Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Similar documents
Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

PSNH INTERCONNECTION REQUEST

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Noble County Rural Electric Membership Corporation

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Noble County Rural Electric Membership Corporation

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Louisville Gas and Electric Company

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

Form C Renewable Energy Micro-Generation Connection Application Distribution System

Small Generator Interconnection Program Interconnection Technical Requirements

Overview of State Distributed Generation Interconnection Rules

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Interconnection System Impact Study Report Request # GI

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

INTERCONNECTION REQUIREMENTS POLICY

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Umatilla Electric Cooperative Net Metering Rules

Form G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

White River Electric Association, Inc. Net Metering Information & Service Requirements

PV Grid Integration Research in the U.S.

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Large Scale Solar Integration

Distribution System DER Hosting Capacity IEEE34 PV

PV System Impact Guide

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

JEA Distributed Generation Policy Effective April 1, 2018

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION

SCHEDULE NO. ACG33 NET METERING SERVICE

Renewable Grid Integration Research in the U.S.

Net Metering Interconnection Requirements

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

Electric Utility Contact Information Indiana Michigan Power

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATOR INTERCONNECTION APPLICATION

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Definitions. Scope. Customer Generation Interconnection Requirements

Section 6. Generation Interconnection

ROANOKE ELECTRIC COOPERATIVE RATE SCHEDULES

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY

Decision on Merced Irrigation District Transition Agreement

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Net +Plus Connection Code

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

Generator Interconnection System Impact Study For

Solutions for Distributed Generation Protection and Control Issues IPCGRID March 28, 2018

Interconnection and Net Metering Service in Ohio

Guidelines for connection of generators:

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

Micro-Generation Connection Application For Connection of Micro-Generation Facilities of 10 kw

Smart- Grid Ready PV Inverter

AGRALITE ELECTRIC COOPERATIVE 320 EAST HIGHWAY 12 P.O. BOX 228 BENSON, MN PHONE: (320) FAX: (320)

Distribution Feeder Hosting Capacity: What Matters When Planning for DER? April 2015

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Targeted Application of STATCOM Technology in the Distribution Zone

CUSTOMER/ TWIN ARROWS PROJECT

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

SA Power Networks Commissioning Witnessing Checklist

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Universal Interconnection Technology Technology Roadmap Workshop. Associated Barriers to Distributed Generation

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

24. SOLAR INCENTIVE PROGRAM II

Merger of the generator interconnection processes of Valley Electric and the ISO;

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw

Consumer Guidelines for Electric Power Generator Installation and Interconnection

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Georgia Power Renewable Update. October 31, 2016 Marc Vinson

Transcription:

Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company

Outline Southern Company GPC Solar Interconnection Process Application requirements Distribution impact study Witness Testing

Southern Company

Southern Company 45,502 MW of generating capacity 41% natural gas, 37% coal, 16% nuclear, 6% hydro PV 60 MW with 115MW in application process Hydro 2,785 MW of generating capacity with 16MW of new capacity planned for next 5 years Biomass 128 MW Landfill Gas 3.2 MW landfill gas generator in Gulf Power Service Territory

Georgia Power Solar Georgia Public Service Commission adopted a motion that requires Georgia Power Company to bring online 260MW of solar capacity by 2015 and 265MW by 2017 (525MW total). 100MW of distributed small scale generation 425MW of utility scale solar Small generators ( 100 ) are eligible to sell their electricity under the Renewable & Non renewable Tariff (RNR 7) and the Solar Purchase Tariff (SP 1). Larger customers ( 80 ) may sell their electricity as a Qualifying Facility RNR 7 Company will pay avoided cost SP 1 Company will purchase at 17.00 cents/kwh

GPC Number of Interconnection Requests 1 to 65 Inter

GPC kw Installed/Proposed/Anticipated 1 to 5000kW

GPC Average kw per Interconnection 1 to 1000kw/Inter

GPC Interconnection Process 10 Days +10 Days +10 Days Customer Submits Application Package GPC Processes & Reviews Application Package GPC and Customer Site Visits GPC Conducts Distribution System Studies +45 Days +45 Days +5 Days/+90 Days +10 Days/+30 Days Distributed GPC Conducts GPC Offers Customer Customer pays GPC Generation Interconnection Interconnection Interconnection Cost Interconnection Equipment Study Proposal Upfront Agreement Executed +10 Days GPC +Construction Installs GPC Interconnection Equipment +7 Days +3 Days GPC Conducts Facility Acceptance Testing GPC Authorizes Parallel Operation Facility Up to 155 Days + Construction

Customer Submits Application Package Facility One Line Electrical Diagram Facility Relay and Metering One Line Proof of site control in the form of a property tax bill, a lease agreement or other legally binding contract Application for Distributed Interconnection Required Technical Data

GPC Interconnection Process Customer Submits Application Package GPC Processes & Reviews Application Package GPC and Customer Site Visits GPC Conducts Distribution System Studies GPC Conducts Interconnection Equipment Study GPC Offers Customer Interconnection Proposal Distributed Generation Interconnection Agreement Executed Customer pays GPC Interconnection Cost Upfront GPC Installs GPC Interconnection Equipment GPC Conducts Facility Acceptance Testing GPC Authorizes Parallel Operation Facility

GPC Conducts Distribution Equipment Study 15 to 30 Business Days for GPC to conduct and complete DSS of Facilities less than or equal to 2MW after Facility is conceptually finalized by both GPC and Customer. 25 to 45 Business Days for GPC to complete DSS of Facilities 2MW to 10 MW after Facility design is conceptually finalized by both GPC and Customer.

