Comparison of Bruce A, Bruce Band Darlington

Similar documents
ANALYSIS OF BREST-OD-300 SAFETY DURING ANTICIPATED OPERATIONAL OCCURRENCES

AP1000 European 7. Instrumentation and Controls Design Control Document

AP1000 European 5. Reactor Coolant System and Connected Systems Design Control Document

Startup and Operation of SEE-THRU Nuclear Power Plant for Student Performance MP-SEE-THRU-01 Rev. 018

Thermal Hydraulics Design Limits Class Note II. Professor Neil E. Todreas

By: Eugenijus Uspuras Algirdas Kaliatka Sigitas Rimkevicius ASME 2012 Verification & Validation Symposium May 2-4, 2012, Las Vegas, NV

Module 09 Heavy Water Moderated and Cooled Reactors (CANDU)

1: CANDU Reactor. B. Rouben McMaster University Nuclear Reactor Physics EP 4D03/6D Sept-Dec September 1

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER E: THE REACTOR COOLANT SYSTEM AND RELATED SYSTEMS

PIPE WHIP RESTRAINTS - PROTECTION FOR SAFETY RELATED EQUIPMENT OF WWER NUCLEAR POWER PLANTS

Key-Words : Eddy Current Testing, Garter Spring, Coolant Channels, Eddy Current Test Coil Design etc.

11,000 teu container vessel

Super-Critical Water-cooled Reactors

CNS Fuel Technology Course: Fuel Design Requirements

Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure

The Establishment and Application of TRACE/FRAPTRAN Model for Kuosheng Nuclear Power Plant

Evaluating Generation Considering All Plant Losses and Efficiencies Duane H. Morris, P.E. Tennessee Valley Authority

First Correlating Revision No. 1-NFPA [ Section No ]

CLOSED CIRCUIT HYDROSTATIC TRANSMISSION

Operational Experience with Startup Optimization for Steam Boilers. E.ON s Staudinger, Heyden, Ingolstadt und Zolling Power Plants

Evaluation of a Gearbox s High-Temperature Trip

Rosatom Seminar on Russian Nuclear Energy Technologies and Solutions

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER D: REACTOR AND CORE

Appendix G Examples and Recommended Methods

SUB-CHAPTER E.4 DESIGN OF COMPONENTS AND SUB-SYSTEMS

Super-Critical Water-cooled Reactor

Sealless magnetic coupled centrifugal pump Type NMR Design with heavy duty oil lubricated bearing bracket. our. contribution for

Operational risks of old nuclear power plants in Switzerland

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

CANDU Fuel Bundle Deformation Model

CENTRIFUGAL PUMP AND SEAL (API Std. 610 and 682) Presented By Prakash Kumar ME(NSPL)

PROF. UNIV. EMERIT DR. ING.

Status of HPLWR Development

AP1000 Nuclear Power Plant Squib Valve Design Challenges & Regulatory Interface. September 2017

ams.t.andard REVIEW PLAN.

SEMPELL TURBINE BYPASS VALVE MODEL 115 CHP

HRSG Operational Challenges and Siemens Solutions

Introduction. 1/2 Overview 1/3 Benefits 1/3 Application. 1/3 Order No. code. 1/4 Protection strategy

Balanced Stator Seal for Reactor Coolant Pump Retrofits

AP1000 European 7. Instrumentation and Controls Design Control Document

ENGINEERING STANDARD FOR MACHINERY PIPING

AP Plant Operational Transient Analysis

Model 133 Models 134 & 135 AURORA 130 SERIES SINGLE STAGE TURBINE TYPE PUMPS

Design Factors for Steam Coils

Modular Standardized Electrical and Control Solutions for Fast Track Projects

STANDARD REVIEW PLAN

Sleeve Valves Energy Dissipaters

Two shift operation power plants. Stop valves. Body materials

STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE

Chempump. G Series. Canned Motor Pumps

Proper Propane Pump Installation

AGN 076 Alternator Bearings

MHI Integrally Geared Type Compressor for Large Capacity Application and Process Gas Application

