RFP Corrigendum 01 The RFP document for selection of Transmission Service provider for the Package- 1 against tender specification ESD-765/4 has been modified to the extent below: S. Clause / Page 1. Definition of: Successful Bidder Transmission Service Agreement Clause no. 1.2 Annexure 2 : Para 1, line 2 Annexure 9: Subject & Para 1, line 2 Annexure 10A: Para 1, line 3 Instead of Build, own, operate and transfer 2. Definition Bid Bond shall mean the unconditional and irrevocable bank guarantee for Rupees 51 Crores (Rs Fifty One Crores only) to be submitted along with the Bid by the Bidder under Clause 2.20 of this RFP, Read as Build, Own, Operate & maintain and Transfer (BOOT) Bid Bond shall mean the unconditional and irrevocable bank guarantee for Rupees 51.23 Crores (Rs Fifty One Crores Twenty Three Lacs only) to be submitted along with the Bid by the Bidder under Clause 2.20 of this RFP, as per the format Uttar Pradesh Power Transmission Corporation Limited Page 1
S. Clause / Page Instead of Read as as per the format prescribed in Annexure 2; prescribed in Annexure 2; 3 Clause 1.2 List of Works (Annexure A) Revised List of Works (Annexure B) 4. Clause 1.4 At the expiry of the TSA, the SPV along with the assets will be transferred to the Long term Transmission Customer(s) or nominee of Long term Transmission Customer(s) at the depreciated value. 5 Clause 1.5 (a) a) Provide to the Bidders a Survey Report for the Project at least thirty (30) days prior to the Bid Deadline. The Survey Report will contain information regarding the transmission line, i.e. voltage level, line configuration (i.e., S/C or D/C), indicative route alignment, conductor type, conductor configuration and type of terrain likely to be encountered. 6 Clause 2.15.1 Project Schedule (Annexure C) Scheduled COD for overall Project: 5th May, 2012. 7 Clause 2.16.1 2.16.1 The Bidders should submit the Bids so as to reach the address specified in Clause 2.18.4 by 14.00 Hrs. on 15th October 2009: 8 Clause 2.16.2 2.16.2 Important timelines are mentioned below: Date Event 10 th Aug 2009 Issuance of RFQ and RFP At the expiry of the TSA, all the assets of the SPV including Substations, Transmission Lines and other related physical assets will be transferred to the permitted nominee of the State Government at zero value. a) Provide to the Bidders a Survey Report for the 765kV line which has already been provided at the RFQ stage. The Survey Report will contain information regarding the transmission line, i.e. voltage level, line configuration (i.e., S/C or D/C), indicative route alignment, conductor type, conductor configuration and type of terrain likely to be encountered. However, Survey for all other lines will be the responsibility of the Bidders. Revised Project Schedule (Annexure D) Scheduled COD for overall Project: 31st December, 2012. 2.16.1 The Bidders should submit the Bids so as to reach the address specified in Clause 2.18.4 by 14.00 Hrs. on 30 th March, 2010: 2.16.2 Important timelines are mentioned below: Date Event 10 th August 2009 Issuance of RFQ and RFP Uttar Pradesh Power Transmission Corporation Limited Page 2
