Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions

Similar documents
I-20 East Transit Initiative

Durham-Orange County Corridor Alternatives Analysis JULY Prepared by: U R S Team

Midtown Corridor Alternatives Analysis Initial Screening Analysis

Highway Transitway Corridor Study

14.0 Capital Cost Estimate Methodology

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

Midtown Corridor Alternatives Analysis Key Issues Memo

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014

Business Advisory Committee. July 7, 2015

Detailed Definition of Alternatives

Alternatives Analysis Findings Report

engineering phase and during the procurement of design build contracts.

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

NJ TRANSIT West Trenton Rail Line Passenger Service Rail Study West Trenton, NJ to Manville, NJ 10/26/2007 PREFERRED ALTERNATIVE CAPITAL COST ESTIMATE

4.0 TIER 2 ALTERNATIVES

Cost to extending KC Streetcar north approximately ½ mile

MIDTOWN CORRIDOR ALTERNATIVES ANALYSIS FINAL REPORT APRIL 2014

Metro Transit Arterial Transitway Corridors Study

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

CONFEDERATION LINE EAST SEGMENT

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Business Advisory Committee. November 3, 2015

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Operating & Maintenance Cost Results Report

FACT SHEET. US 192 Alternatives Analysis Modal Technologies. Alternative Description/Overview

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Denver Metro Association of Realtors

VAN NESS AVENUE BUS RAPID TRANSIT

Community Advisory Committee. October 5, 2015

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No

CEDAR AVENUE TRANSITWAY Implementation Plan Update

1.0 Detailed Definition of Alternatives

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Quarterly Update Meeting

Committee Report. Transportation Committee. Business Item No

Conceptual Design Cost Estimates Report

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Sound Transit East Link: Bus/LRT System Integration Study

METRO Orange Line BRT American Boulevard Station Options

5. OPPORTUNITIES AND NEXT STEPS

CONCEPTUAL ENGINEERING REPORT

Restoration of Historic Streetcar Services in Downtown Los Angeles

West LRT. Alignment Update and Costing Report May Calgary Transit Transportation Planning Clifton ND Lea Consultants

COST ESTIMATES: Curb-Running

Extending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Policy Advisory Committee Meeting November 13, 2013

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

WEST CONTRA COSTA HIGH-CAPACITY TRANSIT STUDY TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

Transit Access to the National Harbor

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

Chapter 4 : THEME 2. Transportation

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES

West Broadway Reconstruction/LRT Design. March 19, 2015

State Avenue Corridor Bus Rapid Transit (BRT)

D Line Station Plan: Table of Contents

Transitways. Chapter 4

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station

Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report

RECOMMENDED ALTERNATIVE REPORT

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

EXECUTIVE SUMMARY. Hartford East Bus Rapid Transit Feasibility Study. Hartford East Hartford Manchester - Vernon. Rail Corridor.

Update on Transportation Activities in Fairfax County

Needs and Community Characteristics

Site Characteristics (topography, grade, land use compatibility, expansion capability and environmental considerations)

C LINE: LONG-TERM GLENWOOD REALIGNMENT STUDY

Develop ground transportation improvements to make the Airport a multi-modal regional

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

Where will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run?

ANDERSON PROPERTY SITE ANALYSIS

A Presentation to: Project Advisory Group Meeting #10

C Tenant Improvements 2,901, C Fire Standpipe Repairs and Fire Sprinkler System Upgrade for

Recommended Station Plan

Orange Line Bus Rapid Transit Project Plan Update. Metro Transit June 2014 D R A F T

FREQUENTLY ASKED QUESTIONS

Appendix F-1 Description of the Long-Term Alternatives

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

ACTION TRANSMITTAL No

BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN

CHAPTER SEVEN: EVALUATION METHODOLOGY FOR COST AND COST EFFECTIVENESS MEASURES Locally Preferred Alternative Report

Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology

Energy Technical Memorandum

Draft Station Plan. Tuesday, November 17th

The range of alternatives has been reviewed with the RTAC Subgroup and the preliminary analysis is proceeding on the following HCT alternatives:

VAN NESS AVENUE BUS RAPID TRANSIT

WELCOME. Transit Options Amherst - Buffalo Public Workshops

APTA Rail Conference 2017 Mark L. Dorn Design Manager for Oklahoma City MAPS 3 Modern Streetcar Jacobs/AECOM Team

