DC Power Grid System Lighting for a Typical Conference Room Evaluation

Similar documents
Hybrid Power for Green Buildings

LOW-VOLTAGE TECHNOLOGY SCOPING STUDY: IMPACT OF SMALL AIR CONDITIONING UNITS ON ELECTRICAL SYSTEM VOLTAGE RECOVERY

Sacramento Municipal Utility District s EV Innovators Pilot

Variable Speed Drive on a Die Casting Machine

DC FlexZone Suspension System Electrical Design Guide. InstallatIon SYSTEMS

Zero Emission Bus Impact on Infrastructure

N.H.P.U.C. No ELECTRICITY GRANITE STATE ELECTRIC COMPANY DBA LIBERTY UTILITIES. SUPERSEDING N.H.P.U.C. No. 17 TEMPORARY RATES

Southern California Edison Clean Energy Future

Solar Power. Demonstration Site. Annual Performance Report 2017

THE PUBLIC SERVICE COMMISSION OF MARYLAND

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019.

Energy Saving Options for Small ISDs. Presented by Casey Stone, PE, CEM

Capture The Power of Photovoltaics. IEEE Power Engineering Society Meeting May 2005

Annex 1. Field Report: Solar Electric Light Fund Energy Harvest Control Study

Evolving our Customer Relationship: Edison SmartConnect Programs & Services Mark Podorsky, Sr. Manager Business Design

2016 UC Solar Research Symposium

Residential Lighting: Shedding Light on the Remaining Savings Potential in California

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Meter Insights for Downtown Store

Impact of Distributed Energy-Efficiency with Solar on SMUD s Peak Load

SOLAR DISTRIBUTED GENERATION PROGRAM UPDATE

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

EMerge Alliance Standards for Hybrid AC/DC Power Distribution in Commercial Buildings. Brian Patterson Chairman, EMerge Alliance

NATIONAL CONFERENCE of STATE LEGISLATURES. October 9 th, 2009 Ervan Hancock

Southern California Edison Company Demand Response Appendices to SCE-1, Volumes 1-4 ERRATA Replacing Appendix D, Pages D-1 & D-3

PG&E California Solar Initiative (CSI) & Net Energy Metering (NEM) Interconnection Webinar. March 26, 2009

Electric Vehicle Basics for Your Business

Overview of Net Energy Metering (NEM) Successor Tariff (NEM 2.0)

Michigan Public Service Commission Grid Tied Solar Photovoltaic

# 1, Bowes Place, Phillip, ACT 2606, Australia. Phone:

CITY OF SANTA CLARA. RATE OPTIONS: Non Time of Use Time of Use CUSTOMER CHARGE For Each Service Address per meter per month $ $306.

Manager of Market Strategy and Planning September 22, 2008

The brand you can trust.

Schedule D DOMESTIC SERVICE

ELECTRIC SCHEDULE AG-ICE Sheet 1 AGRICULTURAL INTERNAL COMBUSTION ENGINE CONVERSION INCENTIVE RATE - EXPIRATION TRANSITION RATE

2018 Customer generation rates

2016 Load & Capacity Data Report

Project Title: Contract Number: Milestone Number: Report Date: Contract Contact: Phone: Congressional District: Executive Summary:

Expanding PIER Partnerships: New Concepts for Development and Demonstration Task 2 National Guard Audit and Recommendations

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE

An Energy Assessment of Fume Hoods with and without Automated Sash Positioning Control Systems at Amgen, Inc.

kwh. 6 February

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

Achieving Energy Efficiency through Smart Grid. Patty Anderson McKinstry Joe Castro City of Boulder

Australian Solar Cooling Interest Group (ausscig) Conference Queensland Solar City

2018 Load & Capacity Data Report

Energy Savings and Incentives with PG&E. Chad Stout Account Manager

Residential ZNE Retrofit EE, DR, IES, HEMS + PV a Tall Loading Order Zero Net Energy Home Design, Development and Implementation

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Using Inverter Input Modes for Smart Grid Management

Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No.

