Virginia Offshore Wind Port Readiness Study

Similar documents
SPECIAL LEGISLATIVE COMMISSION TO STUDY POTENTIAL ECONOMIC OPPORTUNITIES IN THE DEVELOPMENT OF PORT FACILITIES IN THE STATE OF RHODE ISLAND

Hinkley Point C our approach to Health and Safety Iain Graham Head of Health & Safety

Michigan Thumb Loop Transmission Line Project

PLANNED ENHANCEMENTS, NORTHEAST NATURAL GAS PIPELINE SYSTEMS (as of )

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Recommended Vision for the Downtown Rapid Transit Network

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

Engineers Ireland Site Visit 23 rd March 2010

Wheat Marketing Situation

FOR IMMEDIATE RELEASE

THE PORT OF VIRGINIA

January Manufacturing Technology Orders Off After a Strong December

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

U.S. manufacturing technology orders kick off 2018 on a high note

FOR IMMEDIATE RELEASE

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

FOR IMMEDIATE RELEASE

Ministério de Minas e Energia. Minister Eduardo Braga. Brazil - Texas Chamber of Commerce - BRATECC May/2015

FOR IMMEDIATE RELEASE

Within the 300 GW total, the Energy Department estimates that 54 GW will be required from offshore wind to feed the large coastal demand centers.

ABB POWER SYSTEMS CONSULTING

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case

MCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford

Distributed Energy Storage John Steigers Generation Project Development Energy / Business Services

Appendix E Water Supply Modeling

THE TRES AMIGAS PROJECT

Glendale Water & Power Smart Grid Project

Energy Performance Information Request Timeline

Virginia Tech Research Center Arlington, Virginia, USA

TABLE C-43. Manufacturers' new and unfilled orders, {Amounts in millions of dollars] Nondurable. Capital goods. Total. goods.

North Terminal New Bedford. Massachusetts Clean Energy Center 2017 Massachusetts Offshore Wind Ports & Infrastructure Assessment

CEO PROGRAM September 2018

FOR IMMEDIATE RELEASE

Power Transmission Division Erlangen, April 29, 2014

FOR IMMEDIATE RELEASE

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options

City of Austin. Airport Leadership Eliminates GSE Emissions

Appendix G Examples and Recommended Methods

2016 Meteorological Summary for the Galeta Marine Island Laboratory. Prepared by: Steven Paton

Energy Opportunities in Indiana

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

GoToBermuda.com. Q3 Arrivals and Statistics at September 30 th 2015

-1- INTRODUCTION. This report presents historical tabulated data on landings and value of the New Bedford sea scallop fishery from

THE AG INDUSTRY & THE PORT OF VIRGINIA: GROWING OUR ECONOMY

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector


Tidal lagoon snapshot

/

Ocean Energy Development in Korea

McNary Northshore Fishway Hydro Project. History & Lessons Learned

Infrastructure and Offshore Wind: Delivering Energy for an Industry at Scale

End-use petroleum product prices and average crude oil import costs January 2010

Recharge the Future Interim Findings

Hywind Scotland status and plans

Photo on 22 October 2016 Post Matthew. Nags Head Shoreline Management Committee Meeting

HYDROGEN INFRASTRUCTURE & H2MOBILITY ALL ENERGY ABERDEEN MAY 2014

TRAFFIC VOLUME TRENDS July 2002

Operational Opportunities to Minimize Renewables Curtailments

Procurement Plan. Eskom Holdings SOC Limited. Eskom Investment Support Project

March 31, 2014 VIA HAND DELIVERY & ELECTRONIC MAIL

Grain LNG: A Collaborative Approach To LNG Terminal Business Performance Improvement

FOR IMMEDIATE RELEASE

2017 Meteorological Summary for the Galeta Marine Island Laboratory. Prepared by: Steven Paton

End-use petroleum product prices and average crude oil import costs March 2011

AOBA Utility Committee

Mayor and Assembly Briefings

Combining Wind Electricity with Storage in Electric Vehicles

Flexible Capacity Needs and Availability Assessment Hours Technical Study for 2020

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Automotive Aftermarket Giorgio Brusco

NJ Solar Market Update As of 2/29/16

New Jersey Solar Roundtable

Metal Bulletin Conference

Introduction to Veja Mate Offshore Project

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014

Renewable Energy Policy in Japan

Presentation to the Customer Service, Operations and Safety Committee OPERATIONS PERFORMANCE INDICATORS

WIND EXPERIENCE IN RHODE ISLAND MA WIND WORKING GROUP July 8, 2015

The Solar Zone at the UA Tech Park Phase II Expansion

Shadow Flicker Briefing

Rocky Reach Bridge Crane Repair. Commission Presentation February 1, 2016

Thirty Years of Climatological Data: 1969 to 1998

M onthly arket. Jan Table of Contents. Monthly Highlights

Who are the. Metalforming? The leading trade association for the metalforming industry.