Green Line LRT: Beltline Segment Update April 19, 2017

3.15 SAFETY AND SECURITY

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Transcription:

Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for

Table of Contents Introduction... 1 Alternatives Overview... 1 Capital Cost Methodology... 2 FTA Standard Cost Categories (SCC)... 3 SCC 10 - Guideway... 3 SCC 20 - Stations... 4 SCC 30 Support Facilities... 5 SCC 40 Sitework and Special Conditions... 5 SCC 50 Systems... 7 SCC 60 Right-of-Way... 7 SCC 70 Vehicles... 8 SCC 80 Professional Services... 9 Capital Cost Estimate Summary... 10 Tables Table 1 - Vehicle Quantities... 8 Table 2 - Professional Services Estimated Rates... 9 Table 3 - Capital Cost Estimate Summary... 10 Capital Cost Estimation Methodology and Assumptions Page i

Introduction During the Midtown Corridor Alternatives Analysis (AA), a cost estimate was prepared for each of the alternatives included in the study. The cost estimate reflects the alternative refinements that were made during the AA process, based on stakeholder input. This estimate can be considered a snapshot in time and was developed to provide a high-level analysis of the cost impacts associated with the alternative refinements. This report summarizes the assumptions and changes that were used to develop the cost estimate. Alternatives Overview The Midtown Corridor AA evaluated four build alternatives. The following is a summary of each alternative for which costs were prepared. Concept plans for each alternative can be found in Appendix A. Double/Single-Track Rail in the Midtown Greenway: Two concepts were developed for the rail alternative in the Midtown Greenway. The main difference between them is the amount of single track included in the alignment. Under both concepts, it assumed that at all station locations, the alignment would be double-track through the station platform. For costing purposes, this alternative assumes the vehicle to be a light rail transit (LRT) vehicle operating as a single car train as opposed to a smaller, streetcar-type vehicle. Concept 1: This alternative has a combination of single- and double-track rail service operating in the Midtown Greenway between the Green Line and Blue Line LRT. The alignment begins as double-track at the West Lake station located adjacent to the proposed Green Line LRT station and immediately transitions to single-track after the station. It continues east and crosses over Dean Parkway on the existing bridge, prior to becoming double-track at the Calhoun Beach station. The alignment continues as double-track adjacent to the Greenway trail between the Calhoun Beach station and the Bloomington Avenue station. It then becomes single-track prior to the bridge at 17th Avenue and continues to the Midtown station, adjacent to the Hiawatha LRT station. The alignment transitions to double-track immediately prior to the Midtown Station. Under this concept, portions of the Midtown Greenway trail are shifted or modified to accommodate the alignment. A short segment of trail is shifted at the West Lake station to make room for the station platform. The trail is shifted slightly between the Calhoun Beach station and James Avenue, which includes new pedestrian bridges over the Lake of the Isles channel and Calhoun Parkway. There also are trail modifications between the Hennepin Avenue station and Colfax Avenue as well as between 12th and 17th avenues. The existing access ramp from 13th Avenue requires reconstruction to accommodate the shift of the trail. Concept 2: This alternative has a combination of single- and double-track rail service operating in the Midtown Greenway between the Green Line and Blue Line LRT. This concept includes single-track segments as identified in concept 1 as well as an additional single-track segment Capital Cost Estimation Methodology and Assumptions Page 1