S. Clause / Page Instead of Read as 19 th Aug 2009 Submission of written clarifications/ amendments, if any, on the RFQ by Bidders so as to reach BPC by 1700 hours. Such written clarifications/ amendments shall be in the format provided in Annexure-7. 21 st Aug, 2009 Pre-bid meeting for any clarification on the RFQ 28 th Aug 2009 Submission of response to RFQ 4 th Sept 2009 Short listing based on responses received for RFQ and issue of additional information related to the project 16 th Sept 2009 Submission of written clarifications/ amendments, if any, on the balance RFP Project Documents only, by Bidders so as to reach BPC by 1700 hours. Such written clarifications/ amendments shall be in the format provided in Annexure-7. 23 rd Sept 2009 Pre-bid Meeting for any clarification on the RFP 30 th Sept 2009 Issue of final RFP Project Documents 15 th Oct 2009 Submission of Bid 15 th Oct 2009 Opening of Non-Financial Bid 20 th Oct 2009 Opening of Financial Bid 26 th Oct 2009 Selection of Successful Bidder 19 th August 2009 7th October, 2009 11th November 2009 15 th February 2010 22 nd February 2010 Submission of written clarifications/ amendments, if any, on the RFQ by Bidders so as to reach BPC by 1700 hours. Such written clarifications/ amendments shall be in the format provided in Annexure-7. Public hearing for any clarification on the RFQ Submission of response to RFQ Short listing based on responses received for RFQ and issue of additional information related to the project Submission of written clarifications/ amendments, if any, on the balance RFP Project Documents only, by Bidders so as to reach BPC by 1700 hours. Such written clarifications/ amendments shall be in the format provided in Annexure-7. Public Hearing for any clarification on the RFP 26 th February, 2010 5 th March 2010 Issue of final RFP Project Documents 30 th March 2010 Submission of Bid 30 th March 2010 Opening of Non-Financial Bid 15 th April 2010 Opening of Financial Bid 22 nd April 2010 30 th April 2010 Selection of Successful Bidder and issue of LoI Signing of RFP Project Documents and transfer of South East U.P. Power Transmission Company Ltd. Uttar Pradesh Power Transmission Corporation Limited Page 3
S. Clause / Page Instead of and issue of LoI 5 th Nov 2009 Signing of RFP Project Documents and transfer of South East U.P. Power Transmission Company Ltd. 9 Clause 2.17.1 2.17.1 The Bidders shall submit the Bid which shall remain valid up to 12th April, 2010. The BPC reserves the right to reject any Bid which does not meet the aforementioned validity requirement. 10 Clause 2.19.2 2.19.2 The cost of this RFQ including RFP is Rs. 11,250/- (Rupees eleven thousand two hundred fifty only) including VAT (12.5%) or USD 225 (US Dollars two hundred twenty five only) including VAT (12.5%) which shall be non-refundable. This amount shall be payable by a crossed demand draft or banker s cheque drawn in favour of Executive Engineer (A) Electricity Transmission Design Circle, UPPTCL payable at Lucknow. 11 Clause 2.22.1 Opening of Envelope I (Non-Financial Bid): 15:00 hours (IST) on 15th October, 2009 Opening of Envelope II (Financial Bid): 15:00 hours (IST) on 20th October, 2009 12 Annexure 1 List of Long Term Transmission Customers Read as 2.17.1 The Bidders shall submit the Bid which shall remain valid up to six months from the date of submission. The BPC reserves the right to reject any Bid which does not meet the aforementioned validity requirement. 2.19.2 The cost of this RFQ including RFP is Rs. 11,250/- (Rupees eleven thousand two hundred fifty only) including VAT (12.5%) or USD 225 (US Dollars two hundred twenty five only) including VAT (12.5%) for both the packages 1&2, which shall be non-refundable. This amount shall be payable by a crossed demand draft or banker s cheque drawn in favour of Executive Engineer (A) Electricity Transmission Design Circle, UPPTCL payable at Lucknow. Opening of Envelope I (Non-Financial Bid): 15:00 hours (IST) on 30th March, 2010 Opening of Envelope II (Financial Bid): 15:00 hours (IST) on 15th April, 2010 List of Long Term Transmission Customers Sl. Name of the Long Term Transmission Customers Allocate d Project Capacity in MW Sl. Name of the Long Term Transmission Customers Allocate d Project Capacity in MW 1 Paschimanchal Vidyut Vitran Nigam Ltd. 33% 1 Paschimanchal Vidyut Vitran Nigam Ltd. 40% Uttar Pradesh Power Transmission Corporation Limited Page 4
