Customer Guide to Electric Service Requirements

Similar documents
Customer Guide to Electric Service Requirements

GENERAL INFORMATION 1.01 PURPOSE

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS

For Conduit Inspections

7. Residential Single-Family and Duplex Buildings (Dwellings)

ELECTRIC POLICY INTRODUCTION CHAPTER I GENERAL

Commercial Electric Policy

7 Single Family Service

Table of Contents. Electrical Service Requirements. 1. General Requirements

TEMPORARY SERVICE TABLE OF CONTENTS PUD SERVICE TERRITORY AND CONTACTS CHAPTER ONE - INTRODUCTION CHAPTER TWO - TEMPORARY OVERHEAD SERVICE

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING

RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS SECTION II RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS

10 Commercial, Industrial, Agricultural Services

Commercial Electric Service Handbook

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

AMENDMENT ELECTRIC SERVICE MANUAL 2014

Engineering Service Specifications. Commercial Single-Phase Current Transformer Metering Schemes

Installing or Rebuilding Your Electric Service

Associated equipment As related to metering equipment: such as the current transformers, CT wiring and test switches.

Approved Contractor Construction e-guide Residential Commercial

Metering and Service Installation:

Indianapolis Power & Light Company

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE

PERMANENT RESIDENTIAL UNDERGROUND SERVICE

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

RESIDENTIAL NEW CONSTRUCTION PACKET CITY OF VERO BEACH UTILITIES. Important Notice to Builders/Contractors/Developers From Electrical Engineering

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW)

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION

Electric Service Requirements

Engineering Rules and Regulations for Electric Service Platte-Clay Electric Cooperative, Inc.

SECTION 300 OVERHEAD SERVICE

COMMERCIAL QUICK REFERENCE

SPRINGVILLE CITY ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

PUBLIC UTILITY DISTRICT NO. 1 OF LEWIS COUNTY METERING SPECIFICATIONS

Clark Public Utilities Commercial Electric Service Handbook. This page left blank intentionally.

New Service. From... BARRON. Spooner Office: P.O. Box 261 Spooner, WI Barron Office: P.O. Box 40 Barron, WI

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

SALEM CITY POWER ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5

SOUTHWEST LOUISIANA ELECTRIC MEMBERSHIP COORPORATION COMMERCIAL SERVICE REQUIREMENTS

TEMPORARY ELECTRICAL SERVICE

SPRINGVILLE CITY ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE

UNDERGROUND SERVICES - SECONDARY

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code

ELECTRIC DIVISION RULES AND PROCEDURES FOR ELECTRIC SERVICE

Electric Service Requirements & Guidelines

Residential Application for New Electric Service

The cost estimation methodology used to update the charges and credits is the same methodology the Company utilized in the prior year s filing.

ELECTRIC SERVICE HANDBOOK INFORMATION & REQUIREMENTS

Parkland Light & Water Co. ELECTRIC SERVICE REQUEST AND METER STANDARDS

ELECTRIC SERVICE MANUAL

Electric Service Rule No. 2 Description of Service

NEW SERVICE HANDBOOK COMMERCIAL & IRRIGATION SUPPLEMENT

Electric Service Policy Kerrville Public Utility Board

WELLS RURAL ELECTRIC COMPANY Adopted: March 1976 Revised: March 21, 2017 Reviewed: August 21, 1998 RULE NO. 2

OREGON TRAIL ELECTRIC CO-OP ELECTRIC SERVICE REQUIREMENTS & GUIDELINES

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

SINGLE PHASE WIRING SPECIFICATIONS

REQUIREMENTS FOR A RESIDENTIAL STRUCTURE TO BE CONSIDERED A PERMANENT INSTALLATION

ELECTRIC SERVICE RULES UTILITY/CATV SERVICES Issued Jan 2016

TILLAMOOK PEOPLE S UTILITY DISTRICT

KIUC Service Installation Manual

Meter Standards COMMERCIAL. Metering Guidelines for Electric Service. March 28, 2014

THREE PHASE WIRING SPECIFICATIONS

1. General Requirements

RIVER FALLS MUNICIPAL UTILITIES ELECTRIC SERVICE MANUAL

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

ORDINANCE NO

JACKSON ELECTRIC COOP METER LOOP CONSTRUCTION SPECIFICATIONS JUNE 2018

Customer Requirements Downtown Secondary Network Service

INTERMOUNTAIN RURAL ELECTRIC ASSOCIATION. Builder/Developer Information

NEW SERVICE HANDBOOK

CHAPTER 1 INTRODUCTION

ELECTRIC SERVICE REQUIREMENTS

RESIDENTIAL. Metering Guidelines for Electric Service. Meter Standards. October 25, 2017

Transmission & Distribution Glossary of Electrical Terms

10. METERING General Requirements

Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota

Commercial & Industrial

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT

All territory within the incorporated limits of the City and land owned or leased by the City.

Louisville Gas and Electric Company

Net +Plus Connection Code

COMMERCIAL HANDBOOK 2013 EDITION MATANUSKA ELECTRIC ASSOCIATION, INC. PALMER, ALASKA

WPS SERVICE MANUAL. Section Amp and Smaller - Common

GUIDELINES FOR RESIDENTIAL ELECTRIC SERVICE HOOKUP

3.1 Overview of ATCO Electric s URD System Design

RULES AND REGULATIONS FOR ELECTRIC SERVICE

Service Requirements

OVERHEAD SERVICE. Items to consider

Electric Service Guidelines TSN

Panola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004

Transcription:

Customer Guide to Electric Service Requirements Tillamook People s Utility District Power Services Group 1115 Pacific Avenue Tillamook, Oregon 97141 OFFICE: 503.815.8629 FAX: 503.815.8648 TOLL FREE: 800.422.2535 www.tpud.org

Foreword The information contained in this Customer Guide to Electric Service Requirements is intended to serve as a guide for electrical contractors, architects, building contractors, engineers, and other customers to provide information needed for determining acceptable methods of receiving electric service from Tillamook PUD and is intended to promote a safe, efficient method for receiving electrical service. These requirements are based on Tillamook PUD policies and standards in effect at the time of publication. Tillamook PUD reserves the right to change the requirements, specifications, and policies without prior notice. Contact Tillamook PUD Engineering Office for the most current requirements, or you may view this guide on our website: www.tpud.org, under Service and Billing / Construction Specifications. This handbook does not include all possible standards and specifications required by Tillamook PUD or by state, federal, or local codes. It is the customer s responsibility to conform to Tillamook PUD policies and standards, as well as all applicable state, federal, and local codes. Prior to beginning any work order, do the following: Contact the Tillamook PUD Engineering Department Fill out online request form(s), or obtain a form from the Engineering Department. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS i

Contact Information Tillamook PUD Telephone Numbers Engineering Department 503-815-8629 Operations Department 503-842-2122 Toll-free: Operations Department Front Office FAX: Engineering Department Operations Department 800-842-2122 800-422-2535 503-815-8648 503-842-2758 Frequently Requested Telephone Numbers Tillamook County Community Development 503-842-3408 Electrical Inspector 503-842-3440 Locate Service Dial 8-1-1 Website Address Please visit the following website for the most current revisions to this publication: www.tpud.org TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS ii

Table of Contents Foreword... i Contact Information... ii Section 1 General Requirements 1.1 Introduction... 1-1 1.2 Request for Electrical Services Form... 1-2 1.3 Types of Service... 1-2 1.4 Line Extension Policy... 1-3 1.5 Cost Estimate... 1-3 1.6 Reimbursable Work Order Form Policy (Form T-8)... 1-4 1.7 Easements... 1-4 1.8 Standard Service Voltages... 1-5 1.9 Service Entrance Equipment... 1-5 1.10 Quality of Service... 1-6 1.11 Protective Devices... 1-7 1.12 Modifying Existing Electrical Service... 1-7 1.13 Flood Areas... 1-8 1.14 Hazardous Electrical Service... 1-8 1.15 Service Beyond the Meter... 1-8 1.16 Fault Current... 1-8 1.17 Location of Meter (Point of Delivery)... 1-9 1.18 Meter Seals... 1-9 1.19 Location of Pad-mounted Transformers... 1-9 1.20 Power Factor... 1-9 1.21 Clearance to Existing Lines... 1-9 Section 2 Temporary Service, Overhead and Underground 2.1 General... 2-1 2.2 Temporary Overhead Service... 2-2 2.3 Temporary Underground Service... 2-2 Section 3 Overhead Permanent Service 3.1 General... 3-1 3.2 Service Arrangements... 3-2 3.3 Service on Gable End of Building... 3-2 3.4 200- and 400-Ampere Services to Mobile or Manufactured Home Service... 3-3 3.5 Service Locations-Manufactured Homes... 3-3 3.6 Minimum Service Drop Clearances... 3-3 TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS iii

Section 4 Underground Permanent Service 4.1 General... 4-1 4.2 Locating Underground Facilities... 4-2 4.3 Meter Location... 4-2 4.4 Meter Pedestal Arrangements... 4-2 4.5 Single-Phase Service Arrangements... 4-3 4.6 Three-Phase Service Arrangements... 4-4 Section 5 Trenching, Conduit, and Vault Specifications 5.1 Trenching Requirements... 5-1 5.2 Backfill... 5-2 5.3 Locating Underground Facilities... 5-2 5.4 Conduit Installation Requirements... 5-2 5.5 Conduit Specifications... 5-4 5.6 Vault Installation... 5-5 5.7 Vault Purchase... 5-6 5.8 Vault and Lid Specifications... 5-6 Section 6 Metering 6.1 General... 6-1 6.2 Energizing the Service... 6-2 6.3 Meter Locations... 6-2 6.4 Sealing and Locking Requirements... 6-4 6.5 Clearances... 6-5 6.6 Meter Base Requirements... 6-5 6.7 Self-Contained versus CT Metering... 6-7 6.8 Current Transformer Enclosures... 6-7 6.9 Current Transformer Installation... 6-8 6.10 Current Transformer Conduit... 6-8 6.11 Instrument Transformer Rated Meter Worksheet... 6-9 6.12 Current Transformer Switchboard Metering... 6-9 Section 7 Area Lights 7.1 General... 7-1 Section 8 Right-of-Way Clearing 8.1 Customer Requirements... 8-1 Section 9 Generation Permanent and Temporary 9.1 Generator Safety... 9-1 9.2 Portable Generators... 9-1 9.3 Fixed Generators... 9-1 TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS iv

