Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad

Similar documents
Heavy Equipment & Rigging Specialist Training

Presentation of the Baltimore Metro System

Berkeley Lab - Innovative Fleet Ideas, Goal Performance & Challenges

4.2 Series Station Option Description

TRANSFORMER REPLACEMENT

Whither the Dashing Commuter?

For Immediate Release

TECHNICAL MEMORANDUM

ELECTRIC POLICY INTRODUCTION CHAPTER I GENERAL

Glengowrie Depot Upgrade. Nick Marciano, Manager Tram Maintenance, PTS

For Conduit Inspections

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Boat Mold Lift. A custom Pflow Industries Series F material lift,

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

Vernon G. Hartsock, PMP Deputy Chief / Chief Engineer Maryland Transit Administration. Tedd L. Snyder, P.E. Senior System Engineer CH2M Hill

East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015

Steel Products. 8M Series

LIFTING LETTER THE BRIDGING THE GAP STORY ON PAGE 4 A PUBLICATION OF BARNHART CRANE & RIGGING COMPANY BARNHART CRANE & RIGGING COMPANY

PUBLIC TRANSPORTATION

THE AMERICAN SOCIETY OF MECEAWICAL ERGINEERS 2nd BIElWIAL MOVEABLE BRIDGE SYMPOSIUM

Panola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004

Project Status Update January 2017

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

panelclaw.com Polar Bear III for 10 Degree

April 2010 April 2010 Presented by Alan Eirls

Mobility Management: Caltrain

engineering phase and during the procurement of design build contracts.

The original concept for the FL9 was for the Santa Fe

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U)

Positive Train Control (PTC)

Cost Benefit Analysis of Faster Transmission System Protection Systems

3.0 Radial Distribution Systems

Success Case Water and Wastewater

Commissioning chilled water TES systems

Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014

Northeast Diesel Collaborative

commercial epc services

ELECTRONIC OVERHEAD TRAVELLING CRANE DIMENSIONS & LOAD DATA

PROCUREMENT SPECIFICATIONS DELTA MODEL DSC 1500 PORTABLE BEAM - CRASH CERTIFIED BARRIER SYSTEM

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

Advance planning and this powerful generator provided emergency power during the 2003 blackout.

WORKING SAFELY NEXT TO WEST MIDLANDS METRO

A Technique for Selecting Appropriate Allowable Pile Loads for Driven-Pile Projects: Load Matching

Before darkening the room, offer a welcome and overview. Begin by introducing the program and its topic:

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling.

IMPORTANT. Motion Control Engineering New York Office nd Drive, Unit F Glendale NY (718) O. Thompson M00352 Limit Board

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

Safe Driving Standards & Procedures

Table of Contents. Division III: Sign Control ARTICLE 1 GENERAL SIGN REGULATIONS...1

Layout Analysis using Discrete Event Simulation: A Case Study

The equipment manufacturing division of one of the

Technical Information. (Innovative Transport Technology for Open Pit Mines)

PREVENTION OF STRAY CURRENT BY THE MAINTENANCE-OF-WAY

Phase 2 Exposition Metro Line Project

(6) Annual Blanket Permits.

Coal Dust Frequently Asked Questions

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.


MINUTES MATTER. Travel Time and Frequency of Train Service to Grand Central Terminal the Metro-North Railroad System Executive Summary

MTA Long Island Rail Road (LIRR) and MTA Metro-North Railroad (MNR) System-wide Service Standards

HIGH WIRE ACT. When the lights went out at Kitimat, it was the cue for Rio Tinto Alcan to embark on one of its most complex engineering feats ever.

WORK STATION BRIDGE CRANES

Regional Integration of Public Transit - From the Perspective of a Transit Company. April 2019 Thomas Werner MVG Munich

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

Stormwater and sanitary sewer lines 8 inches in diameter or greater

RAA Member Panel. Federal Election 2016

Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019

Electrical Safety Slide Show Presenter s Notes

Metropolitan Council Budget Overview SFY

How to Improve Your Vehicle and Equipment Maintenance Program

2016 Waste and Recycling Program Frequently Asked Questions

The fact that SkyToll is able to deliver quality results has been proven by its successful projects.

Tempe Streetcar. March 2, 2016

Rolling drums while California dreams

Good afternoon Chairman Maziarz and Members of the Senate. Standing Committee on Energy and Telecommunications. We welcome this

Rig Move Hazard Mitigation Procedure

Connecticut PHONE: (860) :00 A.M.-12:30 P.M. 1:00 A.M.- 3:15 P.M. EASTERN TIME. Legal Limits. Connecticut

A Guide to Key Railroad Terminology for the Northeast Corridor

November 6, Agenda

Planetary Surface Transportation and Site Development

FUEL PROVISIONS FOR DREDGING PROJECTS

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Underground Storage Tank Guidance for Commercial Building Inspectors

New Jersey Turnpike Authority Interchange 6 to 9 Widening Program

Call Toll Free GO ALTEC

DO COMMERCIAL BUILDINGS HAVE POWER PROBLEMS? THE ANSWER IS - THEY CERTAINLY DO.

STATISTICS ELECTRICAL INCIDENTS IN ALBERTA. January 1 to December 31, 2012

BUILT WITH INTEGRITY

FY 2013 Candidate Projects ($ Thousands) Street & Traffic Control Program - Thoroughfares

Public Transportation Problems and Solutions in the Historical Center of Quito

M.P.S.C. No. 2 Electric Ninth Revised Sheet No. 50 (Rate Case) Cancels Eighth Revised Sheet No. 50

Western Alberta Transmission Line (WATL) HVDC Project

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS

WORKERS' COMPENSATION AND EMPLOYERS LIABILITY TENNESSEE NCCI CONTRACTING INDUSTRY GROUP As of March 1, 2013.

