not in DEIS cost estimate 7

Project Scope 63 rd Ave Station and pedestrian overpass (over freight to platform) * LRT bridge construction over CR 81 at 73 rd Ave * West Broadway reconstruction from 74 th Ave to Candlewood Brooklyn Blvd Station 85 th Ave Station 93 rd Ave Station Roadway network north of TH 610 * Oak Grove Pkwy Station and park and ride structure Operations and Maintenance Facility * New scope requirement, not in DEIS cost estimate 8

Project Scope: Corridor Wide 28 light rail vehicles (2 more than DEIS) * 13.5 miles of ballasted double LRT tracks 8 miles of ballasted single freight track Freight rail corridor protection treatments * System elements Traction Power Substations Rail Signal System 10 at-grade shared (freight/lrt) crossings Right of Way acquisition Poor soils mitigation * New scope requirement, not in DEIS cost estimate 9

Scope Project Recommendation Summary: Reductions Modified split platform stations to center platforms Reduced size of OMF building and site footprint Minimized need for floodplain mitigation by building bridge structures over ponds Eliminated need for adding floors to existing 63 rd park and ride ramp 10

Nov 12 CMC Recommendation Support project scope/cost estimated as presented on Oct 29 Include additional items to support the Golden Valley Rd Station: Park and Ride Golden Valley Rd and Theodore Wirth Pkwy intersection Trail connections Cost estimate: $8 million Continue to study the feasibility, justification, environmental impacts, cost, public outreach, and jurisdictional support for pedestrian bridges over CR 81 Crystal at Bass Lake Rd Brooklyn Park at 63rd Ave 11

Project Summary Project Corridor Length: Miles of LRT Track 13.5 miles Stations 11 Number of Park and Ride Locations Total Park and Ride Spaces 5 2,235 LRT Bridges 8 Roadway Bridges 5 Pedestrian Bridges 1 LRT/Freight Rail At-Grade Crossings 10 Light Rail Vehicles 28 Operations Maintenance Facility 141,000 SF Ridership (2040) 27,000 12

13 Revised Cost Estimate

Cost Estimates and Budget Timeline C O S T E S T I M A T E B U D G E T DEIS Cost Estimate 1% Engineering Updated Cost Estimate 15% Engineering Project Budget 30% Engineering August 2014 Enter Project Development December 2015 Begin Municipal Consent August 2016 Apply to Enter Engineering 14

DEIS Cost Estimate Assumptions DEIS Cost Estimate (1% Eng.) $1.002 B Total Project Contingency 34% Escalation Factor 3% Base Year Estimate 2012 Forecast Year 2017 (mid-point of construction) 15

Revised Cost Estimate Cost Estimate (15% Eng.) $1.496 B Total Project Contingency 30% Escalation Factor 3% Base Year Estimate 2015 Forecast Year $YOE (2018, 2019 and 2020) 16

Overall Cost Estimate Methodology Cost Estimates Total Project costs include capital improvements, ROW acquisition, vehicles, engineering and environmental consultants, contingency, and finance costs Base year costs: 2015 Costs are escalated to Year of Expenditure ($YOE) 17

Project Cost Drivers Advanced Engineering $202M Inflation $60M New Scope Requirements $232M LRT Bridges $67M Plymouth Ave Station $13M Road Bridges $31M Olson Memorial Highway $23M Roadway Network N. of TH610 $37M Freight Rail Requirements $53M GV Rd Station P&R/Trail/Intersection $8M 18

Advanced Engineering Cost Drivers Poor soils mitigation Retaining walls Two additional light rail vehicles Additional trackwork: special trackwork at stations and non-revenue track to Operations and Maintenance Facility Additional park and ride at Bass Lake Rd 19

Cost Effectiveness Index (CEI) CEI measures cost effectiveness of a federal New Starts project based on estimated ridership, capital and operating costs CEI is one of six project justification criteria FTA uses to evaluate projects CEI anticipated to improve from Medium-Low to Medium under new federal rules 20

21 Municipal Approval

Municipal Approval Process Met Council Submits Municipal Consent Plans to Cities and County Week of Dec 14, 2015 At least 30 days Met Council/ Hennepin County Regional Railroad Authority/Hennepin County Hold Joint Open House and Public Hearing Jan 19, 2016 Cities hold Public Within 45 days Cities/County Approve Plans within 45 Days of the Met Council/Hennepin County Regional Railroad Authority/Hennepin County Joint Open House and Public Hearing Hearing after 30 Days of Met Council Plan Submittal Completed by March 4, 2016 Jan/Feb/Mar 2016 22

A Look Ahead: Design & Engineering Dec 2015: Submit Municipal Consent Plans for City and County Review Mar 2016: Complete Municipal Consent Approval Process Aug 2016: Finalize 30% Design Plans and Specs Aug 2016: Apply to Enter Engineering 23

24 Transportation Committee Action

METRO Blue Line Extension Approve the revised project scope and cost estimate of $1.496 billion as recommended by the Blue Line Extension CMC at their Nov 12, 2015 meeting Direct staff to prepare Blue Line Extension Municipal Consent Plans consistent with the project revised scope, and submit to Hennepin County and corridor communities Authorize scheduling and conducting a joint public hearing with the Hennepin County Regional Railroad Authority, Hennepin County and the Metropolitan Council on the revised plans on January 19, 2016 at Hennepin County s Minneapolis Central Library 25

More Information Website: BlueLineExt.org Email: BlueLineExt@metrotransit.org Twitter: @BlueLineExt 26