between Hennepin Avenue and Blaisdell Avenue. The additional single-track segment would begin under the existing Hennepin Avenue Bridge, continuing to Blaisdell Avenue, generally located within the center portal of the existing bridges. The additional single-track segment would reduce the quantity of retaining walls required in this area and eliminate the trail modifications that are identified between Hennepin Avenue and Colfax Avenue in concept 1. Enhanced Bus on Lake Street: This alternative provides arterial bus rapid transit (BRT) service along Lake Street between the Green Line and Blue Line LRT. A station also is included east of Hiawatha at Minnehaha Avenue as a turnaround point. Corridor improvements are limited to station areas. Improvements include adding 9-inch raised platforms, transit signal priority at intersections, and station amenities such as shelters, branding, and off-board fare collection. Dual Alternative: This alternative combines the double/single-track rail in the Midtown Greenway alternative with the enhanced bus on Lake Street alternative. In this alternative the enhanced bus service on Lake Street runs between the Hennepin Avenue station and the station at Minnehaha Avenue while the double/single-track rail in the Midtown Greenway remains unchanged. Capital costs were developed for two different track types in this alternative, ballasted and turf track. Dual Alternative with Enhanced Bus Extension to St. Paul: This alternative is the same as the dual alternative, except the BRT service on Lake Street is extended on Lake Street and Marshall Avenue to Snelling Avenue where it terminates at a station on Snelling Avenue, near University Avenue. The station at Minnehaha Avenue with this alternative is located on Lake Street, as opposed to the turnaround location with the enhanced bus on Lake Street alternative. Capital costs were developed for two different track types in this alternative, ballasted and turf track. Capital Cost Methodology Capital cost estimates were prepared using the format and procedures currently required for project evaluation by the Federal Transit Administration (FTA). FTA methodology uses standard cost categories (SCC), grouping costs by various components such as guideway, stations, operations and maintenance facilities, sitework, signalization and communications systems, right-of-way acquisition, and vehicles. Soft costs or professional/technical services are included for items such as engineering, construction services, insurance, and owner s costs. This also includes contingencies for uncertainty in both the estimating process and the scope of the project. The cost estimates for LRT and BRT follow the same principles, using similar level of detail for each transit mode. At this early study stage, there was not sufficient definition or detail to prepare true construction cost estimates for the various alternatives under consideration. Rather, capital cost estimates were developed using representative typical unit costs or allowances on a per unit basis that is consistent with the level of alternatives definition. Capital cost estimates will need to be refined when additional studies are conducted to further the design of the corridor. Capital Cost Estimation Methodology and Assumptions Page 2

The following parameters were used to develop the capital cost estimate: Base Year: Year 2013 Allocated Contingencies: Allocated contingencies are contingencies that are associated with individual cost estimate categories. These contingencies are intended to compensate for unforeseen items of work, quantity fluctuations, and variances in unit costs that develop as the project progresses through the various stages of design development. The level of allocated contingency applied to each cost category reflects the relative potential variability of those estimates. The following allocated contingencies were used for the capital cost estimates: o SCC 10 - SCC 50: Infrastructure 20% o SCC 60: Right-of-way 100% o SCC 70: Vehicles 5% o SCC 80: Professional services 0% Unallocated Contingency: An unallocated contingency of 20 percent is included in the capital cost estimates. This contingency is applied to the total estimated capital cost for each alternative and is added to any specific estimating contingencies that are included or allocated to the various cost categories. The level of detail of the capital cost estimates for this study corresponds with the current level of alternatives definition, engineering, and environmental analyses. The level of estimating detail typically increases as the project progresses through the various phases of development during the AA study, environmental impact studies, preliminary engineering, and final design. FTA Standard Cost Categories (SCC) The following section describes each SCC and the items included in each. SCC 10 - Guideway This category includes costs associated with all the civil and structural costs directly associated with construction of the guideway structures, roadbed, and pavement or track. The following are the costs associated with the double/single-track rail in the Midtown Greenway alternative: Two different track type costs were estimated for both of the double/single-track rail alternatives: ballasted and turf track. Both cost scenarios assume that one track type is provided for the entire alignment length of the Midtown Greenway. Further refinement could show that a combination of ballast and turf track segments strikes the appropriate balance. Grading and drainage is included for subgrade preparation of the ballasted or turf track. Special trackwork for transitions into/out of single-track segments and to facilitate movements between eastbound and westbound tracks. There were no guideway costs associated with the enhanced bus on Lake Street alternative, as the construction impacts will be limited to station areas. Capital Cost Estimation Methodology and Assumptions Page 3

