Replacing the Meter Body / Process Head Parts

Similar documents
Kit Instruction (Meter Body Replacement Parts)

Overview Replacement Meterbody and Heads for Model STD 110

Model 3051 Sensor Module Replacement

SB 160 QUICK REPAIR GUIDE FOR HALE THERMAL RELIEF VALVE TRV 120, TRV 170, TRV L

Introduction. Pressed Shaft Flowmeter. Flowmeter Service Kits. Disassembly. Idler Shaft Removal

Model DFR 070/156/220 Rotary Actuator

Installation, Operation and Maintenance Manual RGS Rev. 0 November Bettis RGS F-Series Spring-Return Actuators

Scope. Applicability. Caution. I & M CV3000 Series. Storage. Installation & Maintenance Instructions for Marwin CV3000 Series Three Piece Ball Valves

I-VIC300MS. Vic -300 MasterSeal Butterfly Valves WARNING SERIES 761

I-VIC300MS. Series 761 Vic-300 MasterSeal Carbon Steel Butterfly Valve Series 461 Vic-300 MasterSeal Stainless Steel Butterfly Valve WARNING

Soft Seat Fluid Pressure Regulator

SAE STANDARD BOLT ASSEMBLY NUMBER 60020_IR4 INSTALLATION AND OPERATIONS MANUAL

PV4 - Compact Shut Off Style Pig Valve IOM - Installation, Operation & Maintenance

When installing the screwed end, socket weld & flanged end valves the following respective procedures shall be followed for better performance.

VERSAFLOW MAG 4000 Quick Start

HPS SERIES. Steam Joints DEUBLIN COMPANY Norman Drive, West Waukegan, IL USA Phone: 847/ Fax: 847/ Rev.

THYRISTORS T2-2PH from 45A to 2700A Specifications Universal 2 Phase Thyristor Unit , March 2012

I-795/906. Series 795 and 906 Installation-Ready Knife Gate Valves WARNING INSTALLATION AND MAINTENANCE INSTRUCTIONS

Installation, Operation, and Maintenance Instructions for Bettis RGS F-Series Spring-Return (SR) Actuators

ONYX VALVE CO MODEL CAR, CAP-PFO Installation & Maintenance

0-500 PSI Soft Seat Fluid Pressure Regulator

Series 7000 & 9000 Ball Valves

Fisher 657 Diaphragm Actuator Sizes and 87

SERIES CLASS 300 FULL-BORE REACTOR DISCHARGE VALVES. Installation, Maintenance and Operating Instructions

Paint/Solvent/Dump Valve and Flow-Through Valve

NEECO INDUSTRIES INC. INSTRUCTION MANUAL 7 1/16 10K SLAB GATE BODY

KC Transmission Overhaul

Pressure Sensor No Series

Rosemount Manifolds. Rosemount Manifolds. Product Data Sheet , Rev NB January Contents

2-Way Temperature Sensing Valves

2013 IMPCO Technologies, Inc. Page 1 of 20 EPR Repair Kit Instructions (PPI-122, Rev-B)

DeZURIK DR 125 ROTARY DIAPHRAGM ACTUATOR

Model DF233 Control Valve

Temperature Sensor Series

INSTALLATION INSTRUCTIONS

Escape Cylinder and Valve

Design CP Control Valve with ENVIRO-SEAL Bellows Seal Bonnet

An ISO 9001 Company. BOP 1KW-MG FIRMWARE RETROFIT KIT

Technical Manual MSI Pressure Relief Valve

Cylinder and Valve: AirHawk II Air Mask

0-800 psi Carbide Seat Fluid Pressure Regulator

SERIES 2 4 (DN ) 6300, 2 6 (DN ) 6150, 6 (DN 150) 5300 & 530S, 6 & 8 (DN 150 & 200) 5150 BALL VALVES

Installation, Operation, and Maintenance Manual

OPERATOR S MANUAL

J Flow Controls Model Numbering

OPERATOR S MANUAL

KAM E-IAS ELECTRIC ISOKINETIC AUTOMATIC SAMPLER

MEMORY SEAL BALL VALVES MAINTENANCE MANUAL 2 12, Class 150 & 300, Regular Port, Flanged Unibody

