Generator Interconnection System Impact Study For

Similar documents
Generation Interconnection Facilities Study For

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

System Impact Study Report

100 MW Wind Generation Project

Interconnection System Impact Study Report Request # GI

Interconnection Feasibility Study Report GIP-226-FEAS-R3

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

MILLIGAN SOLAR PROJECT

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Feasibility Study Report

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Feasibility Study Report

Q85 Generation Interconnection

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Sub Regional RTEP Committee Western Region ATSI

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

CUSTOMER/ TWIN ARROWS PROJECT

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Midway/Monument Area TTC Study

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

2015 WDC Disturbance and Protection Standards Overview

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

Q87 Generation Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Southwest Power Pool, Inc TPL Stability Study. MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group

Interconnection Feasibility Study Report GIP-084-FEAS-R2

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0

Gateway South Transmission Project

Q217 Generator Interconnection Project

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

SPS Planning Criteria and Study Methodology

Small Generator Interconnection Program Interconnection Technical Requirements

El Paso Electric Company

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Guidelines for connection of generators:

APPENDIX E: Project Need and Description

PES Cook Islands KEMA Grid Study Final Report

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Consulting Agreement Study. Completed for Transmission Customer

Sub-Regional RTEP Committee PJM South

Feasibility Study for the Q MW Solar Project

PUD ELECTRIC SYSTEM INTERCONNECTION

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Implementing a Microgrid Using Standard Utility Control Equipment

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Feasibility Study Report

Interconnection System Impact Study Final Report February 19, 2018

Georgia Transmission Corporation Georgia Systems Operations Corporation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Western Area Power Administration Sierra Nevada Region

Project #148. Generation Interconnection System Impact Study Report

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Functional Specification Revision History

Sunmine Solar Project. Interconnection System Impact Study

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Project #94. Generation Interconnection System Impact Study Report Revision

Reliability Analysis Update

AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES

APPENDIX E: Project Need and Description

TRANSMISSION PLANNING CRITERIA

2012 LOCAL TRANSMISSION PLAN:

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Feasibility Study for the Q MW Solar Project

North Oregon Coast Area Study. Adam Lint

Composite Load Model Sensitivity Study

Targeted Application of STATCOM Technology in the Distribution Zone

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Session 10 NERC Interconnection Requirements

III. Substation Bus Configurations & Substation Design Recommendations

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Essential Reliability Services From PV Plants

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Transcription:

Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning

Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications... Page 3 II. Transmission Studies... Page 3 A. Power Flow Analysis... Page 3 B. Short Circuit Analysis... Page 4 C. Stability Analysis... Page 4 III. General Engineering Design & Cost... Page 9 A. Engineer Single line Layout... Page 9 B. Transmission and Substation Cost... Page 11 IV. Summary... Page 11 2

General Discussion Generator Interconnection Impact Study For in Estill, SC Generator Interconnection System Impact Studies (GISIS) follow Generator Interconnection Feasibility Studies, and are detailed studies of the SCE&G transmission system considering the full output of the proposed new generation. System Impact Studies include a full test of the NERC Reliability Standards Table 1 and the SCE&G Internal Transmission Planning Criteria. The Estill 8.5 MVA generator was studied based on its position in our generator interconnection request queue. Therefore, generation requests submitted before this one have been included in this study. If any of the higher priority requests do not materialize, an additional study or assessment of this interconnection request will be required. This Generator Impact Study is requested by. In this study, requested a Solar Photovoltaic (PV) plant in Hampton County. This solar facility has a total generation capacity of 8.5 MVA, consisting of (12) Schneider Electric Conext Core XC680-NA 680 kva solar inverters. This facility is proposed for the year 2015. requested this generation be interconnected to the existing SCE&G 46 kv transmission system. In this report, SCE&G Transmission Planning provides interconnection information for a Solar PV plant near the Fairfax Estill 46 kv line near the Hampton County site. I. Generator Interconnection Specifications The solar generation facility design consists of the following information: MVA: 8.5 MW: 8.16 PF: 80% lead/lag GSU: 46/26.56 kv (Wye-Wye) Speed: N/A II. Transmission Studies A. Power Flow Analysis For the proposed generator interconnection at the used the following base cases for the studies: site, Transmission Planning -2014 SERC LTSG 2016 Light, Shoulder, and Peak Load Cases -2014 SERC LTSG 2018 Light, Shoulder, and Peak Load Cases -2014 SERC LTSG 2025 Light, Shoulder, and Peak Load Cases 3

