COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

Similar documents
ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Cost Benefit Analysis of Faster Transmission System Protection Systems

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Aswan high dam - Distributed control system AUTOMATION

SEL Microgrid Lessons Learned

Mar H: SUPPLEMENTAL PARALLELING GEAR (16315-H)

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

BREAKER FAILURE PROTECTION

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

Wang Bin & Michael Ho, TIIAE Power management system

Application Note RESIDUAL BUS MAIN-TIE-MAIN AUTOMATIC TRANSFER SCHEME USING THREE GE 850 RELAYS

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

Welcome to the IDEA Webinar Series

SECONDS CAN COST MILLIONS

Arc-Flash Mitigation Technologies. Dennis Balickie

Transformer Protection

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT

Zone Selective Interlocking

The IAEA does not normally maintain stocks of reports in this series.

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

2009 Wind-Diesel Workshop. Microgrid Control System Technology GE Digital Energy, Markham Ontario

OMAR - Power Generation AUTOMATION

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

Safe, Reliable, Cost-Effective Solutions for the Electrical Power Industry.

Modular Standardized Electrical and Control Solutions for Fast Track Projects

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Smart Grid Automation and Centralized FISR

Dual Power. Protection. Protection

CCHMP Comments on ConocoPhillips Incident Report For 10/22/10 Flaring Event

2015 WDC Disturbance and Protection Standards Overview

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

Control System for a Diesel Generator and UPS

Electrical Systems - Course 135 COMPOSITE ELECTRICAL PROTECTIVE SCHEMES: PART II

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

Zone Selective Interlock Module. For GE Circuit Breakers

MTU Onsite Energy powers critical equipment in Rush University Medical Center expansion

MeteorCalc SL. MeteorCalc SL is a CAD plugin for designing street lighting networks.

MNS PDUpro Intelligent power distribution unit

Intelligence in Substation Automation

I-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Copyright 2003 Advanced Power Technologies, Inc.

UNITROL 6800 excitation systems Proven performance solutions

Advanced Protective Relay Training

T5S4P3 Synchronous Condensers Application. Mr. Marco Schenone Mr. Sandro Tuscano Mr. Alessandro Oldrati

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

Cloud-connected solution for utility-scale renewable power

Capital Needs Assessment Riders Advisory Council July2, 2008

Shippensburg University

NEW SERIES OF ETIBREAK EB2 IN VIEW OF SELECTIVITY

Automatic Genset Controller, AGC-4 Display readings Push-button functions Alarm handling Log list

Cloud-connected solution for utility-scale renewable power

Rex Healthcare Medium Voltage System Presentation APEC 2015 March 15-19, 2015

3.0 Radial Distribution Systems

ABB POWER SYSTEMS CONSULTING

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

Utility Distribution Planning 101

High-Impedance Differential Applications With Mismatched CTs

Static frequency converter couples US paper mill s 25-Hz and 60-Hz electricity grids

ABB AG - EPDS. Ultra-Fast Earthing Switch UFES active internal arc protection

PGE POWER SYSTEMS SEMINAR SERIES

Seabrook Substation Reliability Improvement Project

Mechanical, Electrical, Technology Engineering Firm

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

That s how compact transformer protection is today. The customer newsletter of Kries-Energietechnik

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

Protection with distributed generation, experience with the Mont-Soleil wind farm project

City of Palo Alto (ID # 6416) City Council Staff Report

CHAPTER 4 PROTECTION REQUIREMENTS

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

Brochure. Modular Systems wind portfolio Power Collection and Grid Connection products

Power/Vac Vacuum Replacement Breakers for GE Magne-Blast Type AM & AMH Breakers

100 MW Wind Generation Project

Power Solutions Manager Generac Power Systems, Inc.

Interconnection System Impact Study Report Request # GI

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

Low Voltage Switchgear MNS with Integrated VSD

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

Compatibility of STPA with GM System Safety Engineering Process. Padma Sundaram Dave Hartfelder

Microgrid solutions Delivering resilient power anywhere at any time

2015 Minnesota Power Systems Conference Managing Bakken Oil Field Load Growth From a Transmission Perspective

Protection & Control / Commissioning Engineer

Substation automation for a better Baltic power supply

ELE-MOS-E-2006 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

BP OIL -- TOLEDO REFINERY

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PARALLELING SWITCHGEAR

Session 10 NERC Interconnection Requirements

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Transcription:

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS Rachel Mueller, Mayo Clinic Timothy Coyle, PCT, Inc. Presented to: Minnesota Power Systems Conference November 5, 2014 2014 MFMER slide-1