How it works How your HAN device helps you monitor electricity use

LIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 3rd Revised CPUC Sheet No. 137 Canceling 2nd Revised CPUC Sheet No.

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Technology solutions and innovations for developing economies

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257

PART 2 GUIDELINES. To be eligible to receive a financial incentive, the following conditions must be met:

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

2013 Spring Calendar. be energy wise. California Utilities Partnering for Energy Efficiency. California Energy Wise Foodservice Seminars

Felix Oduyemi, Senior Program Manager, Southern California Edison

Adaptive Lighting for Interior and Exterior Applications

Table of Contents. Electric Rates and Tariffs RESIDENTIAL 1 SMALL COMMERCIAL 4 MEDIUM COMMERCIAL 6 MEDIUM COMMERCIAL (TIME-OF-USE) 9

LIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 20th Revised CPUC Sheet No. 84 Canceling 19th Revised CPUC Sheet No.

THE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Virginia Tech Research Center Arlington, Virginia, USA

Schedule TOU-EV-8 Sheet 1 GENERAL SERVICE TIME-OF-USE, ELECTRIC VEHICLE CHARGING, DEMAND METERED

March 30, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. 1% Franchise Surcharge for City of Santa Barbara Residents

Moixa Home Energy Systems

CL&P s new time-of-use (TOU) rates

Electric Rates. for residential and farm customers. January 2016

P.S.C. No. 9 - Electricity Consolidated Edison Company First Revised Leaf No. 310 of New York, Inc. Superseding Original Leaf No.

Plug-in Electric Vehicles

2018 Summary of Eastern Massachusetts Electric Rates for Greater Boston Service Area

Schedule TOU-EV-9 Sheet 1 GENERAL SERVICE TIME-OF-USE, ELECTRIC VEHICLE CHARGING, LARGE DEMAND METERED

ETSU Solar Array. Suggestions for a potential solar array on campus. Scott Finney

SECTION ROLLER WINDOW SHADES

Alameda Unified School District

Attached please find Chart House Energy s final comments on the DG Tariff U I hope this will help to consider a fair and reasonable tariff.

ADVANCED VEHICLE TECHNOLOGIES RESEARCH

Corporate Partners Committee Smart Meter Data Access Use Case. June 21, 2011

Section A: CUSTOMER INFORMATION. Customer Name Electric Account Number Rate Application Number. Facility Address City State Zip Code

Smart Grid Technology: Measuring Residential Energy Use

2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Thomas Edison, U.S. inventor, in 1931 conversation with Henry Ford and Harvey Firestone

Rate Schedules. Effective 1/1/2019

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities

JEA Distributed Generation Policy Effective April 1, 2018

Using Inverter Input Modes for Smart Grid Management

Schedule TOU-EV-7 Sheet 1 GENERAL SERVICE TIME-OF-USE, ELECTRIC VEHICLE CHARGING

Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee

Solar Plus: A Holistic Approach to Distributed Solar PV Eric O'Shaughnessy, Kristen Ardani, Dylan Cutler, Robert Margolis

THE BUSINESS CASE FOR INDUSTRIAL-SCALE BATTERIES

Electricity Supply System from Nissan LEAF Battery to Houses: LEAF to Home

Design and Installation of A 20.1 kwp Photovoltaic-Wind Power System

Helping you get plug-in ready for electric vehicles

Transcription:

Design & Engineering Services DC Power Grid System Lighting for a Typical Conference Room Evaluation ETO 09.03 Report Prepared by: Design & Engineering Services Customer Service Business Unit Southern California Edison November 2, 2009