List of Figures 2-1 100- to 200-amp Meter Base Temporary Overhead Service... 2-3 2-2 100- to 200-amp Meter Base Temporary Underground Service... 2-4 3-1 200- to 400-amp Meter Base Temporary Overhead Service... 3-4 3-2 Gable End of Building Service Requirements... 3-5 4-1 200- to 400-amp Meter Base Required Underground Service Arrangement... 4-5 4-2 Conduit Installation Guidelines for Secondary Riser Poles... 4-6 4-3 200- to 400-amp Meter Base Underground Pedestal Installation... 4-7 5-3 Vault E11... 5-8 5-4 Single Phase Transformer Vault Cover... 5-9 5-5 Single Phase Vault Cover... 5-10 5-6 Single Phase Sectionalizing Vault Cover... 5-11 5-7 Vault E19... 5-12 5-8 3 Phase Transformer Vault Cover... 5-13 5-9 V or 3 Phase Vault Cover... 5-14 5-11A Single Phase Sectionalizing Vault Cover... 5-15 5-11B V or 3 Phase Sectionalizing Vault Cover... 5-16 5-12 1500 KVA Transformer Vault Cover... 5-17 5-19 Conduit Installation Guidelines for Secondary Riser Poles... 5-18 5-20 Requirements for Conduit Routing into Vaults... 5-19 5-21 Conduit Installation Guidelines for Secondary Pedestals... 5-20 5-22 Trenching Requirements... 5-21 5-23 Underground Utility Equipment Locations... 5-22 6-1 Service Entrance Equipment Overhead 1-Phase... 6-10 6-2 Service Entrance Equipment Overhead 3-Phase Installations... 6-11 6-4 Current Transformer Enclosure Overhead 1-Phase Installations... 6-12 6-5 Current Transformer Enclosure Underground 1-Phase Installations... 6-13 6-6 Current Transformer Enclosure Overhead 3-Phase Installations... 6-14 6-7A Current Transformer Enclosure Underground 3-Phase Installations... 6-15 6-7B Current Transformer Enclosure Underground 3-Phase Installations (Alternative)... 6-16 6-8A Current Transformer Diagrams-Mounting Bracket... 6-17 6-8B Current Transformer Diagrams-Mounting Bracket... 6-18 6-9 Recessed Meter Clearances... 6-19 6-10 Meter Cabinet Enclosure... 6-20 6-11 Ring-type Meter Socket with Test Switch Provision Min. Socket Dimensions... 6-6 8-1 Right-of-Way Clearing Guide... 8-2 8-2 The Right Tree for the Right Place... 8-3 8-3 The Clear Zone... 8-4 TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS v

List of Tables 1-1 Standard Service Voltages... 1-5 5-1 Trenching Requirements... 5-1 5-2 Conduit Installation Requirements... 5-3 5-3 Conduit Specifications Schedule 40 PVC... 5-4 5-4 Conduit Specifications HDPE... 5-5 5-5 Single-Phase Installations Vault and Lid Specifications... 5-7 5-6 Three-Phase Installations Vault and Lid Specifications... 5-7 6-1 Self-Contained versus CT Metering Requirements... 6-7 6-2 CT Enclosure Minimum Dimensions... 6-7 8-1 Right-of-Way Clearances... 8-1 Appendix Line Extension Agreement Reimbursable Work Order Form (Form T-8) Application for Service Customer Certification Request for Electrical Services Residential Service Request for Electrical Services Commercial Service Request for Electrical Services Land Development Request for Electrical Services Service Change Plot Plan Load Data Sheet Instrument Transformer Rated Meter Worksheet TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS vi

Section 1 General Requirements 1.1 Introduction The information in this handbook applies to Tillamook People s Utility District (Tillamook PUD) customers requiring electrical service. This handbook provides the majority of the information and requirements that will be needed by the customer. It does not include all possible standards, specifications, and policies required by Tillamook PUD or by state, federal, and local requirements. It is the customer s responsibility to adhere to existing policies or future changes. Please contact the Tillamook PUD Engineering Department to determine the requirements of the project. The customer is responsible for as applicable: Completing the appropriate Request for Electrical Services form (See samples in Appendix). Completing the Load Data form (See sample in Appendix). Completing the Application for Service form (See sample in Appendix). Signing Tillamook PUD s Line Extension Agreement or a Reimbursable Work Order form (See samples in Appendix). Providing payment, obtaining an approved loan application for the Line Extension Agreement, or signing a Reimbursable Work Order form (For information regarding the loan program, contact the Finance Department at 503-815-8636). Signing or obtaining notarized signatures for easement(s). Easements will be prepared by the Engineering Department on Tillamook PUD forms, for owner s signatures for the installation, operation, and maintenance of Tillamook PUD facilities. Obtaining applicable permits and inspections from appropriate public agencies. Tillamook PUD may provide assistance in preparing the permits for Tillamook PUD facilities. Notifying Tillamook PUD Engineering Department when the meter base(s) has (have) passed electrical inspection. Providing and installing all equipment to meet Tillamook PUD specifications and policies. Keeping the meter base(s) visible and accessible per Tillamook PUD specifications and policies. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-1

Providing and clearing a right-of-way for overhead and underground installations in accordance with Tillamook PUD specifications (Refer to Section 8, Right-of-Way Clearing). Meeting or exceeding all applicable provisions of the National Electric Code (NEC); National Electrical Safety Code (NESC); State of Oregon Electrical Specialty Code; Tillamook PUD standards; and state, federal, and local applicable requirements. 1.2 Request for Electrical Services Form Each prospective customer desiring electrical service must complete a Request for Electrical Services form and, as required, a Load Data Sheet, and an Application for Service form (See samples in Appendix). The Request for Electrical Services form initiates the new service process and provides Tillamook PUD personnel with critical information needed to design the service. The customer shall provide Tillamook PUD with accurate load data and approved plot plan. The plot plan shall show the location of property corners, property lines, and location of existing and proposed facilities (drain fields, home site, outbuildings, or well). It is recommended that customers contact Tillamook PUD early in the project to ensure the successful design and installation of electric service in a timely manner. To obtain a copy of the Request for Electrical Services form: Contact the Engineering Department at: 503-815-8629 800-422-2535 Visit the Tillamook PUD website at: www.tpud.org The Customer Guide to Electric Service Requirements may be viewed at: http://www.tpud.org 1.3 Types of Service Tillamook PUD provides both overhead and underground temporary and permanent service. Some city ordinances require new or upgraded service be underground. It is strongly recommended that permanent service be underground. The service, whether single- or three-phase, will be 60 hertz alternating current. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-2

Refer to specific sections for more complete information on the following types of service: Temporary Overhead and Underground Service(s) Section 2 Overhead Permanent Service Section 3 Underground Permanent Service Section 4 1.4 Line Extension Policy It is the policy of Tillamook PUD to extend service to all customers within its exclusive service territory provided that the service extensions comply with Tillamook PUD policies and with all applicable provisions of the NEC; NESC; State of Oregon Electrical Specialty Code; and other state, federal, and local applicable requirements. The applicant for an electric line extension must own, have a contract to purchase, or have a lease of sufficient duration (as determined by Tillamook PUD) to the property or premises before Tillamook PUD will provide a plan of service or a line extension for that property. To obtain a line extension or plan of service, the applicant or their representative shall complete the Request for Electrical Service form and Load Data Sheet, if applicable. Tillamook PUD may require the applicant to supply evidence of approval for construction by the city, county, or other governing agencies. Such evidence of approval to construct is to provide assurance of the applicant's intent to proceed with construction. Tillamook PUD requires notification by the applicant of any property deed restrictions or zoning requirements that may affect the installation of Tillamook PUD electrical facilities. 1.5 Cost Estimate Tillamook PUD will prepare an initial cost estimate for each line extension. The cost estimate shall include all anticipated Tillamook PUD costs for the line extension. All cost estimates are valid for 180 days and the construction of the line extension must be completed within 180 days from the date of the cost estimate letter. The estimated cost shall be paid by the customer prior to the start of construction. If the construction is not completed within 180 days of the date of the estimate letter, a new cost estimate and Line Extension Agreement will be prepared. If the new cost estimate is greater than the initial estimate by TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-3

$100 or more, the additional cost shall be paid by the customer prior to construction. A refund, if greater than $100, will be made to the customer in the event the actual cost of construction is less than the estimated cost. The District shall not be bound by oral agreements or discussions. Estimates are based upon assumptions that the District obtains from information provided by the customer. If the District determines, in its discretion, that these assumptions or information have changed, the District shall reserve the right to modify the plan of service and the cost estimate. Customer will be charged for any additions, modifications or changes to the original cost estimate. 1.6 Reimbursable Work Order Form Policy (Form T-8) When the customer requests Tillamook PUD to relocate or modify Tillamook PUD facilities for their convenience, Tillamook PUD will prepare a cost estimate based on standard billing rates for man-hours, materials, equipment, associated overhead expenses, and a 10 percent contingency. The cost estimate is valid for 180 days and construction must be completed during the 180-day period. The estimated cost shall be paid by the customer prior to the start of construction. A refund, if greater than $100, will be made to the customer in the event the actual cost of construction is less than the estimated cost. 1.7 Easements Tillamook PUD requires easements prepared on Tillamook PUD easement forms providing for the installation, operation, and maintenance of all primary voltage power lines and where necessary for secondary and service lines. Prior to installation of facilities, it is the customer's responsibility to provide a legal property description to Tillamook PUD for easement preparation. The customer is responsible for signing or obtaining all necessary notarized signatures on Tillamook PUD-prepared easements. The customer is responsible for signing or obtaining all necessary notarized signatures on Tillamook PUDprepared easements. For parcels owned by corporations, limited liability corporations, or family trusts, documentation will be required indicating all parties legally authorized to sign on behalf of the entity. For land development(s), parcels being developed as subdivisions or partition plats will require a metes and bounds description as well as a TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-4

copy of the most recently registered partition plat or subdivision plat. Documentation will be required specifying all parties legally authorized to sign on behalf of the entity. 1.8 Standard Service Voltages The following table shows the standard services provided by Tillamook PUD. Table 1-1 Standard Service Voltages Standard Service Voltages Service Type Single-Phase 1 Voltage 120/240 Volts Three-Phase Network 208Y/120 Volts 240 /120 Volts 2 480Y/277 Volts 480 /240 Volts 2 208Y/120 Volts 1 Any service greater than 600 amps shall be three-phase. 2 Requires approval from Engineering Department 1.9 Service Entrance Equipment The customer is responsible for providing, installing, and wiring service entrance equipment to conform to or exceed all provisions of the NEC; NESC; State of Oregon Electrical Specialty Code; and other state, federal, and local applicable requirements. The customer or their contractor shall connect their equipment to keep the load, under normal operating conditions, balanced within plus or minus 10 percent of the average load across the phase wires. The customer is responsible for maintaining service entrance equipment; therefore, Tillamook PUD strongly recommends stainless steel (meter bases and current transformer enclosures) to mitigate rust and equipment deterioration. All individual three-phase service installations require a neutral (fourth) wire to be provided and installed in the service mast. The neutral must meet the minimum size as set out in the NEC and shall be color-coded white. When aluminum conductors are used, the service panel must be Underwriters Laboratory (UL) listed or approved and clearly marked by the manufacturer that it is acceptable for aluminum conductors. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-5