Easy Riser swing check valve Models E-1 & F-1

ANDERSON GREENWOOD SERIES 500 PILOT OPERATED SAFETY RELIEF VALVES INSTALLATION AND MAINTENANCE INSTRUCTIONS

Sub Section Title Page No. 1 Introduction 3. 2 Significant Equipment Detail 3. 3 Installation Guidelines 4. 4 Routine Maintenance 4

Cylinder Maintenance & Repair Instructions

Model DF269 Control Valve

Hydraulics. Part B, Section 1. This section covers the following unit configurations. 3700V 3800V 3900V

Fisher D2T FloPro Control Valve

In addition to this instruction sheet, the following are included in this kit (some additional parts are included for future maintenance):

TOYOTA RAV RUNNING BOARD

Circulation Kits for CP Pumps

Tidland Air Brake. Installation, Operation, and Maintenance. Models 200, 250, 305, 380, 460, 610

HercuLine 2000 Series Gear Kit Replacement Instructions

DRAFT. Installation, Operation and Maintenance Instructions for Emerson KBG-V Series

Hard Seat Fluid Pressure Regulator

Model DFR 026 Rotary Actuator

Integra Pneumatically Operated Diaphragm Valves with Position Indication Option

Commercial Frontload Washers

ST 3000 R300 Smart Meter & R300 Smart Meter with ZS Option Installation Instruction

CHAPTER 15 WINCH MAINTENANCE. This chapter contains maintenance instructions for disassembly and repair of winch components at the Direct

John Crane Type 5620 and 5620PR Dual O-Ring Cartridge Seal Assembly and Installation Instructions

Cleaning and Rotor Replacement Instructions

Jandy FloPro (FHP) Series Pump Parts Replacement Kit Instructions

Operation and Maintenance Manual

MULTI-POLE MOUNT - G2 ASSEMBLY INSTRUCTIONS. step-by-step assembly and installation. Version 1, Rev D SP PCN

Standard Bore Flanged Ball Valves Series 7150, 730S & , 4 & 6 (DN 80, 100 & 150) Class 150 & 300

D/G-03 Maintenance. Shutdown Procedure During Freezing Temperatures. Daily. Periodically

M-4851-M8A SUPER 8.8 IRS MUSTANG AUTOMATIC PINION FLANGE KIT

Rosemount Manifolds. Product Data Sheet October , Rev PB. Factory assembled, leak-tested, and calibrated

Specifications Information and Repair Parts Manual , , , &

TECHNICAL DATA. model f-1 2. LISTINGS AND APPROVALS 3. TECHNICAL DATA. Page 1 of 11

ONYX VALVE CO MODEL DAO-PFC Installation & Maintenance

SERVICE INSTRUCTIONS Air Motor

TECHNICAL DATA. Table 1: Model F1 Dry Valve Part Numbers and Specifications

NUMBER: S.M. REF.: Listed in Table ENGINE: EPA07 Series 60 DATE: June 2012 SUBJECT: E3 FUEL INJECTOR TUBE ADDITIONS, REVISIONS, OR UPDATES

Operation & Maintenance Instruction , S.9. MARCH, 2005 Supersedes issue dated March, 2003

LP Series Label Feeders

Pressure Independent Flow Controller. SkoFlo Valve Model SF10000DRS OPERATION AND MAINTENANCE INSTRUCTIONS

DISPLACEMENT PUMP INSTRUCTIONS-PARTS LIST Rev. K. Model , Series A Model , Series B Model , Series A

General Specifications

BETTIS SERVICE INSTRUCTIONS DISASSEMBLY AND REASSEMBLY FOR CB-SR SPRING RETURN SERIES PNEUMATIC ACTUATORS

Types C401, C402, C407, C421, C427, C403, and C831 Jet Bleed Internal Valve Retrofit Kits

