Option 2 - Convert to Automatic Train Control (ATC) Signalling Technology

Similar documents
3. SIGNALLING 3.1 INTRODUCTION. Present Operation - Facts and Figures

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

TORONTO TRANSIT COMMISSION REPORT NO.

Precision Station Stopping Progress Update

4.2 Series Station Option Description

Vernon G. Hartsock, PMP Deputy Chief / Chief Engineer Maryland Transit Administration. Tedd L. Snyder, P.E. Senior System Engineer CH2M Hill

System integration through operability

STAFF REPORT INFORMATION ONLY

Preliminary market consultation session

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING

Peninsula Corridor Electrification Project Cost / Schedule Update

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

Issues Facing the Panel

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO.

METRO PERFORMANCE. The quest for system performance in Singapore re-signalling project. L Y Lam FIRSE

Appendix B CTA Transit Data Supporting Documentation

Service and Operations Planning for Ottawa s New Light Rail Line Pat Scrimgeour

LAX Landside Access Modernization Program. APM Operating System Supplier Eligibility Determination Process

Red Line Customer Capacity Update. Fiscal & Management Control Board September 19, 2016

Table 8-1: Service Frequencies for All Short-List Alternatives by Day of Week and Time of Day Frequency Day of Week Time of Day Time Period

PROJECT BACKGROUND 3

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO.

CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018

Public Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Developing Toronto s Transit Network Plan to 2031

Washington Metropolitan Area Transit Authority

Driverless Train Operation

TORONTO TRANSIT COMMISSION REPORT NO.

Travel Time Savings Memorandum

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update

A study of the power capacity of regenerative inverters in a DC electric railway system

4 COSTS AND OPERATIONS

TORONTO TRANSIT COMMISSION REPORT NO.

Automation in urban public transportation

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site

Special Conditions: General Electric Company, GE9X Engine Models; Endurance Test

Roma McKenzie-Campbell Amtrak, Project Manager. Caroline Ducas VHB, Senior Transit Planner. Boston, Massachusetts

P.C.C. Cars 591 Small Witt pay-enter 100 Large Witt pay-enter 75 Large Witt 2-man 173 Trailers 105

Funding Scenario Descriptions & Performance

How do you make your vehicles fit for the future?

Welcome to Open House #5 Scarborough Rapid Transit

United Nations Environment Programme

Accessible Transit Services Plan

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

Automatic Train Control. Stuart Landau CH2M HILL, System Engineer. Port Authority of NY and NJ, Program Manager. Jersey City, NJ

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 40 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ).

State-of-the-art architectures State-of-the-art testing Jürgen Schölzel, Siemens AG, Mobility Division

On-Road Emissions Reductions and the Regional Comprehensive Goods Movement Plan Background and Policy Questions

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

Steering Actuator for Autonomous Driving and Platooning *1

TORONTO TRANSIT COMMISSION REPORT NO.

Grounding Of Standby & Emergency Power Systems

Yonge Relief Network Study (YRNS)

Transit Vehicle (Trolley) Technology Review

Platform Steering Group #11 The Italian feedback from the field (ERTMS lines in commercial operation)

Energy Management for Regenerative Brakes on a DC Feeding System

CalMod Program EMU Procurement Update

HOUSE BILL No Koch

ABB in primary aluminium From mine to market

Opportunities for Improved Bus Service on Finch Avenue 27 April 2011

TORONTO TRANSIT COMMISSION REPORT NO.

Appendix G: Rapid Transit Technology Backgrounder July 2017

High-Power Electric Systems for Transportation and Energy Storage December TransPower

Electric Multiple Unit Procurement Update

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

CalMod Program EMU Procurement Update. TJPA Board May 14, 2015

Attachment 5 Eglinton West LRT Planning and Technical Update

Residential Curbside Recycling

Merger of the generator interconnection processes of Valley Electric and the ISO;

Regional Express Rail: Kipling Station Project Update. Ryah Kazman, Community Relations Specialist Metrolinx

Curbing emissions and energy consumption in the transport sector how can we deal with it in Warsaw 2012 Annual POLIS Conference

Railroad Impact Study

AIR POLLUTION AND ENERGY EFFICIENCY. Update on the proposal for "A transparent and reliable hull and propeller performance standard"

TRANSPORTATION REVIEW

Developing an adaptable and flexible electric vehicle charging station

1.0 Detailed Definition of Alternatives

What action is expected to take place in the foreseeable future in ADRs with regard to seat belts on school buses?

