Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India

Similar documents
Analysis of Indian Electricity Distribution Systems for the Integration of High Shares of Rooftop PV. Final report

Frequently Asked Questions for Grid Connected Solar Rooftop Systems

Experiences with policy instruments and IPP procurement processes for grid-connected RE in the ECOWAS region

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

Solar rooftop for Residential Sector. 10 th January,2017

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation

Uttar Pradesh Electricity Regulatory Commission, Lucknow

Power Sector Trends: Focus on States

Solar PV Projects PPA Model

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

SOLAR PV INTEGRATION: ISSUES & CHALLENGES with NET METERING

northeast group, llc India Smart Grid: Market Forecast ( ) January group.com

Status Update/ Progress for R&D, and Pilot Projects on Battery Energy Storage Systems (BESS) TERI & BRPL

GOVERNMENT OF NCT OF DELHI

Presentation on Electric Vehicles - Impact on Utility and Regulatory Interventions

GLOBAL SUCCESS OF PV & NET METERING

Renewable Energy Integration: Wind, Solar and Energy Storage

Building the Business Case for Energy Storage

GRID-INTERACTIVE SPV ROOFTOP PLANTS: AN OPTION FOR INDIA GROWING ENERGY DEMAND

SOLAR PLANT PERFORMANCE IN INDIA

Overview LEASE AGREEMENT (PPA) One time Cost No Up-front Cost Zero or low Up-front Cost. Own the Solar System. Solar System owned by Wilkins

Enhancing Grid Stability in India

NEW ENERGY -4- MOBILITY TECHNOLOGIES

Pumping, cooling, phone charging and beyond:

Anil Agarwal Dialogue 2014

Evaluation and modelling of demand and generation at distribution level for Smart grid implementation

SUBSIDY SCHEME FOR GRID CONNCTED SOLAR ROOFTOP POJECT IN ASSAM UNDER THE 14 MW RESCO AND CAPEX MODEL

Grid Stability Analysis for High Penetration Solar Photovoltaics

5 th NEAESF. Outline

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

25 th May Amal Sinha, CEO BSES Rajdhani Power Ltd.

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Meeting with Commissioner, Kendriya Vidyalaya Sangathan (KVS) New Delhi 11 April 2016

The Electric Power System

Tariff Design Issues: Approaches for Recovering Grid and System Costs

Economics and Barriers to Solar Photovoltaic Applications in Barbados

PINANK ENERGY An ISO 9001: 2015 (QMS) Certified Company Channel Partner: Ministry of New and Renewable Energy, Govt of India

Title of the Presentation

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

MYPD3 tariff restructuring plan use-of-system charges. Brochure

Cabo Verde s new Renewable-Energy-Friendly Grid Code

Energy and Mobility Transition in Metropolitan Areas

PV Off-Grid Market Trends and Business Opportunities in Southeast-Asia

Role of solar PV prosumers in enabling the energy transition towards a fully renewables based power system for India

kvah Billing - Frequently Asked Questions (FAQs)

BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar

160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

UK Research Activities on Advanced Distribution Automation. Dr. Graham Ault

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE

-Mobility Solutions. Electric Taxis

PV reaching socket parity Policy implications for distributed generation. Cédric Philibert, Simon Müller, Hoël Wiesner Renewable Energy Division

How Micro-grids Can Solve Energy Access in Africa while Building the Energy System of the Future

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Grid Integration at the Distribution Level: Challenges and Trends Thomas Ackermann, PhD, Energynautics GmbH

White Paper. P13008 Net-metering concept for Small Scale Embedded Generation in South Africa. prepared for

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

ROLE OF HAREDA IN NET METERING. By : P.C. Sharma Project Officer

Success Story Scaling Up Energy Efficiency An Indian Experience

REGIONAL MEETING ON SUSTAINABLE ENERGY

Basic tariff guiding principles

Green Solutions to Power Problems (Solar & Solar-Wind Hybrid Systems )

E-Mobility in Sustainable Urban Development GRIHA Summit December 2018, New Delhi

Ron Schoff Senior Program Manager, EPRI. USEA Energy Supply Forum Washington, DC October 2, 2014

Smart grid. Social risks, benefits, opportunities. Pankaj Batra Member (Planning), Central Electricity Authority

Regional Meeting on Sustainable Energy for Asia -Pacific Least Developed Countries Kathmandu, Nepal. Surendra Rajbhandari

Targeted Application of STATCOM Technology in the Distribution Zone

Understanding the EV Elephant Path to Green Energy

Measuring the Smartness of the Electricity Grid

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Photovoltaic Distributed Generation