S. Clause / Page Instead of Read as 2 Dakshinanchal Vidyut Vitran Nigam Ltd. 27% 3 Purvanchal Vidyut Vitran Nigam Ltd. 23% 2 Dakshinanchal Vidyut Vitran Nigam Ltd. 15% 3 Purvanchal Vidyut Vitran Nigam Ltd. 20% 4 Madhyanchal Vidyut Vitran Nigam Ltd. 17% 13 Annexure 4 - Scheduled COD 5th May, 2012 - (25th Anniversary of the Grant of License) 4th May, 2035 14 Annexure 6 Point 8 4 Madhyanchal Vidyut Vitran Nigam Ltd. 5 Kanpur Electricty Supply Company Ltd. 20% - Scheduled COD 31st Dec, 2012 - (25th Anniversary of the Grant of License) 30th Dec, 2035 Scheduled COD for the Project: 5 th May, 2012 Scheduled COD for the Project: 31st December, 2012 15 Annexure 16 -- Annexure 16: Details of the Work (Attached as Annexure E) 5% All other terms & conditions shall remain unchanged. (P.K. Gupta) Superintending Engineer Uttar Pradesh Power Transmission Corporation Limited Page 5
ANNEXURE A: LIST OF WORKS RFP Corrigendum 01 Transmission System for 765 kv S/C Mainpuri-Bara Line with 765 kv/400 kv S. AIS at Mainpuri and Associated Schemes/Work I. Transmission Lines: 1) 765 kv SC Mainpuri - Unnao with Quad Bersimis (191 kms) 2) 400 kv DC Quad Moose Mainpuri - Aligarh (120 kms) 3) 400 kv DC Twin Moose Mainpuri (765kV) - Mainpuri (PG) (30 kms) 4) LILO of 400 kvagra Agra(PG) at 765kV Mainpuri with Twin Moose (90 kms) 5) 765kV 2x SC Mainpuri - Bara with Quad Bersimis (2x351 kms) 6) LILO of 400kV Panki-Obra at 400kV Rewa Road with Twin Moose (12 kms) 7) 400kV DC (Quad Moose) Rewa Road-Karchhana (20 kms) 8) 400kV DC (Quad Moose) Rewa Road-Meja (25 kms) 9) 400kV DC (Quad) Bara-Meja (20 kms) 10) 400kV DC (Quad Moose) Bara-Karchhana (20 kms) 11) 400kV D/C (Twin Moose) Tanda-Gonda (100 kms) 12) 400kV D/C (Twin Moose) Gonda-Shahjahanpur (230 kms) 13) LILO of 400kV Sarojininagar-Kursi Road (PG) at 400kV Sultanpur Rd., Lucknow with Twin Moose (20 kms) 14) LILO of 400kV Obra-Sultanpur at 400kV Aurai with Twin Moose (15 kms) II. III. Sub-Stations: 1) 2X1000MVA, 765/400 kv AIS at Mainpuri 2) 3X315MVA, 400/220kV GIS at Rewa Road 3) 2X315MVA, 400/220kV, 2X100MVA, 220/132kV AIS at Gonda AIS 4) 2X500MVA, 400/220kV, 2X160MVA, 220/132kV AIS at Sultanpur Road,Lucknow AIS 5) 2X200MVA, 400/132kV AIS at Aurai Switching-stations: 1) Mainpuri: One & half breaker scheme for 765&400kV sides and two main and transfer scheme for 220kV side 2) Rewa Road: One & half breaker scheme for 400kV side and two main and transfer scheme for 220kV side 3) Gonda: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside 4) Sultanpur Road, Lucknow: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside 5) Aurai: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside Uttar Pradesh Power Transmission Corporation Limited
ANNEXURE B: REVISED LIST OF WORKS Sr. No (I) Transmission System for 765kV S/C Mainpuri-Bara Line with 765kV/ 400kV AIS at Mainpuri and Associated Schemes/ Work Transmission Lines: 1) 765kV SC Mainpuri - Unnao with Quad Bersimis (175Kms) 2) 400kV DC (Quad Moose)Mainpuri (765kV) -Aligarh (120kms) 3)LILO of both circuits of 400kV DC Orai - Mainpuri (PG) at Mainpuri (765kV) with Twin Moose (30Kms) 4) 765kV 2x SC Mainpuri - Bara with Quad Bersimis (2x350kms) 5) LILO of 400kV Panki - Obra at 400kV Rewa Road with Twin Moose (12 kms) 6) 400kV DC (Quad Moose) Rewa Road -Karchhana (30kms) 7) 400kV DC (Quad Moose) Rewa Road -Meja (25kms) 8) 400kV DC (Quad Moose) Bara - Meja (25kms) 9) 400kV DC (Quad Moose) Bara -Karchhana (30kms) 