EXECUTIVE SUMMARY. Introduction

VAN NESS AVENUE BUS RAPID TRANSIT

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan

Decision on Merced Irrigation District Transition Agreement

Traffic and Toll Revenue Estimates

Epping to Chatswood Railway Temporary Transport Plan

Region of Waterloo Stage 1 Light Rail Project Appendix A System Description. RFP Version 3.0

STAFF REPORT ACTION REQUIRED

Docket No EI Date: May 22, 2014

Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology

PUBLIC TRANSPORTATION

Is Your Factory Power Source Corrupting Your Product Testing? September 2015 Author: Steve Boegle Engineering Group Leader, Behlman Electronics

Downtown One Way Street Conversion Technical Feasibility Report

FIVE WAYS TO OPTIMIZE YOUR FLEET WITH GPS TRACKING

Transcription:

Option 2 - Convert to Automatic Train Control (ATC) Signalling Technology Option 2 is substantially different from the previous options, in that replacement of the existing signalling system, rather than modification, is proposed. Option 2 also differs from the previous options, as an incremental approach to achieving reduced headway capability is not possible when changing signalling technology, as will be explained below. Based on the findings of Gibbs & Hill, Inc., Option 2 represents the only signalling option available that, if implemented, would provide 90 second headway capability on the Y/U/S subway. After concluding that 90 second headway operation is not possible with the existing Y/U/S signalling technology, Gibbs & Hill conducted a review of signalling technologies operating in other transit systems in North America, South America and Europe. The purpose of this review was to identify a signalling technology suitable for implementation on the Y/U/S subway which could provide 90 second headway capability. Gibbs & Hill concluded that the type of signalling system presently operating in Washington, Atlanta and Sao Paulo, Brazil would be best suited to implementation on the Y/U/S subway, and that 90 second headway capability could be achieved with this type of signalling technology. Gibbs & Hill therefore recommended the installation of this type of signalling system on the Y/U/S subway in order to achieve 90 second headway operation. The recommended type of signalling system is an Automatic Train Control (ATC) System, which utilizes audio-frequency coded track circuits for train detection. Automatic Train Control Systems are typically composed of three subsystems: 1. Automatic Train Protection (ATP) which maintains safe train separation, enforces train speed limits, and prevents conflicting moves at crossover areas. 2. Automatic Train Operation (ATO) which performs acceleration, speed control, braking and station stopping functions. Door operation can also be automated. 3. Automatic Train Supervision (ATS) which performs train routing, dispatching and schedule regulation functions. Other more sophisticated functions are also possible. The ATP subsystem, the lowest in the ATC hierarchical structure, provides the primary reduction in headway due to provision of continuous speed control (which permits closer train separation) and due to a reduction in equipment operation and operator reaction times. Basic ATS functions, such as train dispatching, route selection and schedule regulation would be essential for efficient and reliable operation at 90 second headways. Gibbs & Hill suggested that the ATO capability is optional, however, it is recognized that ATO capability would be very desirable in order to achieve smooth and consistent operation. If consistent with Commission policy, it would also be technically possible to reduce train crew size to one operator, resulting in substantial savings in operating labour costs, if ATO capability was provided. Basic ATS and ATO capabilities have therefore been included in the cost estimate. More consistent operation compared to present operation is likely to result from implementation of an ATC System comprised of the three subsystems discussed above.

Extensive testing of proposed ATC train detection equipment would be required before the final selection of an ATC system was made in order to confirm electromagnetic compatibility with the TTC vehicle fleet. Selection of a particular type of ATC System could, however, result in the Commission being "locked in" to a technology which may only be available from one supplier, and which may become obsolete before the project is completed. Close co-ordination between the ATC system supplier, the vehicle manufacturer, and the Commission would be essential in order to ensure compatibility of all system components, both wayside and on-board. In order to achieve 90 second headway capability in the Y/U/S subway, the existing signalling system must be replaced with the ATC system described above. Signals at trackside would, however, be left at crossover areas and possibly at the leaving end of station platforms. On-board ATC equipment must also be installed in all Y/U/S vehicles. Modification of the existing traction power system would be necessary (as discussed under "Impact on Traction Power System"). In order to maintain service during implementation, conversion to ATC would have to be done in segments. Conversion of a segment would be a complex task, requiring a great deal of planning and co-ordination. Much of the difficulty would be related to conversion of the train detection (track circuit) equipment. As work was completed in a segment, ATC operation in that segment could be introduced. However, introduction of ATC operation would not be possible until all trains to be operated on the segment were equipped with ATC equipment. In addition to field work at trackside, extensive modifications would also be required at all signal equipment and control rooms, as well as at the Hillcrest Transit Control Centre, and at the zone control centres at St. George and Eglinton. The extensive modifications at Hillcrest would suggest that the new Transit Control Centre should be constructed if ATC is adopted. In addition to the signalling modifications described above, reconstruction of Bloor Station would be required to reduce station dwell time to about 30 seconds 7. Reconstruction of Finch and Wilson terminals would also be required, in order to provide train turnaround capabilities consistent with 90 second headway operation. The proposed terminal configuration is identical to that proposed under Options IB and 1C, and is shown in Exhibit 3.3.3. Alternatively, subway extensions could be constructed to new terminal facilities designed for 90 second headway operation. (Reconstruction of Bloor and Finch may already be completed under Option IB, if an implementation sequence of 1A, IB, 2 is adopted). Operation at a 90 second headway would correspond to a service of 40 trains per hour. This level of service would provide a capacity increase of about 14,400 pphpd over present levels. Gibbs & Hill estimated that in the ultimate system in which station dwells 7 Gibbs & Hill concluded that 90 second headway operation would be possible with a 45 second dwell at Bloor. However, the operation at Bloor would be extremely sensitive to variations in station dwell. Reconstruction of Bloor Station is therefore considered essential to achieve acceptable operation.