S-PPC. Product Brief. Power Plant Controller Solutions for Energy Storage Systems

Panel Discussion on Accelerating Large Scale Deployment of Rooftop SPV in India

INDIA S LEADING ROOFTOP SOLAR SOLUTIONS PROVIDER 1GW ANNUAL MODULE PRODUCTION CAPACITY

Nehru National Solar Mission, Phase II

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Stationary Energy Storage Solutions 3. Stationary Energy Storage Solutions

Non-network solutions

Utility Operator Model

SOLAR ELECTRIC INVESTMENT ANALYSIS

Singapore CEEA, Oct 2010 Chris Winter, CTO RedFlow. Energy Storage, renewables and the Smart Grid: Technology and business case considerations

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Unnat Jyoti by Affordable LEDs for All Conserve Electricity, Conserve Energy

Forecast Life-Cycle Cost of solar PV Electrity (LCOE) (RM/ KWhr) VS Future Cost of Electricity from Fossil Fuel (RM/ KWhr)

Dispelling Myths: Battery storage is an expensive technology with limited immediate usage

Designing Distributed Generation Tariffs Well

ALZ Electrical Solar Consumer Guide

Utility Distribution Planning 101

INDEPENDENCE. Invest today. Reap benefits for a lifetime.

Application for release of capital subsidy on installation of Grid Connected Solar Power Plant

Electricity industry structure and key players

Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts

NURZAT MYRSALIEVA. Distributed solar technologies: trends and scenarios in the Mediterranean Region

Understanding Impacts of Distributed Solar Generation on Cost Recovery and Rates IAMU Annual Energy Conference Preconference Seminar

UNLOCKING VALUE: MICROGRIDS AND STAND ALONE SYSTEMS

Clark W Gellings, P.E. Fellow CEPSI 2014 October 29, Electric Power Research Institute, Inc. All rights reserved.

JEA Distributed Generation Policy Effective April 1, 2018

Rate Impact of Net Metering. Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010

WHY SOLAR IS GOOD FOR YOU?

Lighting Up Bihar. Robin Burgess, LSE and IGC Michael Greenstone, MIT Nicholas Ryan, Harvard Anant Sudarshan, Harvard and JPAL

Transcription:

Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India Seite 1

Key technical question: How much distributed PV can be integrated in the distribution network without needing any infrastructure upgrades? 05.06.2018 Seite 2

Grid Integration Problem Out of the 40 GW target only 1 GW is achieved as of 01/18 (MNRE) All states have regulatory framework for promotion of rooftop PV via net metering mechanism Delhi Chandigarh At least 20% 50% Haryana 15%/30% Rajasthan 30% Uttar Pradesh 25% Bihar 15% Different states lay down different restrictions for rooftop PV integration 05.06.2018 Limited scientific basis setting these restrictions Only solution proposed - upgrade the transformer / network Concern that high shares of rooftop PV will harm the network ( fear of unknown ) Maharashtra 40% Karnataka 80% Kerala Avg load b/w 8 AM to 4 PM Odisha 75% Andhra Pradesh 60% Tamil Nadu 30% *Map not to scale Restrictions on PV Penetration with respect to Distribution transformer Rated Capacity Seite 3

Study on Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV In partnership with: Government of India Ministry of New and Renewable Energy Consulting support: Partner Distribution licensees: Seite 4

All reports can be downloaded at: link can be found on the last slide Main Report Paper 1: PV Integration manual Brief, high-level overview of the main issues, technical and non-technical and some approaches to carry out similar studies Paper 2: Data Collection and Modelling Data requirements for distribution grid impact study, and how gaps in the data can be closed either by the use of qualified assumptions or by additional data collection and monitoring measures. 05.06.2018 Seite 5

MODEL GRIDS Delhi urban Delhi rural 1 Delhi rural 2 Bhopal urban Bhopal rural Supplied from 33 kv 66 kv 66 kv 132/33 kv 33 kv Dominant cable/line type 300XLPE cable, 5.7 MVA Dog ACSR OHL, 5.7 MVA Dog ACSR OHL, 5.7 MVA Rabbit ACSR OHL, 2.9 MVA Raccoon ACSR OHL, 3.8 MVA Length OHL - 19.8 km 16.7 km 2.7 km 11.0 km Length UG cables 3.1 km 10.9 km 2.6 km - - Total length 3.1 km 30.7 km 19.3 km 2.7 km 11.0 km Installed DT capacity 5.4 MVA 5.2 MVA 4.6 MVA 2.2 MVA 3.7 MVA Peak load 2.5 MW 3.4 MW 3.0 MW 1.1 MW 1.6 MW Seite 6 6