DEUBLIN. DEUBLIN Unions H57 H67 H87

DEUBLIN. Installation Instructions DEUBLIN Unions H57 H67 H87

133 Series Direct-Operated Regulators

REACTOR DISCHARGE VALVES S & DIGESTER BLOW VALVES SB & 5300SB B FLANGED BALL VALVES

225 CARTRIDGE DUAL SEAL

Railroad Ball Valves Series 5REB3

Installation, Operation and Maintenance Guide II NIBCO High Performance Butterfly Valves Series 6822 and 7822

Rosemount Manifolds. Product Data Sheet September , Rev PA. Factory assembled, leak-tested, and calibrated

Assembly Instructions

CP-1, CP-2, CP-2L & CPD-2 Series Overhaul

Filter. Table of Contents. Section 10. Filter NOTE: This section applies to applicators with an out-in filter.

Transcription:

Replacing the Meter Body / Process Head Parts ST 700 and ST 800 Pressure Transmitters and SMV800 Multivariable Transmitter - Instruction sheet Document Number: 34-ST-33-70 Effective Date: 5/27/2016 (Process Heads) Supersedes: 11/1/2015 Overview This kit instruction provides general (disassembly/assembly) procedures for replacing meter body and process head parts. NOTE: Process head replacement and instruction references Does Not apply to In-Line transmitter models. Purpose / Scope of this Kit Instruction All of the parts included in the kits are components of the Meter Body and associated Process Head assemblies. None of the kits include components of the Electronic Housing assembly. However, the procedures include disassembly/assembly instructions for the Electronics Housing as required for replacement of parts included in the kits. Applicability These instructions apply to the models listed in the title above. Parts Replacement Kits Improper selection or application of replacement parts could cause damage to property and equipment. Improper selection or application of replacement parts could cause serious injury or death to personnel. The materials and manufacturing methods of parts vary with transmitter applications. When performing any of the procedures in this kit Instruction, ensure that the proper parts are selected for each application. 34-ST-33-70 Meter Body / Process Head 1

STD700, STD800 and SMV800 models STA700, STA800, STG700 and STG800 models ST700 and ST800 In-Line models (Process connection will vary) Figure 1 - Typical transmitter configurations 2 Meter Body / Process Head 34-ST-33-70

ST700, ST800 and SMV800 Replacement parts NOTE: O-ring (K7) replacement may be done with process head attached as shown in Figure 4 or with process heads removed as shown in Figure 5 Figure 2 STD700/800 and SMA800/SMG800 models Figure 3 - STA700, STA800, STG700 and STG800 models (Only components required for In-Line models are Items 1 & K7) (Item 1 shown with Dual Head meter Body) 34-ST-33-70 Meter Body / Process Head 3

Figure 4 O-ring (K7), process heads attached Figure 5 - O-ring (K7), process heads removed 4 Meter Body / Process Head 34-ST-33-70

Table 1 Kit parts common to Figure 2 and Figure 3 (Generic Listing*) Key Number Description* Quantity Per kit 51452864* Process Head kit (includes the following items) K1 Pipe Plug 2 K2 Vent Plug 1 K3 Vent Bushing 1 K5 Process Head 1 K6 Gasket, Process Head 1 Ka Gasket, Adapter 1 50019274* Reference Head kit (includes the following items) K9 Carbon Steel Reference Head 1 K9 316 SS Reference Head 1 51452865* Meterbody Gasket kit (includes the following items) K6 Gasket, Process Head 6 Ka Gasket, Flange Adapter 6 K7 O-ring, meterbody to Electronics Housing 3 51452866* Bolts & Nuts kit (includes the following items) Kc Bolt, Hex head, 7/16-20 UNF x 1.50" lg (Flange Adapter) 4 K4 Nut, Hex, 7/16-14UNC (Process Head) 4 K8 Bolt, Hex, 7/16-14UNC x 3.25" lg (Process Head) 4 51452867* Flange Adapter kit (includes the following items) Ka Gasket, Flange Adapter 2 or 1 Kb Flange Adapter 2 or 1 Kc Bolt, Hex, 7/16-20 UNF x 1.5" Lg (Flange Adapter) 4 or 2 51452868* Gasket kit (includes the following items) K6 Gasket, Process Head, PTFE 12 (pack) (or) K6 Gasket, Process Head, Viton 6 (pack) K6 (or) Gasket, Process Head, Graphite (use only as replacement of existing graphite gasket) (or) 6 (pack) Ka Gasket, Flange Adapter, PTFE 6 (pack) (or) Ka Gasket, Flange Adapter, Viton 6 (pack) Ka (or) Gasket, Flange Adapter, Graphite (use only as replacement of existing graphite gasket) 6 (pack) 34-ST-33-70 Meter Body / Process Head 5