Parallel conductors shall be uniquely identified with the appropriatecolored tape. 1.9.1 UL Listed Equipment Only UL listed or approved service entrance equipment of the proper rating may be installed. 1.9.2 Grounding Service Equipment All service equipment shall be grounded in compliance with all provisions of the NEC; NESC; State of Oregon Electrical Specialty Code; and other state, federal, and local applicable requirements. 1.9.3 Service Panels and Disconnect Switches Service panels and disconnect switches with associated equipment exposed to the weather shall be of a rain-tight type (NEMA 3R) and shall be manufactured for that purpose. 1.9.4 Service Entrance Wires and Cables 1.10 Quality of Service Service entrance wires and cables shall be sized in accordance with the NEC and extend from the weatherhead a minimum of 18 inches. A customer shall not interfere with the quality of their own service or that of another customer. In situations where the customer desires voltage control within unusually close limits, Tillamook PUD may require the customer to provide, at their own expense, special or additional power-conditioning equipment. Loads greater than 100 kilovolt-amperes (kva) three-phase or 30 kva single-phase from Tillamook PUD s secondary system shall not be switched on and off more frequently than once each hour without written authorization by the Tillamook PUD Engineering Department. The customer may be required to furnish and install special switching equipment to reduce the magnitude of load which will be cycled on and off. Inquiries as to the necessity of special equipment should be directed to the Tillamook PUD Engineering Department. Tillamook PUD requires the customer s electrical facility to meet the power quality standards presented in the latest IEEE Std. 519, IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems, entitled Recommended Practices for Individual Customers. It is the customer s responsibility to verify their equipment meets the latest IEEE Std. 519. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-6

1.10.1 Motors Single-phase Motors Single-phase motors, up to and including 10 horsepower (HP), may be served by single-phase at 240 volts. Motors larger than 10 HP shall be three-phase, unless written approval is obtained from the Tillamook PUD Engineering Department. All single-phase motors shall not exceed the maximum locked rotor amps listed in the National Electrical Manufacturers Association (NEMA) Standards, unless approved in writing by the Tillamook PUD Engineering Department. Three-phase Motors 1.11 Protective Devices Three-phase motors served from a pole-mounted transformer will be served as follows: Three-phase motors 30 HP and smaller may be served from an open delta, vee-phase transformer bank. Three-phase motors larger than 30 HP will be served from a closed transformer bank unless written approval is obtained from the Tillamook PUD Engineering Department. All three-phase loads served from pad-mounted transformers shall be wye connected. It shall be the sole responsibility of the customer to provide adequate protection on all installations against single-phasing on three-phase motors. 1.12 Modifying Existing Electrical Service Customers modifying an existing service are required to contact the Tillamook PUD Engineering Department and complete a Request to Change Service form. All repairs and changes must conform to or exceed all provisions of the NEC; NESC; State of Oregon Electrical Specialty Code; and other state, federal, and local applicable requirements. Notify Tillamook PUD s Operations Department (503-842-2122 or 800-842-2122) as soon as possible for all situations requiring disconnecting and reconnecting of service. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-7

Capacity increases to existing residential, commercial, farm, industrial, irrigation, pumping, lighting, and indeterminate electrical facilities shall be treated as though the increased capacity requirements were a new load. 1.13 Flood Areas Areas within Tillamook PUD s service area that Tillamook PUD determines are subject to flooding will require special consideration. Tillamook PUD will not install its equipment or provide service to customer-owned equipment that Tillamook PUD does not consider suitable for such locations. 1.14 Hazardous Electrical Service The customer s service entrance equipment must be in accordance with Tillamook PUD s electrical service specifications and policies at the time of installation. If the equipment is in such a condition to be dangerous to life or property, the customer will be required to make the necessary repairs and changes in order to conform to or exceed all provisions of the NEC; NESC; State of Oregon Electrical Specialty Code; and other state, federal, and local applicable requirements. If a customer creates a violation of Tillamook PUD policy or requirements; NEC; NESC; State of Oregon Electrical Specialty Code; or other state, federal, and local applicable requirements, the customer will be required to take corrective action. Tillamook PUD reserves the right to discontinue service to any customer who fails to make repairs and/or changes required to remove the danger to life or property. The service will remain disconnected until hazardous conditions and/or equipment are restored to a safe and secure condition. The service will not be reconnected until there is an inspection and approval by the State Electrical Inspector. 1.15 Service Beyond the Meter Customers requiring more than one overhead service beyond the metering point may have such services installed by Tillamook PUD at the customer's expense. Ownership of these services remains with the customer. Underground services beyond the metering point will be owned, installed, and maintained by the customer. 1.16 Fault Current Upon request, Tillamook PUD will supply the available fault current at the customer's service entrance. It is the customer's responsibility to install equipment with sufficient fault current interrupting capability. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-8

1.17 Location of Meter (Point of Delivery) It is in the mutual interest of the customer and Tillamook PUD to locate meters where reading, testing, and replacement can easily occur. See Section 6 for guidelines. The point of delivery, specified by Tillamook PUD, is that point where Tillamook PUD-owned facilities connect to the customer-owned facilities. Only one point of delivery to any dwelling or building is allowed except by written permission by Tillamook PUD and the Electrical Inspector. 1.18 Meter Seals Customers desiring service must obtain Tillamook PUD's approval of the meter location(s) prior to wiring the premises. For specific information about meter location(s), refer to Section 6, Meter Locations. Meter seals or locks are placed on meters and associated service equipment to prevent injury or tampering. Seals or locks are not to be removed except by Tillamook PUD personnel. Broken seals or locks are justification for Tillamook PUD to initiate a theft of service investigation. 1.19 Location of Pad-mounted Transformers Tillamook PUD requires that transformers be located: 1.19.1 A minimum of ten (10) feet from a combustible structure (including a building with metal siding on wood framing); 1.19.2 A minimum of three (3) feet between non-combustible surfaces and pad-mounted transformers; 1.19.3 Within twenty (20) feet of an all-weather drivable surface for single phase transformers; and 1.19.4 At a pre-approved location for three-phase transformers. 1.20 Power Factor The customer will maintain 100 percent power factor. A charge for power factor less than 95 percent is specified in Tillamook PUD s current rate schedule. It is recommended that the customer install corrective equipment to make the most effective use of the electrical system. 1.21 Clearance to Existing Lines Tillamook PUD s goal is to ensure your project worksite is as safe as possible for both the public and its employees. The High Voltage Overhead Line Safety Act in part states the following: TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-9

1.21.1 Restricted Space For lines rated between 600 volts and 50 kv, the restricted space extends 10 feet in all directions from the surface of the line or equipment. For lines rated over 50 kv, the restricted space extends 10 feet plus 0.4 inch for each 1 kv over 50 kv, or twice the length of the insulator (but never less than 10 feet) in all directions from the surface of the line or equipment. Typically, clearance for Tillamook PUD transmission lines is 12 ½ feet. 1.21.2 General Requirements Do not enter or perform any function or activity (such as handling, erecting, operating, transporting, and storing tools, equipment, materials, and moving a building or structure) within the restricted space surrounding an overhead highvoltage line or equipment unless proper notification is provided to Tillamook PUD and the line and/or equipment is deenergized and is visibly grounded by Tillamook PUD. If a violation occurs, Tillamook PUD will request a stop work order from the Tillamook County Community Development Department. Work will not be allowed to resume until an agreement is reached for construction to resume safely. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 1-10

Section 2 2 Temporary Service Overhead and Underground 2.1 General Temporary services for construction work shall conform to Tillamook PUD requirements and shall be located to provide protection to the meter and situated to be usable throughout the construction period. Location of the temporary service is to be approved by Tillamook PUD s Engineering Department prior to placement. Customer installations shall meet or exceed all provisions of the NEC, NESC, State of Oregon Electrical Specialty Code, other state, federal, and local applicable requirements, and Tillamook PUD requirements. Temporary services will be disconnected upon expiration of the building permit or when permanent service is installed. Once the customer has completed the Request for Electrical Services form, Load Data Sheet and Application for Service form (see samples in Appendix), an Engineering Field Representative will visit the site and work with the customer to determine the location of the temporary meter base and the route for the service lines. The following items must be completed before temporary service can be energized: Request for Electrical Services form (See samples in Appendix). Load Data Sheet (See sample in Appendix). Application for Service form (See sample in Appendix). Signed Line Extension Agreement, if applicable (See sample in Appendix). Providing payment, obtaining an approved loan application for the Line Extension Agreement, or signing a Reimbursable Work Order form, if applicable. (For information regarding the loan program, contact the Finance Department at 503-815-8636). Signing or obtaining required notarized signatures for easement(s) (if required). Easements will be prepared on Tillamook PUD easement forms and provide for the installation, operation, and maintenance of Tillamook PUD facilities. Obtaining applicable permits and inspections from appropriate public agencies. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 2-1

