Installing a Purged Packed (PP) Inlet

Similar documents
Installing a Purged Packed Inlet

Installing a PTV Inlet

Installing a PTV Inlet

Installing a Cool On-Column Inlet

Installation Guide. Flame Ionization Detector on a 6850 GC Accessory G2621

Installation Guide. Thermal Conductivity Detector on a 6850 GC Accessory G2623A

Installing an Auxiliary Pressure Control Module

Installing an Auxiliary Pressure Control Module

Installing the CO 2 Cryogenic Oven Cooling Kit

Agilent G2738A Upstream Capillary Interface

Installation Guide. Purged Packed Inlet, Electronic Pneumatics Control on 6890 GC Accessory G1551A

Installation Guide. Flame Ionization Detector on a 6890 GC. Accessories G1561A, G1562A, G1591A, G1598A

Installation Guide. Nitrogen-Phosphorus Detector on 6890 GC Accessories G1575A, G1576A, G1594A, G1599A

Installation Guide. Auxiliary Pressure Control Manifold on 6890 GC Accessory G1570A

Installing the Flame Ionization Detector EPC Flow Control Manifold

Agilent G1554A On-Column Capillary Inlet with EPC

Installation Guide. Volatiles Interface for 6890 Gas Chromatograph Accessory G2319A

Installation Guide. Heater Interface Cable for Mass Sensitive Detector Accessory G1590A

Agilent G3969A Transfer Line Interface for an Agilent 7697A HS Accessory

Nickel Catalyst Tube on a 6820 GC, Accessory G4318A

Installation Guide Thermal Conductivity Detector Accessory 19232E

Installing the 6850 Direct Valve Column Connector Kit

Nickel Catalyst Tube Accessory 19205A

Agilent G3510A/G3511A Multimode Inlet

Installation Guide NPD/ECD Chemical Filters Accessory 19199N

Valve Box and Valve Accessories G4315A, G4316A, G4317A

Customer Information. Service Engineer s Responsibilities. Additional Instruction Notes GC Preventive Maintenance Checklist Standard

Installation Note for Solvent Selection Valve Upgrade Kit (G1360A)

1350 Valves. 1 of 14. Jun Illustrated Parts Breakdown Agilent 6890 Gas Chromatograph Service Manual

Agilent 6890 Gas Chromatograph

Agilent G3348B Flame Photometric Detector

1310 Inlets. 1 of 36. Jun Illustrated Parts Breakdown Agilent 6890 Gas Chromatograph Service Manual

260 Solvent Vapor Exit Accessory

Agilent G2333B (Single) and G2334B (Dual) Flame Photometric Detectors

Troubleshooting Tips & Tricks for your GC Analyzer & CFT Application

Agilent G2647A (Single) and G2648A (Dual) Flame Photometric Detector Update Kits

HP Adjustable Depth Fixed Rail Kit Installation

6890 Installing ¼ Glass Columns

For more information about Agilent Technologies services please visit our web site using the following URL

Agilent 7820A Gas Chromatograph

A g i l e n t A G a s C h r o m a t o g r a p h Service Manual

Agilent G4367A Auxiliary Electronic Pressure Control (Aux EPC) Module

Installing the G2743A/G2745A Valve Actuator Kits

Customer Information. Service Engineer s Responsibilities. Additional Instruction Notes GC Preventive Maintenance Checklist Standard

29 Installation Step 1. Unpacking the GC Cable diagrams Step 2. Placing the GC system on the benchtop Step 3. Turning the power on

Deans Switch Microfluidics

Agilent 210/218 - Isocratic Pump

Lamp House with 2.5 kw lamp

Installation Instructions. PowerFlex 700 Drive - Frame 8 Components Replacement

Agilent 6850 Series II Network GC System G2630A Performance Specifications

Agilent 490 Micro GC Internal and External Mount Genie Filter Brackets

Ultra Clean Gas Filters Reference Guide ULTRA CLEAN GAS FILTERS

Torque Module Installation and User Guide for model 250i Motorcycle Dynamometers.

Achieving Higher Sensitivities Using GC-FID with the Agilent Multimode Inlet (MMI)

Replacing the Battery in the Patriot SPS 250, SPS 300 and SPS 450

INSTALLATION OF OPTIC 3 INJECTOR SYSTEM ONTO AN SHIMADZU GC-2010 GAS CHROMATOGRAPH.