REPLACEMENT OF METER BODY AND / OR METER BODY O-RING (All models) ESD HAZARD. Use a ground strap or ionizer when handling the PWA. Electrostatic discharge can damage circuit components. 1. Save or record device configuration data. 2. Turn OFF transmitter power. 3. It is recommended to remove the Transmitter from service, and move it to a clean area before disassembling. 4. Refer to Figure 6. Loosen the End Cap Locking Screw, and unscrew the End Cap from the electronics side of the Transmitter housing. Figure 6 Disassembly for Meter Body Replacement ELECTROSTATIC DISCHARGE HAZARD! Use a ground strap or ionizer when handling the PWA, because ESD can damage circuit components. 6 Meter Body / Process Head 34-ST-33-70

5. If a display is present, press the two snaps along the side, and remove it from the communication module assembly. Note: Do not discard or misplace the Display/Communication connector, it will be required to reassemble the Display Module. 6. Loosen the two retaining screws on the Communication Module assembly, and remove the Communication Module assembly from the electronics housing. 7. Disconnect the Sensor Ribbon Cable from the Communications Board. 8. Refer to Figure 7. Use a 2 mm hex wrench to completely loosen the set screw on the outside of the housing to permit rotation of the meter body. Figure 7 Hardware Location to Remove the Meter Assembly NOTE: Process Heads present on STA700/800, STD700/800, STG700/800 and SMV800 models only 34-ST-33-70 Meter Body / Process Head 7

Note: Steps 10 through 14 and 16 to 17 are not required for ST700 and ST800 In-Line models. 9. Carefully turn the complete meter body counterclockwise to unscrew it from the electronics housing. 10. Remove the nuts from bolts that hold the process head(s) to the Meter Body. 11. Remove process heads and bolts. 12. Remove the gaskets or O-rings from the process heads. 13. Clean the interior of the process head(s) with a soft bristle brush and suitable solvent. CAUTION To prevent damage to the diaphragm in the Meter Body, use extreme care when handling or placing the Meter Body on any surface. Carefully assemble gaskets or O-rings to the process head. 14. Coat threads on process head bolts with LOCTITE Silver Anti-Seize Lubricant or equivalent. 15. Refer to Figure 8. Apply Parker Super O-ring silicone grease to the meter body adapter O- ring and carefully assemble the O-ring to the meter body. 16. Assemble the process head(s) and bolts to the new meter body. For now, make the bolts only finger-tight. Figure 8 Meter Body Reassembly 8 Meter Body / Process Head 34-ST-33-70