With a single solar photovoltaic plant consisting of (12) 680 kva solar inverters connected near the Fairfax Estill 46 kv line, there are no overloaded transmission facilities in the base case. The full test of the NERC Reliability Standards Table 1 and the SCE&G Internal Transmission Planning Criteria shows no overloaded lines or voltage violations on the SCE&G transmission system for contingencies on the SCE&G transmission system. The 8.5 MVA PV plant will at times exceed the minimum daylight loading on the four 46 kv circuits fed through the two 115-46 kv transformers at the Fairfax Transmission Substation. This will result in reverse power flow from the 46 kv to 115 kv system; therefore, all existing voltage regulating and metering and protective devices will need to be capable of managing bi-directional electrical flow. The need for this capability exists in higher priority generator interconnection requests and may be completed as part of a generator interconnection that has a higher position in the generator interconnection queue. If the higher position generator interconnection requests drop out of the queue, then these modifications will need to be made at an estimated cost of $8,000. This $8,000 cost is not included in the cost estimate in section III of this report. B. Short Circuit Analysis A short circuit analysis was performed to assess the impact of the addition of the proposed Solar PV plant to the SCE&G transmission system. The analysis shows no overstressed breakers on the SCE&G transmission system due to the proposed Solar PV plant. C. Stability Analysis 1. Overview of Stability Analysis The stability study examined the effects of connecting one Solar PV plant consisting of (12) 680 kva solar inverters connected to SCE&G s 46 kv system through a 26.56/46 kv step-up transformation on the Fairfax Estill 46 kv line in Hampton County. The effects of the proposed generator on the SCE&G system as well as the effects of system events on the proposed generators were studied. The base cases used in the stability study were the following: -2013 MMWG 2015 Summer Case -SCE&G area updated with 2016 Summer model including Dynamic Load Model (DLM) data -2013 MMWG 2014 Light Load Case -SCE&G area updated with 2016 Light Load model including Dynamic Load Model (DLM) data 4

The stability study of the interconnection of the Solar PV plant to the SCE&G transmission system assessed the ability of this generator to remain in synchronism following selected transmission system contingencies. Also reviewed was the adequacy of the damping of generation/transmission oscillations and the impact of the proposed generator on the stability performance of other system generators. In addition, generator frequency responses and generator protective system performance were evaluated. Phase locked loop (PLL) angle responses of the Solar PV plant were simulated in order to determine if angular instability could result from likely contingencies. Generator frequency deviations were examined in order to determine if generator frequency protection could result in generator tripping. The results of the loss of generation at the Solar PV plant were examined in order to determine if any resulting underfrequency relay operations would lead to system load shedding. Also, the effects of each contingency were examined in order to determine if SCE&G voltages were adversely affected. SCE&G system responses were examined in order to identify any resulting voltage instability, transient stability limits, system operating limits (SOLs), or interconnection reliability operating limits (IROLs). Contingency output data and response plots are not included in this report but are available for review upon request. An initial 20-second steady state simulation for the selected interconnection configuration was performed in order to establish that steady state conditions existed prior to fault conditions. The simulation of each contingency repeated the steady state condition for one second prior to introducing permanent fault conditions so that the responses could be compared to the initial steady state condition. In order to determine the effects on all system generators, each contingency was simulated under system peak load conditions. Contingencies were selected in order to satisfy each of three categories as specified by NERC Reliability Standards TPL-001 through TPL-003. No valid Category D contingencies (TPL-004) were applicable to this study. The results of the stability analysis are described in the following sections and are summarized following the detailed results. 2. Results of Stability Analysis A. Steady State Conditions. (NERC Category A/P0 condition) The interconnection of the Solar PV plant was shown to result in system steady state conditions. Generator rotor angles and frequencies showed no deviations throughout the 20-second simulation. System voltages showed no deviations throughout the simulation period. There was no indication of generator or system voltage instability. No system stability limits were encountered. There were no transient stability limits, system operating limits (SOLs), or interconnection reliability operating limits (IROLs) found. B. Normal clearing of a three phase fault on the 115 kv line from which the 5

Solar PV plant is to be served. (NERC Category B-2/P1 Contingency) Following a one second steady state period, a permanent fault was simulated on the Fairfax Yemassee 115 kv line near the Estill 115 kv tap. This resulted in the opening of the Fairfax Yemassee 115 kv line six cycles after the appearance of the fault, then reclosing 26 cycles later and finally opening six cycles after that. Since the Fairfax Yemassee 115 kv line is the only connection point between the proposed Solar PV plant and the SCE&G 115 kv network, the proposed unit would no longer be connected and would therefore trip. Rotor angle oscillations were moderate and sufficiently damped with no indication of angular instability. Likewise, system frequency responses were also moderate and well damped with no indication of system underfrequency load shedding or generator frequency protection operations. No generator frequency protection operations were indicated. Local system voltages were initially depressed by the presence of the fault; however, all voltages recovered once the fault was cleared and there was no indication of generator or system voltage instability. No system stability limits were encountered. There were no transient stability limits, system operating limits (SOLs), or interconnection reliability operating limits (IROLs) found. Steady state conditions were reestablished with no further system operations. C. Normal clearing of a three phase fault at the Fairfax 115 kv bus. (NERC Category C-1/P2 Contingency) Following a one second steady state period, a permanent fault was simulated at the Fairfax 115 kv bus. The fault is cleared after six cycles, resulting in the opening of three 115 kv lines. Rotor angle and Phase Locked Loop angle oscillations were moderate and well damped with no indication of angular instability. Likewise, system frequency responses were also moderate and well damped with no indication of system underfrequency load shedding operations. No generator frequency protection operations were indicated. Local system voltages were initially depressed by the presence of the fault; however, all voltages recovered once the fault was cleared and there was no indication of generator or system voltage instability. No system stability limits were encountered. There were no transient stability limits, system operating limits (SOLs), or interconnection reliability operating limits (IROLs) found. Steady state conditions were reestablished with no further system operations. 6

