South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Similar documents
South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Regional Transmission Planning. Stakeholder Meeting. Web Conference

Review how to acquire data and study assumptions used to conduct the Economic Transmission Planning Studies

South Carolina Regional Transmission Planning. Stakeholder Meeting. Lake Murray Training Center. Lexington, SC. September 12, 2013

Information Postings

Information Postings

Review Initial Results of Reliability Assessments. Inter-regional. Discuss Alternative Solutions from Stakeholders

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

VACAR 2015 SUMMER PEAK RELIABILITY STUDY

Generator Interconnection System Impact Study For

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

MTEP13 SPM #2- Central Region. March 25, 2013

Generation Interconnection Facilities Study For

Sub Regional RTEP Committee - Southern. August 19, 2011

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

Chapter 7 - Appendix A

Reliability Analysis Update

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Black Hills Project Summary

System Impact Study Report

Sub-Regional RTEP Committee PJM South

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Sub Regional RTEP Committee South

Sub Regional RTEP Committee Mid-Atlantic

GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC

Sub Regional RTEP Committee - Southern

Appendix D Black Hills Project Summary

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Feasibility Study Report

Feasibility Study Report

Sub Regional RTEP Committee South

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Q0044 interconnection at

Sub Regional RTEP Committee Western Region ATSI

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Falcon-Midway 115 kv Line Uprate Project Report

SERTP rd Quarter Meeting

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic

SERTP rd Quarter Meeting

100 MW Wind Generation Project

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting

2016 SPP Transmission Expansion Plan Project List Kansas Projects

SPP Notification to Construct

BC Hydro System 2017 Annual Progress Report

Illinois State Report

Transmission Expansion Advisory Committee

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

West Station-West Cañon 115 kv Transmission Project

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Transmission Expansion Advisory Committee. Reliability Analysis Update

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

2013 ANNUAL PROGRESS REPORT

Project #148. Generation Interconnection System Impact Study Report

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Interconnection Feasibility Study Report GIP-157-FEAS-R2

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Appendix B. Summary of Changes to the Year Assessment

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

PREPARED DIRECT TESTIMONY

Sub Regional RTEP Committee Mid-Atlantic

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

North Oregon Coast Area Study. Adam Lint

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

MILLIGAN SOLAR PROJECT

Generation Deactivation Notification Update

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Pacific Gas and Electric Company s Revised 2015 Annual Progress

The Long-Range Transmission Plan

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

TRANSMISSION PLANNING CRITERIA

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Gateway South Transmission Project

MTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Key to Status Fields in the Project List

Proposed New Construction for

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

BY KIM ASBILL PHOTOS BY ROBERT CLARK. Investing in resiliency. New transmission projects will ensure the reliability of SCE&G s electrical system.

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Reliability Analysis Update

Transcription:

Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the Pineland Winnsboro 115 kv line, re-tap the Killian S. Lubeca (Amcor) 115 kv and Killian Blythewood 115 kv lines. Load growth in the Blythewood and Columbia areas requires additional transmission capacity and reliability. This project is required to meet NERC TPL standards and SCE&G s internal Planning Criteria. Completed In-Service Date 2/15/17 $4,667,024 $457,976 $0 $0 $0 $0 $5,125,000 *Total Amount applied to 2017 Rate Base Calculation

Project 2 of 28 Ward 230/115 kv substation: Add Back-up Bank & Bus Tie Breakers 1725A Relocate the spare 230/115 kv autotransformer from Summerville to Ward as a second bank. Install one 230 kv bus tie breaker and one 115 kv bus tie breaker. Load growth in the Lexington, Gilbert, and Saluda areas requires the increased capacity of the 230/115 transformation at the Ward substation, which is used as a secondary source to these areas. Completed In-Service Date 3/9/17 $2,268,265 $131,735 $0 $0 $0 $0 $2,400,000 *Total Amount applied to 2017 Rate Base Calculation

Project 3 of 28 Summerville 230 kv: Replace 224 MVA transformer with 336 MVA 1722A, 1725A Replace Summerville 224 MVA transformer with a 336 MVA transformer and relocate the 224 MVA transformer to the Ward substation Load growth in the Summerville area requires additional 230/115 kv transformation. This project is required to meet NERC TPL standards and SCE&G s internal Planning Criteria. Completed In-Service Date 3/15/17 $3,744,589 $55,411 $0 $0 $0 $0 $3,800,000 *Total Amount applied to 2017 Rate Base Calculation

