Feasibility Study Report

Similar documents
System Impact Study Report

Feasibility Study Report

Feasibility Study Report

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project

Interconnection System Impact Study Report Request # GI

Project #94. Generation Interconnection System Impact Study Report Revision

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Georgia Transmission Corporation Georgia Systems Operations Corporation

CUSTOMER/ TWIN ARROWS PROJECT

Project #148. Generation Interconnection System Impact Study Report

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

Interconnection Feasibility Study Report GIP-226-FEAS-R3

100 MW Wind Generation Project

Supplemental Report on the NCTPC Collaborative Transmission Plan

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

MILLIGAN SOLAR PROJECT

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Interconnection Feasibility Study Report GIP-222-FEAS-R3

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Relative Power Factor Correction costs

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Interconnection System Impact Study Final Report February 19, 2018

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

TRANSMISSION PLANNING CRITERIA

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report Request # GI

Falcon-Midway 115 kv Line Uprate Project Report

Generator Interconnection System Impact Study For

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Sub Regional RTEP Committee - Southern. August 19, 2011

SPS Planning Criteria and Study Methodology

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Q87 Generation Interconnection

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

Consulting Agreement Study. Completed for Transmission Customer

ABB POWER SYSTEMS CONSULTING

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

New Mexico Transmission Expansion Concepts For Wind Resources

15 Nelson-Marlborough Regional Plan

New 115 kv Disconnect Switches at Bloomsburg MTS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Q85 Generation Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Stability Study for the Mt. Olive Hartburg 500 kv Line

Reliability Analysis Update

Q217 Generator Interconnection Project

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Transmission Planning using Production Cost Simulation & Power Flow Analysis

PSE Attachment K Puget Sound Area Transmission Meeting

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

SERTP rd Quarter Meeting

El Paso Electric Company

ATTACHMENT Y STUDY REPORT

Decision on Merced Irrigation District Transition Agreement

Overview of State Distributed Generation Interconnection Rules

PUD ELECTRIC SYSTEM INTERCONNECTION

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee South

Midway/Monument Area TTC Study

New Jersey State Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

The Long-Range Transmission Plan

Sub Regional RTEP Committee South

2012 LOCAL TRANSMISSION PLAN:

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

Sub-Regional RTEP Committee PJM South

Illinois State Report

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Gateway South Transmission Project

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Small Generator Interconnection Program Interconnection Technical Requirements

Generation Interconnection Facilities Study For

Q51 Generation Interconnection

Transcription:

Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014 Prepared By: Jeff Rhyne Date: 04/11/2013

Table of Contents 1.0 Introduction... 3 2.0 Study Assumptions and Methodology... 3 3.0 Thermal Study Results... 4 3.1 NRIS Evaluation... 4 3.2 ERIS Evaluation... 4 4.0 Fault Duty Study Results... 4 5.0 Reactive Capability Study Results... 5 2

1.0 Introduction Following are the results of the Generation Feasibility Study for the installation of 79.2 MW of generating capacity in Rutherford County, North Carolina with an estimated Commercial Operation Date of 09/01/2014. 2.0 Study Assumptions and Methodology The power flow cases used in the study were developed from the Duke internal year 2014 summer peak case. The results of Duke s annual screening were used as a baseline to identify the impact of the new generation. All cases were modified to include 79.2 MW of additional generation at the customer site. To determine the thermal impact on Duke s transmission system, the new generation was modeled on the 100 kv line at the connection point. The customer will install a substation and 100/34.5 kv transformer. The economic generation dispatch was also changed by adding the new generation and forcing it on prior to the dispatch of the remaining Duke Balancing Authority Area units. The study cases were re-dispatched, solved and saved for use. The Network Resource Interconnection Service (NRIS) thermal study uses the results of Duke Energy Power Delivery s annual internal screening as a baseline to determine the impact of new generation. The annual internal screening identifies violations of the Duke Energy Transmission System Planning Guidelines and this information is used to develop the transmission asset expansion plan. The annual screening provides branch loading for postulated transmission line or transformer contingencies under various generation dispatches. The thermal study results following the inclusion of the new generation were obtained by the same methods, and are therefore comparable to the annual screening. The results are compared to identify significant impacts to the Duke Energy transmission system. Fault studies are performed by modeling the new generator and previously queued generation ahead of the new generator in the interconnection queue. Any significant changes in fault duty resulting from the new generator s installation are identified. Various faults are placed on the system and their impact versus equipment rating is evaluated. Reactive Capability is evaluated by modeling a facility s generators and step-up transformers (GSUs) at various taps and system voltage conditions. The reactive capability of the facility can be affected by many factors including generator capability limits, excitation limits, and bus voltage limits. The evaluation determines whether sufficient reactive support will be available at the Connection Point. 3

3.0 Thermal Study Results 3.1 NRIS Evaluation The following network upgrades were identified as being attributable to the studied generating facility: Facility Name/Upgrade Existing Size/Type Proposed Size/Type Mileage Estimated Cost Lead Time (months) 1. Install 100 kv Circuit Switcher, relaying, and metering at the connection point. Customer will install substation and 100/34.5 kv transformer. $ 778,447 12 2. Tap transmission line w/ GOAB; 100 kv transmission line to the connection point. $ 350,000 12 3. Off-site relaying upgrades. $ 954,000 12 CUSTOMER TOTAL COST ESTIMATE $2,082,447 12 3.2 ERIS Evaluation Energy Resource Interconnection Service (ERIS) allows the interconnection customer to connect its generation facility to the transmission system and be eligible to deliver its output using the existing firm or non-firm capacity of the transmission system on an as available basis. This section is not applicable for the NC jurisdictional generator interconnection requests. 4.0 Fault Duty Study Results The following breakers will need to be replaced: No breakers were found to have over duty concerns. Total estimated cost for breaker replacements: N/A The fault duty impact was reviewed with the installation of the proposed generation. Breakers at the two nearest tie stations and buses two tiers away were evaluated. There were no breakers overdutied or significantly impacted by the generation. 4

5.0 Reactive Capability Study Results The Duke Energy Carolinas Facilities Connection Requirements (FCR) for generators connected directly to the Transmission System requires that the generator must be able to operate in a power factor range from.93 lag (producing VARS) to.97 lead (absorbing VARS), measured at the connection point. The facility must be capable of supplying at least 0.395 MVAR (0.93 lagging power factor) of dynamic reactive power for each MW supplied at the connection point. The facility shall have the capability to supply this reactive power on a continuous basis at rated MW at a transmission voltage of 1.0 p.u. The facility must also be capable of absorbing 0.251 MVAR (0.97 leading power factor) of dynamic reactive power for each MW supplied at the connection point. The facility shall have the capability to absorb this reactive power on a continuous basis at rated MW at a transmission voltage of 1.05 p.u. For information on generator reactive requirements, reference the Generator Power Factor Requirements document on the Duke Energy OASIS site: http://www.oatioasis.com/duk/dukdocs/generator_interconnection_information.html Assuming the proposed generating facility will meet the VAR requirements as outlined in the Transmission Facilities Connection Requirements, evaluation of MVAR flow and voltages in the vicinity of the Customer s site indicates adequate reactive support exists in the region. Study completed by: Jeff Rhyne, Duke Energy Reviewed by: Ben Harrison, Duke Energy Director, Transmission Planning Carolinas 5