Franklin Heating Station Statistics Established in 1927 390 KPH steam, 12,000 tons cooling, 16.1 MW generation One of two plants serving the 7.2 million square feet of Clinic campus buildings Generation: Condensing turbines TG1 and TG2: Backpressure turbine TG3: Dual-fuel engines DG6 and DG7: 2.5 MW each 6.3 MW 2.4 MW each Distribution: Approximately 4 MW to buildings via 13.8 kv and 2400V feeders Emergency/standby power from DG6 and DG7 2014 MFMER slide-2

161 KV Line To Byron 345 37.5 MVA 37.5 MVA 161 KV Line To Silver Lake RPU Crosstown Substation BUS 6 Ozmun DAHLC Harwick ~7MW BUS 7 BUS 8 G TG6 6.4 MW BUS 5 To SMH Prospect Utility Plant ~2.2MW Mayo ~4.3MW Gonda Hilton/Gugg RMH ~3.7MW Charlton/ Harwick ~6.5 MW Harwick ~1.4MW BUS 3 BUS 4 Franklin Heating Station G TG2 2.5 MW G TG3 6.3 MW G TG1 2.5 MW 2014 MFMER slide-3

2014 MFMER slide-4

Justification for Replacement Age and Condition Inadequate Working Clearance Short Circuit Ratings Exceeded Protection Shortcomings Many breakers in series Long current differential circuits Complex hard-wired load shedding scheme 2014 MFMER slide-5

Pre-Project Short Circuit Duties 2014 MFMER slide-6

Upgraded Short Circuit Duties 2014 MFMER slide-7

Design Constraints No Additional Space Available on Turbine Floor or in Proximity Maintain Crane Access to Basement through Grating in Front of Existing Switchgear Maintain Service to Loads and Generation Capacity During Installation and Commissioning Narrow Time Window for Taking TG3 Out of Service Highly Congested Cable Space Below Existing Switchgear 2014 MFMER slide-8

Selected Option: Three 13.8 kv Buses (Sync Bus) 2014 MFMER slide-9

161 KV Line To Byron 345 37.5 MVA 37.5 MVA 161 KV Line To Silver Lake Charlton/Harwick ~6.5 MW BUS 6 Ozmun DAHLC Harwick ~7MW BUS 7 BUS 8 G TG6 6.4 MW BUS 5B BUS 5A To SMH ~2.2MW Mayo Prospect Utility Plant ~4.3MW Gonda Hilton/Gugg RMH ~3.7MW Proton ~2MW + Buildout Block 12 ~MW?? Sync BUS 3 BUS Z BUS 4 Franklin Heating Station Harwick ~1.4MW G TG2 2.5 MW G TG3 6.3 MW G TG1 2.5 MW 2014 MFMER slide-10

161 KV Line To Byron 345 37.5 MVA 37.5 MVA 161 KV Line To Silver Lake Charlton/Harwick ~6.5 MW BUS 6 Ozmun DAHLC Harwick ~7MW BUS 7 BUS 8 G TG6 6.4 MW BUS 5B To SMH Block 12 ~MW?? ~2.2MW Mayo Prospect Utility Plant ~4.3MW Gonda Hilton/ Guggenheim Sync BUS 3 BUS Z BUS 4 RMH ~3.7MW Proton ~2MW + Buildout Franklin Heating Station BUS 5A Harwick ~1.4MW G TG2 2.5 MW G TG3 6.3 MW G TG1 2.5 M 2014 MFMER slide-11

Protection System Criteria Provide Primary and Backup Protection for all Buses and Circuits Provide Zoned Primary Protection of Buses and Tie Circuits Utilize Micro-Processor Based Relays Consistent with Existing Installed Base Provide Metering Data for All Circuits over Ethernet Implement Simplified Under-frequency Load Shedding 2014 MFMER slide-12

Protection System Design Based on GE UR Platform: F60, F35, G30 Protection Schemes: Buses: Traditional High Impedance Differential, MIB Tie Circuits: Directional Comparison Permissive Tripping with Backup Time Overcurrent, F60 Load Feeders: Time Overcurrent, F60 and F35 Generator: C37.102 with Redundant G30s IEC 61850 Communications for Tie Circuit Protection Redundant Fiber Optic Networks Monitoring at Engineering Workstation 2014 MFMER slide-13