SCC 20 - Stations This category includes costs associated with station platforms, ramps, platform fixtures, canopies, and passenger amenities as well as costs for vertical circulation (elevators and stairs) to the platform, where necessary. Stations for the double/single-track rail in the Midtown Greenway alternative are assumed to be center loading platforms that are 90 feet long by 20 feet wide. This category also includes a shelter that is similar in concept, but roughly one-third of the length of an LRT platform. Vertical circulation includes provisions for stairs and an elevator within an enclosed building to provide access between stations that are located within the Midtown Greenway and the adjacent street. Stations that are located on atgrade intersections will require pedestrian railroad crossings. The following stations on the Midtown Greenway include vertical circulation: Hennepin Avenue Lyndale Avenue Nicollet Avenue I-35W/Stevens Avenue Chicago Avenue Bloomington Avenue The following stations on the Midtown Greenway are at-grade: West Lake Street Calhoun Beach 5 th Avenue Midtown Stations for the enhanced bus on Lake Street alternative and the Lake Street alignment portion of the Dual Alternatives are similar in concept to those developed as part of the Arterial Transitway Corridors Study (ATCS). The minimum length of station platform areas is 60 feet and the maximum length is 100 feet, which provides room to combine the local bus stop with the enhanced bus station. Shelters are a modular concept that can be used to create various configurations based on constraints and ridership demand at each station. Four major classifications of shelters were assumed: extra small, small, medium, and large. Stations located on a bumpout were assumed to include a windscreen, except for the extra small shelter. The following at-grade stations are included in the enhanced bus on Lake Street alternative: West Lake Street Lyndale Avenue Chicago Avenue Calhoun Parkway Nicollet Avenue Bloomington Avenue Knox Avenue Hennepin Avenue I-35W/Stevens Avenue/2 nd Avenue Cedar Avenue Midtown Dupont Avenue Portland Avenue Minnehaha Avenue Capital Cost Estimation Methodology and Assumptions Page 4

The following at-grade stations are included in the dual with extension to St. Paul alternative: Hennepin Avenue Chicago Avenue 44 th Avenue South Dupont Avenue Bloomington Avenue Otis Avenue Lyndale Avenue Cedar Avenue Cretin Avenue Nicollet Avenue Midtown Cleveland Avenue I-35W/Stevens Avenue/2 nd Avenue Minnehaha Avenue 31 st Avenue South Fairview Avenue Fry Street Portland Avenue 36 th Avenue South Spruce Tree Avenue SCC 30 Support Facilities The support facilities SCC includes the capital cost of operations, maintenance, and storage facilities for the corridor. Approximately three acres will be required for an operations and maintenance facility for the double/single-track rail alternative. It is assumed that a new facility will be constructed adjacent to the corridor and will include yard track, a light maintenance building that can accommodate enclosed storage of five LRT vehicles, employee parking, and office space. The requirements for enhanced bus support facilities are dependent on the type of vehicle, the size of the fleet, and the maintenance needs of the system. The enhanced bus alternatives were assumed to use low-floor 60-foot buses. It is currently unclear whether an entirely new facility would be needed to support the enhanced bus on Lake Street alternative or whether existing Metro Transit facilities could be modified and expanded to meet the need. A per bus capital cost was included for a new maintenance facility, or modifications to an existing bus facility, as part of the enhanced bus on Lake Street alternative or the dual alternatives. SCC 40 Sitework and Special Conditions The sitework and special conditions SCC includes estimated costs for all other construction activities that are not accounted for in the guideway, stations, support facilities, or systems categories. Two different sets of line items were used for SCC 40 because the double/single-track rail in the Midtown Greenway alternative and the enhanced bus on Lake Street alternative have very different construction impacts. The sitework and special conditions unit cost line items for the enhanced bus on Lake Street alternative and the dual alternatives include: Curbside and bumpout demolition (each) Utilities and drainage improvements (each) Install or relocate signal-pole pedestals (each) Electrical service (each) Additional site improvements (each) Curbside and bumpout sidewalk/pedestrian improvements (each) Capital Cost Estimation Methodology and Assumptions Page 5

Street signage (each) Curbside and bumpout street improvements (each) Traffic control (each) The sitework and special conditions unit cost line items for the double/single-track rail in the Midtown Greenway alternative include: Common excavation and export for new retaining walls only (cubic yard) Removals (route foot) Utility allowance protect in place existing and cathodic protection (each) Relocate existing watermain Lyndale Avenue bridge (lump sum) Bridge modifications new wall and soil strengthening (square foot) Bridge abutment reconstruction (each) Bridge pier protection (each) Horizontal overhead catenary system (OCS) shield (linear foot) Retaining walls (square foot) Trail modifications (square foot) Sidewalk (square foot) Trail retaining wall (square foot) Pedestrian bridge (each) Landscape allowance (route foot) Station landscape allowance (each) Fence allowance (linear foot) Roadway Reconstruction (square yard) Temporary trail (route foot) Traffic control allowance (route foot) Coordination with the Green Line LRT (Southwest) project occurred throughout the project to verify that a platform can be accommodated adjacent to the future Southwest platform at the West Lake Station. Capital cost estimates prepared as part of this project have included costs associated with any modifications required to accommodate a Greenway platform, outside of improvements that the Southwest project are including as part of their capital cost. These modifications include trail and roadway realignment and property acquisition. Planned redevelopment and reconstruction of the Nicollet Avenue Bridge is assumed to accommodate the Midtown project, but construction will be completed by others and is not included as part of this cost estimate. Each bridge along the Midtown Greenway will require slightly different modifications to accommodate the double/single-track rail system and will be designed on a case-by-case basis if the project moves forward. For the purpose of this high-level cost estimate, a line item was added for bridge modifications that portrays the cost to add soil strengthening and new retaining walls at bridges with shallow abutments, where tracks or trail will be constructed through existing abutment slopes. Capital Cost Estimation Methodology and Assumptions Page 6