Altivar 61/71 Adjustable Speed Drives Plastic Kits and Power Terminal Kit

Fast Simulated Distillation Based on Agilent 6890N Gas Chromatograph Application

Alcatel-Lucent 7310 DC Metro Cell AWS (B4) Kit MC-DBR1, MC-DBR2, MC-DBR3, MC-DBR4, MC-DBR5. Installation Manual

Agilent 7697A Headspace Sampler

Gas Chromatographic Analysis of Diesel Fuel Dilution for In-Service Motor Oil Using ASTM Method D7593

Agilent 210/218 - Binary Pump

HP 6890Series Gas Chromatograph. Installation Guide. Flame Ionization Detector. Accessories HP G1561A HP G1562A HP G1591A HP G1598A

Series 3900/M Pump Retrofit Kit

DESCRIPTION. Replacement of batteries B ,2. Charging of batteries B ,4. Replacement of motor B ,6

Agilent Multimode Inlet for Gas Chromatography

Power Fuse Assembly Replacement (for 3000A 1395 DC Drives)

Agilent G2855A Deans Switching System

DURAMAX LBZ EGR DELETE

Oxygenates in Fuels Analysis Solutions From Trace Levels to Ethanol Fuels

Agilent SD-1 Purification System ml/min

Technical Procedure for Gas Chromatography (GC-FID)

Agilent 5975T. Mobile Lab Hardware Installation. Agilent Technologies

Siemens Drives & PLCs

RENA AF371Feeder Operating Manual. Feeder. Operating Manual. Manual Part #: M AF371 Operations Rev

Battery Replacement. Installation Instructions. Summary of Changes. Catalog Number 2711P-RY2032. Original Instructions

Hot Injection Adapter Kit - Installation Guide

Ford 7.3L SuperDuty Cold Air Intake

Model 8610C Gas Chromatograph. GC Chassis Types ECD PID FID / DELCD FPD. Mounts up to Six Detectors and Five Injectors

Model 4430 Photoionization Detector (PID) Operator s Manual

S4M Pulley and Gears Maintenance Kit

GC Injector Liners. Bruker Varian Agilent (HP) Perkin Elmer Finnigan. Phone: Page 4

Genuine Restek Replacement Parts For Agilent 5890 GCs

Replacing the Batteries in the Fortress LI 660

Page 1. Alternate Carrier Gas Considerations and Faster GC Analysis

Model: TON AXLE JACK. March 1999 Rev.-02

Upgrading the Sure Coat Modular Gun Control System

I-VIC300MS. Series 761 Vic-300 MasterSeal Carbon Steel Butterfly Valve Series 461 Vic-300 MasterSeal Stainless Steel Butterfly Valve WARNING

5000TOC Sensor Service Manual

Altivar 61/71 Adjustable Speed Drives Spare Parts Kits

ELECRAFT KX3 Application Note

Spare Allen-Bradle. Battery Replacement. Installation Instructions. About This Publication. Catalog Number 2711P-RY2032

Electrically Held to Mechanically Latched Contactor

Using a New Gas Phase Micro-Fluidic Deans Switch for the 2-D GC Analysis of Trace Methanol in Crude Oil by ASTM Method D7059 Application

Installation Instructions

Agilent and ASTM. Update on Recent Activities. Page 1

Thermo Scientific. TRACE GC Ultra UFM. Ultra Fast Module Device Instruction Manual. PN , Revision May 2010

Agilent InfinityLab LC Series 1260 Infinity II Delay Coil Organizer

INSTRUCTION MANUAL AND PARTS LIST FOR PG/RG3D_-187, 218, 250 and 312 SERIES PUMPS

Enelion Vertica. Installation manual. 22 kw. for the specialists

Transcription:

Installing a Purged Packed (PP) Inlet Agilent 6850 Gas Chromatograph Accessory G2651A These instructions are divided into two parts: Part 1 to prepare the Electronic Pressure Control ("EPC") module for later installation into the Agilent 6850 Gas Chromatograph ("GC") Part 2 to perform the actual Accessory installation into the GC Part 1: Preparation of the PP EPC module Locate the following item found in your Accessory kit: Cover Kit G2630-60081 consisting of: Qty. EPC cover 1 Hex nuts, 7/16-inch 2 Vent fitting 1

5/16-inch hex nuts EPC module cover EPC module vent fitting Caution Some of these assemblies contain printed circuit boards so standard ESD precautions must be followed: use a static control wrist strap (supplied) connected to a suitable ground in handling the assemblies. 2

The following tools are required for this assembly: Tools Required 7/16-inch open end wrench or nut driver Procedure 1. Prepare a suitable clean, dry, static-free work area. 2. Place the inlet system assembly such that its EPC module is centered in your work area with its ribbon cable extending to the right. 3. Remove any dust caps from gas connection fittings. 4. Fold the cable back on itself and gently crease it about midway along its length. 3

4 5. Next, fold the cable back on itself again, but at an angle such that it now extends at 90-degrees in the direction of the gas connection fitting. Again, gently crease the cable at the fold.