17. Use a torque wrench to gradually tighten nuts to torque rating in sequence shown in Figure 9. Tighten head bolts in stages of 1/3 full torque, 2/3 full torque, and then full torque, per Table 2. Figure 9 Head Bolt Tightening Sequence 18. Feed the ribbon cable on the new meter body through the neck of the housing. CAUTION To prevent damage to the ribbon cable, use care when assembling the Meter Body to the electronics housing. 19. Screw the new meter body into the housing until the bottom of the Meter Body adapter is flush with the neck of the electronics housing. 20. Tighten the outside set screw to be sure it is fully seated in the slot in the header. 21. Loosen the set screw ½- turn. 22. Rotate the housing to the desired position (Max. 180 o in either direction), and tighten the set screw. 23. Carefully align and connect the Sensor Ribbon Cable to connector J4 at the bottom of the Communication module board. When installing the Communication module in the next step, be careful not to pinch the Sensor Ribbon Cable. 24. Carefully, insert the Communication module into the Electronics compartment. Ensure that the Sensor Ribbon Cable is not pinched. 25. Tighten the two Communication module retaining screws. 34-ST-33-70 Meter Body / Process Head 9

Table 2 Torque Table, Process Head Bolt/Nuts Bolt Part Number Nut Part Number Bolting Type B7M 51452557-004 51452559-003 MONEL K500 51452557-005 51452559-005 SUPER DUPLEX 51452557-006 51452559-006 316 STAINLESS STEEL Grade 660 (NACE A286) with NACE 304 SS Nuts Grade 660 (NACE A286) Bolts & Nuts 51452557-003 51452559-004 51452557-002 51452559-002 51452557-002 51452559-008 Grade 660 (NACE A286) Bolts & Nuts 6000 PSI (415 BAR) OPTION ONLY 51452557-202 51452559-008 CARBON STEEL 51452557-001 51452559-001 All Transmitters Except Draft Range 48,8 Nm +/- 2,4 Nm 36.0 Lb Ft +/- 1.8 L Ft 56,9 Nm +/- 2,8 Nm 42.0 Lb Ft +/- 2.1 Lb Ft 67,8 Nm +/- 3,4 Nm 50.0 Lb Ft +/- 2.5 Lb Ft Draft Range Transmitters Only 20,3 Nm +/- 1,0 Nm 15.0 Lb Ft +/- 0.8 Lb Ft 26. If applicable, re-install the Display module as follows: a) Orient the display as desired. b) Install the Interface Connector in the Display module such that it will mate with the socket for the display in the Communication module. c) Carefully line up the display, and snap it into place. Verify that the two tabs on the sides of the display latch. Orient the Display for proper viewing through the end cap window. You can rotate the meter mounting orientation in 90 o increments. 27. Connect the bracket to the Transmitter housing 28. Recalibrate the Transmitter per the Calibration section of the relevant Transmitter User manual (ST 800 #34-ST-25-35, ST 700 #34-ST-25-44, SMV 800 #34-SM-25-03) 29. Return the Transmitter to service, and turn ON power 30. Verify the Transmitter configuration data. Restore the saved database if necessary. 31. Lubricate the end-cap O-rings with Parker Super O-ring silicone lubricant or equivalent before replacing the end caps. 10 Meter Body / Process Head 34-ST-33-70

Table 3 ST700 and ST800 Flange Adapter Removal/Replacement Perform steps 1, 2 & 3 on page 6 before performing the following procedure. NOTE: This procedure does not require that the Meter Body be removed from the Electronics Housing. If the Flange Adapters are being replaced in conjunction with procedures for other kits parts (that is, Process heads, etc), follow those procedures and incorporate the following steps. Step Action 1 Note: The threaded hole in each Flange Adapter is offset from center. To ensure correct orientation when it is reassembled, make a note of the orientation of the offset relative to each Process Head before removing any adapter. Remove and discard: - the two bolts (Kc) that attach the Adapter to the Process Head - Adapter (Kb) - Gasket (Ka) 2 Clean the mating surface(s) of the Process Heads. Note: transmitter shown for context. Actual appearance may vary. 3 Apply anti-seize lubricating compound to the new bolts, and carefully assemble the new Adapter(s) and Gasket(s) to the Process Head(s). 4 Evenly torque the bolts to 47,5 N M +/- 2,4 N M (35 Lb-Ft +/- 1.8 Lb-Ft). 5 Place the transmitter back into service. 34-ST-33-70 Meter Body / Process Head 11