AP1000 Plant Overview

Forsmark 12. S3K Applications. Thomas Smed US User Group Meeting Arizona, October 2008

ME High Pressure Stage Casing Pump

our contribution for Sealless Magnetic Coupled Multistage Centrifugal Pumps Type HZM / HZMR / HZMB environmental protection

Effect of Compressor Inlet Temperature on Cycle Performance for a Supercritical Carbon Dioxide Brayton Cycle

(Refer Slide Time: 1:13)

MC High Pressure Stage Casing Pump

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

Vent/Fan Silencers UNIVERSAL. Vent/Fan Silencers ENERGY ENVIRONMENTAL

PALO VERDE NUCLEAR GENERATING STATION

Complicated Minimal Piping Authors: Presenters: Shelley

Appendix J - 14 (EUB IR-16)

PREHEATER BYPASS SYSTEMS

Presented at SC-2, Meeting October 5-6, 2010,, Seattle, WA

Severe Service Hydraulic Actuators for the Nuclear Power Industry. Enertech Nuclear Qualified Electro-Hydraulic Actuators

Recent Predictions on NPR Capsules by Integrated Fuel Performance Model

Al- Ameen Engg. College. Fluid Machines. Prepared by: AREEF A AP/ ME AL AMEEN ENGINEERING COLLEGE Shoranur.

**EthosEnergy, Power Plant Services Americas

DESIGN AND ANALYSIS OF PRE- INSERTION RESISTOR MECHANISM

IMPROVED BWR CORE DESIGN USING HYDRIDE FUEL

Current Status of the Melcor Nodalization for Atucha I Nuclear Power Plant. Zárate. S.M. and Valle Cepero, R.

Ph: (07) Fax: (07) Pump Manual

BULLETIN January Goulds Model 3700 API th Edition/ISO Process Pumps

An Explosive Situation. Definitions

CASH VALVE K SERIES BACK PRESSURE VALVES

Aoý. 0Constellation Nuclear. Calvert Cliffs Nuclear Power Plant. February 27, U. S. Nuclear Regulatory Commission Washington, DC 20555

MD High Pressure Stage Casing Pump

in Preventing Explosions within Fired Equipment: The Role of Basic Design Data Robert Wasileski A Case Study Process Safety & Loss Prevention Engineer

The IAEA does not normally maintain stocks of reports in this series.

Levalarm Gold. Installation, Operation, & Maintenance Instructions R500.E253A 03/16/2016

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

VARIABLE PUMPS FOR CLOSED LOOP OPERATION type HV-02

Power Jacks have taken time, engineering excellence and the best people to produce the ultra compact Neeter Drive gearbox.

Stress Analysis in Pulley of Stacker-Reclaimer by Using Fem Vs Analytical

A Helium Cooled Particle Fuelled Reactor for Fuel Sustainability. T D Newton, P J Smith, Y Askan. Serco Assurance. Work Sponsored by BNFL

Chemical decontamination in nuclear systems radiation protection issues during planning and realization

Main Steam Isolation Valves (MSIV) in Nuclear Power Plants with PWR

ROTAN INTERNAL GEAR PUMPS. Serving industry since 1921 Available in cast iron, carbon steel, and stainless steel construction

DO COMMERCIAL BUILDINGS HAVE POWER PROBLEMS? THE ANSWER IS - THEY CERTAINLY DO.

SAE Mini BAJA: Suspension and Steering

Design and Performance Study of Shell and Tube Heat Exchanger with Single Segmental Baffle Having Perpendicular & Parallel-Cut Orientation.