Notifying Tillamook PUD when the temporary meter base(s) has (have) passed electrical inspection ("orange tagged"). Providing, installing, and maintaining all equipment to meet Tillamook PUD specifications and policies. Keeping the meter base(s) visible and accessible per Tillamook PUD specifications and policies. Providing and maintaining a right-of-way clearing, if applicable, for overhead and underground installations in accordance with Tillamook PUD specifications and policies. (Refer to Section 8, Right-of-Way Clearing.) The location of the temporary post must be approved by the Tillamook PUD Engineering Department. 2.2 Temporary Overhead Service Figure 2-1 The customer shall install the temporary post, bracing, and associated meter base. Temporary services may not be placed on trees or Tillamook PUD poles. The meter base shall be UL listed, meeting NEC, NESC, and Tillamook PUD s specifications and policies as shown in Figure 2-1. Two-hundred amperes temporary service assemblies shall use galvanized rigid steel or rigid electrical conduit or Schedule 40 conduit. The placement of an overhead temporary meter base shall be within 15 feet of a power pole where secondary voltage is available. Temporary services shall be placed to avoid crossing overhead conductors, streets, and driveways. Taller temporary posts may be required if crossings cannot be avoided. 2.3 Temporary Underground Service Figure 2-2 Underground temporary services are available in those areas where existing electric facilities are underground. Placement of underground temporaries shall be within 3 feet of a secondary pedestal (see Figure 2-2). Conductor to serve a temporary WILL NOT be installed in the permanent conduit. The customer shall install the temporary post bracing with conduit, meter base, and ground rod. All trenching and backfilling shall meet Tillamook PUD specifications and is the responsibility of the customer. Conduit may or may not be required from the temporary post to Tillamook PUD s point of connection. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 2-2

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 2-3

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 2-4

Section 3 Overhead Permanent Service 3.1 General The requirements of this section are for residential and small commercial installations. For larger commercial or three-phase installations, contact Tillamook PUD Engineering Department. Once the customer has completed the Request for Electrical Service form, Load Data Sheet and Application for Service form (see samples in Appendix), an Engineering Field Representative will visit the site and work with the customer to determine the location of the meter base and the route for the overhead service lines. At that time, the service strike location on the building/structure shall be approved by Tillamook PUD Engineering Department. The following items must be completed as applicable before overhead permanent service will be energized: Request for Electrical Services form. (See samples in Appendix) Load Data Sheet (See sample in Appendix). Application for Service form. (See sample in Appendix) Signed Line Extension Agreement. (See sample in Appendix) Providing payment (or obtaining an approved loan application for the Line Extension Agreement or Reimbursable Work Order form). (For information regarding the loan program, contact the Finance Services Department at 503-815-8636). Signing or obtaining required notarized signatures for easement(s) (if required). Easements will be prepared on Tillamook PUD easement forms and provide for the installation, operation, and maintenance of Tillamook PUD facilities. Obtaining applicable permits and inspections from appropriate public agencies. Notifying Tillamook PUD when the meter base(s) has (have) passed electrical inspection ("green tagged"). Providing and installing all equipment to meet Tillamook PUD specifications and policies. Keeping meter base visible and accessible per Tillamook PUD specifications and policies. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 3-1

Providing and clearing a right-of-way for overhead installations in accordance with Tillamook PUD specifications and requirements. (Refer to Section 8, Right-of-Way Clearing.) Meeting or exceeding all applicable provisions of the National Electric Code (NEC); National Electrical Safety Code (NESC); State of Oregon Electrical Specialty Code; Tillamook PUD standards; and state, federal, and local applicable requirements. 3.2 Service Arrangements Figure 3-1 3.2.1 Service Mast The service mast for overhead 200- and 400-ampere services, whether flush- or surface-mounted, must extend through the roof a minimum of 36 inches. Service masts that extend more than 36 inches shall be guyed in a direction to resist forces. Two-hundred amperes service assemblies shall be a minimum of 2-inch galvanized rigid steel. Four-hundred ampere services shall use a minimum of 3-inch galvanized rigid steel. Service conductors shall protrude a minimum of 18 inches out of the weatherhead. The center of the meter socket shall be located between 4 ½ and 5 ½ feet above final grade. The customer shall be required to supply, install, and maintain meter-mounting equipment in accordance with Tillamook PUD s specifications and policies, NEC, and all applicable codes. All meter bases, masts, and weatherheads remain the property of the customer. 3.2.2 Meter Location The meter shall be located on the front or side of the structure closest to utility facilities. All meter locations shall be approved by Tillamook PUD Engineering Department before installation. If a meter is located on the side of a structure, it shall be placed within 10 feet of the front corner. For more specific information about meter location, refer to Section 6, Meter Locations. 3.3 Service on Gable End of Building Figure 3-2 Where conditions permit and upon approval of Tillamook PUD Engineering Department, a service mast may be installed on the gable end of a building. The minimum requirements are: The overhead service wire shall strike the building not less than 13 feet above the finish grade and shall meet all applicable clearance TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 3-2

requirements. A ⅝-inch eye bolt with 2¼-inch square washers is to be installed by the customer through a secure 2 by 4 or larger wooden member. The center of the meter is to be installed at 4 ½ to 5 ½ feet above the final grade. The eye bolt shall be positioned 22 inches to the side of and 8 inches below the weatherhead. The eye bolt may be furnished by Tillamook PUD. (See Figure 3-2.) Standard duty pipe straps shall be installed every 3 feet along the length of the service mast. The service mast must be galvanized rigid steel or Schedule 40 PVC electrical conduit. Minimum clearances around windows, above decks, etc., shall be 3 feet and meet or exceed all applicable provisions of the National Electric Code (NEC); National Electrical Safety Code (NESC); State of Oregon Electrical Specialty Code; and state, federal, and local applicable requirements. 3.4 200- and 400-Ampere Services to Mobile or Manufactured Home Service All efforts should be made to mount meter sockets on the structure. Exceptions may be approved by Tillamook PUD Engineering Department on a case-by-case basis. 3.5 Service Locations Manufactured Home A meter pole shall be located not more than 30 feet from the exterior wall of the manufactured home it serves. When exceptions are approved for meter poles, they shall be located along the front or along the side of the structure within 10 feet from the front corner. 3.6 Minimum Service Drop Clearances For minimum service drop clearances, contact Tillamook PUD Engineering Department. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 3-3

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 3-4

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 3-5

Section 4 Underground Permanent Service 4.1 General The requirements of this section are for residential and small commercial installations. For larger commercial or three-phase installations, contact Tillamook PUD Engineering Department. Once the customer has completed the Request for Electrical Service form, Load Data Sheet and Application for Service form (see samples in Appendix), an Engineering Field Representative will visit the site and work with the customer to determine the location of the meter base and the route for the underground service lines. The meter base location on the structure shall be approved by Tillamook PUD Engineering Department. The following items must be completed as applicable before underground service will be energized: Request for Electrical Services form. (See samples in Appendix.) Load Data Sheet (See sample in Appendix). Application for Service form. (See sample in Appendix) Signed Line Extension Agreement. (See sample in Appendix) Providing payment (or obtaining an approved loan application for the Line Extension Agreement or Reimbursable Work Order form). (For information regarding the loan program, contact the Finance Department at 503-815-8636). Signing or obtaining required notarized signatures for easement(s) (if required). Easements will be prepared on Tillamook PUD easement forms and provide for the installation, operation, and maintenance of Tillamook PUD facilities. Obtaining applicable permits and inspections from appropriate public agencies. Notifying Tillamook PUD when the meter base(s) has (have) passed electrical inspection ("green tagged"). Providing and installing all equipment to meet Tillamook PUD specifications and policies. Keeping meter base(s) visible and accessible per Tillamook PUD specifications and policies. Providing and maintaining a right-of-way for underground TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-1

installations in accordance with Tillamook PUD specifications and policies. (Refer to Section 8, Right-of-Way Clearing.) Meeting or exceeding all applicable provisions of the National Electric Code (NEC); National Electrical Safety Code (NESC); State of Oregon Electrical Specialty Code; Tillamook PUD standards; and state, federal, and local applicable requirements. Complying with all conduit and vault installation requirements specified in Section 5. 4.2 Locating Underground Facilities Before beginning to dig on any project, contact the locating service. There is no charge to the customer for this service. All underground utilities in the area will be located and identified. CALL BEFORE YOU DIG! 4.3 Meter Location The meter shall be located on the front or side of the structure closest to utility facilities. All meter locations shall be approved by Tillamook PUD Engineering Department before installation. If a meter is located on the side of a structure, it shall be placed within 10 feet of the front corner. For more specific information about meter locations, refer to Section 6, Meter Locations. 4.4 Meter Pedestal Arrangements Figure 4-3 The location of the meter pedestal shall be approved by Tillamook PUD Engineering Department. The meter pedestal may be a manufactured meter pedestal or a customer-assembled meter pedestal. (See Figure 4-3 for specifications and requirements and Section 6, Meter Locations, for additional information.) Compacted gravel or concrete backfill is required around the meter pedestal. The customer is responsible for trenching to meet Tillamook PUD specifications and requirements. Customer or customer s contractor TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-2

shall install all service conduit, install ½-inch mule tape or equivalent with a tensile strength of 1800 pounds or greater, and install Tillamook PUDprovided warning tape from the meter base to the secondary pedestal, pad-mount transformer, or pole, a minimum of 12 inches above the conduit. All backfilling must comply with Tillamook PUD s specifications. When a meter pedestal is located in or near a parking area, it must be located so that parked vehicles will not restrict meter accessibility or be damaged by vehicular traffic. The customer is responsible for all underground services beyond the metering point. Conduit installation must be inspected and approved by the Tillamook PUD Engineering Department prior to backfilling. For more specific information about meter pedestal arrangement, refer to Figure 4-3. 4.5 Single-Phase Service Arrangements Figures 4-1 and 4-2 The 2-inch Schedule 40 PVC in the case of 200-ampere service, or the 3- inch Schedule 40 PVC in the case of a 400-ampere service, shall be installed with either surface- or flush-mounted meter bases. The center of the meter socket is to be located 4 ½ to 5 ½ feet above final grade. The conduit must be placed through the footing wall for flush-mounted service arrangements or on the building exterior for surface-mounted service arrangements, with a 90-degree sweep, buried to a depth of 36 inches from final grade level to the top of the conduit (Refer to Section 5.5 Conduit Specifications for specific information). The location of the meter on the building and route of the trench shall be approved by Tillamook PUD Engineering Department. (Refer to Section 6, Metering for specific information.) The customer is responsible for trenching to meet Tillamook PUD specifications and requirements. Customer or customer s contractor shall install all service conduit, install ½-inch mule tape or equivalent with a tensile strength of 1800 pounds or greater, and install Tillamook PUDprovided warning tape from the meter base to the secondary pedestal, pad-mount transformer, or pole, a minimum of 12 inches above the conduit. All backfilling must comply with Tillamook PUD s specifications. Conduit installation must be inspected and approved by Tillamook PUD Engineering Department prior to backfilling. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-3

