Operational Tests of the Three-Gorges Changzhou HVDC Thyristor Valves by Using a Synthetic Test Circuit

Similar documents
A New Synthetic Test Circuit For the Operational Tests of HVDC Thyristor Modules

Reliability Enhancement of HVDC Transmission by Standardization of Thyristor Valves and Valve Testing

Electrical Test of STATCOM Valves

Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON

A novel synthetic test system for thyristor level in the converter valve of HVDC power transmission

Lecture 2. Power semiconductor devices (Power switches)

Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank

Independent Testing Laboratory for High Voltage Equipment

The 1,400-MW Kii-Channel HVDC System

Design and Reliability of a High Voltage, high Current Solid State Switch for Magnetic Forming Applications

A low loss mechanical HVDC breaker for HVDC Grid applications THOMAS ERIKSSON, MAGNUS BACKMAN, STEFAN HALÉN ABB AB, CORPORATE RESEARCH SWEDEN

Product brochure Generator circuit-breaker HVS-63S System type GCB with innovative built-in monitoring

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

A Revolution in Circuit Breaker Operating Mechanism Technology

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

Dual Power. Protection. Protection

Soft Switching of Two Quadrant Forward Boost and Reverse Buck DC- DC Converters Sarath Chandran P C 1

Implementation of FC-TCR for Reactive Power Control

DEPARTMENT OF ELECTRICAL ENGINEERING DIT UNIVERSITY HIGH VOLTAGE ENGINEERING

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Second Edition. Power Electronics. Devices and Circuits. V. Jagannathan

GAS INSULATED VOLTAGE TRANSFORMERS.

Study of 345 kv Transient Recovery Voltages on the Illinois Power System

Increasing Wanzhou Power Transfer Capability by 550kV Fixed Series Capacitor FSC Fengjie

Modelling of Hybrid DC Circuit Breaker Based on Phase-Control Thyristors

A Transient Free Novel Control Technique for Reactive Power Compensation using Thyristor Switched Capacitor

Pankaj Khali, ABB India Limited Representing :ABB Switzerland limited, September 2016 Generator Circuit-Breakers. Technical Seminar: PLN

The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions

ADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

EXPERIMENTAL VERIFICATION OF INDUCED VOLTAGE SELF- EXCITATION OF A SWITCHED RELUCTANCE GENERATOR

T5S4P3 Synchronous Condensers Application. Mr. Marco Schenone Mr. Sandro Tuscano Mr. Alessandro Oldrati

Item 1: Contents of the complete training & CV of the lecturer

R13 SET - 1. b) Describe different braking methods employed for electrical motors. [8M]

Enhancement of Transient Stability Using Fault Current Limiter and Thyristor Controlled Braking Resistor

Surge Current, I 2 t Value and Short - Circuit Protection of High Power Semiconductors.

Power Quality and Power Interruption Enhancement by Universal Power Quality Conditioning System with Storage Device

VEIKI-VNL Electric Large Laboratories Ltd. H-1158-Budapest, Vasgolyó utca 2-4. HUNGARY

HVDC. TMT&D provides the best and most economical HVDC system.

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

ELEC-E8421 Components of Power Electronics. Thyristors

Rural electrification using overhead HVDC transmission lines

Modelling and Analysis of Thyristor Controlled Series Capacitor using Matlab/Simulink

Review paper on Fault analysis and its Limiting Techniques.

Enabling the power of wind. Competence and expertise for wind power customers

Excitation systems for high power synchronous generators with redundant configurations

High Power Semiconductor Devices and Solid State Switches for Pulsed Discharge Applications

Statcom Operation for Wind Power Generator with Improved Transient Stability

Overview of Flexible AC Transmission Systems

The Development of ±800kV/4750A UHVDC Valve & HVDC/FACTS Status in China. For EPRI HVDC & FACTS Conference Aug. 30, 2011 Palo Alto, California, USA

Development and Performance Evaluation of High-reliability Turbine Generator

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

SVC Light For electrical transmission grids

SEMIS Simulation Tool for 6 pulse Controlled Rectifier

OPF for an HVDC feeder solution for railway power supply systems

Concepts And Application Of Flexible Alternating Current Transmission System (FACTS) In Electric Power Network

Course Name: POWER ELECTRONICS Course Code: EE603 Credit: 4

Overview Overvoltage protection

Reverse power relay and protection assemblies

Fault Rid Through Protection of DFIG Based Wind Generation System

Fast thyristors. When burning for induction heating solutions.