Protection Network Diagram 2014 MFMER slide-14

Network Detail at Bus 3 and Bus Z 2014 MFMER slide-15

Tie Feeder Protection Logic (F60 - Z5) 2014 MFMER slide-16

Load Shed System Design Implemented from RPU ties at Buses 7 and 8 through Bus 5B to Bus Z Manual Enable/Disable switch at FHS Separate from RPU at Buses 7 and 8 on UF and RCOF Arm feeder load shedding at each plant based on separation from RPU and Enable/Disable switch position Shed plant chiller load and feeders based on underfrequency setpoints IEC 61850 Signals: Enable/Disable status from Bus Z to Bus 7 Separation from RPU from Bus 7 to Bus Z Separation from RPU from Bus 5B to Bus Z 2014 MFMER slide-17

Load Shed System Design 161 KV Line To Byron 345 37.5 MVA 37.5 MVA 161 KV Line To Silver Lake Breaker R4 or R5: Trip for f <= 59.95 Hz AND df/dt > - 3.0 Hz/s Shed Plant Load at f <= 59.90 Hz G TG6 BUS 7 BUS 8 No Shed at Bus 5B BUS 5B Shed Plant Load at f <= 59.90 Hz Mayo Hilton/ Guggenheim RMH Harwick Block 12 Sync BUS 3 BUS Z BUS 4 Shed Feeders at Staggered Frequencies G TG2 2.5 MW G TG3 6.3 MW G TG1 2.5 M 2014 MFMER slide-18

Bus 7 Load Shed Logic Trip RPU Tie 2014 MFMER slide-19

Bus 7 Load Shed Logic: Shed Plant Loads 2014 MFMER slide-20

Bus Z Load Shed Logic 2014 MFMER slide-21

Bus Z Load Shed Logic 2014 MFMER slide-22

DEMOLITION, INSTALLATION AND COMMISSIONING Reliability Expectations Tasks What led to things going smoothly? 2014 MFMER slide-23

Mayo Clinic Campus Utility Expectations Zero Electrical or Utility Outages 6 Week Turbine Outage Plant Staff expected to Maintain Plant Operations New Gear but Existing Infrastructure 3 Phases of Project Required Temporary Connections 2014 MFMER slide-24

TASKS End to End Relay Testing Electrical Switching Procedures Operation of Electrical System 2014 MFMER slide-25

End-to-End Relay Testing TYPICAL INSTALLATION REMOTE BUS OUR INSTALLATION REMOTE BUS GOAL: Function test system components simultaneously Settings Communication Fiber Optics Network Coordination GPS PLANT PLANT 2014 MFMER slide-26

TEST STATION Created Test Stations to Simulate End-to-End Installation REMOTE BUS TEST STATION Tested Protective Relaying Elements Tested Load Shed Signals Verified Functionality and Operation of Gear PLANT 2014 MFMER slide-27

On-Line Live Verification using GE UR Software At project completion we used On Line Monitoring to verify Remote I/O 2014 MFMER slide-28

Electrical Switching Procedures Live-Transfer Switching Done Off Hours (night/weekend) Procedures Allowed Safer Practice for Switching Load Insured Safety of Personnel - LOTO Updated Procedure Led to Zero Switching Outages 2014 MFMER slide-29

Electrical Switching Procedures 2014 MFMER slide-30

TIME AND EFFORT DRAFT PROCEDURE WRITING 1 PERSON ~4 HOURS WALKDOWN 3 PERSON ~1 HOUR FINAL PROCEDURE AND REVIEW 1 PERSON ~ 1 HOUR 21 PROCEDURES = 336 HOURS DEDICATED TO WRITING AND PERFORMING SAFE SWITCHING PERFORMING SWITCHING PROCEDURE 4 PERSON ~ 1 HOUR before 4 PERSON ~ 1 HOUR after 2014 MFMER slide-31

Operation of the Electrical System Configuration was Complex During the Installation Process Electrical System was Changing Daily and was Difficult to Operate Management Utilized Tools to Protect from Operation Error 2014 MFMER slide-32

Simplified One-Lines 2014 MFMER slide-33

What led to things going smoothly? PRIORITIZING Safety First Reliability PLANT PREPARATION Utilized other project opportunities to prepare Field verification CULTURE Communicate openly Team 2014 MFMER slide-34

NEW GEAR 2014 MFMER slide-35

NEW GEAR Bus Diff CT 2014 MFMER slide-36

What Happened? We Got Comfortable Started with a Schedule Change. We Didn t Allow for any Mistakes to Occur Failed to Plan for Human Error 2014 MFMER slide-37

Questions? 2014 MFMER slide-38