Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

Similar documents
for DRECP Alternatives

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT

Tehachapi Renewable Transmission Project. Chino Hills Proposed Alternative. for Segment 8A of the. Chino Hills - September 11, 2007

Updates and Modifications to Report

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

Updates and Modifications to Report

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

March 31, 2014 VIA HAND DELIVERY & ELECTRONIC MAIL

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE.

Pacific Gas and Electric Company TM

Application No Exhibit No. SCE- Witnesses: Charles Adamson Monica Quiroga (U 338-E) Before the

Updates and Modifications to Report

Appendix D Black Hills Project Summary

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Southern California Edison Clean Energy Future

APPENDIX F: Project Need and Description

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

California s RPS Program: Progress Towards California s 33% RPS Goal and the Role of Concentrating Solar Power CSP Conference

Energize Eastside. Underground transmission lines and EMF webinar. Leann Kostek. Senior Project Manager, Puget Sound Energy

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

California and the Western Grid: Transmission Challenges

Susan MacAdams Transit Consultant 269 S. Beverly Drive, Unit 1187 Beverly Hills, CA 90212

The Capital Grid Project:

Microgrids A Regulatory Perspective

March 7, Subject: Southern California Edison 2011 Annual Progress Report

California Independent System Operator. Memorandum

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Black Hills Project Summary

Michigan Thumb Loop Transmission Line Project

SunZia Southwest Transmission Project

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Alameda Point Electric Infrastructure Improvements Public Utilities Board Update May 15, 2017

The Development of Competitive Renewable Energy Zones in Texas

California PUC Rule 21 Generating. Facility Interconnection Application Guide. Technical Note

SAN RAFAEL CITY COUNCIL AGENDA REPORT

California Street Light Association

CPUC Net Metering Decision Is Good News For Clean Energy

Transmission s Future Today. High Capacity High Efficiency Low Profile

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Southern California Edison

Zero Emission Bus Impact on Infrastructure

STATE OF CALIFORNIA ) ) ) ) ) ) )

STORAGE TECHNOLOGIES

STATE OF NEW HAMPSHIRE Inter-Department Communication

Successful Strategies. for Managing the Complex ebart Extension

Rolling Road (Route 638) Widening Project

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) )

March 30, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. 1% Franchise Surcharge for City of Santa Barbara Residents

Powering Sydney s Future

Energy Storage at PG&E

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

West Station-West Cañon 115 kv Transmission Project

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

SCE s 2017 Integrated Distributed Energy Resources Request for Offers ( IDER RFO ) Market Awareness Webinar. August 30, 2017

City of Palo Alto (ID # 6416) City Council Staff Report

PROJECTS $500K AND OVER FOR 2012

Alternative Delivery as a Form of Risk Mitigation

Alternatives to Utility-scale Renewable Energy in the Desert. Basin & Range Watch

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Decision on Merced Irrigation District Transition Agreement

An Inside Look at Electric Reliability 2016 Electric Reliability Report

Solar Electric Systems for Multi-Tenant Units. Presenters

Please Refer to Attached Sample Form

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) NOTICE OF EX PARTE COMMUNICATION

Transportation Electrification: Reducing Emissions, Driving Innovation. August 2017

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

ABB Group August 27, 2010 Slide 1

Introducing ITC Midwest

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Merger of the generator interconnection processes of Valley Electric and the ISO;

Schedule TOU-EV-8 Sheet 1 GENERAL SERVICE TIME-OF-USE, ELECTRIC VEHICLE CHARGING, DEMAND METERED

Proposed Dounreay - Mybster 275 kv / 132 kv

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (U 39 E)

March 13, 2000 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. Modification to Power Factor Adjustment Special Condition

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Schedule TOU-EV-9 Sheet 1 GENERAL SERVICE TIME-OF-USE, ELECTRIC VEHICLE CHARGING, LARGE DEMAND METERED

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

NOTICE OF PREPARATION ENVIRONMENTAL IMPACT REPORT ALAMEDA NORTH BAY FARM ISLAND PIPELINE CROSSINGS PROJECT EAST BAY MUNICIPAL UTILITY DISTRICT

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Re: California Independent System Operator Corporation

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

CPUC Transportation Electrification Activities

JCP&L Verbatim Response to Middletown Township s Questions

Statewide Joint IOU Study of Permanent Load Shifting Workshop #2: Expanding the Availability of Permanent Load Shifting in California

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U338-E) NOTICE OF EX PARTE COMMUNICATION

Study Report. McCredie-Overton Transmission Line Right-of-Way Analysis. City of Columbia, Missouri. prepared for the (S49)

The Value of Energy Storage. Dr. Ralph Romero Steven Rupp

Transcription:

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

Noe Bargas, PE Supervising Senior Civil Engineer Southern California Edison Keith McCullough, Esq Alvarado Smith David Guder, SR/WA CCIM Manager, Valuation & Title Southern California Edison