SCC 50 Systems The systems SCC includes capital costs for many elements including train control signals, communication systems, central control hardware and software, traction power substations, overhead catenary systems, underground duct banks, automated fare collection, grade crossing protection, and roadway traffic signal systems. Two different sets of line items were used for SCC 50, as the double/single-track rail in the Midtown Greenway alternative and the enhanced bus on Lake Street alternatives have distinct system differences between LRT and BRT. The systems unit cost line items for the enhanced bus on Lake Street alternative and the dual alternatives include: Transit signal priority (TSP) (each) TSP central system upgrades (lump sum) Station communication allowance (each) Fare collection allowance (each) Fare enforcement equipment (each) On-board GoTo validator (each) The systems unit cost line items for the double/single-track rail in the Midtown Greenway alternative include: Train control interlocking, signals, and switches (each) S/C duct bank Allowance (route-foot) Station train-to-wayside Communications (TWC) allowance (each) Crossing protection pedestrian and grade crossing (each) Mainline traction power substation (TPSS) (each) OCS foundation and pole allowance (route foot) OCS simple catenary allowance (track foot) Station communication allowance (each) System communication allowance (route foot) Fare collection allowance (each) Central control allowance (route-foot) SCC 60 Right-of-Way The right-of-way SCC includes costs for acquisition of right-of-way needed for construction and operation of the project. In the Midtown Corridor, right-of-way requirements are anticipated along portions of the corridor, at stations, at traction power substations, and at the operations and maintenance facility; however, the specific needs and actual costs will not be known until detailed design is underway. For this AA study, a high-level review of the right-of-way impacts was performed to determine partial and full parcel acquisitions for the project. The unit costs reflect the general land use characteristics of the area. Capital Cost Estimation Methodology and Assumptions Page 7

The right-of-way unit cost line items include: Purchase or lease of real estate (square foot) Relocations (lump sum) The enhanced bus on Lake Street alternative and the Lake Street alignment of the dual alternative include construction of station areas that are located within the existing public roadway right-of-way. No permanent right-of-way acquisition is anticipated. The double/single-track rail in the Midtown Greenway alternative will include limited right-of-way impacts along the corridor due to trail relocations and vertical circulation buildings. A full parcel take is anticipated on the eastern portion of the corridor, where the alignment runs through an undeveloped parcel owned by Soo Line Railroad. This parcel is approximately 0.3 acres and is located between 21 st Avenue and Hiawatha Avenue, immediately south of 28 th Street. It also is anticipated that three acres of right-of-way is necessary to construct a new operations and maintenance facility adjacent to the corridor. SCC 70 Vehicles The vehicles SCC includes costs for single LRT vehicles and low-floor, 60-foot articulated BRT buses. Vehicle quantities include a 20 percent spare ratio and were updated based on the most current operating and ridership information. This category also includes an allowance for other service vehicles to support operations and maintenance. The vehicle unit cost line items include: LRT vehicle Metro Transit Type II LFLRV (each) Low-floor, 60-foot bus (each) Nonrevenue vehicle allowance (route foot) Spare parts allowance (each) Table 1 - Vehicle Quantities Alternative LRT Vehicles BRT Vehicles Double-/Single-Track Rail in the Midtown Greenway 5 Enhanced Bus on Lake Street (Green Line to Blue Line) 21 Dual Alternative (Green Line to Blue Line) 5 9 Dual Alternative with Enhanced Bus Extension to St. Paul 5 16 Capital Cost Estimation Methodology and Assumptions Page 8