Project 4 of 28 Cainhoy 230/115kV Sub: Construct and Line Upgrades 2499A, 2499B, 2499C, 2499E, 2499F, 2499G, 2499H Establish a new 230/115 kv substation near the Cainhoy distribution substation, initially with one 230/115 kv 336 MVA transformer. System load growth in the Cainhoy, Hamlin, Mt Pleasant, and Thomas Island areas require additional 230/115 kv transformation. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 5/30/2017 $15,316,829 $4,906,710 $0 $0 $0 $0 $20,233,539 *Total Amount applied to 2017 Rate Base Calculation

Project 5 of 28 Toolebeck 115 kv Switching Station: Construct and R/W 1273A Construct 230/115 kv substation at Toolebeck site with four 115 kv terminals and spacing for future additional 230 kv autotransformer and line terminals. Acquire additional R/W to allow for fold-in of existing 115 kv lines. Also add two 115 kv capacitor banks. There are several potential line overloads under certain contingencies and the need for additional capacity to continue providing reliable service to Aiken area load. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. Completed In-Service Date 5/15/17 $4,940,475 $898,432 $0 $0 $0 $0 $5,838,907 *Total Amount applied to 2017 Rate Base Calculation

Project 6 of 28 Okatie 115 kv Switching Station, 230/115 kv Sub Construct and Line Upgrades 0139A, 0139B Construct 115 kv Switching Station at Okatie Distribution substation site with three 115 kv terminals and spacing for future additional 230 kv autotransformer and line terminals. System load growth in the Hardeeville and Bluffton areas require additional transmission capacity. In Progress $2,440,868 $4,084,132 $0 $0 $0 $0 $6,525,000 *Total Amount applied to 2017 Rate Base Calculation

Project 7 of 28 Queensboro 115 kv Switching Station: Construct 0062A, 0062B Build 4 terminal 115 kv switching station at Queensboro substation. Terminate the existing Queensboro - St. Andrews, Church Creek Queensboro, Queensboro Ft. Johnson Rd, and Queensboro Bayfront 115 kv lines into Queensboro Switching station. System load growth in Church Creek, Faber Place and Queensboro areas require increased transmission capacity from the Charleston Peninsula. In Progress 9/30/17 $1,448,706 $1,501,294 $0 $0 $0 $0 $2,950,000 *Total Amount applied to 2017 Rate Base Calculation

Project 8 of 28 Faber Place - Hagood 115 kv #2 Line: Construct and Faber Place Charlotte Street 115 kv Line Upgrade 1721L, 1721K Construct Faber Place to Hagood 115 kv #2 line with 1272 ACSR. Upgrade the Faber Place to Hagood Junction 115 kv line to 1272 ACSR or equivalent capacity conductor. System load growth in the Charleston area requires additional 115 kv transmission capacity. In Progress 12/29/2017 $821,250 $4,578,750 $0 $0 $0 $0 $5,400,000 *Total Amount applied to 2017 Rate Base Calculation

Project 9 of 28 Thomas Island - Jack Primus 115 kv Line: Acquire R/W and Construct 0270B, 0270C Acquire remaining R/W and then construct a new 115 kv line from the Thomas Island substation to the new Jack Primus substation with 1272 ACSR conductor. Total line length approximately 4 miles. System load growth around Thomas Island requires additional transmission capacity in the area. In Progress 12/31/2017 $3,867,544 $5,082,456 $0 $0 $0 $0 $8,950,000 *Total Amount applied to 2017 Rate Base Calculation

Project 10 of 28 VCS2 St. George 230 kv #1 Line 0094D6 Tear-out and rebuild existing 115 kv and 230 kv lines on the transmission corridor between the Riverbanks Zoo and Dunbar Road substation to SPDC 1272 ACSR construction. This is the System Improvement component (Non-BLRA) of the projects associated with constructing the two 230 kv lines from VCS #2 to future St. George 230 kv switching station. VCS Nuclear Unit #3 Interconnection Requirement. Distribute power from the generation to load while meeting NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 7/31/2017 $6,625,083 $2,374,917 $0 $0 $0 $0 $9,000,000 *Total Amount applied to 2017 Rate Base Calculation

