Simulation of Robotic Regolith Mining for Base Construction on Mars. Eric Halbach, Vadim A. Zhmud, Aarne Halme

Similar documents
EFFECT OF TRUCK PAYLOAD WEIGHT ON PRODUCTION

Why? Faster To reduce the duration of the process

QA Mobile Crushing & Screening. Stu Gamble - Sandvik

VOLVO CE SITE SIMULATION LOAD AND HAUL TUTORIAL METRIC UNITS

Autonomously Controlled Front Loader Senior Project Proposal

MARITIME AFTERNOON. Torben Ole Andersen. June 14, 2017 Aalborg University, Denmark

DOZERS. Tractor equipped with a front mounted earthmoving blade is known as bulldozer or dozer.

2a. Excavating and Lifting

Initial Concept Review Team Alpha ALUM Rover (Astronaut Lunar Utility Mobile Rover) Friday, October 30, GMT

PRELIMINARY DESIGN REVIEW

MIFACE INVESTIGATION #06MI209

* S stm. 0r 0. 0tin. and. Hadling. Ble. Lare~un I - I

APPENDIX B. POTENTIAL CONSTRUCTION EQUIPMENT

Guidelines for Battery Electric Vehicles in the Underground - Mine Design

Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) 48" Pallet Fork

CEM 417 WEEK 6. CONSTRUCTION TECHNOLOGY & maintenance. Construction Plants 22/02/2011 WEEK 6 CONSTRUCTION PLANTS

Mars Surface Mobility Proposal

MAI UNITED STATES DEPARTMENT OF LABOR MINE SAFETY AND HEALTH ADMINISTRATION Metal and Nonmetal Mine Safety and Health REPORT OF INVESTIGATION

Optimising the Mining Fleet Series Part 5: The Optimised Fleet in Action

UNITED STATES DEPARTMENT OF LABOR MINE SAFETY AND HEALTH ADMINISTRATION Metal and Nonmetal Mine Safety and Health REPORT OF INVESTIGATION

Abstract. General N BANDA

Conveyor Belt Monitoring

PwC Autofacts. The Transformation of the Automotive Value Chain.

Q1. Figure 1 shows how atmospheric pressure varies with altitude.

Hydraulic power is the key to the utility of many excavators.

Excavator-mounted drill rigs

PRODUCTION OF CONSTRUCTION OPEARTIONS: AN EXAMPLE ON READY MIX CONCRETE BATCH PLANT

Design and evaluate vehicle architectures to reach the best trade-off between performance, range and comfort. Unrestricted.

AMI Wheel Loader Attachments

Special Specification 7010 Debris Removal and Disposal

Critical Chain Project Management (CCPM)

Technical Information. (Innovative Transport Technology for Open Pit Mines)

SIMULATING AUTONOMOUS VEHICLES ON OUR TRANSPORT NETWORKS

Modeling and Optimization of a Linear Electromagnetic Piston Pump

IMnI s 5 th OHES Workshop April 28-30, 2014 CaraJas - Brazil. Dr Doreen McGough OHES Manager, IMnI

Dump Point Safety. Vehicle concerns and Additional Points. Jonathan Hall, PE Tech Support, A&CC, M&ESD

Whatcom County Invitation to Bid Bid #17-09

reliable Wher ver gears and shafts turn, Timken innovation is in action. From equipme t mining deep in the earth to exploration in the

WorkWell Consulting Ergonomic Risk Identification & Assessment

Cooperative EVA/Telerobotic Surface Operations in Support of Exploration Science

A COMPUTER MODEL FOR SELECTING EQUIPMENT FOR EARTHMOVING OPERATIONS USING QUEUING THEORY

1) The locomotives are distributed, but the power is not distributed independently.

ATTACHMENT E: CONSTRUCTION EQUIPMENT SUMMARY

COMMITTED TO YOUR SUCCESS. Cat Recycling and Waste Solutions

Lunar Architecture and LRO

The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection.