DIFFERENCES DELHI VS. BHOPAL Upstream network for Bhopal only Delhi uses 66 or 33 kv for primary distribution, while Bhopal uses 33 kv exclusively. Delhi: Automatic OLTC Main difference: In Bhopal, the 132/33 kv on-load tap changing transformer is the last instance of voltage control. Voltage and loading in the 33 kv grid thus directly impact 11 and 0.4 kv levels and must thus be considered in the simulations. Delhi is currently retrofitting all 66/11 kv and 33/11 kv OLTC transformers with automatic voltage control. 11 kv is thus decoupled from the upstream network, which need not be modelled. + detailed 400 V networks for Delhi only For one feeder in Delhi, data was available to model the low voltage level (400 V) in detail. All other models used aggregated models for 400 V. Seite 7 7

PV equal distribution 2 EXEMPLARY SCENARIOS/ 1DAY PV DISTRIBUTION ALONG THE FEEDER PV end of feeder Upstream network for Bhopal only PV development may not always be homogeneous. Upstream network for Bhopal only A concentration of PV capacity at the end of a feeder has a higher impact on voltage than homogeneous distribution. + detailed 400 V networks for Delhi only + detailed 400 V networks for Delhi only Seite 8 8

01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 00:00 load in pu SCENARIOS ADAPTED LOAD Additional Load is added with the assumption that there would be a 25% energy consumption (kwh) increase in the load (5% per year for 5 years, 2016 to 2022), typically with regard to Air-Conditioning, where a high evening peak is considered Additional AC Load 1 0.8 0.6 0.4 0.2 0 time of day Seite 9 9

SIMULATIONS Stepwise increase of installed PV generation Delhi urban Delhi rural Bhopal urban Bhopal rural % of DT MW % of DT MW % of DT MW % of DT MW 20% 1.1 15% 1.5 30% 3.9 30% 10.9 50% 2.7 40% 3.9 50% 6.5 50% 18.2 75% 4.1 75% 7.4 75% 9.8 75% 27.2 100% 5.4 100% 9.8 100% 13.0 100% 36.3 150% 8.1 150% 14.7 150% 19.5 150% 54.5 Both rural feeders combined Bhopal: Including upstream PV and parallel feeders Seite 10 10

SIMULATIONS Loading Voltage Peak values Peak values Simulation of a full day with Maximum PV infeed profile Minimum load Evaluation of Highest voltage Highest loading at every time step regardless of position in the grid Peak loading and peak voltage get stored for each variation of installed PV Seite 11 11

1.14 [p.u.] 1.08 RESULTS ON INCREASING PV PENETRATION PV Penetration: 20 % of DTs Voltage 1.1 pu Loading 1.03 0.97 0.92 0.9 pu 0.86-0.00 0.70 1.40 2.10 2.80 [km] 3.50 011kV_Va.. Voltage, Magnitude S02_VVR0.. 29505055.. 29505059.. 29505059.. S03_VVR0.. 29501304.. 29501304.. 29501032.. 29501305.. 29501239.. Seite 12 12

1.14 [p.u.] 1.08 RESULTS DELHI URBAN (1) PV Penetration: 50 % of DTs Voltage 1.1 pu Loading 1.03 0.97 0.92 0.9 pu 0.86-0.00 0.70 1.40 2.10 2.80 [km] 3.50 011kV_Va.. Voltage, Magnitude 29505059.. 29505055.. 29505059.. 29505059.. 29501304.. 29501304.. 29501304.. 29501032.. 29501305.. 29501239.. Seite 13 13

1.14 [p.u.] 1.08 RESULTS DELHI URBAN (2) PV Penetration: 75 % of DTs Voltage 1.1 pu Loading 1.03 0.97 0.92 0.9 pu 0.86-0.00 0.70 1.40 2.10 2.80 [km] 3.50 011kV_Va.. Voltage, Magnitude 29505059.. 29505055.. 29505059.. 29505059.. 29501304.. 29501304.. 29501304.. 29501032.. 29501305.. 29501239.. Seite 14 14

1.14 [p.u.] 1.08 RESULTS DELHI URBAN (3) PV Penetration: 100 % of DTs Voltage 1.1 pu Loading 1.03 0.97 0.92 0.9 pu 0.86-0.00 0.70 1.40 2.10 2.80 [km] 3.50 011kV_Va.. Voltage, Magnitude 29505059.. 29505055.. 29505059.. 29505059.. 29501304.. 29501304.. 29501304.. 29501032.. 29501305.. 29501239.. Seite 15 15