CHAPTER THREE DC MOTOR OVERVIEW AND MATHEMATICAL MODEL

SUB-CHAPTER B.3 COMPARISON TABLE COMPARISON WITH REACTORS OF SIMILAR DESIGN (N4 AND KONVOI)

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

Study on Flow Fields in Variable Area Nozzles for Radial Turbines

EMERGENCY DIESEL GENERATOR SETS FOR NUCLEAR POWER PLANTS

Commissioning chilled water TES systems

Transcription:

CompariSOIl ofbmce and Darling/oil A-I Appendix 1 Comparison of Bruce A, Bruce Band Darlington 1.1 Introduction An over'iiew of the differences between Bruce A, Bruce B and Darlington A has been made, concentrating on the nuclear portions of the designs. An overview of the difference between Bruce A and B is also given. Generally, differences between stations arise since the industry is on a learning curve. The equipment suppliers, the designers and the regulatory agencies all contribute their share of progressive and retro-grade changes. All of the difference outline below are a result of this phenomenon. 1.2 The two zone design decision Prior to the design of Bruce A, no power reactor in operation experienced boiling in the primary heat transport system (except for a brief period at NDP during an experimental stage). The two zone system for Bruce A was therefore devised to increase the heat transfer in high power fuel channels without experiencing boiling, increasing the system pressure, increasing channel flow, or boiler area; channel flow was limited to 190,000 Ibmlhr. As illustrated in Figure I, to increase the heat transfer using a single zone system required lowering the RIH temperature (increased steam generator area) raising the ROH temperatore (i.e., increasing ROH pressure), permitting HTS boiling, lowering steam drum pressure and hence temperatore, or some combination of the above. Boiling was not permitted in the HTS. The ROH pressure could not be raised without incurring a bumup penalty due to increased pressure tube thickness. The secondary side conditions could not be changed without an efficiency penalty and an increased torbine cost due to the larger size resulting from lower pressures. This left the one possibility of lowering the RIH temperature. This is not possible in a single zone system without increasing the boiler area, given the above constraints. The 2 zone system evolved, therefore, as a means to lower the RIH temperature of those channels in the centre of the core (inner zone) which nominally have a higher power rating than the outer channels (outer zone). This was achieved by dividing the D 2 0 from the boilers into 2 parts: one cooled by the preheater and one bypassing the preheater (see Figures I and 2). This bypass flow is thus hotter than the preheater outlet flow. The bypass flow supplies the outer zone and the preheater flow supplies the inner zone. Thus, boiling is prevented in all channels. At a later date, the reactor power was uprated and, as a result, some boiling occurs in some outer zone channels. This was judged acceptable based on increased confidence of boiling gained in the interim. However, no net boiling was predicted for the ROH. 1.3 Ramifications of the two-zone system The above design decision to go to the 2 zone system led to the majority of difference between Bruce and Darlington. At the time of the Darlington A design, confidence of a boiling design was already

Comparison ofbroce and Darlington A-2 expressed in the 600 MW(e) design. Hence, Darlington A heat transport system design was based on the 600 MW(e) concept even though the reactor was basically that of Bruce. This meant that boiling, resulting in up to 4% quality at the ROH was pennitted and that a single zone was adequate. Separate Preheaters vs. Integral Preheaters The Bruce concept dictated that the preheater and the boiler be separated to permit a preheater 0,0 bypass flow. Thus, Bruce has separate preheaters while Darlington has integral preheaters. The feedwater train routing, number of valves and control design for each plant reflects this difference. Process Piping The PHT piping is different to reflect the pipe routing requirements as shown in figures 8.4 and 8.6. PHT Pumps and Motors - Trimmed Flow The PHT pumps of Bruce are larger than those of Darlington since full flow is needed for the outer zone channels at Bruce; all channels at Bruce have the same design flow. Trimmed flow is used at Darlington since the inlet temperature is constant for all channels; only enough flow is provided to match the power input of that channel to give a constant enthalpy rise for all channels. Pressurizer Size "e pressurizer size needed for the boiling core Of Darlington is 2247 ft' compared to 1200 ft' of Bruce. The extra volume is required to meet the increased swell and shrink needs resulting from increased void fonnation and collapse. Shutdown Cooling System The separate preheater of Bruce allowed their use in a Shutdown Cooling System. However, full PHT inventory and nonnal PHT circulation are required for its operation. A separate Maintenance Cooling System is required for maintenance requiring partial draining of the heat transport system (pumps, steam generators, etc.). However, Darlington A has a system similar to the maintenance cooling system at Bruce, but called the Shutdown Cooling System, which is used for both shutdown and maintenance cooling. 1.4 Boiler size considerations The state of the art in boiler design dictated that eight boilers be used at Brucc. Larger boilers were deemed feasible by the time of the Darlington A design and four integral preheater "light bulb" type steam generators were chosen. 1.5 One vs. two loops Also following the state of the art thinking on safety concepts and environmental regulations. the two