기계시스템해석 System Dynamics/System Analysis

Heavy-Duty Vehicles. Regulatory opportunities, design challenges and policy- relevant research. Fanta Kamakaté. July 30, 2009

LHD Vehicles. Product Line

LOADERS Ideal for virtually every rugged job, Woods loaders provide years of worry-free service

Modeling and Optimization of a Linear Electromagnetic Piston Pump

Tractor-Trailer Combination Braking and Safety. Presented by : Paul Schutte Date: 12 April 2007

Western Land Area Programmatic Environmental Assessment. APPENDIX K: Climate

Energy Efficient Hydraulic Fluids

AMI Wheel Loader Attachments

Automated Garbage Collection ANSWERS TO FREQUENTLY ASKED QUESTIONS:

Brief overview of lunar surface environment Examples of rover types and designs Steering systems Static and dynamic stability

Selection of Shaft Hoisting or Decline Trucking for Underground Mines

Local Climatic Effects of Coal Fires:

The Knowledge Bank at The Ohio State University. Ohio State Engineer. Central Mixing Plants for Concrete. Heck, Edward

GHG Emissions A Canadian Perspective

DEVELOPMENT AND EVALUATION OF HYDRAULIC SIMULATION MODEL FOR WHEEL LOADER

Quarterly Stakeholder Call

Wheel Loader Buckets Rugged. Versatile. Dependable.

CONVEYOR SYSTEM COMMISSIONING, MAINTENANCE AND FAILURE ANALYSIS USING BLACK BOX TECHNIQUES. By A. J. Surtees Conveyor Watch (Pty) Ltd

CONVEY-ALL BTS290 Seed Tender

A.M. MONDAY, 19 January minutes

Design and Simulation of New Versions of Tube Launched UAV

Liebherr machines in use worldwide in the quarry industry

Loading and Hauling. Håkan Gustafsson David Nus Martin Mattsson

Draglines. Product Line

PARTING COMPANY. Producer Switches Parts Brand After Proven Performance. written by Michelle Cwach 6 THE FEED

Steel Products. 8M Series

Maintaining frictional resistance on mine road surfaces. Presented by Cres Bulger Inspector Of Mines (Qld)

4.4.2 FRONT-END LOADERS

SHIFT INTO WORK MODE. CAT CX31 AUTOMATIC TRANSMISSION FOR CAT VOCATIONAL TRUCKS

MDEC Conference October 5 th,

: Anandro Amellonado. Alternatives of Dredging Method Based on Interpretation of Soil Investigation in The North Kalibaru Project

TRADE ENGINEERING. Solutions for Success. Products for the Mining Industry. Slip Ring Units

Abstract. Executive Summary. Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County

EMPACK MECHELEN, 11 OCTOBER 2017, STAF SEURINCK, ABB BENELUX Upcoming digital solutions and services.

MBS Models. ADAMS/Hydraulics - an Embedded Hydraulics Environment

200 SERIES SKID STEERS LOADERS/COMPACT TRACK LOADERS

Occupations (Construction)

DRAG-A-BOX BRAND MATERIAL SPREADERS

EFFICIENT URBAN LIGHT VEHICLES.

Service & Operation Manual. H619 Pulled Scraper

Modernisation of a Bucket-Wheel Excavator at the Welzow-South lignite mine, Lausitzer Braunkohle AG, Germany (1996)

Army Ground Vehicle Use of CFD and Challenges

Hybrid Wheel Loaders Incorporating Power Electronics

Solid Waste Management

Current Status of Alt Truck Technologies

**Equipment production**

AUTOMATION AND CONTROL TRADE 19 TAR SANDS

MindSphere The IoT operating system for smart cities. Hakan Olcay, Energy Efficiency Coordinator at Siemens

How to Store a Billion Beans [Language Arts]

Information Meeting Transfer Station Options. September 30, 2014

Wet flame-jet drilling: An alternative technique to access deep heat reservoirs

REX8+ COVERT MAGMOUNT TRACKING UNIT

Robots in Mining. Jeremy Green Centre for Mining Innovation. 1 September CSIR 2010 Slide 1

Transcription:

Simulation of Robotic Regolith Mining for Base Construction on Mars Eric Halbach, Vadim A. Zhmud, Aarne Halme eric.halbach@aalto.fi May 17, 2013

Motivation Image: SpaceX Image: James Cameron Manned landings on Mars may soon be a reality. After initial outposts are established, the challenge will be to build permanent, growing settlements out of mostly local materials.