Total Production by Month (Acre Feet)

ENVIRONMENT C RSIA CARBON OFFSETTING AND REDUCTION SCHEME FOR INTERNATIONAL AVIATION IMPLEMENTATION PLAN

State of the States NATIONAL BIODIESEL BOARD. Jacobsen Conference. Shelby Neal. May 24, 2018 Chicago, IL

ENERGY SLIDESHOW. Federal Reserve Bank of Dallas

Selling PFIFFNER in the UK. Paul Haines

Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792)

Parcels M and M-1 (7 & 8) South Boston. Massachusetts Clean Energy Center 2017 Massachusetts Offshore Wind Ports & Infrastructure Assessment

Feasibility Study for Promotion of International Infrastructure Projects in FY2011

Energy use in potato stores

Eyre Peninsula electricity supply options investigation

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

/

Smart Grid Subcommittee Report

Draft Results and Open House

Security of Supply. on the European Electricity Market

Transcription:

Virginia Offshore Wind Port Readiness Study Briefing to Virginia Offshore Wind Development Authority Richmond, VA 23 April 2015 George Hagerman VCERC Director of Research Virginia Tech Advanced Research Institute 1100 Exploration Way, Suite 315 Hampton, VA 23666 Email: hagerman@vt.edu Phone: 757-325-6994

Port Evaluation Study Motivation Domestic Manufacturing Impact on Offshore Wind Costs The greatest upside opportunity for reducing the cost of offshore wind energy in Virginia is to attract major elements of a Mid-Atlantic offshore wind supply chain to the state. VIRGINIA COASTAL ENERGY RESEARCH CONSORTIUM, 2010. VIRGINIA OFFSHORE WIND STUDIES, JULY 2007 TO MARCH 2010, FINAL REPORT. 67 PP. Scale of Economic Opportunity (see backup slides) Foundation substructures: 3,300 direct jobs to supply VA, MD, DE, and NJ Wind Energy Areas for a decade Wind turbines & towers: for same market, at least 1,000 direct and 4,000 indirect jobs for a decade Timing of Economic Opportunity (see backup slides) Study must be completed mid-2015 for recommended sites to be ready for supplying Virginia WEA by mid-2020

Port Evaluation Study Objectives Primary objective: to evaluate the general readiness of Virginia s waterfront sites (VEDP value proposition) Secondary objective: to develop waterfront site build-out scenarios for producing and staging various specific offshore wind components wind turbines & towers foundation substructures offshore substation platforms submarine power cables

RFP Primary Sites (Potential Staging Areas)

RFP Secondary Sites (Potential Manufacturing)

Port Evaluation Study Timeline to Date 10 Nov 2014 RFP issued 10 Dec 2014 Proposals due (two received and reviewed) Third week Dec 2014 Scoring completed and selection made 14 Jan 2015 Kick-off meeting Fourth week Feb 2015 Team site visits in Hampton Roads 10 Mar 2015 Interim review meeting #1 23 Apr 2015 Interim review meeting #2 24 Apr 2015 Meetings with Port, Maritime Association, shipyards by 31 July 2015 Final report published

Thank You! Any questions? Email: hagerman@vt.edu

Scale of Economic Opportunity

Total Offshore Wind Potential Capacity in the Smart from the Start Mid-Atlantic WEAs 4800 m 4800 m 456 km 2 ~ 1,980 MW 419 km 2 ~ 1,820 MW 323 km 2 ~ 1,400 MW 1,434 km 2 ~ 6,220 MW Assumes NREL 5 MW reference offshore wind turbine with 126 m diameter rotor, and 20 turbines per whole lease block, which represents a capacity density of 4.34 MW per square kilometer and 11,400 MW of total potential Ormonde project (next slide) uses turbines nearly identical to the NREL 5 MW reference turbine, but is four times more densely packed, with 30 x 5MW turbines and a project area of 8.7 sq. km, representing a capacity density of 17.2 MW per square kilometer. Thus our estimate of total offshore wind potential in the NJ, DE, MD and VA WEAs is very conservative.