Table 4 ST700 and ST800 Process Head Removal/Replacement Step Action Perform steps 1, 2 & 3 on page 6 before performing the following procedure. NOTE: This procedure does not require that the Meter Body be removed from the Electronics Housing. 1 Note: actual appearance may vary Caution: To prevent damage to the diaphragm in the Meter Body, use extreme care when handling the Meter Body (center section) or when placing it on any surface. Loosen and remove the four nuts (K4). Carefully separate the Process Head(s) (K5) from the Meter Body (item 1). Discard the old Gaskets(s) (K6) and Process Head(s). 2 Apply sealant or PTFE Tape to the new bushings (K3) and pipe plugs (K1), and install into the new Process Head. Tighten Bushings and Pipe Plugs to a torque of 58 +/- 2,7 N- m (43 +/- 2 Lb-Ft). If Bushings (K3) require special orientation, then torque further up to an additional 180 degrees of rotation to desired orientation. Tighten Vent/Drain (K2) to 4,0 +/- 0,5 N-m (35 +/- 4 Lb-in). Note: If Flange Adapters (Kb) are to be attached, use the procedure given in Step 1 of Table 3. 3 If the old nuts and bolts for the Process Heads will be used, clean and then lubricate them. If new nuts and bolts are to be installed, lubricate them. 12 Meter Body / Process Head 34-ST-33-70

Step Action 4 Note: The bolts for the Process Heads (K8) should be on the low-pressure side of the Meter Body, and the nuts (K4) should be on the high-pressure side. (High- and low-pressure sides are marked on the Meter Body.) Carefully assemble the new Gasket(s) and Process head(s) to the Meter Body as shown in the illustration above, and hand-tighten the nuts. 5 Note: Refer to Table 2 for torque specifications for the Process Heads. Tighten the four nuts in three steps, using a torque wrench in the sequence shown in the illustration and as listed below. a. Tighten all four nuts to approximately 1/3 full torque. b. Tighten all four nuts to approximately 2/3 full torque. c. Tighten all four nuts to full torque. 7 Place the transmitter back into service. 34-ST-33-70 Meter Body / Process Head 13

Sales and Service For application assistance, current specifications, pricing, or name of the nearest Authorized Distributor, contact one of the offices below. ASIA PACIFIC Honeywell Process Solutions, (TAC) hfs-tacsupport@honeywell.com Australia Honeywell Limited Phone: +(61) 7-3846 1255 FAX: +(61) 7-3840 6481 Toll Free 1300-36-39-36 Toll Free Fax: 1300-36-04-70 China PRC - Shanghai Honeywell China Inc. Phone: (86-21) 5257-4568 Fax: (86-21) 6237-2826 EMEA Honeywell Process Solutions, Phone: + 80012026455 or +44 (0)1344 656000 Email: (Sales) FP-Sales-Apps@Honeywell.com or (TAC) hfs-tac-support@honeywell.com AMERICAS Honeywell Process Solutions, Phone: (TAC) 1-800-423-9883 or 215/641-3610 (Sales) 1-800-343-0228 Email: (Sales) FP-Sales-Apps@Honeywell.com or (TAC) hfs-tac-support@honeywell.com Singapore Honeywell Pte Ltd. Phone: +(65) 6580 3278 Fax: +(65) 6445-3033 South Korea Honeywell Korea Co Ltd Phone: +(822) 799 6114 Fax: +(822) 792 9015 For more information To learn more about SmartLine Transmitters, visit www.honeywellprocess.com Or contact your Honeywell Account Manager Process Solutions Honeywell 1250 W Sam Houston Pkwy S Houston, TX 77042 Honeywell Control Systems Ltd Honeywell House, Skimped Hill Lane Bracknell, England, RG12 1EB Shanghai City Centre, 100 Jungi Road Shanghai, China 20061 www.honeywellprocess.com 34-ST-33-70 May 2016 2016 Honeywell International Inc.