4.5.1 Travel Trailer Service Installations shall be on post-mounted meter socket or main, or a mobile home pedestal. Exceptions may be granted by Tillamook PUD Engineering Department. Refer to Figure 4-3. 4.5.2 Manufactured or Mobile Homes Manufactured or mobile home meter pedestals shall be located within 30 feet of the manufactured or mobile homes. All meter locations shall be approved by Tillamook PUD Engineering Department. 4.6 Three-Phase Service Arrangements The point of delivery from a pad-mounted transformer shall be the secondary bushings of the serving transformer, unless a better point of delivery is designated by Tillamook PUD Engineering Department. The customer shall provide secondary wire and two hole compression lugs at the transformer. The point of delivery for an underground service from an overhead assembly shall be a splice vault or pedestal near the base of the pole, unless a better point of delivery is designated by Tillamook PUD Engineering Department. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-4

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-5

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-6

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 4-7

Section 5 Trenching, Conduit, and Vault Specifications 5.1 Trenching Requirements Figures 5-22 and 5-23 Table 5-1 depicts general requirements for trenching. Refer to Figure 5-22 or contact Tillamook PUD Engineering Department for further information. ALL exceptions must be approved by Tillamook PUD Engineering Department. Table 5-1 Trenching Requirements DEPTH Requirement PLACEMENT IN TRENCH Primary Voltage Conduit 48-inches deep, measured from top of conduit. Center and bottom of the trench. Secondary Voltage Conduit 36-inches deep, measured from top of conduit. Either on the right or left side of trench and on the bottom. LAYOUT WARNING TAPE Trench path must be approved by Tillamook PUD Engineering Department. Installed at a minimum of 12-inches above electrical conduit. JOINT TRENCHES TELEPHONE AND TELEVISION CABLES 12-inches above electric service, placed on the right or left side of trench. Refer to Figures 5-22 and 5-23 for specifications. Placed on the right or left side of trench. Refer to Figures 5-22 and 5-23 for specifications. WATER, SEWER AND GAS Water, Sewer, or Gas shall not be in the same trench with electrical. For crossings, electrical will be located below all water, sewer and gas lines with a minimum 2-foot horizontal and 2-foot vertical separation. Exceptions: All exceptions must be approved by Tillamook PUD Engineering Department TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-1

5.2 Backfill A selected earth cushion around conduits is required. Final backfill shall be done on all conduit installations following inspection by Tillamook PUD Engineering Department. Complete backfill and compaction shall be done before energization of the electrical system. 5.3 Locating Underground Facilities Before beginning to dig on any project, contact the locating service. There is no charge to the customer for this service. All underground utilities in the area will be located and identified. CALL BEFORE YOU DIG! 5.4 Conduit Installation Requirements The customer is responsible for providing and installing all conduit. No elbows or bends will be allowed in the wall between the bottom of the meter base and the bottom of the trench. When conduit will be placed into an existing energized vault or secondary pedestal, contact Tillamook PUD Operations Department at 503-842-2122 or 1-800-842-2122 to arrange for Tillamook PUD personnel to be onsite. The customer is responsible for ensuring that the conduit installations are inspected and approved by Tillamook PUD Engineering Department prior to backfill. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-2

Table 5-2 Conduit Installation Requirements DEPTH Requirement CEMENT PVC MATERIALS CEMENT HDPE MATERIALS PATH OR LAYOUT PULL ROPE CAPPING AND MARKING CONDUIT ENDS CONDUIT RUNS INSPECTIONS OF INSTALLATIONS CONDUIT INSTALLATION INTO VAULTS WARNING TAPE Primary Voltage Conduit 48-inches deep, measured from top of conduit. All weather Rain-R-Shine PVC Cement (No. 30891, blue medium) or equivalent. Secondary Voltage Conduit 36-inches deep, measured from top of conduit. BonDuit Conduit Adhesive (No. 30891, blue medium) or equivalent, or other methods approved by Tillamook PUD Engineering Department. The path of the trench or conduit layout must be approved by Tillamook PUD Engineering Department prior to installation. ½-inch mule tape with a tensile strength of 1800 pounds or greater. All conduit ends shall be capped and plugged to eliminate dirt, rocks, and other material from entering the conduit. When conduit is to be extended at a later time, a Tillamook PUD-supplied, red warning, fiberglass sign shall be placed at the end of the conduit to facilitate its future uncovering. Continuous conduit runs shall not have more than a total of 270 degrees in angle between the connection to the Tillamook PUD system and the customer s facility. Conduit installations must be inspected and approved by Tillamook PUD prior to backfill. Vaults See Figure 5-20. 200-amp service 400-amp service See Figure 5-21. See Figure 5-21. Tillamook PUD-provided warning tape must be placed a minimum of 12-inches above electrical conduit. Note: When conduit will be placed into an existing energized vault or secondary pedestal, contact Tillamook PUD Operations Department at 503-842-2122 or 1-800-842-2122 to arrange for Tillamook PUD personnel to be onsite. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-3

5.5 Conduit Specifications Conduits identified in Table 5-3 are acceptable, or Tillamook PUDapproved equivalent. Table 5-3 Conduit Specifications Schedule 40 PVC For Schedule 40 PVC with integral bell ends, meeting: UL Standard 651 NEMA TC-2-1978 Federal Specification WC-1094A 2-inch Description Catalog No. 2-inch I.D.; wall thickness, 0.154 inches Carlon No. 49011 or equivalent Size 36" radius 48" radius 90-degree sweep (36 or 48 radius) UA9FJBR UA9HJBR 45-degree sweep (36 or 48 radius) UA7FJBR UA7HJB 30-degree sweep (36 or 48 radius) UA6FJB UA6HJB 22½-degree sweep (36 or 48 radius) UA5FAJB UA5HJB 3-inch Description 3-inch I.D.; wall thickness, 0.216 inches Catalog No. Carlon No. 49013 or equivalent Size 36" radius 48" radius 90-degree sweep (36 or 48 radius) UA9FLBR UA9HLBR 45-degree sweep (36 or 48 radius) UA7FLBR UA7HLB 30-degree sweep (36 or 48 radius) UA6FLB UA6HLB 22½-degree sweep (36 or 48 radius) UA5FLB UA5HLB 4-inch Description 4-inch I.D.; wall thickness, 0.237 inches Catalog No. Carlon No. 49015 or equivalent Size 36" radius 48" radius 90-degree sweep (36 or 48 radius) UA9FNBR UA9HNBR 45-degree sweep (36 or 48 radius) UA7FNBR UA7HNB 30-degree sweep (36 or 48 radius) UA6FNB UA6HNB 22½-degree sweep (36 or 48 radius) UA5FNB UA5HNB 5-inch Description Catalog No. Carlon No. 49016 or equivalent Size 48" radius 60" radius 5-inch I.D. or 6-inch I.D.; wall thickness, 0.258 inches 90-degree sweep (48 or 60 radius) UA9HPB UA9IPB 45-degree sweep (48 or 60 radius) UA7HPB UA7IPB 30-degree sweep (48 or 60 radius) UA6HPB UA6IPB 22½-degree sweep (48 or 60 radius) UA5HPB UA5IP 6-inch Description Catalog No. 6-inch I.D.; wall thickness, 0.280 inches Carlon No. 49017 or equivalent Size 48" radius 60" radius 90-degree sweep (48 or 60 radius) UA9HRB UA9IRB TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-4

45-degree sweep (48 or 60 radius) UA7HRB N/A 30-degree sweep (48 or 60 radius) UA6HRB UA6IRB 22½-degree sweep (48 or 60 radius) UA5ARB UA5IR Conduits identified in Table 5-4 are acceptable, or Tillamook PUDapproved equivalent. Table 5-4 Conduit Specifications HDPE For HDPE ETL Schedule 40, meeting: UL Standard 651B ASTM F2160 NEMA TC-7 2-inch Description Color: Black with red stripes 3-inch Description Color: Black with red stripes 5-inch Description Color: Black with red stripes 6-inch Description Color: Black with red stripes Catalog No. Carlon U13C4N1A3KB1000 or equivalent Catalog No. Carlon U15C4N1A3KB500 or equivalent Catalog No. Carlon U18C9N1A3KA550 or equivalent Catalog No. Carlon U22C9N1A3KA450 or equivalent 5.6 Vault Installation The customer is responsible for trenching to meet Tillamook PUD specifications and requirements. Customer or customer s contractor shall provide and install all vaults, service conduit, install ½-inch mule tape or equivalent with a tensile strength of 1800 pounds or greater, and install Tillamook PUD-provided warning tape, a minimum of 12 inches above the conduit. All backfilling must comply with Tillamook PUD's specifications. Vaults shall be leveled upon installation. A minimum of a 6-inch gravel base below the vault is required to provide drainage for the vault. Vault lids shall not be sealed to the vault. Tillamook PUD will require customers to remedy any deviations from Tillamook PUD specifications. Deviations may delay scheduling of installation. Refer to applicable figures for individual specifications. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-5