Comparison of Bruce and Darlington A-3 loop concept, as per the 600 MW(e) design. was chosen for Darlington. This limits the building overpressure upon a loss of primary coolant and prevents fuel failures in the unfailed loop. The single loop concept was considered adequate at the time of the Bruce design. This single loop design can lead to re,"erse flow through a failed pump, unlike the two loop concept. 1.6 Process optimization For Darlington design, an optimization computer code was available which was not available for the Bruce design. Consequently, the flows, temperatures and pressures of both designs are different. Darlington was optimized to generally higher values of the main process parameters compared to Bruce, as shown in Table 8.1. Initially the channel flows limit for Darlington was, as per Bruce, 190,000 Ib,,;hr. Measurements at Bruce A G.S., however, showed that some channels were operating in excess of 200,000 Ibm/hr and the Darlington figures has since been updated for 200,000 IbmJhr with a resulting drop in ROH quality from 4% to 2%. 1.7 Boosters vs. adjusters The Bruce A design uses boosters for reactivity insertion during poison over-ride whereas all subsequent reactors use adjusters. This reflects a reassessment of the Bruce A experience from points of view of economics, safety and complexity. 1.8 Magnetic filters Advances in magnetic filter design prompted the use of these filters on Darlington to augment PHT purification and to reduce the heat loss due to purification. However, experience at Bruce A indicates reduced purification flow requirements and, hence, the magnetic filters may not be economical. 1.9 Process control In the area of process control. Bruce A was designed with digital control for the Reactor Regulating System, the Demand Power Routine. the Unit Power Regulator and the Boiler Pressure Control. Analogue control is used for the Boiler Level Control and the Pressure and Inventory Control. Current thinking on Darlington A is to incorporate all control functions into the main computer as digital controllers. This gives greater flexibility for generating enhanced control routines ifdesired or needed after commissioning and is cost effective if a main computer is being used in any case. 1.10 Separate vs. common steam dj1lm Because of difficulties being experienced at Pickering A in drum level control of the 16 separate drums, a common drum for a bank of four boilers was chosen for Bruce A. Experience gained in the interim plus the fact that Darlington only has 4 steam generators led to the decision to have a separate drum for each boiler. 1.11 Seismic considerations

Comparison of Bmce and Darlington A-4 Darlington A was designed to more stringent seismic requirements than Bruce A. The Bruce A concept ofhanging the boilers from the fixed drum and also hanging the preheaters, allowed for flexibility for thermally induced motion. Seismic snubber requirements were not stringent and hence the cost was acceptable. The more stringent requirements for Darlington A and the fact that a common drum was not available for support led to fixed boilers and pumps plus an expansion loop in the primary pump suction line. 1.12 Critical heat flux Bruce A was designed at AECL based on a critical heat flux correlation as developed by Krishnan, the Krishnan Lower Bound Correlation, for 37-Element fuel bundles. A critical power ratio limit of 1.29 was set as the design criterion. For Darlington A, the design criteria set by Ontario Hydro was a 10% improvement on the Lower Bound Correlation but with a CPR limit of 1.39; this is presently susceptible to a rcdefmition pending the outcome of the recent tests on 37-Element fuel at CRNL and Westinghouse (Canada). 1.13 Differences between Bruce A and Bruce B Operating and Design Pressures Bruce A trip set point is 70 psi above normal operating pressure, whereas the Bruce B reactor trip set point is 100 psi above normal operating pressure. The Bruce B value will reduce the incidence of spurious trips. The Bruce A relief valve sct point is 50 psi above normal operating pressure, whereas the Bruce B relief valve set point is 80 psi above the normal operating pressure to reduce the incidence of spurious operation. Bruce B has an outlet header operating pressure 18 psi above the Bruce A value. This is the highest pressure practical without changing pressure tube thickness. This has a small benefit on CPR. Preheater Design The preheater internals for Bruce B were strengthened and the preheater bypass and rupture disc eliminated. This is \0 eliminate the possibility of excessive damage to the preheater internals due to certain secondary side line failures. Steam Generator Design The Bruce A arrangement consists of a cross-drum design with a common drum serving four steam generators. Warm-up and cooldown rates were severely limited by high stress levels in the Tee Junction area. The Bruce B arrangement consists of integral steam drums for each steam generator which permits