Distribution Study Practices (Inverter Based) Less than 25kW Stamp and Go Procedure Inverter must be UL Standard 1741 Less than 1MW Stiffness Factor Procedure Engineering Guide for Integration of Distributed Storage and Generation EPRI ID: 1024354 Stiffness Factor = Isc/Idsg

DPV Hosting Capacity Category Criteria Basis Flag Voltage Overvoltage Normal Voltage (ANSI C84.1) 1.05 Vpu Voltage Voltage Deviation Maximum difference in node voltage from no PV to full PV Voltage Unbalance Phase voltage deviation (ANSI C84.1) Loading Thermal Element loading 3% at primary 5% at secondary ½ band at regulators 3% 100% normal rating Protection Total Fault Total fault current contribution at Contribution each sectionalizing device 10% increase Protection Forward Flow Fault Contribution Forward flow fault current contribution at each sectionalizing device 10% increase Protection Sympathetic Breaker zero sequence current due to Breaker 150A an upstream fault Tripping Protection Reduction of Deviation in breaker fault current for Breaker Reach feeder faults 10% decrease Protection Breaker/Fuse Fault current increase at fuse relative Coordination to breaker current increase 100A increase Protection Anti-Islanding Minimum load at each sectionalizing device 50% Power Individual Individual harmonic voltage Quality Harmonics magnitude 3% Power Total Quality Harmonics Total harmonic voltage distortion 5% Control Regulator Increased duty > basecase+1 Control Capacitor Increased duty > basecase+1

CYME Analysis (Inverter Based) Voltage Violations 97% to 105% ANSI C84.1 Primary 3% Voltage Imbalance Overload Conditions Neutral current Total current less than 33% of trip setting Simulations Summer peak load without DG Summer peak load with DG Valley at 10:00AM 2:00PM without DG Valley at 10:00AM 2:00PM with DG Locked automation setting testing

CYME Analysis Assumptions Connected Transformer kva Load Allocation Model Use historical peak and valley substation loading information Locked customer loading for customers > 2MVA 60% constant impedance & 40% constant power loads Electronically Coupled Generator Kw, pf, Fault Contribution (140% of nameplate)

GPC Interconnection Process Customer Submits Application Package GPC Processes & Reviews Application Package GPC and Customer Site Visits GPC Conducts Distribution System Studies GPC Conducts Interconnection Equipment Study GPC Offers Customer Interconnection Proposal Distributed Generation Interconnection Agreement Executed Customer pays GPC Interconnection Cost Upfront GPC Installs GPC Interconnection Equipment GPC Conducts Facility Acceptance Testing GPC Authorizes Parallel Operation Facility

Facility Acceptance Testing Inverters >250kW Witness Test GPC Witness Test Personnel Required to record and witness test GPC Switching Personnel Required to operate the disconnecting of the high side fuse or switch Customer Setting Engineer Required to make adjustments to interconnection protection equipment Customer Test Engineer Required to perform secondary injection testing on interconnection protection equipment Customer Systems Operator Required to perform the customer switching of DC and AC systems Inverter Control Engineer Required to make adjustments to set points of the inverter if needed Customer Representative Required to sign witness test report upon completion

Facility Acceptance Testing Transient Overvoltage Test Single Phase Disconnect Test Shut down timing 2 sec disconnect, 5 min reconnect Inverter Control Mode Test Control power factor to predetermined set point 30 min

Site Testing Pictures

Normal Peak Voltage = 400 Volt = 1 PU Maximum Peak reached = 702 Volt = 1.76 PU PASS

Maximum Peak reached = 1100 Volt = 2.75 PU FAIL Normal Peak Voltage = 400 Volt = 1 PU

Maximum Peak reached = 1171 Volt = 2.93 PU Normal Peak Voltage = 400 Volt = 1 PU FAIL Transient Over Voltages last 24 ms

By Comparison, look at the same inverter installed at another location Notice the voltage peaks barely goes above 800 Volts or 2 PU PASS

By Comparison, look at the same inverter installed at another location Notice the voltage peaks barely goes above 800 Volts or 2 PU PASS

Single Phase Open Voltage Test Single phase opened here Single phase closed here Approximately 7 seconds of open phase

After settings on the inverter were changed The inverter takes 2 seconds before shutting down.

Next Steps Interconnection study with multiple connected DG Winter peak interconnection study? Need better estimate of time series impact Need CBA of constant PF inverter control Need to share learnings from utility experiences Southern Company needs to develop a DERMS Develop strategic plans at all business units for the integration of DER

Questions? Dexter Lewis Research Engineer Research and Technology Management Southern Company