Agenda Project Background Tehachapi Renewables Transmission Project Overhead to Underground Objectives Project Elements Duct Bank and Vault System Cable System Transition Stations Right of Way and Legal Issues/Challenges Valuation Issues Questions

Project Background

Tehachapi Wind Resource Area

Project Map (1 of 2)

Project Map (2 of 2)

The Renewable Portfolio Standard (RPS) In 2002, the CA Senate enacted SB 1078, mandating all Investor Owned Utilities (IOUs) to increase their renewable energy procurement to 33% by 2020. As of 8/2014: Pacific Gas & Electric 21% So Cal Edison 21% San Diego Gas & Electric 22% Cost (so far): 4 New Major Transmission Lines (const) $4 Billion 12 More Transmission Lines (planned) $12 Billion Timeline: 2009 California Public Utility Commission (CPUC) issued a CPCN to construct TRTP Segments 4 11. The City of Chino Hills fought to have the 500kV lines of Segment 8 routed into the Chino Hills State Park, but the CPUC chose the route through the city instead. Construction started on the line soon thereafter. Garamendi Principles 1988

October 2011: SCE filed a Petition For Modification (PFM) to modify Segment 8 due to FAA recommendation regarding marking and lighting. October 2011: City of Chino Hills filed to re open the record. July 2012: SCE received orders to submit cost and design details to the CPUC by February 2013. July 11, 2013: CPUC voted 3 2* to underground a portion of Segment 8 according to Option UG 5, but did not allow the installation of 500kV reactive compensation. (*ALJ Recommends No Underground) December 2013: CPUC reinstates the reactive compensation scope to the underground line. Current Planned Operating Date: Late 2016

Engineering Overhead to Underground Objectives: The original design parameters were based on matching the 500kV overhead transmission lines already planned and well into construction between Mira Loma and Vincent substations. This included configuring the right of way to accommodate two 500kV underground circuits. Various cable system configurations were studied, including gas insulated lines (GIL), solid dielectric insulation cables, direct buried cables, cables in tunnels, cables in the streets. But the design team settled on cross linked polyethylene (XLPE) cables in concrete duct banks.

Objectives: (cont.) To minimize impacts to the community and existing infrastructure, the circuits will be installed using trenchless techniques at select areas. Transition stations on either end of the circuit would need to be constructed in very hilly terrain and a congested commercial site. The sites would need to connect to the 500kV lines already in construction. Because of the introduction of the 3.7 mile underground circuit, reactive compensation was needed. Mira Loma Sub was selected for the installation. Interconnect the underground circuit in time to meet a late 2015/early 2016 operating date.

Underground Configuration UG5: Single Circuit XLPE w/ 2 cables per phase, with ducts and vaults for 3 rd cable Items Unit Approximate Quantity 5000 kcmil XLPE Cable Feet 120,000 Cable Pulling Segments Each 90 Splice Vaults Each 42 (14 vault clusters, 3 vaults per clusters) Restraint Vaults Each 18 (6 vault clusters, 3 vaults per clusters) Telecom Vaults Each 32 Cable Splices Each 84 Cable Terminations Each 12 Ductbank Linear Feet 17,250 HDD Installation Linear Feet 14,500

500 kv UG T/L Installations Japan (in service 2000, the world s first) 24.7 miles double circuit in tunnel 5000 kcmil cable China (in service 2010) 10.6 miles double circuit in tunnel 5000 kcmil cable Russia (in service 2012) 6.8 miles double circuit directly buried 5000 kcmil cable China (in service 2014) 4.2 miles single circuit in tunnel 5000 kcmil cable

500 kv Cable vs. Conductor

500 kv Splice and Termination

Underground Route Terrain

Vault/Duct Bank/HDD Statistics 3.7 Miles (~19,500 ft) Approx. 3.2 Miles (17,250 ft) Duct Bank (open trench construction) 2 HDD Locations 6 Individual Long Bores (~2100 ft ea.) 3 Individual Short Bores (~800 ft ea.) 14 Splice Vault Clusters 6 Restraint Vault Clusters 92 Total Vaults for Single Circuit Installation 42 Splice 18 Restraint 16 Edison Carrier Solutions Telecom 16 Potential Discharge Monitoring

Splice Vault

Vault Design Considerations Use Full ROW Width

Overview of Transition Stations, Segment 8

East Transition Station

West Transition Station Visual Simulation

Right of Way Issues

Circa 1952

Today

Right of Way Issues WTS Access Roads Golf Course Parks Parks Road/Util Crossings 2 Flood Cntl Xings Commercial ETS

Golf Course

New Roads to Access Vaults/Landlocked Parcels

The Land Rights Cake Easement vs. Fee Fee Control

Other R/W Issues FHA Financing Road Crossings Safety Defending spurious valuation methodology (land use, listings, secondary use contracts ) Construction Safety

Questions?

FHA Addl Slides