Comparison of Bmce and Darlington A-5 wann-up and cooldown at the design rate. Seismic Design On Bruce A all nuclear structures were analyzed on the basis of a dynamic analysis in both the horizontal and vertical directions based on the ma."ximum hypothetical earthquake that can be expected at or near the Bruce A site. On Bruce B all structures, components and systems are seismically qualified. Two levels of earthquake are defined. The design basis earthquake (DBE) and the site design earthquake (SDE). In addition, three categories of qualification are defined. Category A systems must retain their pressure boundary integrity or structural integrity during and following the specified earthquake. Category ft systems must retain their pressure boundary and remain operating (or operable) during and/or after the specified earthquake. Category C systems must retain their pressure boundary integrity during and after and be operable after the specified earthquake. Heat Transport 'Pump' Design Tlte Bruce B pumps are equipped with an auxiliary impeller that assure adequate flow to the hydrostatic bearings during both forward and reverse turbining conditions. The Bruce A arrangement depended on tlte pump discharge pressure being higher than the pump suction pressure (i.e., forward rotation only). The pump feet strength are significantly higher o~ Bruce B due to the higher postulated burst pipe loads. Heat Transport Pump 'Motor' Design The solid flywheel was eliminated on Bruce B to reduce inspection requirements and ease motor disassembly. Bruce B Itas an improved brake. The Bruce A brake restricts operation under certain conditions. Improved bearing design on Bruce B is incorporated to give better acceptability and to maintain adequate lubrication during reverse rotation. Fuel Channel Assembly Design Seyeral detailed design changes were made on Bruce B to accommodate the effects of a.xial creep. Feeder Design Several changes were made to the Bruce B feeder design to accommodate fuel channel creep. Feedwater Control With the independent steam generators on Bruce B, the feedwater control to ~ steam generator must be regulated. Trim valves are provided in the feed line to each steam generator downstream of the preheaters. '

Comparison ofbnlce and Darlington A-6 Table 8.7 Main Process Parameters and Features Parameter Bruce A Bruce B Darl. A Darl.A Revised ROH pressure 1332 1350 1450 1450 ROH Temperature of 579 579 591 591 ROH Quality %.08 08 3.8 2.0 RIH Temper.ture of 509t483 509/483 509 509 Maximum Channel Flow 190,000 190,000 190.000 200,000 # of channels 480 480 480 480 # of pumps 4 4 4 4 # of steam generators 8 8.\.\ 11 of preheaters 4 4 4.\ Type of preheatclseparate separate integral integral # of Zones 2 2 I 1 # of Loops 1 I 2 2 Channel Flow Typot trimmed not trimmed trimmed trimmed Power Output 750 750 850 850 (balance to BHWP) (Balance to BHWP) PHT Pump Size 9,100 (Hot) 9,100 (Hot) 8,133 (Hot) 8,133 (Hot) Pressurizer Volume (ftl) 1200 1200 2247 2247

ComparisOI1 of B ntce CIJld Darlington A 7 _~R{).J./ TEMP Ii./.H 7" HR,lJIlUM 7E1'1P. I I! feej)i,irt(",,-r::.-_1'" TEMP. '-:-: ~----------J BOJlE:R... i H%D IN flij OlJ"J. 0:0 OUT I)tO IN. I!I Figure A1.1 Bruce heal duly diagram