10) 400kV DC (Quad Moose) Tanda - Gonda (100kms) 11) 400kV DC (Quad Moose) Gonda -Shahjahanpur (230kms) 12) LILO of 400kV Sarojininagar - Kursi Road (PG) at 400kV Sultanpur Rd, Lucknow with Twin Moose (20kms) 13) LILO of 400kV Obra - Sultanpur at 400kV Aurai with Twin Moose (15kms) (II) Sub-Stations : (III) 1) 2x1000MVA (765/400kV) AIS at Mainpuri 2) 2x315MVA (400/220kV) GIS at Rewa Road 3) 2x315MVA (400/220kV), 2x100MVA (220/132kV) AIS at Gonda 4) 2x500MVA( 400/220kV), 2x160MVA, (220/132kV) GIS at Sultanpur Road, Lucknow 5) 2x315MVA ( 400/220kV), 2x160MVA(220/132kV) AIS at Aurai Bus Switching-Arrangement: 1) Mainpuri : One & half breaker with double main bus scheme for 765&400kV side 2) Rewa Road : Double Main Bus scheme for 400kV and 220kV side 3) Gonda : One & half breaker with double main bus scheme for 400kV,Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side 4) Sultanpur Road, Lucknow : Double Main Bus scheme for 400kV, 220kV & 132kV side 5) Aurai : One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side Uttar Pradesh Power Transmission Corporation Limited
ANNEXURE C: PROJECT SCHEDULE RFP Corrigendum 01 Sr. No I Name of the Transmission Element/Project Transmission Lines: 1) 765 kv SC Mainpuri - Unnao with Quad Bersimis (191 kms) 2) 400 kv DC Quad Moose Mainpuri - Aligarh (120 kms) 3) 400 kv DC Twin Moose Mainpuri (765kV) - Mainpuri (PG) (30 kms) 4) LILO of 400 kvagra Agra(PG) at 765kV Mainpuri with Twin Moose (90 kms) 5) 765kV 2x SC Mainpuri - Bara with Quad Bersimis (2x351 kms) 6) LILO of 400kV Panki-Obra at 400kV Rewa Road with Twin Moose (12 kms) 7) 400kV DC (Quad Moose) Rewa Road-Karchhana (20 kms) 8) 400kV DC (Quad Moose) Rewa Road-Meja (25 kms) 9) 400kV DC (Quad) Bara-Meja (20 kms) 10) 400kV DC (Quad Moose) Bara- Karchhana (20 kms) 11) 400kV D/C (Twin Moose) Tanda-Gonda (100 kms) 12) 400kV D/C (Twin Moose) Gonda-Shahjahanpur (230 kms) 13) LILO of 400kV Sarojininagar- Kursi Road (PG) at 400kV Sultanpur Rd., Lucknow with Twin Moose (20 kms) 14) LILO of 400kV Obra-Sultanpur at 400kV Aurai with Twin Moose (15 kms) Schedule d COD in months from Effective Date 24 months Percentage of Quoted Transmission Charges recoverable on Scheduled COD of the Element of the Project Element(s) which are pre-required for declaring the commercial operation (COD) of the respective Element/ project 100% Approval of State Govt under section 68 of Electricity Act 2003. Transmission License from Uttar Pradesh Electricity Regulatory Commission (UPERC) Clearance from Electrical Inspector. Statutory Consents, Clearances and Permits (way leave, environment & forest, civil aviation, railway/ road/river/canal/power crossing/ptcc, etc.) II Sub-Stations: 1) 2X1000MVA, 765/400 kv AIS at Mainpuri 2) 3X315MVA, 400/220kV GIS at Rewa Road 3) 2X315MVA, 400/220kV, 2X100MVA, 220/132kV AIS at Uttar Pradesh Power Transmission Corporation Limited
Sr. No III Name of the Transmission Element/Project Gonda AIS 4) 2X500MVA, 400/220kV, 2X160MVA, 220/132kV AIS at Sultanpur Road,Lucknow AIS 5) 2X200MVA, 400/132kV AIS at Aurai Switching-stations: 1) Mainpuri: One & half breaker scheme for 765&400kV sides and two main and transfer scheme for 220kV side 2) Rewa Road: One & half breaker scheme for 400kV side and two main and transfer scheme for 220kV side 3) Gonda: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside 4) Sultanpur Road, Lucknow: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside 5) Aurai: One & half breaker scheme for 400kV and two main and transfer scheme for 220kV & single main and transfer bus scheme for 132kVside Schedule d COD in months from Effective Date Percentage of Quoted Transmission Charges recoverable on Scheduled COD of the Element of the Project Element(s) which are pre-required for declaring the commercial operation (COD) of the respective Element/ project Scheduled COD for overall Project: 5th May, 2012. Uttar Pradesh Power Transmission Corporation Limited
