Age-dependent & multi-load reliability analysis in transmission systems

Similar documents
What makes a smart grid profitable? Dipl. Ing. Hans Schäfers Center for Demand Side Integration, University of Applied Sciences Hamburg

successful integration of distributed generation in rural areas

Implementation of a Wide Area Monitoring System (WAMS) for Austria's Power Grid

New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems

Regenerative braking and the different traction systems

National Committee Kosovo. SEERC October 2017 Istanbul

Protection with distributed generation, experience with the Mont-Soleil wind farm project

Agility in energy Ahead of the challenge, ahead of the change

Case study: Utility-scale battery for balancing power in Germany

Back Up Power for Sochi

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Power Electronics for Medium Voltage Grid Applications Topologies and Semiconductors

Large Scale Storage and Demand Resources - Enabler of Transmission Delivery? Paper Number: 14PESGM2398

Getting Smart Evolution to the Smart Grid April 2008

BSCP31 Trading Unit Application for West Burton A&B Power Stations

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

The Electric Power System

The Baltic Sea Regional Power Market Escape from Isolation! Taavi Veskimägi. CEO Elering AS

Electric Utility Power Systems. Generation of Electricity

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Distributed Energy Storage & More. P.K. Sen, Professor Colorado School of Mines

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2.

ABB Automation & Power World: April 18-21, 2011 WPS System Planning. ABB Inc. April 21, 2011 Slide 1

Pumped Storage Power Plants Solution

Demand and applications for battery energy storage systems in new energy markets with high share of renewables

The Electric Power System

LDC 2.0 EVs, DER, Transactive Energy

Small DER Aggregation Example

PMU-based Wide Area Protection System Concept and application in a large longitudinal system

Measuring the Smartness of the Electricity Grid

Xiangping Wang,PGGI, ABB Engineering (Shanghai) Co. Ltd.,Nov ABB 1000kV Grid Integration AIS Solution in PP. ABB November 16, 2016 Slide 1

Siemens AG 2015 All rights reserved. Answers for energy. Page 1 Amsterdam June 09-11, 2015

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Experiences and Lessons Learnt from Germany

SPEN, Rasmus Larsson, High Voltage Breakers Innovative breaker solutions Substation design

Transmission System Operators in the Interplay between Physics and Market

Northern European power system scenarios for EMPS 2010 to 2030

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

The Energy Queensland Group Notice of no non-network options

Opportunities for Export and Trade Development: Electricity Export Expansion to Europe. Joint EFET & DTEK Legal Workshop

Energiespeicher, Bindeglied zwischen Elektromobilität und Netz

The New Electricity Age

The Influence of Voltage Stability on Congestion Management Cost in a Changing Electricity System. Fabian Hinz.

Modern Regulatory Frameworks for a Flexible, Resilient, & Connected Grid

ECET 211 Electric Machines & Control Lecture 1-1 Electrical Power Generation, Transmission and Distribution

Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

TECHWARE is partner of CONSORZIO ITALIA 2000 (CI2000) Leader in the world for the HHV/HV overhead lines TCW and CI2000 a global

Solar & Storage the Opportunity

Contact person: Pablo Taboada Mobile:

Transmission Grid Development & Investment Planning on EHV Level in Germany

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

SUBSTATION DESIGN TRAINING

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Service and Rehabilitation Electrical Power Systems

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1

The Electric Power System

Final Written Examination.

100 MW Wind Generation Project

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

HVDC Interconnectors Benefits and Challenges

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1

Smart Grids and Integration of Renewable Energies

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Time Delay Technique for Pinpointing PD Noise on Combined Cycle Systems Troy Coleman, Plant Technical Services

REEML. Flicking the Switch: Retail Demand-Side Response under Alternative Electricity Pricing Contracts. IRLE May 21, Tim Capon Taylor Smart 13

The accompanying materials were prepared by EDP and are not to be distributed or reused in any manner without prior consent.

Evaluation of offshore HVDC grid configuration options

Diversifying into Marine Energy. ABB March 2015

A study of the power capacity of regenerative inverters in a DC electric railway system

Substation Concepts for the Future

PV Aggregation Results from Germany

Relative Power Factor Correction costs

The Smarter Network Storage Project

The R&S Group Reliable products for grid systems Hannover Messe companies of Rauscher & Stoecklin SERW ZREW Tesar

Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects

Superconducting Cable Systems for Urban Areas AmpaCity Project - Germany

The Romanian Grid a Hub for Regional Electricity Markets in SEE

EUCL AMI Project Experience Share

BERLIN, Grid compatible flash charging technology E-Mobility Integration Symposium

Optimization Strategies for Electric Vehicle Charging Schedules

Recent Trades in Distribution System

Energy from Waste Grid Connections

Climate change drivers for a single and smart EU grid

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Generation Interconnection Facilities Study For

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2016

The German Solar Experience and Market Thomas Rudolph, Chairman Communications Working Group. Bundesverband Solarwirtschaft e.v.

Power Grid & Blackouts. Prof. Ramzy R. Obaid

High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd.