Acknowledgements Southern California Edison s (SCE) Design & Engineering Services (D&ES) group is responsible for this project. It was developed as part of SCE s Education, Training, and Outreach program under internal project number ETO 09.03. D&ES project manager Doug Avery conducted this technology evaluation with overall guidance and management from Ramin Faramarzi. For more information on this project, contact doug.avery@sce.com. Disclaimer This report was prepared by SCE and funded by California utility customers under the auspices of the California Public Utilities Commission (CPUC). Reproduction or distribution of the whole or any part of the contents of this document without the express written permission of SCE is prohibited. This work was performed with reasonable care and in accordance with professional standards. However, neither SCE nor any entity performing the work pursuant to SCE s authority make any warranty or representation, expressed or implied, with regard to this report, the merchantability or fitness for a particular purpose of the results of the work, or any analyses, or conclusions contained in this report. The results reflected in the work are generally representative of operating conditions; however, the results in any other situation may vary depending upon particular operating conditions. Southern California Edison

ABBREVIATIONS AND ACRONYMS AC DC kw kwh PV VAC VDC W Alternating current Direct current Kilowatt Kilowatt-hour Photovoltaic Volts alternating current Volts direct current Watt Southern California Edison Page i

FIGURES Figure 1. Post-Retrofit Conference Room...7 Figure 2. DC Power Connector on the Ceiling Grid...7 Figure 3. Nextek Power Server Post-Retrofit...7 Figure 4. Intu Control Node...7 Figure 5. Ceiling Mounted DC Power Grid...7 Figure 6. Synergistic Logger Box...8 Figure 7. Electric Panel...8 Figure 8. Load Profile of Conference Room Lighting...9 Figure 9. Average Weekday Lighting kw Baseline and Post- Retrofit... 10 Figure 10. Average Weekend Lighting kw Baseline and Post- Retrofit... 10 Southern California Edison Page ii

CONTENTS EXECUTIVE SUMMARY 4 INTRODUCTION 5 PRODUCT DESCRIPTION 5 TECHNICAL APPROACH 8 RESULTS AND RECOMMENDATIONS 9 Results...9 RECOMMENDATIONS 11 Southern California Edison Page iii

EXECUTIVE SUMMARY The main objective of this study is to determine if there are any energy savings associated with the installation of a direct current (DC) power grid and associated controls in the Southern California Lighting Technology Center s (SCLTC) conference room. The efficiency of this new system will be compared to the baseline lighting and controls system operating on an alternating current (AC) circuit. Three industry partners provided the material for the installation of the system. Armstrong Building Products provided the grid work for the ceiling mounted DC power distribution. Nextek Power Systems provided a power server as well as DC lighting ballasts. Kanepi Innovations provided the sensors and other equipment for the lighting control system. Although new lighting ballasts were installed for this project, the baseline lighting fixtures were not replaced. During the baseline period of November 5, 2008 through February 17, 2009, excluding holidays, the weekday peak lighting load ranged from 0.004 kw to 0.436 kw. During the post-retrofit period of June 4, 2009 through July 14, 2009, excluding holidays, the weekday peak lighting load ranged from 0.008 kw to 0.073 kw. The annualized conference room lighting energy use decreased from 324 kwh in the baseline period to 156 kwh in the post-retrofit period - a decrease of 52%. It is important to note that the savings was obtained by programming the lighting system to operate only when the space was occupied and by requiring a manual on to select the lighting scene that provided the desired lighting levels for each specific meeting. Southern California Edison Page 4