ANNEXURE D: REVISED PROJECT SCHEDULE Sr. No I II III Name of the Transmission Element/Project Transmission Lines: 1) 765kV SC Mainpuri - Unnao with Quad Bersimis (175Kms)* 2) 400kV DC (Quad Moose)Mainpuri (765kV) -Aligarh (120kms)* 3)LILO of both circuits of 400kV DC Orai - Mainpuri (PG) at Mainpuri (765kV) with Twin Moose (30Kms)* 4) 765kV 2x SC Mainpuri - Bara with Quad Bersimis (2x350kms) 5) LILO of 400kV Panki - Obra at 400kV Rewa Road with Twin Moose (12 kms)* 6) 400kV DC (Quad Moose) Rewa Road -Karchhana (30kms) 7) 400kV DC (Quad Moose) Rewa Road -Meja (25kms) 8) 400kV DC (Quad Moose) Bara - Meja (25kms) 9) 400kV DC (Quad Moose) Bara - Karchhana (30kms) 10) 400kV DC (Quad Moose) Tanda - Gonda (100kms) 11) 400kV DC (Quad Moose) Gonda - Shahjahanpur (230kms) 12) LILO of 400kV Sarojininagar - Kursi Road (PG) at 400kV Sultanpur Rd, Lucknow with Twin Moose (20kms) 13) LILO of 400kV Obra - Sultanpur at 400kV Aurai with Twin Moose (15kms) Sub-Stations : 1) 2x1000MVA (765/400kV) AIS at Mainpuri* 2) 2x315MVA (400/220kV) GIS at Rewa Road* 3) 2x315MVA (400/220kV), 2x100MVA (220/132kV) AIS at Gonda 4) 2x500MVA( 400/220kV), 2x160MVA, (220/132kV) GIS at Sultanpur Road, Lucknow 5) 2x315MVA ( 400/220kV), 2x160MVA(220/132kV) AIS at Aurai Bus Switching-Arrangement: 1) Mainpuri : One & half breaker with Scheduled COD in months from Effective Date 30 months Percentage of Quoted Transmission Charges recoverable on Scheduled COD of the Element of the Project 100% Element (s) which are prerequired for declaring the commercial operation (COD) of the respective Element/project Approval of Sate Govt under section 68 of Electricity Act 2003. Transmission License from Uttar Pradesh Electricity Regulatory Commission (UPERC) Clearance from Electrical Inspector. Statutory Consents, Clearances and Permits (way leave, Environment & forest, civil aviation, railway/ road/ river/ canal/ power crossing/ PTCC,etc.) Uttar Pradesh Power Transmission Corporation Limited
Sr. No Name of the Transmission Element/Project Scheduled COD in months from Effective Date double main bus scheme for 765 & 400kV side* 2) Rewa Road : Double Main Bus scheme for 400kV and 220kV side* 3) Gonda : One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side 4) Sultanpur Road, Lucknow : Double Main Bus scheme for 400kV, 220kV & 132kV side 5) Aurai : One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side *Scheduled COD of these elements would be 30th October, 2011 Percentage of Quoted Transmission Charges recoverable on Scheduled COD of the Element of the Project Element (s) which are prerequired for declaring the commercial operation (COD) of the respective Element/project Scheduled COD for overall Project: 31st December, 2012. (Elements mentioned in Serial I (1), (2), (3) & (5) and Serial II (1) & (2) would have Scheduled COD in 30th October, 2011) Uttar Pradesh Power Transmission Corporation Limited