Alvin Xu & Johnny Wang, ABB Xiamen Switchgear Co,. Ltd., November, 2016 ABB lead the intelligent revolution Intelligent technology (Part 2)

INTER PLANT STANDARD STEEL INDUSTRY SPECIFICATION FOR STATIC EXCITATION CONVERTORS FOR SYNCHRONOUS MOTORS (FIRST REVISION)

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

CIGRÉ SC B1 International Colloquium on H.V. Insulated Cables Oct 2017, New Delhi, India

Modelling and Simulation of DFIG with Fault Rid Through Protection

PQC - STATCON The ultra fast Power Quality Compensator

Characteristics of LV circuit breakers Releases, tripping curves, and limitation

Gas-Insulated Switchgear. Type 8VN1 blue GIS up to 145 kv, 40 ka, 3150 A

SIDACtor Protection Thyristors Baseband Protection (Voice-DS1)

ZENSOL AUTOMATION INC.

Experiences in a Motor Protection Retrofit

The Modeling and Simulation of DC Traction Power Supply Network for Urban Rail Transit Based on Simulink

B kv Gas-insulated Substations

POWER QUALITY IMPROVEMENT BASED UPQC FOR WIND POWER GENERATION

OPF for an HVDC Feeder Solution for Railway Power Supply Systems

ELEC-E8421 Components of Power Electronics. Protection of Power Semiconductor Devices

Reactive Power Management Using TSC-TCR

A study of the power capacity of regenerative inverters in a DC electric railway system

AIR CORE REACTORS. Phoenix Electric Corporation

Variable speed control of compressors. ABB drives control the compressors of the world s longest gas export pipeline

RESPONSE OF A MEDIUM VOLTAGE CURRENT LIMITING FUSE OF SMALL SIZE TESTED AS GENERAL PURPOSE AND FULL- RANGE TYPE.

ELECTRICAL POWER and POWER ELECTRONICS

Ref No: Date: February 8, 1995 INDUSTRIAL CONTROL EQUIPMENT NO. 2

Thyristors for >10 GW Power Transmission

Modelling and Simulation of DFIG based wind energy system

Breaker-failure protection RAICA

COMPARISON OF DIFFERENT METHODS FOR EXCITATION OF SYNCHRONOUS MACHINES

Newly Developed High Power 2-in-1 IGBT Module

RAPTOR DEFAULT TEST TEMPLATES

Product Brochure. Generator Circuit-Breaker HVR-EBCB For hydro or pump storage power plant

LINE CONDITIONERS USER'S GUIDE

Wind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment

Advance Electronic Load Controller for Micro Hydro Power Plant

Latest development in transmission in 800kVDC

Performance study of combined test rig for metro train traction

GENERATION, CONVERSION, OR DISTRIBUTION OF ELECTRIC POWER

Outdoor live tank SF6 circuit breaker EDT with integrated current transformer up to 72.5 kv

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

ABB s hybrid HVDC breaker, an innovation breakthrough enabling reliable HVDC grids

Transcription:

Operational Tests of the Three-Gorges Changzhou HVDC Thyristor Valves by Using a Synthetic Test Circuit Baoliang Sheng, Member, IEEE; Hans-Ola Bjarme; Pierre Riffon, Member, IEEE; Weimin Ma Abstract Three-Gorges Changzhou (G) HVDC thyristor valves have a high power rating per thyristor level. Testing of these thyristor valves by using a conventional Back-to-Back test circuit would necessitate huge investments and would not give an improved testing regime than produced by the solution chosen. A synthetic test circuit using the conventional Back-to-Back test circuit to supply the current and an oscillating circuit to supply the voltage has been developed for the testing of the G thyristor valves. The conditions of the four operational states of HVDC thyristor valves can be adequately represented in this synthetic test circuit. The test parameters used gave test stresses on the test object equal to or higher than those that are foreseen to appear in service. The successful type test results showed that the design of G HVDC thyristor valves is fully adequate. The tested modules have also shown a substantial margin in the thyristor valve design since, for most of the tests, the test parameters were globally more severe than specified. Index Ter Synthetic test circuit, operational tests, Three- Gorges thyristor valves, testing T I. INTRODUCTION HE G HVDC thyristor valves are designed to transmit MVA at ±5 [1]. Using a conventional six-pulse Back-to-Back test circuit (direct test circuit) to test the G HVDC thyristor valves would had need a huge power installation in the test plant. To expand the testing power of the direct test circuit is neither an economical nor a very practical solution. Synthetic test circuit, as an alternative, is widely used by the different test laboratories for the operational testing of thyristor valves. This method is also recommended by CIGRE [2] and allowed by IEC []. One of the main advantages of using a synthetic test circuit is that the number of series connected thyristors per test set-up could easily meet the minimum number stated in the IEC standard. The synthetic test circuit developed in ABB Power Syste is based on the current injection method [4]. This circuit meets Baoliang Sheng and Hans-Ola Bjarme, ABB Power Syste AB, 7718 Ludvika, Sweden ( e-mails: baoliang.sheng@se.abb.com and hansola.bjarme@se.abb.com ) Pierre Riffon, Hydro Québec, Montréal, H2L 4P5 Canada (e-mail: riffon.pierre@hydro.qc.ca ) Weimin Ma, Beijing HVDC Engineering Consultant Co., Ltd, Beijing 88, China ( e-mail: maweimin@sp-bdcc.com ) the requirements of IEC standard as well as the test requirements specified in the user specification. In a synthetic test circuit, the current and voltage are fed by two power sources. The auxiliary valves are connecting alternatively the test valve to the two sources during different time intervals in order to produce the required stresses (voltage and current). The two sources are feeding simultaneously the test valve during the commutation and prior to the extinction process in order to minimize the influence caused during the transfer from one source to another, especially from the current source to the voltage source. To obtain this test condition, the voltage source has to be connected prior to the current zero of the current source in the same way as used for synthetic tests on circuit-breakers (current injection method). The current injection has two roles: to get a single source feeding the test object at current zero and to represent the current derivative (di/dt) prior to the current zero crossing as it will appear in service. The current injection synthetic testing method is widely used for the testing of high voltage AC circuit breakers. This method is generally considered superior to other synthetic test methods in ter of stress representation, especially close to current zero during the current extinction process. II. THREE-GORGES CHANGZHOU HVDC THYRISTOR VALVES G HVDC thyristor valves are built with several thyristor modules. Each module has six thyristor levels including their snubber circuits, thyristor control units and voltage dividers. A saturable reactor is connected in series with each thyristor module. One of G HVDC thyristor valve under the dielectric test program is shown in Fig.1. G thyristors are using a well-proven semiconductor product developed by ABB Semiconductors in Switzerland. The main technical data of the thyristors used are shown in Table 1. Table 1 Main technical data of the G thyristors V DSM Q rr I TSM* V T r T 72V 6µAs 6 1,26V.197mΩ * surge on-state current with reapplied off-state voltage 1

without changing the test set-up and real time interaction with valve control and converter firing syste for the intermittent direct current test. By using of two sources to supply the current and voltage independently, the test parameters are fully controllable. Inverter D/Y Impulse Generator G D/D Rectifier Ls L1 Va L2 Va2 DC Source Va1 Vt Ct Va4 Cs Va5 C2 High Current Section High Voltage Section Fig. 2 The synthetic test circuit for the operational tests of G HVDC thyristor valves Fig.1 View of G HVDC thyristor valve III. SYNTHETIC TEST CIRCUIT FOR THE OPERATIONAL TESTS The synthetic test circuit for the operational tests of the G HVDC thyristor valves is shown in Fig.2. The operating principle of this circuit is reported in [4] and will be briefly described in the following paragraph. As one arm of a six-pulse rectifier in a Back-to-Back circuit, the test modules (Vt) conduct a current representing the service current shape after firing. Prior to the end of the commutation (current zero), the voltage source is connected to the test valve (Vt) by the firing of the auxiliary valve Va. At this moment and up to the current zero of the current source, the test modules conduct a current, which is the sum of the current fed by the current source and the current supplied from the voltage source. After the blocking of the current fed by the current source by the auxiliary valve (Va1), the test modules are fed uniquely by the synthetic circuit and continue to conduct the injection current for about 6µs. The inductance L1 and the voltage on Cs are chosen to have the same current derivative (di/dt) as in service for approximately 2µs prior to current zero. The reverse recovery voltage and forward voltage are produced by the firing of auxiliary valves Va4 and Va5 at specific instants. The circuit parameters have to be carefully chosen in order to be representative of system conditions, and to adequately reproduce the stresses on the thyristor modules in the two most critical operation states, i.e. at turn-on and at turn-off [5]. The integration of a conventional six-pulse Back-to-Back direct test circuit in the synthetic test circuit offers several technical merits beside the close representation of in service valve current shape. They are: no transition time from normal operation to fault operation for valve fault current tests, possibility of performing the minimum firing voltage tests IV. TEST DESCRIPTIONS The complete operational type test program, as required in IEC67-1 and the Technical Specifications of G HVDC Thyristor Valves, has been strictly followed during the tests for G thyristor valves. The whole operational test program for the G HVDC thyristor valves was performed with the abovedescribed synthetic test circuit. The required operational test program includes: Heat-run test and protective firing test; Maximum temporary operating duty test (α=9 ο ); Minimum AC voltage tests (minimum firing voltage test and minimum extinction voltage test); Intermittent direct current test; Tests with transient during the recovery period; One-loop fault current test with re-applied forward voltage; Three-loop fault current test without re-applied forward voltage. A. Design of Test Parameters A careful follow up of the stresses applied to the thyristor modules (applied voltages, di/dt, thyristor junction temperature, thyristor losses and snubber losses) during each series of tests have been done in order to produce stresses equal to or greater than those that would been applied in service (taking into account the safety test factors given in IEC67-1). The characteristics of synthetic tests are such that both the test current and voltage wavefor are different than those occurring during service or in a Back-to-Back direct test circuit. During the on-state condition, an extra injection current loop (sinusoidal shape) is added to the normal valve 2