Motivation Mars Homestead Project (MHP) by the Mars Foundation: a detailed plan for a growing, permanent settlement using local resources. Extensive use of regolith: locally manufactured bricks for masonry construction and burying inhabited spaces for radiation protection. Mackenzie, B., Leahy, B., Petrov, G., and Fisher, G. (2006). The Mars Homestead: a Mars Base Constructed from Local Materials. In Space 2006. Images: Mars Foundation Petrov, G. I. (2004). A Permanent Settlement on Mars: The First Cut in the Land of a New Frontier. Master s thesis, Massachusetts Institute of Technology.

Mars Homestead Project Images: Mars Foundation First phase of construction: excavation into hillside 45 m wide, 30 m deep (laterally). Assumptions: slope angle 30 deg., debris apron with consistency of loose gravel no fragmentation required. Assertion: robotic machinery should be used to increase safety. Direct teleoperation should be avoided to reduce operator workload, allow one operator to oversee fleet of machines and possibly allow long time-delay control from Earth.

Simulated Worksite Simulation of first MHP construction phase using Matlab-based simulator. Purpose: develop and test high-level planning and control for robotic machines, investigate feasibility of job within reasonable time and without direct teleoperation. 1 Loader + 2 Dump Truck combination considered minimum requirement, to allow for continuous loader operation.

High-Level Plan Interactive 3D graphical tools used to make high-level plan. Red slope surface: section to be excavated; blue virtual pile: where to dump material. Low dump pile (1m) possible with dump trucks takes up large area, may hinder base construction and operations. Requirement identified for machine capable of depositing material from higher above the ground.

High-Level Plan High storage pile (6m) possible with conveyor belt spreader stores material more efficiently.

Automatic Plan Interpretation High-level plan automatically interpreted: points for scooping, hauling and dumping generated and represented by cones.

Plan Modification by User User can modify plan by clicking and dragging a point. Attached and associated points adjusted automatically.

Work Cycle 1. Scooping 2. Loading dump truck 3. Hauling and driving back 4. Unloading at the spreader

Scooping Strategy Automated scooping approach is towards highest point in specified area. With large area, this tends to result in persistent scooping in same direction likely an unwise strategy with inefficient bucket penetration and risk of loader getting stuck or tipping over.

Scooping Strategy 1. 2. User can reduce target area, resulting in more balanced scooping approaches. Requires occasional updates when moving target area to new location. 3.

Long-Term Simulation Long duration simulation with growing dump pile. 128 cubic metres of regolith moved in 6 hours of simulated time. Driving speed is 0.5 m/s, loader bucket capacity 0.31 cubic metres. Automatically-updated dumping location: spreader has shifted to the left.

Hauling Distance Trade-Off empty truck still returning loader ready, standing idle With increased hauling distance, the loader must sometimes wait for the next empty dump truck, standing idle and lowering productivity. A long hauling distance may however be necessary, to avoid storing the material too close to the base and potentially disrupting operations. The maximum hauling distance with no waiting time for a particular simulation was found by adjusting the position of the blue virtual pile until it was observed for several cycles that the loader did not need to wait.

Trade-Off Analysis Larger loader scoop capacity increased work rate, as expected. Mars Homestead Project excavation requirement: 30 degree slope segment, 45 m wide, 30 m deep = 11691 cubic metres. At 8 hours/day: Work Rate A: 132 days (18.8 weeks) Work Rate B: 59 days (8.4 weeks). Ratio of dump truck capacity to loader scoop capacity affects maximum hauling distance at which loader will operate without interruptions, i.e. not having to wait for an empty truck.

Future Work Further investigate conflicting requirements of cost (smaller machines/buckets, fewer machines) and work rate (larger machines/buckets, more machines) Add more loaders, see if remote operator workload becomes saturated Add more dump trucks, see how many can share one spreader

Conclusion High-level planning identified machinery requirement for conveyor belt spreader to store material more efficiently Combination of 1 loader and 2 haulers allowed for reasonable work rates and hauling capabilities Trade-off between bucket ratio and maximum hauling distance was identified and analyzed All simulations were conducted without direct teleoperation, i.e. one remote operator could monitor all machines and provide high-level direction Simulation was shown to be useful for comparing machinery specifications and site plans