Commuter Rail in Connecticut: Present and Future. Robert Aloise H. James Boice Stephen Gazillo David Chase

Photovoltaic Installation in Ecuador and The Amazon

The Value of Travel-Time: Estimates of the Hourly Value of Time for Vehicles in Oregon 2007

CRANE STATISTICS & CASE STUDIES WSHC Safety Forum May 2009

CP-1TT Remote System

Transcription:

Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad David W. Jacobs, PE Senior Construction Engineer MTA Metro-North Railroad Company Union Station 50 Union Avenue New Haven, Connecticut 06519 (203) 786-8204 (203) 786-8230 (fax) Jacobs@mnr.org

Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad D. W. Jacobs, P.E. Senior Construction Engineer MTA Metro-North Railroad New Haven, Connecticut With the delivery of 342 new MU cars a few years away, Metro-North s MU car fleet will be approximately 525 cars. In order to perform maintenance on this equipment, both monthly inspections as well as running repairs, it was necessary to construct a new MU car repair facility at Metro-North New Haven Line s main terminal in New Haven, Connecticut. The project, from schematic design through construction, was fast-tracked so that the entire project took only approximately a year and a half. Construction of the 2-track, 600 foot long by 65 feet wide building in Metro-North s New Haven, Connecticut yard involved extensive utility relocations and close coordination between the consultant, contractor and Metro- North forces. In order to expedite the schedule, 1,400 steel piles and other long lead time construction materials were ordered and delivered to the site before a contractor was chosen. Working through the winter, the entire construction process took just over one year from start to completion. Key Words: shops, construction

Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad New Haven, Connecticut is the eastern terminal of Metro-North Railroad s New Haven Division. It is also the location of its major car fleet maintenance and inspection shops, as well as storage yards. With the high annual growth in Metro- North s ridership, approximately four percent per year, the Connecticut Department of Transportation (CDOT) recently announced plans to purchase 342 new multiple-unit (MU) cars. This will increase the total number of New Haven Line MU cars to approximately 525. These new cars, designated M-8, will have pantographs to pick up 13.8kv as well as 25kv, 60 hertz AC power, and third rail shoes to collect 700-volt DC power when operating in the New York City area. At present, New Haven Line cars are maintained at one of two shops in Connecticut: New Haven and Stamford. While the Stamford shop is less than ten years old, the New Haven shop is over forty years old and was designed for a much smaller car fleet. Thus, it was recognized that in order to be able to adequately service the existing fleet plus the 342 new M-8s, expanded maintenance facilities would be required by the time the new cars started to arrive on the property. Two options were considered. The first was to add on to the existing shop. This could be done by either lengthening the existing shop, or making it wider to increase it capacity from three tracks to five. The other option was to building an entirely new shop somewhere in New Haven yard.

After considering costs, space availability, disruption to service, construction time and long range yard development plans, it quickly became obvious that a new shop was by far the preferred option. However, because of the projected delivery schedule for the new M-8 cars, as well as other operational factors, it was necessary to fast-track the design and construction of the new facility. An on-call consultant was authorized by CDOT to begin preliminary plans, along with sub-surface soils explorations, surveys, evaluation of interferences from existing utilities and preliminary foundation design. The area of the yard selected for the new facility was, up until construction of the Connecticut Turnpike in the mid-1950s when it was filled in, part of New Haven Harbor. Stable rock was very deep and the overlaying indigenous soil and fill was basically an organic, muddy material with poor bearing capability. Thus, many deep friction piles would be required. Since time was of such essence in the project, purchase of the steel piles was not placed in the construction contract. Rather, the piles were order directly by CDOT during final design and delivered to the site. This way, all the piles were available to the contractor to begin installing as soon as he was mobilized. This alone saved several months time and thousands of dollars in contractor s profit and handling. In total, over 700 piles were driven. Each pile was 80-feet long. A

40-foot section was driven and then another 40-foot section was spliced and driven for a total of 80-foot of embedment. The new shop, 600-feet long by 65-feet wide, will have two tracks. This will allow up to twelve cars to be serviced simultaneously, in either pairs or triplets. The building will also include a stores facility area, locker rooms and private offices for shop management personnel. Inspection pits will run the entire length of both tracks. Overhead catenary is being installed on both tracks leading to both ends of the building, and will be dead-ended on structures outside each end of the building. For safety, cars will be brought into the shop with diesel powered car movers. In order to provide hotel power to the cars (for lighting and system testing) while in the shop, a DC stinger system is being installed. This system brings 700 volt DC power directly to the car s third rail shoes by attaching a cable. One of the reasons that the catenary wire is terminated outside the building is so that workers have safe access to car roofs for maintenance. For example, an important function of the shop is to change car pantographs. In order to do this, six building column mounted one-ton jibs cranes have been installed. Jib cranes, rather than overhead cranes were specified, in order to eliminate interference

with the DC stinger system support steel, which is suspended from the main building beams. One of the major preconstruction issues that Metro-North had to deal with was the relocation of many underground and aerial utilities. Among these utilities was a ballast car washing tower, yard roadways, fiber and copper communications lines and 13.8kv yard power distribution lines. Again, prior to the contractor s start, Metro-North crews worked days, night and weekends to have all these utilities out of the contractor s way when he was ready to begin. This fast-track approach between CDOT, their design consultant (STV, Inc. of Stratford, Connecticut), Metro-North and CDOT s construction contractor (Manafort Brothers, Inc. of Plainville, Connecticut) required extensive cooperation among all parties. That happened and the result was a very successful project. Complete design was accomplished in approximately six months, and construction in only sixteen months.