Project 11 of 28 Wateree Orangeburg 230 kv & Eastover Orangeburg 115 kv: Rebuild 0094D25 Rebuild the Wateree Orangeburg 230 kv and Eastover Orangeburg 115 kv lines as SPDC steel pole construction to make room in existing right of way for the new VCS2 St. George 230 kv #1 & #2 lines. This is the System Improvement component (Non-BLRA) of the projects associated with constructing the two 230 kv lines from VCS #2 to future St. George 230 kv switching station. VCS Nuclear Unit #3 Interconnection Requirement. Distribute power from the generation to load while meeting NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 9/1/2017 $88,953 $2,711,407 $0 $0 $0 $0 $2,800,000 *Total Amount applied to 2017 Rate Base Calculation

Project 12 of 28 Orangeburg 230 kv Sub: Fold in VCS2_St. George #1 Line 94D23, 94D24 Fold in the future VCS2 St. George 230 kv #1 line at Orangeburg Transmission. Add two 230 kv line terminals at Orangeburg transmission, replace existing 230 kv 2000 Amp bus-tie breaker with 3000 Amp circuit breaker. This is the System Improvement component (Non-BLRA) of the projects associated with constructing the two 230 kv lines from VCS #2 to future St. George 230 kv switching station. Canadys generation previously provided 323 MW of support to the 115 kv transmission system serving load around the Orangeburg, St. George and Walterboro load centers. Increased support of Orangeburg 230 kv will decrease the burden of 115 kv system in Orangeburg/St. George areas. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria, as well as providing increased reliability to the Orangeburg and St. George areas. In Progress 12/29/17 $1,905,589 $594,411 $0 $0 $0 $0 $2,500,000 *Total Amount applied to 2017 Rate Base Calculation

Project 13 of 28 Church Creek Faber Place 230 kv & 115 kv Lines: Rebuild Ashley River Crossing 1730A Rebuild the Church Creek Faber Place 230 kv and 115 kv section of lines at the Ashley River crossing, consisting of four spans which will be rebuilt to SPDC steel pole construction. Structures are in need of replacement. Wood poles will be replaced with steel pole construction. Planned 5/31/2018 $0 $0 $2,000,000 $0 $0 $0 $2,000,000 *Total Estimated Amount to be applied to 2018 Rate Base Calculation

Project 14 of 28 Hopkins 230/115 kv Sub: Install 2 nd Autobank & Fold-in CIP Wateree 230 kv Line 5386A, 5386B, 5386C Install a second autotransformer at Hopkins with a high and low side PRCB, along with back to back bus tie breakers. Fold-in the Columbia Industrial Park Wateree 230 kv line and add terminals and associated equipment at Hopkins. System load growth in the Hopkins and Eastover areas require additional transmission capacity. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. Planned 5/31/2018 $38,992 $50,000 $7,446,008 $0 $0 $0 $7,650,000 *Total Estimated Amount to be applied to 2018 Rate Base Calculation

Project 15 of 28 AMW Cainhoy 115 kv: Rebuild SPDC B795 ACSR (115 kv & 230 kv) 2499K, 2499L Rebuild the existing AMW Cainhoy 115 kv line to steel pole SPDC construction using B795 ACSR for both circuits. The Williams Cainhoy 115 kv #1 line will be built insulated to 115 kv, and the Williams Cainhoy 115 kv #2 line will be built insulated to 230 kv for future expansion capability. Total line length is 8.5 miles. System load growth in the Cainhoy, Hamlin, Mt Pleasant, and Thomas Island areas require additional 230/115 kv transformation. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 12/3/2018 $346,972 $3,253,028 $5,400,000 $0 $0 $0 $9,000,000 *Total Amount applied to 2018 Rate Base Calculation

Project 16 of 28 Urquhart Sub: Replace Switch House 1060K Replace switch house and relays at the Urquhart substation Substation Maintenance and Equipment Upgrade Planned 12/31/2018 $2,832,343 $0 $167,657 $0 $0 $0 $3,000,000 *Total Estimated Amount to be applied to 2018 Rate Base Calculation

Project 17 of 28 VCS2 St. George 230 kv Line #1 & #2: Construct 0094D6, 00948A, 0094D9, 0094D13, 0094D21, 0094D22, 0094D23, 0094D24, 0094D25, 0094P4, 0094P2, 0094U Tear-out and rebuild existing 115 kv lines on the transmission corridor between the Dunbar Road and Orangeburg substations to SPDC 1272 ACSR construction. This is the System Improvement component (Non-BLRA) of the projects associated with constructing the two 230 kv lines from VCS #2 to future St. George 230 kv switching station. VCS Nuclear Unit #3 Interconnection Requirement. Distribute power from the generation to load while meeting NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 12/31/2018 $8,978,054 $4,500,000 $5,021,946 $0 $0 $0 $18,500,000 *Total Estimated Amount to be applied to 2018 Rate Base Calculation