Vault lids shall not be sealed to the vault. Conduits shall extend through the vault walls a distance of 4-inches with a minimum of 2-inch separation between conduits. Bell ends are not allowed for vault penetration. Conduit penetration is to be sealed from the outside. Tillamook PUD will indicate appropriate knockouts to be used prior to installation. Grout shall be used to patch and seal the holes in the vault created for the installation of the conduits. Conduits shall be perpendicular to the wall. 5.7 Vault Purchase It is best for the conduit installer to remove the knockouts from the inside of the vault. Vaults may be purchased from Oldcastle Precast / Utility Vault or other suppliers of vaults that meet Tillamook PUD vault specification requirements. Oldcastle Precast / Utility Vault 28499 SW Boberg Road PO Box 323 Wilsonville, OR 97207 Telephone: 503-682-2844 Toll Free: 800-967-3551 Website: www.uvwilsonville.com 5.8 Vault and Lid Specifications The following is a list of approved vaults and lids to be used in primary and secondary underground installations. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-6

Table 5-5 Single-Phase Installations Vault and Lid Specifications Vault E-11 Inside Dimensions: 50" x 50" x 37" deep Lid No. Use Description CE-11T CE-11S CE-11SE CE-19SE 1PH Transformers Splice Vault Sectionalizing Sectionalizing 56 x 56 with 21 x 25 B.O. 56 x 56 with 36 x 36 galvanized door 56 x 56 with 12 x 26 B.O. and 30 x 30 galvanized door 60 x 79 with 12 x 26 B.O. and 24 x 36 galvanized door Oldcastle Precast/ Utility Vault No. 504-LA (Figure 5-3) Oldcastle Precast/ Utility Vault No. Table 5-6 Three-Phase Installations Vault and Lid Specifications Vault E-19 Inside Dimensions: 66" x 42" x 38" deep Spec Sheet 55-2125 Fig. 5-4 55-332P Fig. 5-5 55-3030P-1226 Fig. 5-6 6079-2436P-1226 Fig. 5-11A Oldcastle Precast/ Utility Vault No. 644-LA (Figure 5-7) Lid No. Use Description Oldcastle Precast/ Utility Vault No. Spec Sheet CE-19T <1000 kva Transformers 56 x 80 with 15 x 60 B.O. 64-1560 Fig. 5-8 48 x 72 with 36 x 36 CE-19S CE-19SE CE-19-1500 Splice Sectionalizing >1000 kva Transformers galvanized Door 64-332P Fig. 5-9 60 x 79 with 12 x 56 B.O. and 24 x 36 6079-2436P-1256 Fig. 5-11B 90 x 80 x 6 with 17 x 65 B.O. 8090-1765 Fig. 5-12 For information regarding specialized vaults not listed in the preceding tables, contact Tillamook PUD Engineering Department. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-7

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-8

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-9

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-10

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-11

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-12

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-13

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-14

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-15

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-16

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-17

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-18

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-19

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-20

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-21

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 5-22

Section 6 Metering 6.1 General The information contained in this section is intended to serve as a guide for customers and is not intended to address all metering requirements. Prior to beginning any work, contact Tillamook PUD Engineering Department for the requirements of your project and to obtain approval of your metering equipment. The customer shall supply, install, and maintain all meter equipment and facilities to meet or exceed Tillamook PUD specifications except the following: Meter Current transformers (CTs). (Except for switch gear or switch board applications ) Test switches CT metering wire All meter bases, masts, CT enclosures, and weatherheads are the property of the customer. Metering shall not be mounted on Tillamook PUD padmount transformers. Meter bases shall be mounted plumb and be securely fastened to the structure or wall to withstand forces of installation or removal of the meter. Tillamook PUD requires ring-type meter bases. Link-style, manual bypass devices shall be required for residential services with meter base capacity in excess of 200 amperes and all commercial applications. Conduit runs from CT enclosures to the meter base shall be galvanized, rigid conduit, and be limited to 50 feet. The minimum conduit size will be 1 inch. Meter bases with automatic circuit-closing devices are prohibited. The line supply conductors to a meter base shall be connected to the top or left terminals; and the load supply conductors shall be connected to the bottom or right terminals. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-1

The customer shall provide sufficient access at all times in an area free of stored materials and exercise proper care to protect Tillamook PUD property on customer premises. In the event of loss or damage to Tillamook PUD property on the customer s premises arising from neglect, carelessness, or misuse, the cost of necessary repairs or replacement will be billed to the customer. 6.2 Energizing the Service When a Tillamook PUD representative arrives to initially connect a new service, access is required to the main electrical panel in order for the service to be energized. Service will not be connected until the following criteria have been met: 6.3 Meter Locations An approval sticker issued by the state electrical inspector is attached to the meter base. The main breaker is turned off. The panel cover is installed. The customer must comply with the following items regarding meter location: Customers desiring service must obtain Tillamook PUD's approval of the meter locations prior to wiring the premises. Residential and small commercial meters shall be installed outdoors at a location readily accessible for reading, testing, and replacement. The meter shall be located on the front or side of the structure closest to utility facilities unless an alternate location is approved by Tillamook PUD Engineering Department. If the meter is located on the side of the structure, it shall be placed within 10 feet of the front corner. A meter installed in an alley or driveway shall be recessed in the wall or protected adequately to prevent damage from vehicular traffic. Refer to Figure 6-9. Meters shall not be located on porches, in carports, in garages, dog runs, kennels, over window wells, steps in stairways or stairwells, or other unsafe locations. The meter must be free from vibration. The meter location shall not be within a corrosive atmosphere. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-2

The meter shall not be located in an area with abnormal temperatures. The equipment shall be protected from damage. Permanent walking access to meters and equipment shall be provided and maintained by the customer. When a meter pedestal is located in a parking area, it must be located so that parked vehicles will not restrict meter accessibility or be damaged by vehicular traffic. Multiple unit buildings shall use grouped or ganged meters and shall install permanently engraved placards on the meter base for meter-to-structure identification. Multiple services on a property shall install permanently engraved placards on the meter base for meter-to-structure identification. When county regulations specify the meter base be located above the flood plain (more than 6½ feet above the ground), a permanent step or landing (a minimum of 4 feet by 4 feet) must be installed below the meter base for accessibility of reading and routine maintenance. The platform must be accessible by a permanent stairway, which conforms to OSHA regulations. Exceptions to any of the above requirements must be approved by Tillamook PUD Engineering Department. 6.3.1 Grouped Meter Locations Installation of six meters or less shall be on the outside wall of a building and shall be grouped in such a manner that a singleservice feed will serve all meters. Meter bases shall have permanently engraved placards on each meter base for meterto-unit identification. 6.3.2 Metering Rooms The installation of seven or more meters may be located in a dedicated metering room with 24-hour accessibility by Tillamook PUD. Meter bases shall have permanently engraved placards on each meter base for meter-to-unit identification. When a metering room is to be used, a floor plan showing the location of all proposed and existing equipment shall be submitted to Tillamook PUD for approval prior to any wiring. All meters shall be grouped on a common wall. The metering room shall be dedicated and secured for electrical equipment and never used for storage. The only access to the metering room shall be from the exterior of the building via a solid-core door with minimum dimensions TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-3

of 2 feet 8 inches by 6 feet 8 inches. The access door shall be installed such that it will not make contact with the meters or other electrical equipment. Doors must open outward and be equipped with a "panic bar." The locking system shall not allow common access to unauthorized individuals. The customer shall install a sign on the exterior of the door which reads, "Metering Room." For complexes which have multiple buildings, the building number or name shall be permanently engraved on the placard with lettering a minimum of 2 inches in size. Telephone and cable television terminal equipment may occupy this metering room provided they do not interfere with the electrical equipment; each may have its own provision for access. The metering room shall be illuminated by permanent fixture(s) providing a minimum of 10 foot candles per square foot with a switch located inside the door next to the latch side of the door. Water, gas, sewer, fire sprinkler, and drain pipes shall not terminate or pass through the metering room. Proper drainage will be required when there is a possibility of standing water. 6.4 Sealing and Locking Requirements At the time of installation, the meter base and/or raceways containing unmetered conductors or busbars shall be sealed. Unused threaded openings and knockouts in enclosures must be fitted with an approved plug locked in place from the inside. Meter seals are placed on meters and associated service equipment to prevent injury and tampering. Seals are not to be removed except by Tillamook PUD personnel. Broken seals are justification for Tillamook PUD to initiate a theft-of-service investigation. All Tillamook PUD seals shall be readily visible without having to open or remove any covers or panels. Seal tabs designed to accommodate lead meter seals are not acceptable. CT enclosures shall have padlocking provisions that are an integral part of the door. Service entrance equipment shall be arranged such that metered circuit conductors or busbars do not enter or pass through raceways, enclosures, or conduits containing unmetered circuit conductors or busbars. Refer to Figure Nos. 6-4, 6-5, 6-6, and 6-7. EXCEPTION: That portion of service load-side conductors or busbars exiting the meter base or current transformer enclosure. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-4

6.5 Clearances All meters shall be readily accessible. Working space in front of meters or metering equipment shall not be less than 36 inches, measured from the front of the meter glass. The height in this area shall not be less than 8 feet above the finished grade, floor, or working platform. The platform must be accessible by a permanent stairway which conforms to OSHA regulations. Working space behind freestanding switchboards shall not be less than 36 inches from the panels or the rear wall with a provision for safe exit. Electric meters shall be installed a minimum of 3 feet from natural gas meters and 10 feet from propane regulators (NFPA 58). Measurement shall be from edge to edge in accordance with the requirements from the following references: National Electrical Safety Code (NESC), IEEEC2-2007. National Electrical Code (NEC), NFPA 70-2002. Flammable & Combustible Liquids Code, NFPA 30-1996. Standard for the Production, Storage & Handling of Liquefied Natural Gas, NFPA 59A-1994. 6.6 Meter Base Requirements 6.6.1 Self-contained meter bases Minimum self-contained meter base dimensions shall be: Depth: Width: Height: 4 inches 10½ inches 14 inches Exceptions must be approved by Tillamook PUD Engineering Department prior to installation. Conduits entering underground meter bases shall not enter the center of the bottom of the meter base, but shall be located to one side to provide conductor clearance. 6.6.2 CT meter bases Minimum CT meter base dimensions shall be: Depth: Width: Height: 4 inches 10 inches 20 inches Exceptions must be approved by Tillamook PUD Engineering Department prior to installation. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-5