SCC 80 Professional Services Cost estimates for the professional services SCC were generated by applying assumed rates to different categories of the estimate. Table 2 lists the professional services assumptions that were incorporated into the capital cost estimates. Table 2 - Professional Services Estimated Rates Description Construction Right-of-way Vehicles Preliminary engineering 2% - - Final design 5% 2% 1% Project management for design and construction Construction administration and management 2% 2% 2% 8% 1% - Insurance 4% - - Legal, permits, and review fees by other agencies Surveys, testing, investigation, and inspection 1% 5% - 2% 10% 2% Agency force account work 6% 10% 1% Total 30% 30% 6% Capital Cost Estimation Methodology and Assumptions Page 9

Capital Cost Estimate Summary Tables 3 and 4 below summarize the capital costs for each of the alternatives, for each concept identified above, included in the Midtown Corridor AA. Table 3 Concept 1 Capital Cost Estimate Summary Double/Single Track Rail in the Midtown Greenway Enhanced Bus (Green Line to Blue Line) Dual Alternative (Green Line to Blue Line) Dual Alternative w/ Enhanced Bus Extension to St. Paul Total (2013$) Total (2013$) Total (2013$) Total (2013$) 10 GUIDEWAY & TRACK ELEMENTS $15,800,000 $15,800,000 $15,800,000 (ballasted) (ballasted) (ballasted) $32,500,000 (turf track) $0 $32,500,000 (turf track) $32,500,000 (turf track) 20 STATIONS, STOPS, TERMINALS, INTERMODAL $18,000,000 $5,600,000 $22,500,000 $24,600,000 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $10,800,000 $1,800,000 $11,100,000 $11,100,000 40 SITEWORK & SPECIAL CONDITIONS $43,900,000 $2,800,000 $46,700,000 $48,600,000 50 SYSTEMS $31,100,000 $5,500,000 $35,800,000 $39,200,000 SUBTOTAL INFRASTRUCTURE (ballasted track) $119,600,000 $15,700,000 $131,900,000 $139,300,000 60 ROW, LAND, EXISTING IMPROVEMENTS $3,100,000 $0 $3,100,000 $3,100,000 70 VEHICLES $19,100,000 $20,200,000 $27,800,000 $34,500,000 80 PROFESSIONAL SERVICES $31,500,000 $5,100,000 $35,000,000 $37,200,000 90 UNALLOCATED CONTINGENCY $23,900,000 $6,500,000 $27,600,000 $30,100,000 Total Ballasted Track $197,200,000 $47,500,000 $225,400,000 $244,200,000 Total Turf Track $220,800,000 $248,900,000 $267,900,000 Table 4 Concept 2 Capital Cost Estimate Summary Double/Single Track Rail in the Midtown Greenway Enhanced Bus (Green Line to Blue Line) Dual Alternative (Green Line to Blue Line) Dual Alternative w/ Enhanced Bus Extension to St. Paul Total (2013$) Total (2013$) Total (2013$) Total (2013$) 10 GUIDEWAY & TRACK ELEMENTS $14,900,000 $14,900,000 $14,900,000 (ballasted) (ballasted) (ballasted) $29,900,000 (turf track) $0 $29,900,000 (turf track) $29,900,000 (turf track) 20 STATIONS, STOPS, TERMINALS, INTERMODAL $18,000,000 $5,600,000 $22,500,000 $24,600,000 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS $10,800,000 $1,800,000 $11,100,000 $11,100,000 40 SITEWORK & SPECIAL CONDITIONS $36,310,000 $2,800,000 $39,100,000 $41,040,000 50 SYSTEMS $33,100,000 $5,500,000 $37,700,000 $41,100,000 SUBTOTAL INFRASTRUCTURE (ballasted track) $113,100,000 $15,700,000 $125,300,000 $132,700,000 60 ROW, LAND, EXISTING IMPROVEMENTS $3,100,000 $0 $3,100,000 $3,100,000 70 VEHICLES $19,100,000 $20,200,000 $27,800,000 $34,500,000 80 PROFESSIONAL SERVICES $29,800,000 $5,100,000 $33,300,000 $35,600,000 90 UNALLOCATED CONTINGENCY $22,800,000 $6,500,000 $26,500,000 $29,000,000 $47,500,000 $187,900,000 $47,500,000 $216,000,000 $234,900,000 Total Turf Track $209,200,000 $237,200,000 $256,100,000 Capital Cost Estimation Methodology and Assumptions Page 10