INTRODUCTION The objective of this project was to determine power and energy savings associated with conversion of an AC lighting system to a DC system. The baseline energy use for the installed lighting system normally operates on an AC circuit. The existing lighting fixtures were retrofitted to operate on DC power, and the DC grid was installed. A new baseline for the energy use of the DC system was recorded. The next potential step is to install Photovoltaic (PV) cells on the roof and measure the energy use of a DC-to-DC lighting system. PRODUCT DESCRIPTION The existing lighting system in the conference room consists of: Three suspended fixtures with two 4-foot 28W T-5 lamps. Three recessed fixtures with one 4-foot 28W T-5 lamp. One recessed fixture with two 2-foot 40W biaxial lamps. The materials for this project were provided by three industry partners and are listed below: Armstrong Building Products provided: Ultima Tegular 2x2 ceiling tiles for the conference room area above the conference table and for private offices (shown in Figure 1). New Tierra High Light Reflectance (LR) and rapidly renewable lay-in 2x2 ceiling tiles for the conference room area by the front hallway. A new ceiling suspension system, including wall moldings, main beams, and cross tees. A silhouette style in the Ultima ceiling areas and a Suprafine style in Tierra ceiling area. (All grid main beams are new Armstrong DC power versions compatible with the draft EMerge Alliance standard.) All of the DC power connectors (shown in Figure 2) and cable assemblies required for connectivity between the Armstrong power grid and Nextek power server, and between all lighting devices, Kanepi devices, and the occupancy sensor and the grid. Nextek Power Systems provided: One 16-channel AC-DC power server compatible with later integration to solar panels (shown in Figure 3). The DC lighting ballasts that mate with the conference room lighting fixture schedule provided by SCE. Southern California Edison Page 5

Kanepi Innovations (formerly Light Corporation) provided: One web-based Intu control system panel assembly (includes the gateway as well as a touch screen for wall installation). Ten 24vdc multiple Intu nodes (shown in Figure 4). One 24vdc Watt Stopper daylight sensor. Two occupant sensing Watt Stopper wall switches. The new lighting equipment listed above was installed in February 2009, and the controls were tuned in June 2009. During the period after the installation of the lighting equipment and prior to the tuning of the controls, the new lighting fixtures were operating continuously. Southern California Edison Page 6

Figure 2 through Figure 6 show various components of the new lighting distribution system. FIGURE 1. POST-RETROFIT CONFERENCE ROOM FIGURE 2. DC POWER CONNECTOR ON THE CEILING GRID FIGURE 3. NEXTEK POWER SERVER POST-RETROFIT FIGURE 4. INTU CONTROL NODE FIGURE 5. CEILING MOUNTED DC POWER GRID Southern California Edison Page 7

TECHNICAL APPROACH In early November 2008, a synergistic multi-channel data recorder logger was installed to record the conference room electric lighting load. This type of logger records true root mean squared (RMS) power measurements for 120 volts alternating current (VAC) or 277 VAC electric loads, either single phase or three phase. Baseline and post-retrofit data was recorded in 15-minute intervals. Figure 6 shows the synergistic logger above the conference room ceiling. The logger was connected to the electric panel, shown in Figure 7, with a breaker to the conference room overhead lighting. During the post-retrofit period, the power of the DC lighting system and controller was monitored as two separate loads. For analysis purposes, both loads were combined as the total energy use of the overhead conference room lighting. After installation of the monitoring equipment, the SCE staff periodically gathered the monitored data. FIGURE 6. SYNERGISTIC LOGGER BOX FIGURE 7. ELECTRIC PANEL Southern California Edison Page 8

RESULTS AND RECOMMENDATIONS This section presents and discusses the data collected from monitoring the retrofitted lighting, as well as recommendations based upon the results. RESULTS The conference room does not have a regular schedule of occupancy. The average and maximum daily conference room lighting load from November 5, 2008 to July 14, 2009, shown in Figure 8. During the baseline period of November 5, 2008 through February 17, 2009, excluding holidays, the weekday peak lighting load ranged from 0.004 kw to 0.436 kw. During the post-retrofit period of June 4, 2009 through July 14, 2009, excluding holidays, the weekday peak lighting load ranged from 0.008 kw to 0.073 kw. 0.50 0.45 0.40 Baseline Post-Retrofit 0.35 0.30 kw 0.25 0.20 0.15 0.10 0.05 0.00 11/5/08 11/19/08 12/3/08 12/17/08 12/31/08 1/14/09 1/28/09 2/11/09 2/25/09 3/11/09 3/25/09 4/8/09 4/22/09 5/6/09 5/20/09 6/3/09 6/17/09 7/1/09 Date Average Daily kw Peak Daily kw FIGURE 8. LOAD PROFILE OF CONFERENCE ROOM LIGHTING Figure 9 shows the average weekday lighting electric load during the baseline period of November 5, 2008 through February 17, 2009, and during the post-retrofit period of June 4, 2009 through July 14, 2009. During the baseline period, the average weekday lighting load peaked at 0.118 kw at 3:00 PM. During the post-retrofit period, the average weekday lighting load peaked at 0.035 kw at 2:45 PM. Figure 10 shows the average weekend lighting electric load during the baseline period and during the post-retrofit period. During the baseline period, the average weekend lighting Southern California Edison Page 9