ANNEXURE E: DETAILS OF THE WORKS Package-1 : 765kV S/C Mainpuri - Bara line with 765/400kV AIS at Mainpuri & Associated Schemes / Work Scope of work in Substation Sl. Name of Substation Type Rating Bus Switching Scheme 1 765/400kV Manipuri AIS 2x1000MVA 765/400kV 2 400/220kV Rewa Road GIS 2x315MVA 400/220kV 3 400/220/132kV Gonda AIS 2x315MVA 400/220kV, 2x100MVA 220/132kV 4 400/220/132kV Sultanpur Road, Lucknow GIS 2x500MVA 400/220kV, 2x160MVA 220/132kV One & half breaker with double main bus scheme for 765kV & 400kV side Double Main bus scheme for 400kV and 220kV side One & half breaker with double main bus scheme for 400kV side, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side Double Main bus scheme for 400kV, 220kV & 132 kv side Feeder Bay - 5, Tfr Bay - 2, BR Bay - 1, No of bays 765kV 400kV 220kV 132kV Feeder Bay - 6, NA NA Tfr Bay - 2, NA Feeder Bay - 10, Tfr Bay - 2, BR Bay - 1, BC -1, NA Feeder Bay - 4, Tfr Bay - 2, BR-1, Spare Bay -2 NA Feeder Bay - 2, Tfr Bay - 2, BR - 1, BC - 1, Spare Bay -2 Feeder Bay - 4, Tfr Bay - 2, BC-1, Feeder Bay - 2, Tfr Bay - 4, BC - 1, BT - 1, Spare Bay -2 Feeder Bay - 2, Tfr Bay - 4, BC-1, NA Feeder Bay - 4, Tfr Bay -2, TBC-1, Spare Bay -2 Feeder Bay - 6, Tfr Bay - 2, BC-1, Uttar Pradesh Power Transmission Corporation Limited Page 12
5 400/220/132kV Aurai AIS 2x315MVA 400/220kV, 2x160MVA 220/132kV One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side NA Feeder Bay - 2, Tfr Bay - 2, BR - 1, Feeder Bay - 2, Tfr Bay - 4, BC - 1, BT - 1, Feeder Bay - 7, Tfr Bay - 2, TBC - 1, NOTE :- 1. All the 765kV & 400kV Sub-station shall be constructed with latest design & technology in accordance with latest IS & IEC. All the Substations shall have Sub-station automation system (SAS) comprising SCADA system for transferring data to CLDS. 2. Digital PLCC cabinets shall be installed at each 765kV & 400kV sub-stations for protection and data communication. Other end digital PLCC cabinets (which are inter face points with UPPTCL, Other PPP Package & generator of Bara, Meja, Karchhana) shall also be procured by the developer. The interface would be associated for erection, testing & commissioning of these cabinets. 3. Stringing of Bus for spare bays is under the scope of developer. No equipment shall be commissioned in spare bay. Scope of Work in Lines Sl. Name of line Approx. Line Length ( Km) Provision of OPGW 1 765kV SC Mainpuri - Unnao with Quad Bersimis 175 To be provided 2 400kV DC (Quad Moose) Mainpuri (765kV) - Aligarh 120 To be provided 3 LILO of both circuits of 400kV DC Orai - Mainpuri (PG) at Mainpuri ( 765kV ) 30 To be provided on one circuit 4 765kV 2xSC Mainpuri - Bara with Quad Bersimis 2x350 To be provided on one line 5 LILO of 400kV Panki-Obra at 400kV Rewa Road 12 with Twin Moose 6 400kV DC (Quad Moose) Rewa Road-Karchhana 30 To be provided Uttar Pradesh Power Transmission Corporation Limited Page 13
Sl. Name of line Approx. Line Length ( Km) Provision of OPGW 7 400kV DC (Quad Moose) Rewa Road-Meja 25 To be provided 8 400kV DC (Quad Moose) Bara-Meja 25 To be provided 9 400kV DC (Quad Moose) Bara-Karchhana 30 To be provided 10 400kV DC (Quad Moose) Tanda-Gonda 100 To be provided 11 400kV DC (Quad Moose) Gonda-Shahjahanpur 230 To be provided 12 LILO of 400kV Sarojninagar-Kursi Road (PG) at 20 400kV Sultanpur Road Lucknow with Twin Moose 13 LILO of 400kV Obra-Sultanpur at 400kV Aurai with Twin Moose 15 NOTE: 1. The Steady state active power flow from 765kV Bus in UP, considering Ultimate system peak load of 18957MW, has been preliminary worked out by UPPTCL and is enclosed in the CD. 2. The indicative MW & MVAR loadings of different 765, 400 & 220kV feeders as worked out by UPPTCL and enclosed in the CD. 3. The indicative ultimate system short circuit levels as worked out by UPPTCL ( as enclosed in the CD) show that short circuit levels of 40KA for 1sec will be sufficient for all substations except for Rewa Road, which should be 63KA for 1 sec. 4. OPGW shall be laid on the lines as mentioned above. 5. The repeater station, wherever required shall be commissioned by prospective Developer. Uttar Pradesh Power Transmission Corporation Limited Page 14