D. Delayed clearing of a single phase-to-ground fault at the Yemassee 230 kv #1 Bus. (NERC Category C-9/P3 & P4) Following a one second steady state period, a single phase-to-ground fault was simulated at the Yemassee 230 kv #1 Bus. This fault was cleared after 60 cycles by opening the 230 kv and 115 kv tielines at Yemassee. Rotor angle and Phase Locked Loop angle oscillations were moderate and sufficiently damped with no indication of angular instability. Likewise, system frequency responses were also moderate and well damped with no indication of system underfrequency load shedding operations. No generator frequency protection operations were indicated. Local system voltages were initially depressed by the presence of the fault; however, all voltages recovered once the fault was cleared and there was no indication of generator or system voltage instability. No system stability limits were encountered. Nor were any transient stability limits, system operating limits (SOLs), or interconnection reliability operating limits (IROLs) found. Steady state conditions were reestablished with no further system operations. STABILITY STUDY RESULTS SUMMARY A. Steady state conditions 1. Generator rotor angles demonstrate steady state condition. 2. Generator frequencies show no deviation. 3. There are no voltage instabilities, transient instabilities, SOLs, or IROLs. B. Normal clearing of a three phase fault on the 115 kv line from which the Solar PV plant is to be connected. (NERC Category B-2/P1 Contingency) 1. There was no indication of system UFLS or generator overfrequency operation. 2. There were no resulting voltage instabilities, transient instabilities, SOLs, or IROLs. C. Normal clearing of a three phase fault at the Fairfax 115 kv bus. (NERC Category C-1/P2 Contingency) 1. There was no indication of system UFLS or generator overfrequency operation; however, facility frequency protection should be coordinated with system frequency protection plan. 2. There were no resulting voltage instabilities, transient instabilities, SOLs, or IROLs. D. Delayed clearing of a single phase-to-ground fault at the Yemassee 230 kv #1 Bus. (NERC Category C-9/P3 & P4) 7

1. There was no indication of system UFLS or generator overfrequency operation; however, facility frequency protection should be coordinated with system frequency protection plan. 2. There were no resulting voltage instabilities, transient instabilities, SOLs, or IROLs. 8

III. General Engineering Design & Cost A. Engineer Single line Layout 9

10

B. Transmission and Substation Cost Scope of Work Estimated Cost 1 Complete 2 Time to Make modifications to the SCE&G transmission system to provide a radial Generator Interconnection off of the Fairfax Estill 46 kv line adjacent to. (See Figure 1 and 2) - Construct an SCE&G-owned 46 kv switching station including, but not limited to, a 46 kv Circuit Breaker, structures, foundation, switches, PT s, CT s, batteries, revenue quality metering, SCADA, station service, lightning arresters, gravel, fencing and ground grid. - Install a Triple Suspended Pull Off (TSPO) wood pole in the center line of the Fairfax Estill 46 kv line adjacent to Install two spans of transmission conductor from the TSPO to a structure in the SCE&G-owned 46 kv switching station. This cost assumes the SCE&G-owned 46 kv switching station is adjacent to or within 150 ft of the R/W. The cost does not include R/W procurement due to the unknown location of the station. $677,900 12 months $62,000 8 months TOTAL Required for Generator Interconnection $739,900 12 months 1. Estimated Costs based on future required In-service date. Costs do not include site cost, site preparation, road access or Right of Way procurement if needed. 2. Time to Complete based on normal lead times for structures and major equipment and timing to allow an off-peak outage of the Estill-Estill 46 kv line. Time to Complete does not include time to acquire site and/or Right of Way if needed. IV. Summary This Generator Interconnection Impact Study assesses the impact of interconnecting a new generation facility consisting of a total NET summer/winter rating of 8.16 MW. Studies indicate that modifications will be necessary to the SCE&G Transmission System, and additional facilities are required to accommodate this interconnection request. 11