Wind Turbine. Commissioning Utilizing Mini-Grid Power. Scottish Renewables Onshore Wind Conference & Exhibition Aggreko

Energy storage projects for smart distribution grids

Building Smart Grid with µems CEZ Spring Conference, 16 th -17 th April 2014 Igor Dremelj, VP Smart Grid Solutions EMEA

MANAGING CRITICAL GRID SITUATIONS A MARKET ANALYSIS

American Electric Power s Energy Storage Deployments

Article Approach and examples from Denmark

Electricity markets in Europe : EDF s experience 14/10/2005 EDF-DPI-EPSI

Power System Restoration with Black-Start Pump Storage Power Plants

Smart Control of Low Voltage Grids

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

INCREASING electrical network interconnection is

Transcription:

CIGRE US National Committee 2013 Grid of the Future Symposium October 20-22, 2013 Boston, USA Age-dependent & multi-load reliability analysis in transmission systems Marco Fleckenstein, Prof. Dr. -Ing. Claus Neumann, Prof. Dr. -Ing. Gerd Balzer Technical University of Darmstadt, Institute of Electrical Power Systems Landgraf-Georg-Str. 4, 64283 Darmstadt, Germany phone: +49 6151 16-75004 e-mail: marco.fleckenstein@eev.tu-darmstadt.de

Content Motivation Transmission system model Vertical load situations Reliability values Results Conclusions 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 2

Motivation Technical aspects Higher network utilization Availability of the transmission system Financial interests Liberalization of the energy market Achieve profit Limited billable fees Reduce network risk by constant maintenance costs with risk based maintenance Exact determination of individual asset risk Multi-load reliability analysis Age-dependent outage values 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 3

Structure of the transmission system model Overview Large part of the transmission system from a TSO in Germany The model includes this voltage levels: 380 kv transmission system 220 kv transmission system 110 kv network groups 380 kv overhead line network 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 4

Structure of the transmission system model 380 kv transmission system Detail level: Substations & busbar configurations Switch positions Power plant units & transformers Length of overhead lines Connection points to other TSOs More detailed modeling is difficult. Element Number of Elements Bus bar 145 Center break disconnector 263 Circuit breaker 337 Generator 30 Overhead line Pantograph disconnector Power transformer 4453 km 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 5 952 380/110kV: 78 380/220kV: 25

Structure of the transmission system model 220kV transmission system Detail Level: Length of overhead lines Power plant units No substation layout No reliability data for assets Only modeled structurally. Modeling necessary for load flow in 380 kv system 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 6

Structure of the transmission system model 110kV sub-transmission network groups Detail Level: Coupling transformers from 380 kv & 220 kv Load aggregated as loading of coupling transformers X X X X X X X X Infeed of power plant units disregarded 34 Utility network groups 8 industrial network groups 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 7

Power in GW Load & power plant scenarios 35 30 25 20 15 10 5 0 water uranium hard coal natural gas lignite vertical load 1 2 3 4 5 6 7 8 9 10 number of load scenario k All common network states within one year adopted. Surplus power is transferred into neighboring transmission systems. Power plant power gradients are considered in the model Reliability & Availability analysis for all ten load scenarios T ND (n,k) non-delivered outage duration in h P ND (n,k) non-delivered power in MW T NS (n,k) non-supplied outage duration in h P NS (n,k) non-supplied power in MW 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 8

Values for power plants Type of power plant Load gradients in % per minute Share of auxiliary power in % Number of power plant units Installed gross power in MW Hard coal 2-4 7 10 18 10038 Lignite 1.5 2.5 10-16 27 8599 Gas turbine 25 2-4 1 112 Combined cycle 5 4-6 9 6286 Nuclear 10 4-5 3 3925 Pump storage 100 8.5 1 1096 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 9

Outage Rate of PTR in 1/a Outage Rate of CB, BB, DIS and OHL in 1/a Reliability values Element Outage rate H in [1/a] Outage duration T in [h] Bus bar 0.00032 6.35 Center break disconnector 0.000513 67.63 Circuit breaker 0.001473 64.69 Overhead lines a 0.001562 5.34 Selector switch disconnector b 0 0 Power transformer 0.006411 65.99 0.014 0.012 0.01 0.008 0.006 0.004 0.002 0 0-5 years DIS CB BB OHL PTR 25-30 years 20-25 years 15-20 years 10-15 years 5-10 years 30-35 years 35 years and 0.004 0.0035 0.003 0.0025 0.002 0.0015 0.001 0.0005 0 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 10

outage rates in 1/a Results: outage rates (1) (2) H n W C,n W P,n n outage rate of the individual asset in 1/a. non delivered energy caused by the individual asset n in MWh. non feed in energy of power plants caused by the individual asset n in MWh. identification number of the individual asset. 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Consumption Production 1 2 3 4 5 6 7 8 9 10 number of load scenario k 10 load scenarios peak load scenario 0.7006 0.8887 0.4804 0.5739 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 11

Energy in MWh Number of assets Results outage rates Non-delivered & non-supplied energy of the ten load scenarios 10000 8000 6000 4000 2000 0 Consumption Production 1 2 3 4 5 6 7 8 9 10 number of load scenario k Number of assets responsible for outages 700 600 500 400 300 200 100 0 Consumption Production 1 2 3 4 5 6 7 8 9 10 number of load scenario k 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 12

K(n) in percent 1 27 53 79 105 131 157 183 209 235 261 287 313 339 365 391 417 443 469 495 521 547 573 599 625 651 677 703 729 755 781 807 833 859 885 911 937 Results outage rates W C,Peak,n W C,TL,n non delivered energy caused by the individual asset n during the Peak load with averaged outage rate in MWh. averaged non delivered energy caused by the individual asset n with age-dependent outage rate within the ten load scenarios in MWh. 100% 0% -100% -200% -300% -400% -500% -600% -700% -800% -900% asset n of the 380 kv level 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 13

Conclusions & further work Different load & power plant scenarios are important for asset risk determination Age-dependent outage rates are necessary for exact analysis More reliability and availability data must integrated in the database Source: abb.com Risk-based maintenance is a good possibility to improve the reliability and availability of the transmission system and reduce operative costs. 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 14

End Thank you for your attention. 24 October 2013 Electrical Engineering and Information Technology Institute of Electrical Power Systems Marco Fleckenstein 15