load peaked at 0.019 kw at 1:30 PM. During the post-retrofit period, the average weekend lighting load peak at 0.012 kw at 11:45 AM. 0.14 0.12 0.10 0.08 kw 0.06 0.04 0.02 0.00 12:00:00 AM 12:45:00 AM 1:30:00 AM 2:15:00 AM 3:00:00 AM 3:45:00 AM 4:30:00 AM 5:15:00 AM 6:00:00 AM 6:45:00 AM 7:30:00 AM 8:15:00 AM 9:00:00 AM 9:45:00 AM 10:30:00 AM 11:15:00 AM 12:00:00 PM 12:45:00 PM 1:30:00 PM 2:15:00 PM 3:00:00 PM 3:45:00 PM 4:30:00 PM 5:15:00 PM 6:00:00 PM 6:45:00 PM 7:30:00 PM 8:15:00 PM 9:00:00 PM 9:45:00 PM 10:30:00 PM 11:15:00 PM Time Baseline Post-Retrofit FIGURE 9. AVERAGE WEEKDAY LIGHTING KW BASELINE AND POST-RETROFIT 0.025 0.020 0.015 0.010 0.005 0.000 12:00:00 AM 12:45:00 AM 1:30:00 AM 2:15:00 AM 3:00:00 AM 3:45:00 AM 4:30:00 AM 5:15:00 AM 6:00:00 AM 6:45:00 AM 7:30:00 AM 8:15:00 AM 9:00:00 AM 9:45:00 AM 10:30:00 AM 11:15:00 AM 12:00:00 PM 12:45:00 PM 1:30:00 PM 2:15:00 PM 3:00:00 PM 3:45:00 PM 4:30:00 PM 5:15:00 PM 6:00:00 PM 6:45:00 PM 7:30:00 PM 8:15:00 PM 9:00:00 PM 9:45:00 PM 10:30:00 PM 11:15:00 PM kw Time Baseline Post-Retrofit FIGURE 10. AVERAGE WEEKEND LIGHTING KW BASELINE AND POST-RETROFIT Southern California Edison Page 10

The annualized conference room lighting energy use decreased from 324 kwh in the baseline period to 156 kwh in the post-retrofit period a decrease of 52%. The decrease is primarily due to the tuning of the controls system to ensure lights were off when not in use and because the lighting system required a manual on and directed the user to select the appropriate scene that would provide the lighting needed for each specific meeting. RECOMMENDATIONS A successful installation of DC-powered lighting with controls was demonstrated in this project evaluation. SCE is looking at zero net energy buildings and as a result, a decision was made to expand this project to include a larger area of the test site to include a kitchen, multiple bathrooms, a hallway, and a manager s office. The preliminary results of this study indicate that there is potential for significant savings to be realized using a DC power grid directly powered by a PV grid producing DC power. It is recommended that a second phase evaluation to study how a typical conference room, kitchen, bathrooms and a manager s office, equipped with a DC power grid and DC-adapted fixtures and appliances can be integrated into a solar PV power distribution, and be done without efficiency losses due to AC power conversion. Southern California Edison Page 11