current shape prior to the commutation. This results in extra conduction losses of the thyristor and prolongs the conduction period. During the turn-off interval, the damping effect of the snubber circuit in auxiliary valve Va1 decreases the rate of rise of recovery voltage (dv/dt) on the test valve and the reverse and wavefor have not the same voltage jumps as seen in service. To compensate the low dv/dt and absence of some voltage jumps in the applied thyristor voltage, higher test voltages were chosen during tests. The test voltage levels were determined by using several formulas. The first calculation step is to calculate the voltage levels seen by the thyristor valve at turn-on and turn-off for the required testing operation modes in service. Then, the losses in the different components were derived (conduction losses in the thyristors, turn-on losses, snubber losses, recovery charge losses in the snubbers and in the thyristors). Losses were calculated according to the equations given in [6]. These test parameters were used as reference values for the calculation of the synthetic test circuit parameters. Since the synthetic circuit voltage waveshape is quite different from the normal waveshape across the thyristor valve, the same calculations as performed for an equivalent Back-to-Back direct circuit were made in order to select a proper synthetic test voltage producing losses equal to or higher than the required operation modes. The test parameters for the operational tests of the G HVDC valves are given in Tab. 2. B. Test Description Before the start of each required test duty, the inlet coolant temperature and its flow rate were carefully controlled. A ten minutes preheating period having the heat-run test parameters was also performed in order to closely represent the pre-load condition of test object before any of the required test duty. A total of 15 (fifteen) modules or 9 thyristors levels of G HVDC thyristor valves were type tested. All 15 modules were tested according to the test program and parameters listed in table 2 except for the protective firing test. An eight hours protective firing test was performed on one test set-up only (2 thyristor modules). A RCR voltage divider has been used to measure the applied voltage while a Rogowski coil has been used to measure the current through the test object. Current transformers were used to measure the line currents fed by the transformers. Several voltage probes were employed to monitor the phase-to-phase voltages and DC side voltage. All these signals were recorded and processed by a digital data acquisition system. The MACH 2 system, a control system developed by ABB for power system control and protection, was used to control the synthetic circuit operation. Pre-programmed test sequences for each test duty were recalled. The pre-programmed test sequences comprise the current and voltage order, firing sequences for the test object and the auxiliary valves and the test duration. The coolant temperature and the flow rate in each individual valve were also monitored by the MACH 2 system during tests. A graphical operator window was displayed from the MACH 2 control system in order to obtain an easy access for execution or modification of the above functions. The MACH 2 control system is also used to set-up the test circuit (back-to-back and synthetic source) by using remote control functions. The following figures show typical examples of the recorded oscillogra: Tab. 2 Test parameters for the operational tests of G HVDC thyristor modules Test Duty Duration I dc I fault U E U H U F U F_block U R_block (A) () () () () () () Protective firing test 8 h. 217 4.7.5 Heat-run test min. 217 4.7.5 Maximum temporary operating duty test (α=9 ο ), repetitive voltage test sec. 5 62.7 57. Maximum temporary operating duty test sec. 5 4. (α=9 ο ), heat run test Maximum temporary operating duty test (α=9 ο ),heat run test 2 sec. 5 5. Minimum AC voltage tests 15 min. 217.8 5.4 Minimum AC voltage tests 1 min..2.7 Intermittent direct current tests 2 min. <2.5 Tests with transient during 217 4.7.5 the recovery period One-loop fault current with re-applied 217 4.7 4.7.7 44. Three-loop fault current without re-applied 217 5.9 4.7.7 26.9 U E transient recovery voltage peak U H reverse power frequency recovery voltage peak U F prior to firing U F_block forward block voltage peak U R_block reverse block voltage peak