CT metering arrangements require ring-type meter bases with test switch provisions. The test switch shall be located behind a sealable panel. See Figure 6-11. When aluminum conductors are used, the meter base must be UL-listed or approved and clearly marked by the manufacturer that it is acceptable for aluminum conductor. The neutral service conductor shall be bonded to the meter base using the grounding screw or bonding terminal. The neutral service conductor may be continuous from the weatherhead through the meter base to the service panel or disconnect. Figure 6-11 Ring-type Meter Socket with Test Switch Provision Minimum Socket Dimensions TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-6

6.7 Self-Contained versus CT Metering Table 6-1 Self-Contained versus CT Metering Requirements Service Entrance Metering Conductor Ampacity Equipment SINGLE PHASE manual link bypass, as required 400 amps and less Self-contained 401 600 amps CT rated with CT enclosure NOTE: Single-phase service is not available for greater than 600 amps. THREE PHASE (Requires bypass links and safety socket) 200 amps and less Self-contained 201 800 CT rated with CT enclosure Greater than 800 amps Switchboard mounted CTs 6.8 Current Transformer Enclosures A CT enclosure is a separate enclosure, furnished and installed by the customer, which contains a prefabricated bracket to terminate the supply and load conductors and for mounting the CTs. CT enclosures shall be UL-approved. CT enclosures in wet locations shall be rain-tight (NEMA 3R); stainless steel is recommended. The CT enclosure door shall be lockable with a padlock and utilize factoryinstalled side hinges for side opening. Locking provisions shall be an integral part of the door for installation of Tillamook PUD locks. The door on CT enclosures shall not be used for mounting meter(s) or other equipment. Refer to Figure 6-10. Table 6-2 CT Enclosure Minimum Dimensions Service Entrance Conductor Ampacity Single-phase service 401-600 amps 36" x 36" x 11" Minimum Dimensions (W x H x D) NOTE: Service equipment in excess of 600 amps shall be three-phase service. Three-phase service 201 599 amps 36" x 36" x 11" 600 800 amps 48" x 48" x 11" Above 800 amps Consult Tillamook PUD Engineering Dept. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-7

Prefabricated brackets shall be installed in CT enclosures for terminating conductors and mounting CTs. The brackets shall meet the requirements specified in Figures 6-8A and 6-8B specifically for (Single phase CTs: Equipment Utility Service Requirements Committee [EUSERC] Drawing No. 328A, 328 B and for three-phase CTs: EUSERC Drawing No. 329A, 329B). For EUSERC 328A and 329A, the customer shall supply NEMA 2-hole lugs. Services rated 400 to 600 amp shall be limited to 2 runs of service conductor. Services rated 800 amp shall be limited to 3 runs of service conductor and customer shall supply offset style lugs. Spacers are not allowed. CT enclosures shall be grounded. The mounting height of CT enclosures shall be limited such that the top of the enclosure shall not be more than 8 feet above the floor or working platform of same unless exception is specifically permitted by Tillamook PUD. The minimum height shall be 2 feet above the floor or working platform level. Enclosures shall not be mounted in or under floor crawl spaces. CT enclosures shall be mounted on the outside walls of buildings. Other locations require prior written approval by Tillamook PUD Engineering Department. The CT enclosures shall contain only the CTs and associated equipment. The CT enclosure shall not be used as a junction box for other wires or conduits. 6.9 Current Transformer Installation Tillamook PUD will provide bar or perch-type CTs. The customer shall connect the load side service conductors to the load side of the CT mounting brackets using customer-supplied connectors. Refer to Figure Nos. 6-4, 6-5, 6-6, 6-7A and 6-7B. The customer shall install the CT enclosures. Tillamook PUD will provide and install the CTs, test switch, CT wires and meter. In cases of switch board and switch gear installations, Tillamook PUD will provide perch mounted CTs for perch mounted installations. 6.10 Current Transformer Conduit Only CT wires shall be allowed in CT conduit. The customer shall provide and install conduit for the metering conductors between the meter base and the CTs. A minimum of 1-inch galvanized rigid conduit is required; no opening condulets or flex will be permitted. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-8

CT enclosures must be connected to the meter base or meter enclosure with conduit and shall be bonded by approved methods. A minimum of 1-inch galvanized rigid conduit is required; no opening conduit bodies or flex is permitted. The customer is responsible for providing and installing ½ inch mule tape between the CT can and the CT meter base. 6.11 Instrument Transformer Rated Meter Worksheet (See Appendix A) The customer is to provide the meter base, conduit, and CT enclosures in accordance with the Instrument Transformer Rated Meter Worksheet (See Appendix). No automatic circuit-closing devices are allowed on any services. For services in excess of 480 volts, consult Tillamook PUD Engineering Department for metering requirements. 6.12 Current Transformer Switchboard Metering On all services 801 amps and above, the perch type CTs shall be installed in all switchboards and switch gear by the customer All services installed in switchboards and switch gear shall be metered with perch type CTs for installation on removable bus sections in the customer s switchboards. This compartment shall be lockable using a padlock. The customer shall submit one copy of switchgear drawings to Tillamook PUD for approval and determination of the type of meter or meters that will be used, type, and size of CTs, and arrangements for mounting prior to the manufacture of the switchgear. Switchboards shall conform to EUSERC standards. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-9

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-10

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-11

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-12

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-13

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-14

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-15

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-16

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-17

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-18

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-19

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 6-20

Section 7 Area Lights 7.1 General Tillamook PUD provides area lighting and public street lighting for customers located within Tillamook PUD s service territory. Currently, the lights provided are dark-sky compliant fixtures in standard output LED and high output LED sizes. Lighting provided by developers must meet Tillamook PUD specifications and policies. To request area lighting, contact Tillamook PUD Engineering Department. Once the necessary information is received, a Tillamook PUD Engineering Field Representative will visit the proposed location to determine if existing facilities are adequate or if additional facilities will be required to serve the light (poles, conductor, or transformers). If additional facilities are required to serve the light installation, costs will be at the customer s expense as specified in Tillamook PUD Policy Bulletin 4-2. Tillamook PUD requires the customer sign a one-year contract obligating payment of a monthly service fee. The customer shall allow Tillamook PUD free access to the customer s property to inspect and maintain the equipment or to remove the installation upon termination of service. The customer shall exercise care to prevent damage to lighting fixtures. Every effort shall be made to minimize the impact of light pollution on neighboring properties. The customer shall not place customer-owned area lighting on Tillamook PUD-owned poles. The customer has the option of providing and installing an area lighting system, provided service to these electrical facilities is connected behind an approved disconnect. The monthly billing of customer-owned area lighting will be a flat rate schedule based on the connected load. Ownership and maintenance of the complete lighting system behind the approved disconnect will remain the responsibility of the owner. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 7-1

Section 8 Right-of-Way Clearing 8.1 Customer Requirements Figures 8-1, 8-2, and 8-3 The customer is required to provide all right-of-way clearing when a new service is established. It is imperative that Tillamook PUD employees can quickly locate existing electrical facilities and have adequate space to safely serve those facilities. Tillamook PUD s requirements for right-of-way clearances are listed below: Table 8-1 Right-of-Way Clearances Overhead Primary Service Type of Service Required Right-of-Way Pole Line (Cleared Each Side of Pole) Three-phase 40' wide 20' wide Single-phase 20' wide 10' wide Overhead Secondary Service Secondary 10' wide 5' wide NOTE: Tillamook PUD may require additional clearing of danger trees outside the right-of-way. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 8-1

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 8-2

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 8-3

TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 8-4

Section 9 Generation Permanent and Temporary 9.1 Generator Safety When any of the types of generation systems defined below are used, they must be isolated from Tillamook PUD facilities to prevent serious danger to Tillamook PUD personnel and damage to customer property. To assure the safety of Tillamook PUD personnel and to avoid potential damage to customer property when portable generators are used, all electricallyoperated devices shall be connected directly to the portable generator or approved transfer switch. Never overload the generator. Always operate the generator in accordance with the manufacturer s recommendations. Never attempt to power the house wiring by plugging the generator into a wall outlet, a practice known as backfeeding. This is an extremely dangerous practice that presents an electrocution risk to utility workers and neighbors served by the same utility transformer. Backfeeding also presents a serious risk of damaging the generator, owner s property, and neighboring properties. It also bypasses some of the built-in household protection devices. Never operate the generator inside your home. Good ventilation is important. Generators produce carbon monoxide, a colorless, odorless, toxic gas that can result in serious injuries, or even death, if levels become too high. 9.2 Portable Generators The simplest way to use a portable generator is to plug appliances directly into the generator. A heavy-duty, outdoor-rated extension cord can be used but it should be rated (in watts or amps) at least equal to the sum of the connected appliance loads. 9.3 Fixed Generators The only approved method to connect a generator to building wiring is by having a qualified electrician install a transfer switch. The transfer switch is installed between the generator and the electrical panel. It allows power to be fed from only one source at a time. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 9-1

This switch must be installed in accordance with the National Electrical Code (NEC), which is published by the National Fire Protection Association, and all applicable state and local electrical codes. An electrical permit must be obtained from the Tillamook County Department of Community Development and the installation must be inspected and approved by the Oregon State Electrical Inspector prior to operation. TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS 9-2