average 30 seconds, a total of 88 trains would be required in service, based on standard rate of operation and train turnaround behind modified terminal stations. If it is assumed, however, that the average station dwells in the ultimate system will be similar to dwells that exist today (i.e. less than 30 seconds at most stations), a total of 83 trains would be required in service. Allowing 12% spare cars, a total fleet of 558 cars would be required. All cars would have to be equipped with ATC equipment. A fleet increase of 196 cars over Option IB (or 256 cars over present) would be required, which would necessitate construction of additional yard storage facilities. Part of the fleet increase would be due to the increase in round trip time which would result from reduced speeds associated with achieving 90 second headway capability. New and existing yard facilities would have to be equipped with ATC test and repair facilities, including an ATC test track. Maintenance vehicles would also have to be equipped with ATC equipment. It must be noted that the current ability to interchange vehicles between the Y/U/S and Bloor- Danforth subways would be lost. Implementation of ATC in the Y/U/S subway could be completed within about 15 years from approval based on the present duration of the line shutdown period each night. Most of this time (11 years) is required for the segment conversion process previously described which must be done during non-revenue hours. An additional 2 years would be required for system planning and design, and a further 2 years would be needed for testing and training. It is considered however, that the duration of the implementation period could be reduced to 8 years minimum, (after completion of planning activities), if sections of the Y/U/S Line could be closed at 10:00 p.m. each night on a regular basis. It is recognized however, that the impact of closing the subway early at night would be significant. It is important to note that no benefit, in terms of reduced headway capability, would be realized until the entire project was completed. Interruptions and delays to service would be unavoidable during the implementation period, and temporary shutdowns of the subway (during evenings or weekends) would be required. The estimated cost for the implementation of an ATC system is $132,850,000 including removal of the existing signalling equipment. Traction power modifications are estimated to cost $1,150,000 based on standard rate of operation. Signals and trackwork at Finch are estimated to cost $10,800,000. Signals and trackwork at Wilson are estimated to cost up to $32,600,000 including a new connection to Wilson Yard. Retrofitting of the existing vehicle fleet (as of Option 1B) to accept ATC equipment is estimated to cost $36,200,000 (including work vehicles). Procurement of 196 additional ATC-equipped cars is estimated to cost $372,400,000. Two relief crews would be required at each terminal station at an estimated cost of $200,000 annually per relief crew, over and above the cost of operating and maintaining the additional service. The primary features of Option 2 are summarized in Exhibit 3.3.5.

PROPOSED OPERATION EXHIBIT 3.3.5 OPTION 2 SUMMARY CONVERT TO ATC SIGNALLING TECHNOLOGY capacity increased by about 14,400 pphpd 90 seconds headway operation (40 trains/hour) train turnaround accomplished behind modified terminals provide 2 relief crews at each terminal MODIFICATIONS REQUIRED replace existing signalling system with ATC technology replace central control panel at Hillcrest, and zone control panels at St. George and Eglinton replace all auxiliary control panels on Y/U/S line retrofit existing vehicles with on-board ATC equipment construct a new yard to accommodate increased fleet provide ATC test and repair facilities in all yards provide increased traction power capacity reconstruct Bloor Station to reduce dwell time reconstruct Wilson terminal, or alternatively, extend the subway to a new terminal north of Wilson. reconstruct Finch terminal FLEET REQUIREMENTS 83 service trains required to provide 90 second headway operation (based on standard rate, station dwells similar to existing dwells, and train turnaround behind modified terminals) fleet increase of 196 cars (over Option IB) required including spares all cars to be equipped with on-board ATC equipment IMPLICATIONS major change in signalling and operating philosophy increased trip time due to reduced speed and increased travel distance at terminals lost value of existing signalling system which is not at the end of its design life reduced vehicle reliability due to on-board ATC equipment more complex train control system

BENEFITS OF ATC TECHNOLOGY potential for reduced manpower operating cost provision of continuous train overspeed protection more consistent train operation compared to wayside signalling design objective of 90 second headway achieved IMPLEMENTATION long implementation period (8 years minimum after planning and related studies are completed.) benefits only realized when entire project completed significant disruption to service during implementation the Commission would be "locked in" to an ATC technology which may become obsolete before the project is completed ESTIMATED COST ($1988) $134,000,000 for ATC equipment and traction power $43,400,000 for signals & trackwork at Finch & Wilson $36,200,000 to retrofit existing vehicles for ATC $372,400,000 for 196 additional ATC-equipped cars TOTAL COST OF OPTION 2 (SEQUENCE 1A,1B,2) $708,000,000 INCREMENTAL COST OF OPTION 2 (OVER IB) $575,200,000 (Structural modifications at Bloor, Finch and Wilson, plus new yard facilities. not included.)