6. Next, install a vent fitting and secure it with a 7/16-inch wrench or nut driver. Vent fitting Ribbon cable (folded) 7. Install the cover onto the two gas fittings making sure the ribbon cable and its connector exit through the slot provided. Secure the cover using 7/16-inch hex nuts, one onto each fitting. 5

8. Replace protective dust caps onto gas connection fittings to maintain cleanliness. This completes EPC module preparation for this Accessory. 6

Part 2: Installation of the PP Accessory This kit contains: Description Purged packed column inlet system 1 Top block insulation 1 Bottom block insulation 1 Insulation cup 1 Top cup insulation 1 Bottom cup insulation 1 Bottom cover plate 1 Screw, M4 x 8 mm, Torx T-20 2 Wrist strap, disposable, large 1 Installation sheet (this document) 1 Quantity The purged packed inlet and flow module are a factory-assembled and leaktested unit. Do not disassemble the unit during installation. 7

Insulation cup & insulation Top block insulation Flow module Bottom block insulation Screws Capillary adapter Bottom cover plate Heater/sensor cable Purged packed inlet Inlet shipping kit, containing: Inlet inserts FID jet Detector adapter Inlet liner Tools Required Torx T-10 driver Torx T-20 driver Open end wrenches Safety Information Before continuing, read the safety information on your Agilent 6850 Gas Chromatograph User Information CD-ROM. 8

WARNING Before proceeding, turn off the oven and any heated zones and let them cool down. Turn off all gases at their source, then turn off the main power switch and unplug the power cord. Remove the Lid Top Cover Remove vent tubing, if present Lid top cover, without valve box accessory Remove T-20 Torx screws (8 places) Remove detector cover, if desired Remove the Existing Inlet Removing a Split/Splitless Inlet 1. Open the lid. Disconnect the column from the inlet. 2. Remove the insulation cup and insulation. 9

3. Loosen the screws holding the connector cover plate next to the inlet flow module. Disconnect Remove Loosen 4. Slide the plate off and disconnect the cable from the flow module. 5. Disconnect the gas fitting on the back of the flow module. 6. Remove the three screws on top of the flow module. 7. Use the inlet wrench to release the large nut on top of the inlet. Large nut Insert weldment (includes nut) 8. If you do not have a gas or liquid sample valve Remove the insert weldment and the flow module. If you do have a gas or liquid sample valve The insert weldment is part of the valve assembly. Move it out of the way. Disconnect the gang block fitting, which is also part of the valve assembly, from the flow module. Remove the flow module. 10

9. Use forceps to remove the liner and O-ring. 10. Disconnect the split vent trap. Disconnect Top of liner 11. Trace the heater/sensor cable to the wiring harness connector. Disconnect it. 12. Remove the three screws holding the inlet body. 13. Lift the inlet assembly out of the lid. Remove the insulation in the hole under the inlet. Removing a Purged Packed Inlet 1. Open the lid. Disconnect the column from the inlet. 2. Remove the insulation cup and insulation. Remove the bottom cover plate. 3. Close the lid. 11

4. Loosen the screws holding the connector cover plate next to the inlet flow module. Disconnect Remove Loosen 5. Slide the cover plate off and disconnect the cable from the flow module. 6. Disconnect the gas fitting on the rear of the flow module. 7. Remove the three screws on top of the flow module. 8. Trace the heater/sensor cable from the inlet to the wiring harness connector. Disconnect it. 9. Remove the three screws holding the inlet. 10. Lift the inlet and flow module out of the lid. Remove the insulation in the hole under the inlet. Installing the Purged Packed Inlet 1. Place the bottom block insulation in the inlet hole. 2. Place the top block insulation in the hole. Align the long sides of the hole parallel to the sides of the lid. 3. Place the flow module in position. Secure it with three screws. 4. Lower the inlet into the block insulation. Secure the inlet with three screws. 5. Plug the flow module cable into its connector. Replace the connector cover plate and tighten the screws. 12

6. Connect the carrier supply line to the back of the flow module. 7. Connect the heater/sensor cable to the wiring harness. Finishing Up 1. Discard the center plug in the bottom block insulation. Inside the oven, push the remaining ring over the bottom of the inlet. Force it up until the bottom cover plate can rest flush with the oven top. Secure the cover plate with two screws. 2. Install the cup insulation and the cup. Restore the column connection. 3. Restore carrier and other gases to the instrument. 4. Restore power. 5. Apply your normal operating pressures. Leak-check the flow module, back panel, and column fittings. 13

Agilent Technologies, Inc. 2007 All Rights Reserved. Reproduction, adaptation, or translation without permission is prohibited, except as allowed under the copyright laws. Part number G2652-90108 First Edition, May 2004 Second Edition, March 2007 Replaces part numbers G2651-90107 Printed in USA Agilent Technologies, Inc. 2850 Centerville Road Wilmington, DE 19808-1610 Acknowledgements Torx is a U.S. registered trademark of Textron, Inc. Safety Symbols Warnings in the manual or on the instrument must be observed during all phases of operation, service, and repair of this instrument. Failure to comply with these precautions violates safety standards of design and the intended use of the instrument. Agilent Technologies assumes no liability for the customer s failure to comply with these requirements. In the manual A warning calls attention to a condition or possible situation that could cause injury to the user. A caution calls attention to a condition or possible situation that could damage or destroy the product or the user s work. On the instrument See accompanying instructions for more information. Indicates a hot surface. Indicates hazardous voltages. Indicates earth (ground) terminal. Indicates explosion hazard. Indicates radioactivity hazard. Indicates electrostatic discharge hazard. Pinch hazard.