Appendix

Work Order No.: TILLAMOOK PEOPLE'S UTILITY DISTRICT LINE EXTENSION AGREEMENT The Tillamook People's Utility District, hereinafter referred to as "District", and the Undersigned mutually agree to the terms and conditions set forth below: District hereby agrees to construct and maintain all electric lines, facilities, machinery, and apparatus which the District determines to be required for the delivery of electricity to the point of delivery, approved by the District. Installation, construction, and maintenance of the above shall be under the complete control of the District. The undersigned acknowledges that all electric lines, machinery, and facilities on the source side of the point of delivery which may be required shall become the sole property of District. Before completion of construction and all connections, Undersigned shall not assign any rights hereunder without District's prior written consent. The covenants, conditions, and terms of this agreement shall be binding upon Undersigned, Undersigned's assigns, successors, heirs, and personal representatives. This connection may require service be provided undersigned by way of a temporary connection. For this connection, as well as for the permanent connection, undersigned hereby grants District an easement and, in this regard, undersigned shall sign such additional documents as District may reasonably require. The District estimates that the cost for 1 connection(s) to be served under this Agreement shall be $ dollars to be paid prior to the commencement of construction. This estimate is valid for 180 days from [ENTER ESTIMATE LETTER DATE], and all electric lines, facilities, machinery, and apparatus for this connection must be installed within this 180-day period or the Agreement and estimate become null and void. New estimates will be prepared using policies in effect at the time the new estimate is prepared. The estimate does not include PUD account processing fee(s) which will appear on first month's electrical bill. The Undersigned shall receive reimbursement from subsequent permanent service connections made to this line extension provided that Undersigned's investment is over $5,000 dollars and provided the subsequent extensions are made within five (5) years of the execution of this agreement. Such reimbursements shall be applied first to the loan balance of the Undersigned in the event this line extension is financed through the District. The amount of reimbursement will be calculated in accordance with District's Policy Bulletin 4-2. Reimbursements are not allowed for additional connections off developer extensions, or the permanent service for area or street lighting purposes, or for approved attachments by licensees of the District. At all times, District shall have complete right of inspection, ingress, and egress, rights-of-way, and all easements necessary for the line extension work. The District reserves the right to interrupt service without notice for any reason, including but not limited to repair or inspection of any aspect of the District's electrical system. The undersigned agrees to hold from any damage, loss, or injury to persons or property resulting from any outage, interruption of service, or deviation in power quality not caused by the willful and intentional fault of the District. Undersigned shall abide by, perform, and be subject to all laws, rules, regulations, ordinances, and policies, now or hereafter enacted by District and all federal, state, county, and city governmental bodies and agencies thereof, with particular reference herein made to District Policy Nos. 4-2, 4-7, and 4-13. UNDERSIGNED HEREBY ACKNOWLEDGES THAT UNDERSIGNEDs HAS BEEN PROVIDED AN OPPORTUNITY FOR REVIEW OF THE ABOVE POLICIES, WHICH ARE BY THIS REFERENCE MADE A PART OF THIS AGREEMENT. On default by the Undersigned for any reason of this agreement, any policy of the District or any other agreement or obligation, the District may stay further construction, maintenance, and service to the Undersigned until such default is cured. Upon ten (10) days written notice of default by District and Undersigned's failure to cure such default within said period of time, District may terminate this agreement and all service to Undersigned, without waiver of its right to collect any sum in damages owned to it by Undersigned. Assertion or non-assertion of any rights and remedies by District shall not be a waiver of any rights or remedies. All previous communications between the parties hereto, either verbal or written, with reference to the subject matter of this agreement are hereby abrogated and this agreement shall constitute the complete agreement between the parties. Undersigned represents, warrants, and covenants that Undersigned is (are) the sole owner(s) in fee simple and all necessary persons having any right, interest, claim or lien therein have executed this agreement except: SAMPLE The parties hereto have executed this agreement in on the dates noted below. UNDERSIGNED TILLAMOOK PEOPLE'S UTILITY DISTRICT Date: Date: FOR DISTRICT OFFICE USE ONLY Total Paid: Actual Job Cost: Reimbursement: Amt. Reimbursed: Tap-off WO#: Date Connected: TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS

TILLAMOOK PEOPLE'S UTILITY DISTRICT REIMBURSABLE WORK ORDER FORM (T-8) DATE: [DATE] WORK ORDER NO.: [WO#] CUSTOMER NAME AND MAILING ADDRESS: [NAME] [ADDRESS] [CITY/STATE/ZIP] DESCRIPTION OF WORK TO BE PERFORMED: [SCOPE OF WORK] ================================================================== ESTIMATED JOB COST: $ [AMOUNT] 10% CONTINGENCY: $ [AMOUNT] TOTAL ESTIMATE: $ [AMOUNT] ================================================================== ATTENTION: Pursuant to District Policy 4-5 (attached), this cost estimate is being submitted for your consideration and signature. This estimate is based on standard billing rates for man-hours, materials, equipment, associated District overhead expenses, and a 10 percent contingency. A refund, if greater than $100.00, will be issued in the event the actual cost of construction is less than the estimated cost. SAMPLE The cost estimate is valid for 180 days and construction must be completed during the 180-day period. This estimate is valid for 180 days from the date of this letter. All electric lines, facilities, machinery, and apparatus for this connection must be installed within this 180-day period or the estimate becomes null and void. New estimates will be prepared using policies in effect at the time the new estimate is prepared. The estimated cost must be paid prior to the start of construction. SIGNATURE DATE PRINTED NAME TITLE ================================================================== ACTUAL JOB COST: $ ================================================================== TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS

7,//$022. 3(23/( 6 87,/,7< ',675,&7 $33/,&$7,21 )25 (/(&75,& 6(59,&( 5(6,'(17,$/ Primary Applicant First Name: Last Name: SS#: Date of Birth: DL#: Email: Home Phone: Employer: Mobile Phone: Alt. Phone: M PL E State: Additional Applicant First Name: Last Name: SS#: Date of Birth: DL#: Email: Home Phone: Employer: Mobile Phone: Alt. Phone: State: Address Information Service Address: City: City: Zip: SA Mailing Address: State: OR State: Zip: Please provide electric service to the service address noted. By signing this application, I understand that I am responsible for payment for service. I will abide by the policies of the district and will advise you when to discontinue service. I understand that a soft credit check will be performed on each applicant, and that a deposit may be required as a condition of service. Tillamook PUD policies are available for review upon request. Primary Applicant Signature: Date: Additional Applicant Signature: Date: *****TPUD USE ONLY BELOW THIS LINE***** TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS

Customer Certification Engineering Department 503-815-8629 REQUIRED INFORMATION Applicant Information (Please print full, legal name, or business name) Owner Information Project Information Name: Mailing address: City / State / ZIP: Daytime Phone: Cell Phone: Assessor Parcel No.: TOWNSHIP: RANGE: SECTION: TAX LOT: Service address: City: Customer Certification I certify that the information provided on the attached request form is accurate and complete to the best of my knowledge; and that I own, lease, or have a contract to purchase the property or premises referenced in the attached request for service, or I have been authorized by the owner or lessee to complete this request on their behalf. Plan of Service and Load Requirements My signature below indicates my acknowledgement that I am required to notify Tillamook PUD- Engineering if load requirements at this service location change significantly. Tillamook PUD conducts routine inspections and monitoring; if load measurements consistently exceed PUD equipment ratings, I will be contacted and could be responsible for the cost of any damages and/or upgrades deemed necessary to ensure the safety and protection of utility equipment and personnel. Applicant s Signature: Date: SAMPLE SUBMIT COMPLETED CERTIFICATION AND SERVICE REQUEST FORMS TO: PO BOX 433; TILLAMOOK, OR 97141 FAX TO: 503-815-8648 EMAIL: engineering-requests@tpud.org TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS

Request for New Electrical Service Residential Service Engineering Department 503-815-8629 REQUIRED INFORMATION Applicant Information (Please print full, legal name or business name) Temporary service: Name: Name and address of party Mailing address: responsible for temporary City / State / ZIP: service billing? Daytime Phone: Cell Phone: Email address: Permanent service: Name: Same as above Name and address of party Mailing address: responsible for permanent City / State / ZIP: service billing? Daytime Phone: Cell Phone: Email address: Project No. of Units: Single-family residence Duplex Quad Temporary service? Yes No Overhead Underground Date Desired: Permanent service? Yes No Overhead Underground Date Desired: Contractor Information Name of contractor: Same as above Mailing address: City / State / ZIP: Daytime telephone: Contact Information Name of contact: Role: Mailing address: Same as above City / State / ZIP: Telephone Numbers: Daytime Phone: Cell Phone: Email address: Project Information Street address & city OR (EXAMPLE: 2N 10 29AC 1400) assessor s parcel number: Who will trench, install Applicant conduit, and backfill? Contractor Name: Cell Phone: Electrical Load Information Main breaker size: Amps Total square footage: Voltage: 120/240, 3-wire, 1Ø Other: Check all that apply: (electric appliances) Standard residential loads (Lighting, refrigerator, freezer, dishwasher, washer) High load, extra lighting, fans, etc. Air-conditioner ( tons) Range/Oven Spa Domestic water pump ( hp) Clothes Dryer Heat pump ( tons) Other electric heat ( kw) Water Heater Other: Attachments Provide a copy of the following documents: Legal description of property or copy of last recorded deed. County assessor s parcel map indicating homesite(s), easements, and rights-of-way. Detailed plot plan (see reverse). Applicant s Signature: Date: SAMPLE MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141 FAX TO: 503-815-8648 EMAIL: engineering-requests@tpud.org TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS

Request for New Electrical Services Commercial Service Engineering Department 503-815-8629 REQUIRED INFORMATION Applicant Information (Please print full, legal name or business name) Temporary service: Owner s name and address or party responsible for temporary service billing? Permanent service: Cell Phone: Same as above Cell Phone: M PL E Owner s name and address or party responsible for permanent service billing? Name: Mailing address: City / State / ZIP: Daytime Phone: Email address: Name: Mailing address: City / State / ZIP: Daytime Phone: Email address: Project Description Temporary service? Permanent service? Yes No Overhead Underground Date Desired: Yes No Overhead Underground Date Desired: Contractor Information Name of contractor: Mailing address: Same as above City / State / ZIP: Daytime phone number: Contact Information Name of contact: Role: Mailing address: Same as above City / State / ZIP: Telephone Numbers: Email address: Daytime Phone: Cell Phone: Project Information SA Street address and city OR assessor s parcel number Directions to project (include cross streets, mile post numbers, etc.): Who will trench, install conduit, and backfill? Applicant Contractor (EXAMPLE: 2N 10 29AC 1400): Name: Cell Phone: Electrical Load Information Main breaker size: Total square footage: Voltage (select one): amps ( COMPLETE ATTACHED LOAD SUMMARY) square feet 120/208; 3-wire, 1Ø 120/208Y; 4-wire, 3Ø 277/480Y; 4-wire 3Ø 120/240; 3-wire 1Ø Other: Attachments Provide a copy of the following documents: Load summary sheet (attached). County assessor s parcel map indicating site, easements, and rights-of-way. Detailed plot plan (see reverse). Applicant s Signature: Date: MAIL COMPLETED FORM TO: PO BOX 433; TILLAMOOK, OR 97141 FAX TO: 503-815-8648 EMAIL: engineering-requests@tpud.org TILLAMOOK PUD ELECTRIC SERVICE REQUIREMENTS SAMPLE FORMS