Project 18 of 28 St. George Summerville 230 kv #2 B1272: Construct 94P4 Upgrade St. George to Summerville 230 kv to SPDC Bundled 1272 ACSR conductor, adding an additional St. George Summerville 230 kv #2 line. This is the System Improvement component (Non-BLRA) of the upgrade of the St. George Summerville 230 kv line associated with VC Summer Unit 3 interconnection requirement. System load growth in the Charleston and outlying areas requires an additional 230 kv source, in conjunction with the in-service dates for VC Summer Units 2 and 3. In Progress 12/31/2018 $7,544,557 $5,800,000 $4,155,443 $0 $0 $0 $17,500,000 *Total Estimated Amount to be applied to 2018 Rate Base Calculation

Project 19 of 28 Canadys 230 kv: Add Back-Back Bus Tie Breakers 6074A, 6075A Upgrade the 230kV bus from single 1272 ACSR to bundled 1272 ACSR. Install back to back 230 kv bus tie breakers and re-terminate existing lines into substation. The 230 kv bus upgrades are required for additional load growth in the southern portion of the SCE&G system, and back-to-back bus tie breakers are required for system reliability improvements. Planned 5/1/2019 $11,561 $0 $0 $4,288,439 $0 $0 $4,300,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation

Project 20 of 28 Lake Murray Harbison 115 kv: Re-terminate Saluda Hydro Harbison and rebuild SPDC O203B, 0203C Re-terminate the Saluda Hydro Harbison 115 kv line to Lake Murray substation in preparation for the SPDC rebuild of the Lake Murray Harbison 115 kv which will add an additional line to create Saluda Hydro Denny Terrace 115 kv line. System growth in the Irmo, Harbison, Piney Woods Road, and Kingswood areas requires additional 115 kv capacity and redundancy to increase reliability. Planned 5/31/2019 $191,720 $0 $4,500,000 $508,280 $0 $0 $5,200,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation

Project 21 of 28 Burton-Yemassee 115 kv #2 Line Rebuild SPDC B795 ACSR 1268A, 1268C Yemassee-Burton 115 kv Line #2: Rebuild 115 kv SPDC using B795 ACSR (line length 21.24 miles). Communications has requested fiber optic cable be added. System load growth in the Burton area requires additional transmission capacity from the Yemassee 230/115 kv substation and added redundancy to increase reliability. In Progress 5/31/2019 $11,860,061 $630,212 $12,500,000 $12,097,727 $0 $0 $37,000,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation

Project 22 of 28 Urquhart - Graniteville South Augusta 230 kv Line: Construct 7973A 7973N Rebuild current Urquhart Graniteville 115 kv line to 230 kv SPDC B1272 ACSR construction in order to upgrade the Urquhart Graniteville 230 kv #2 line and create Graniteville South Augusta 230 kv SCE&G/SOCO tieline. The old Urquhart Graniteville 230 kv line will be converted to 115 kv and reconnected to the newly built South Augusta 115 kv SOCO line to create the Graniteville South Augusta 115 kv tieline. In addition, a 230 kv Series Reactor will be installed on the SRS Vogtle 230 kv SCE&G/SOCO tieline in order to reduce real-time and post contingency line-loading concerns. Load growth in the Aiken area requires additional transmission capacity. Constructing a new 230 kv line from South Augusta to Graniteville will provide an additional source needed during contingencies and increase the transfer capability between SCE&G and Southern Company. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. Planned 5/31/2019 $135,320 $3,850,000 $10,400,000 $16,164,680 $0 $0 $30,550,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation

Project 23 of 28 Bluffton Santee 115 kv Tie Line Construct 7101A, 7101B Construct a new 115 kv tie line from SCE&G Bluffton substation to SCPSA Bluffton substation. Total line length approximately 1.5 miles. This line will run normally open and will only be used in planned outages or emergency situations to feed SCE&G s Bluffton, Hardeeville and Pritchardville substations. Planned 12/31/2019 $0 $0 $350,000 $2,200,000 $0 $0 $2,550,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation

Project 24 of 28 Summerville Pepperhill Goose Creek 230 kv: Construct 2600A, 2600A2 Construct a new 230 kv line from Pepperhill to Summerville with B-1272 ACSR. The existing Canadys Williams 230 kv line will be re-terminated to Pepperhill and Goose Creek to create Canadys Goose Creek 230 kv line and Williams Pepperhill 230 kv line. System load growth in the Pepperhill and Summerville areas require additional transmission capacity. This project is required to meet NERC TPL standards and SCE&G s Internal Planning Criteria. Planned 5/31/2020 $239,765 $0 $700,000 $5,000,000 $3,760,235 $0 $9,700,000 *Total Estimated Amount to be applied to 2020 Rate Base Calculation

Project 25 of 28 Coit Gills Creek 115 kv Line: Construct 5392A Construct a new 115 kv tie line from Coit substation to the Gills Creek substation. System growth in the Eastern Columbia and Garners Ferry areas requires additional 115 kv capacity and redundancy to increase reliability. Planned 12/31/2020 $0 $0 $0 $0 $2,500,000 $0 $2,500,000 *Total Estimated Amount to be applied to 2020 Rate Base Calculation

Project 26 of 28 Union Pier 115-13.8 kv Sub: Tap 0167C Construct a new 115 tap line off of the Charlotte St. Faber Place 115 kv line to serve the new Union Pier 115-13.8 kv substation. Line length approximately 0.7 miles. System load in the downtown area of Charleston requires an additional 115-13.8 kv transformation to support distribution load growth and reliability. Planned 12/31/2021 $0 $0 $0 $0 $0 $2,500,000 $2,500,000 *Total Estimated Amount to be applied to 2021 Rate Base Calculation

Project 27 of 28 New Nuclear Deployment BLRA Unit 2 - Transmission 0090B, 0090D,0090E, 0090F, 0090G, 0090H, 0090I, 0090J, 0090K, 0090L, 0090M, 0090N, 0090Q, 0090R, 0090S, 0090T, 0090U, 0091F, 0091M, 0091N, 0091P, 0091F, 0091U Various projects in the northwestern portion of the SCE&G transmission system needed to accommodate SCE&G s portion of the 1,165 MW of generation from VC Summer Unit #2: - Construct a new 230 kv generator switchyard using breaker-and-a-half design with ten (10) 230 kv terminals - Install a VC Summer #2 generator step-up transformer - Construct a 230 kv connection from the switchyard to the GSU - Construct a 230 kv connection from the switchyard to the reserve auxiliary transformers - Construct two VC Summer #2 VC Summer #1 230 kv lines with B1272 ACSR - Re-terminate multiple lines at VC Summer #1 to accommodate new transmission lines associated with Unit #2 - Construct an additional VC Summer #2 Lake Murray 230 kv line - Construct a VCS #1 Killian 230 kv line - Replace existing 115 kv and 230 kv circuit breakers with higher interrupting capability breakers VCS Nuclear Unit #2 Interconnection Requirement. Distribute power from the generation to load while meeting NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress In-Service Date 12/31/16 $138,260,582 $0 $0 $4,739,418 $0 $0 $143,000,000 *Total Estimated Amount to be applied to 2019 Rate Base Calculation (To coincide with on-line commercial operation date for VC Summer Unit 2)

Project 28 of 28 New Nuclear Deployment BLRA Unit 3 - Transmission 0094D, 0094E, 0094H, 0094I, 0094J, 0094K, 0094M, 0094N, 0094O, 0094P, 0094Q, 0095A Various projects in the western/southern portion of the SCE&G transmission system needed to accommodate SCE&G s portion of the 1,165 MW of generation from VC Summer Unit #3: - Add six (6) terminals to the VC Summer #2 switchyard using breaker-and-a-half design - Install a VC Summer #3 generator step-up transformer - Construct a 230 kv connection from the switchyard to the GSU - Construct a 230 kv connection from the switchyard to the reserve auxiliary transformers - Construct one additional VC Summer #2 VC Summer #1 230 kv line with B1272 ACSR - Construct a 230 kv switching station located in St. George, SC with six (6) terminals - Construct two lines from VC Summer #2 to St. George using B1272 ACSR (135 miles) - Upgrade Canadys St. George 230 kv line - Upgrade St. George Summerville 230 kv line - Replace existing 115 kv and 230 kv circuit breakers with higher interrupting capability breakers VCS Nuclear Unit #3 Interconnection Requirement. Distribute power from the generation to load while meeting NERC TPL standards and SCE&G s Internal Planning Criteria. In Progress 12/31/18 $139,308,431 $0 $0 $0 $91,691,569 $0 $231,000,000 **Total Estimated Amount to be applied to 2020 Rate Base Calculation (To coincide with on-line commercial operation date for VC Summer Unit 3)