1.14 [p.u.] 1.08 RESULTS DELHI URBAN (4) PV Penetration: 150 % of DTs Voltage 1.1 pu Loading 1.03 0.97 0.92 0.9 pu 0.86-0.00 0.70 1.40 2.10 2.80 [km] 3.50 011kV_Va.. Voltage, Magnitude 29505059.. 29505055.. 29505059.. 29505059.. 29501304.. 29501304.. 29501304.. 29501032.. 29501305.. 29501239.. Seite 16 16

RESULTS DELHI URBAN (6) No issues with PV Seite 17 17

C & R PV systems with an aggregated capacity of up to 75% of the transformer rating can usually be connected without any further measures. In most cases 100% are actually possible. Above 75% the rural networks suffers predominately from over-voltage issues. Voltage issues can be solved with wide area control of the 66/11kV transformer and reactive power provision by the PV systems Above 75% in the urban network, mostly loading problems occur. As the lines are short there is less voltage drop across them. Above 75% line loading issues and above 100% distribution transformer overloading have to be considered critical Besides conventional network reinforcement, implementing peak-shaving battery systems is a possible solutions Seite 18

PV Port + store How can we address the peak(s)? Use of distributed storage with PV: a win-win for both the consumers and distribution licensees Seite 19

Plugs in regular power socket Meets 2x the annual electricity demand of an Indian Home Sprinkler mechanism for cleaning Central Cube housing batteries / inverters / control mechanism Six glass-glass modules (300-350 Wp) Light weight collapsible structure Puncture less foundation Acts as dead weight 05.06.2018 Seite 20

05.06.2018 Seite 21

Electrical configuration of PV Port + Storage Seite 22

Benefit to the Distribution licensees (contd..) Analysis of a discom s power demand with 50,000 PV Ports 0 kwh = no PV-Port 0 kwh = no PV-Port Seite 23

Imperatives of PV Port + Store for the DisComGrid Left: Annual Energy Demand of BRPL with 50,000 PV-Ports, Right: Maximum Reduced Peak Demand of BRPL with 50,000 PV-Ports. 0 kwh = no PV-Port.. 05/06/2018 Seite 24

RESCO Equipment Lease to DISCOM Model Subsidy on Assets Delivers PV Port & Store via Plug and Save SRISTI Scheme Pays Electricity bill at regulated tariff House Owners Owner of PV Seite 25

Scenario 4: At 30% subsidy to RESCO and applicable SRISTI Scheme At 16% ROE Consumer Investment: Initial Contribution of 10% of the capital cost. The Additional capital investment in 8 th and 16 th year. Seite 26

PROSUMER Buying and installing PV will become as simple as to a consumer durable product (e.g. Buying and installing an air conditioner) Mass-scale procurement could lead to substantial cost reduction (e.g. LED by EESL) UPS and PV system are merged in a single product Subsidies if any could be integrated in advance Storage will allow consumers to save more money considering Time of Day tariff scheme introduced by DERC Quality assurance and reliability could be ensured through embedding checks and balances in mass procurement Easy financing (e.g. Zero interest EMI financing) may be encouraged with Banks Lead time for installation may be reduced from several weeks/months to few days DISCOM Reduction in peak demand Increased life of stressed assets Reliability of the network elements shall be improved due to reduced stress on the equipment Promotion of rooftop in residential market will reduce the need of cross-subsidy PV ports shall reduce the requirement of purchase of expensive electricity through exchange market by using firm capacity of storage In several instances Discoms purchase electricity @ more than 5 Rs/kWh Reduction in expensive power procurement / backing down expensive power plant will reduce the overall power purchase cost 05.06.2018Page Page Seite 27 27

http://www.comsolar.in/what-we-do/ capacity-development/grid-integration-study/ Rooftop Photovoltaic project under Indo German Energy Programme Responsible Joerg Gaebler Project Manager Sandeep Goel As a federal enterprise, GIZ supports the German Government in achieving its objectives in the field of international cooperation for sustainable development. Published by Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH Registered offices, Bonn and Eschborn, Germany Indo-German Energy Programme B-5/2, Safdarjung Enclave New Delhi 110 029, India T +91 11 4949 5353 F +91 11 4949 5391 E sandeep.goel@giz.de I www.giz.de 05/06/2018 Seite 28