Ormonde Offshore Wind Jacket Foundation (UK Round 1 project commissioned in February 2012) Project capacity = 150 MW (30 x 5 MW REpower turbines) Mid-Atlantic total potential capacity with same turbine would be 11,400 MW or 76 Ormonde Projects (2,280 turbines & 2,280 jacket foundations) Sources: http://www.vattenfall.co.uk/en/ormonde.htm www.4coffshore.com/windfarms/ormonde-united-kingdom-uk17.html and photo from: www.vattenfall.com/en/image-bank.htm

Jackets for Mid-Atlantic WEAs Equivalent to 3,300 Direct Steel Fabrication Jobs for a Decade Steel Weights in Ormonde Foundations PIN PILES: 4 piles per jacket x 75 metric tons each PRIMARY STEEL: 450 metric tons per jacket SECONDARY STEEL: 50 metric tons per jacket Steel Fabrication Unit Labor Estimates PIN PILES: 10 hours per metric ton PRIMARY STEEL: 50 hours per metric ton SECONDARY STEEL: 100 hours per metric ton Steel Fabrication Total Labor Estimates PIN PILES: 3,000 hours per jacket PRIMARY STEEL: 22,500 hours per jacket SECONDARY STEEL: 5,000 hours per jacket ---------------------------------------------------------------------------------------------------------------------------------------------- 30,500 hours per jacket x (30 jackets for Ormonde project) x 76 Ormonde-equivalent projects in Mid-Atlantic WEAs = 69,540,000 direct hours or 33,430 direct job-years

Jacket Foundations for Mid-Atlantic WEAs Equivalent to Structural Steel Weight of ~38 CVNs Total Steel in two Ormonde Project s PIN PILES + PRIMARY STEEL + SECONDARY STEEL = 800 metric tons per jacket x 30 jackets per project = 24,000 metric tons per project x two such projects = 48,000 metric tons (47,240 long tons) Foundation steel for two Ormonde Projects equivalent to one Nimitz-class nuclear aircraft carrier (CVN) 76 Ormonde Projects divided by two such projects per CVN = 38 CVNs Nimitz-class Nuclear Aircraft Carrier (CVN) 47,000 long tons of structural steel Source: www.dailypress.com/news/dp-cvn77-01,0,5744629.htmlstory

Alstom Manufacturing Footprint French Offshore Wind Program Tower Assembly plant FRANCE Cherbourg Blade Manufacturing plant Saint-Nazaire Nacelle Assembly plant Generator Manufacturing plant Four new plants to supply Alstom s 1,400-MW French tender award, producing 100 turbines per year, will create 1,000 direct jobs and 4,000 indirect jobs

Timing of Economic Opportunity

Virginia WEA Leased One Month after RI-MA AMI Rhode Island Massachusetts Area of Mutual Interest (AMI) Deepwater commercial lease effective date: 01 Oct 2013 Virginia Dominion commercial lease effective date: 01 Nov 2013

Fastest Possible Commercial Project Timeline (does NOT consider state regulatory processes) Construction Start mid-2019 (or mid-2020 if EIS takes 36 months) 5 (or 6) years of site assessment from 01 May 2014 through mid-2019 (or mid-2020 if EIS takes 36 months) Finding of No Significant Impact for Mid-Atlantic Offshore WEA Lease Issuance and Site Assessment VA lease effective date 01 Nov 2013 Add 2 to 3 years for construction of first 500 600 MW phase & achieving full Phase I power

US Commercial Project Timeline Compared with UK Round 3 Timeline UK Site Award equivalent to US Lease Effective Date UK Lease milestone equivalent to US COP Approval For Lease Effective Date of Oct or Nov 2013, as in RI-MA or VA, the earliest possible offshore construction start would be mid-2019 (or mid-2020 if COP environmental review takes 36 months) UK Round 3 timeline reflects a supply chain that has evolved through two prior rounds of project development, while no US supply chain now exists

Prudent Commercial Project Development Should be Informed by VOWTAP Experience At least one year VOWTAP operating experience needed to effectively inform commercial project engineering & design

New Bedford Commerce Marine Terminal: Five Years from Evaluation Report to Completion Timeline from www.masscec.com/content/port-and-infrastructure-analysisoffshore-wind-energy-development and www.masscec.com/programs/marinecommerce-terminal-new-bedford Feb 2010: Massachusetts Clean Energy Center port survey final report issued, recommending expansion of South Terminal at the Port of New Bedford Nov 2012: Project environmental approval Dec 2012: Solicitation of bids to construct May 2013: Groundbreaking Dec 2014: Completion, 28 acres ready for tenant occupancy TOTAL COST: $113 million See overview video at www.youtube.com/watch?v=-_iajefq4vw and photo sequences at www.flickr.com/photos/mass_cec/sets/72157633230120194

New Bedford Commerce Marine Terminal: Site Aerial Photo Looking East, 30 July 2013 Source: www.flickr.com/photos/mass_cec/sets/72157633230120194

New Bedford Commerce Marine Terminal: Site Aerial Photo Looking East, 10 July 2014 Source: www.flickr.com/photos/mass_cec/sets/72157633230120194

New Bedford Commerce Marine Terminal: Site Aerial Photo Looking East, 06 January 2015 Source: www.flickr.com/photos/mass_cec/sets/72157633230120194