- Fig.: Test current and voltage during one cycle in the heat-run test duty. - Fig. 4: Maximum temporary operating duty with α equal to 9 electrical degree. The test object was fired twice per cycle in order to obtain the required snubber losses. - Fig. 5: Intermittent direct current and voltage during the intermittent direct current test. After the ten minutes preheating period, the current from the current source is gradually reduced to the level that the DC current becomes intermittent. As shown on this oscillogram, the voltage circuit is trigged after the last power frequency current pulse for reproducing the turn-off voltage and the following turn-on voltage during such mode of operation with high firing angles. - Fig. 6 and Fig. 7: Oscillogra of one-loop fault current test with re-applied and three-loop fault current test without re-applied. The upper trace is the test current through the test object while the middle trace is the line current measured by the current transformers. The lower trace is the voltage applied on the test object during the test. - Fig. 8: Test with transient during the recovery period. As required, three different impulses with front times of 1µs, µs and µs respectively were applied at different times in the interval from to 15µs after current extinction. Fig. 8 illustrates specifically an oscillogram of the 1 µs transient impulse applied on the test object 4µs after current zero. 1.6 1.2 4 /div.4 -.2 4 2 k/div - - I_ 5 4 k/div - -7 15 2 5 25 5 /div Fig. 5 Intermittent direct current test - 2-2 /div Fig. 6 One-loop fault current with re-applied 4 1 k/div 1 -.5 4 I_ 4 2 k/div - k/div -2-15 2 25 5 /div Fig. Periodic firing and extinction tests -2-2 4 5 6 /div Fig. 7 Three-loop fault current without re-applied 2.4 2 1.8 1.2 6 /div.6.4 8 /div -.4-1.2 -.6 5-2 9 6 2 k/div - k/div - -7 2 25 15 5 5 /div -4 - -2-2 4 5 µs/div µs Fig. 4 Periodic firing and extinction test (α = 9 ο ) Fig. 8 Test with transient voltage during the recovery period 4

C.Test Result No component or parts of the thyristor modules were damaged or failed during the operational tests. The routine tests have been repeated after the operational tests and no defective components were found. There was no evidence of any component degradation after the operational type tests. The fifteen G HVDC thyristor modules successfully passed the operational type tests. V. SUMMARY A synthetic test circuit was used to verify the design of Three-Gorges Changzhou HVDC thyristor valves. This synthetic test circuit is based on the current injection method. This circuit comprises a conventional six-pulse Back-to-Back test circuit and a voltage oscillating circuit. To correctly stress the test object, the test parameters have to be carefully chosen in each operational test duty. These test parameters should produce stresses equal to or greater than those that would meet in service (taking into account the safety test factors given in IEC67-1). A total of fifteen Three-Gorges Changzhou HVDC thyristor modules have been type tested with this synthetic test circuit for the entire operational test program specified by IEC67-1 and in the Technical Specifications of Three- Gorges Changzhou HVDC Thyristor Valves. The successful type test results showed that the design of Three-Gorges Changzhou HVDC thyristor valves is fully adequate. The tested modules have also shown a substantial margin in the thyristor valve design since, for most of the tests, the test parameters were globally more severe than specified. VI. REFERENCES [1] Z. Xiaoqian, G. Flisberg, et al, Design Features of the Three Gorges Changzhou ±5 HVDC Project, CIGRE paper 14-26, session 2 [2] Task Force of Working Group 14.1, Test Circuits for HVDC Thyristor Valves, CIGRE Technical Brochure 11 [] Thyristor valves for high voltage direct current ( HVDC ) power transmission - Part 1: Electrical testing, IEC 67-1 ( 1998 ) [4] B.L.Sheng, E.Jansson, A.Blomberg, H-O. Bjarme and D.Windmar, A New Synthetic Test Circuit for the Operational Tests of HVDC Thyristor Valves, in Proc. IEEE 16 th APEC 21 conf., pp.42-46 [5] Task Force 1 of Working Group 14.1, Voltage and current stresses on HVDC valves, ELECTRA No.5, July 1989 [6] IEEE Recommended Practice for Determination of Power Losses in High-Voltage Direct-Current (HVDC) Converter Stations, IEEE Std 1158-1991 VII. BIOGRAPHIES Baoliang Sheng was born in Changchun, China in 1961. He obtained his B.Sc degree in 1982 from Xi an Jiaotong University, China, and his Ph.D. in 1995 from Delft University of Technology, the Netherlands, both in electrical engineering. From 1982 to1992 he worked at National High Power Laboratory (XIHARI), China, as a test engineer and research engineer. He worked at KEMA as a research engineer and towards his Ph.D. at Delft University of Technology from 1992 to 1996. He joined the High Power Laboratory of ABB Switchgear AB, Sweden, in May 1996 as a research and development engineer. He was appointed as Company Specialist in the field of High Power Testing of Electrical Power Equipment in January 1999. He joined ABB Power Syste AB in September 2 as a research and development engineer for the electrical design of HVDC and SVC thyristor valves. His special fields of interest include study of transient phenomena in power syste, laboratory reproduction of network switching conditions, synthetic testing of HVAC circuit breakers and HVDC circuit breakers, direct and synthetic operational tests of HVDC thyristor valves and SVC valves, application of thyristor valves in power syste. Hans-Ola Bjarme was born in Stockholm, Sweden in 1949. He obtained his Master degree from Royal Technical University, Sweden in 1976. He was a college lecturer in Stockholm from 1977 to 1982. He joined ASEA in 1982 as a research and development engineer. From 199 to 1995 he had been with STRI (Swedish Transmission Research Institute) as a research scientist and project manager. From 1995 to 1997 he was a development engineer in ABB Power Transmission, Australia. Since 1997 he has been working in ABB Power Syste AB as the manager of Thyristor Valve Electrical Design Department. He is member of IEC working group IEC 22F MT9. Pierre Riffon was born in Montreal, Quebec, Canada on October 18, 1958. He received his B.Sc.A. in electrical engineering from École Polytechnique de Montréal in 198 after which he joined Hydro- Québec's Research Institute (IREQ) as a Test Engineer for the High Power Laboratory. Since 1988, he has been working as a Test Specialist for the Hydro-Québec's Quality Control department and is responsible for type tests on high voltage substation equipment and special project apparatus (static and series compensation, HVDC Converter, etc...). Mr. Riffon has been involved on several HVDC Projects either for Hydro-Quebec and for Hydro-Quebec International as a test specialist (consultant) for several international HVDC projects. Mr. Riffon is a member of the IEEE Transformers Committee on which he is participating to several Subcommittees and Working Groups. He is member of: - HVDC Converter Transformers and Smoothing Reactors Subcommittee; - Dry Type Reactors Working Group; - Switching Transients Induced by Transformer/Breaker Interaction Working Group; - Co-chairman of IEEE Working Group on Test Requirements for Instrument Transformers for Nominal Voltage 115 and above. Mr. Riffon is also the chairman of the Canadian IEC Technical Committee TC17 and Subcommittees SC17A and SC17C, Switchgear and Controlgear. He is also the convener of an IEC WG on High-Voltage alternating current by-pass circuit-breakers and the Task Force leader of an IEC group working on the Guide for Asymmetrical Short-Circuit Breaking Test Duty Ta. He is also a member of IEEE Power Engineering Society and of Ordre des Ingénieurs du Québec. Ma Weimin was born in Wuhan, China in 1966. He obtained his Ph.D. for the study of large power transmission line from Wuhan Institute of Hydraulic and Electric Engineering in 1994. From 1994 to 1996 he worked in Tsinghua University as a postdoctor. After finishing the study work on digital measurement in high voltage engineering field he jointed State Power of China as a senior engineer mainly for the Three Gorges to Changzhou HVDC project and Three Gorges to Guangdong HVDC project technical specification, test supervision and construction. 5