BSCP31 Trading Unit Application for West Burton A&B Power Stations

Similar documents
UK Power Networks Use of System Charging Methodology

Guideline for Parallel Grid Exit Point Connection 28/10/2010

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS

Elia Ancillary Services: Black-Start

Energy from Waste Grid Connections

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM

Clarification of Definitions. Jonathan Sprooten Power System Planning, Elia 24/01/2017

Generation Connections

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

33kV Connection up to 90MVA

Net Consumption (GWh)

Introduction to Charging: Which Parties Pay Which Charges?

Generating unit functional document submission form

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

NATIONAL GRID ELECTRICITY TRANSMISSION plc THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS

Feasibility Study Report

Standards, Procedures and Policies for Grid Connection

GC0096 Storage Grid Code Workgroup. Monday 30 th January 2017

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

The Power Potential Project A guide to participating

SUBSTATION INTERLOCKING SCHEMES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Guidelines for Solar Grid Power Projects

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Street Address. City-Village-Township

3.7 Areas where increasing levels of DER potentially affects operation of the system under Emergency Conditions

RATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015

Distribution Charging Update

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

Interconnection Feasibility Study Report GIP-226-FEAS-R3

APRIL 2011 FINAL RATES

Age-dependent & multi-load reliability analysis in transmission systems

Page 1 of 5. 1 The Code Administrator will provide the paper reference following submission to National Grid.

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Net Metering & Compensation Seminar

Small DER Aggregation Example

Network. ENMAX Power Corporation Network Planning & Design November 4, 2011

Georgia Transmission Corporation Georgia Systems Operations Corporation

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan

Wind Turbine. Commissioning Utilizing Mini-Grid Power. Scottish Renewables Onshore Wind Conference & Exhibition Aggreko

Guidelines for connection of generators:

JSC ELECTRICITY SYSTEM COMMERTIAL OPERATOR ACTIVITY REPORT YEAR 2016

Standard Battery Energy Storage System (BESS) Connection Arrangements

ABB Wind Power Solution

Street Address. City-Village-Township

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

OVERVIEW OF UNIFORM TRANSMISSION RATES

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Interconnection System Impact Study Report Request # GI

Selling PFIFFNER in the UK. Paul Haines

Emerald Reactive Support Alternative Solution Expressions of interest

Clean Energy Transmission Summit. Stephen Beuning Director Market Operations 1/9/13

Co-location Informal Guidance Note. March 2018 Version 1.1

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Feasibility Study Report

Please Refer to Attached Sample Form

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

NOVA SCOTIA UTILITY AND REVIEW BOARD

Balancing and Settlement Code. Code Subsidiary Document. Loss of Load Probability Calculation Statement. Version 1.0. Effective Date: 5 November 2015

Static frequency converter couples US paper mill s 25-Hz and 60-Hz electricity grids

Exemptions currently in force

Potential Transmission Charging Arrangements at Exporting Grid Supply Points (GSPs)

GRID CONSTRAINTS IN THE SOUTH WEST: OPTIONS FOR CONNECTION

GC0023 Protection Fault Clearance Time & Back-Up Protection

New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems

Electric Networks/Ina Lehto Updated Original 12/2011

Non-BM Balancing Services Volumes and Expenditure

100 MW Wind Generation Project

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Overview of State Distributed Generation Interconnection Rules

TABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS...

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

Key DRAFT OPERATING CODE 2 LEGAL TEXT

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw

Draft for an Appendix G Electrical System

Electricity Transmission network charging

REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS. International Competitive Bidding (ICB)

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Building Collaboration Between East African Nations via Transmission Interconnectors

Sub Regional RTEP Committee South

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Transcription:

Attachment 1 BSCP31 Trading Unit Application for West Burton A&B Power Stations Full description of nominated BM Unit(s) (in conjunction with form BSCP31/4.5) West Burton A Power Station comprises: Plant 4 x 500MW coal fired steam generating units, each with an associated 50MVA 22/11kV unit transformer connected to 11kV unit boards within the station and a 600MVA 22/400kV generator transformer connected to transmission at NGET s West Burton 400kV substation busbars. 2 x 20MW gas turbine generators, one connected within the station to the 11kV unit boards for main generating unit 1, the other connected within the station to the 11kV unit board for main generating unit 4. 2 x 50MVA station transformers connected to the 132kV busbars at NGET s 132kV West Burton substation, which is fed via 400/132kV Grid Supply Transformers from the adjacent 400kV substation (see Attachment 2 map and Attachment 3 NGET line diagram). BMUs The net flow to the transmission system for each main generator/unit transformer pair (T_WBUPS 1, T_WBUPS 2, T_WBUPS 3, T_WBUPS 4) and for each gas turbine generator (T_WBUGT 1, WBUGT 4) is represented as a transmission connected BM Unit. The main generator/unit transformer pairs have transmission Connection Entry Capacity (CEC) 503 MW each. The GT generators 1 and 4 have CEC 20 MW each, and share connection with main generators 1 and 4 respectively (see Attachment 4 Extract from West Burton A Connection Agreement). The aggregated metered station demand from the 132kV substation busbars is represented as a single embedded station demand BM Unit (E_WBUPS STX), since it is connected at 132kV. The 7 BMUs at West Burton A are included in existing Class 1 Trading Unit West Burton Power Station V2. This would be de registered if (and only if) the proposed combined West Burton Power Stations A&B Trading Unit becomes effective. Settlement Active Energy Metering & BMU Meter Aggregations The active energy metering equipment is compliant with Code of Practice E in effect at the time of installation (allowing metering on the low voltage side of grid transformers, with compensation to the high Page 1 of 6

voltage transmission boundary). Lifetime meter dispensation D/472 allows use of protection rated current transformers for reactive measurements for generator unit 3, rather than measurement rated current transformers. Settlement active energy meters for each main generator and for its associated unit transformer are located on the low voltage 22kV side of each generator transformer. The auxiliary Gas Turbine connections to the Unit Boards are metered at 11kV. Settlement metering for the gas turbine generator 1 connected to unit board 1 is used to determine its BM Unit metered volume, and is subtracted in aggregation rules from the boundary flow for main generator and unit transformer 1 to give the main generator/unit 1 BM Unit volume. Similarly, settlement metering for the gas turbine generator 4 connected to unit board 4 is subtracted from the boundary flow for the BM Unit representing main generator 4 and unit transformer 4. Ie. T_WBUPS 1 (coal/unit) = Unit 1 transmission boundary flow auxiliary gas turbine 1 flow. T_WBUPS 4 (coal/unit) = Unit 4 transmission boundary flow auxiliary gas turbine 4 flow. Settlement active energy metering for the station load is located on the Low Voltage 11kV side of the station transformers, with compensation to the 132kV high voltage side. West Burton B Power Station comprises: Plant 3 x CCGT Units, each comprising a 388 MVA gas turbine generator with 390 MVA 400/17kV power transformer and a 200 MVA steam turbine generator with 200 MVA 400/15 kv power transformer. The CCGT Units operate at less than the maximum theoretical capacity. All 6 power transformers are connected to EDF Energy s 400kV banking compound busbars within the West Burton power station site, from which two 400kV cables run to NGET s 400kV busbars at NGET s 400kV substation situated at the West Burton site. Units 1 and 3 each have a 22/6.6kV unit transformer connected to respective 6.6kV unit boards within the station. Unit 1 is normally used to provide power to the unit boards for main Unit 2, which does not have its own unit transformer. There are no separate station transformers, and no other connections to the transmission or distribution total system. A +/ 50 MW battery system comprising 10 x 5 MW sub modules is situated within the West Burton B site. Part of the system is connected to the main CCGT unit 1 6.6kV boards, and the remainder to the main CCGT unit 3 6.6kV unit boards within the station. Two of the battery sub modules can switch between the unit 1 and unit 3 boards, with normal configuration giving +/ 20 MW capability through unit 1 and remaining +/ 30 MW capability through unit 3. Page 2 of 6

BM Units The 3 CCGT Modules are each represented as a BM Unit. Each has a transmission Connection Entry Capacity 470 MW (Attachment 5). The battery is operated as a single controllable entity, but an approved non standard BM Unit arrangement (ISG198/02) is in effect until 31 December 2021 to represent it as two BM Units, as requested by NGET due to its connection to transmission via two separate circuits. Its combined transmission CEC is 50 MW. Its two separate settlement metered connections within the station are each represented as a BM Unit (T_WBURB 41 and T_WBURB 43). EDF Energy will consider how best to address the ongoing battery BM Unit configuration before the current permission for a non standard configuration expires (31Dec2021). The Trading Unit composition will be revisited at that time if appropriate, for example if the current battery BM Units were to be consolidated or sub divided. The 3 CCGT Module BMUs at West Burton B are included in existing Class 1 Trading Unit West Burton B CCGT. This would be de registered if (and only if) the proposed combined West Burton Power Stations A&B Trading Unit becomes effective. Settlement Metering & BMU Meter Aggregations CoP1 settlement meters are situated on the high voltage side of the six generator transformers connected to EDF Energy s 400kV banking compound busbars, in accordance with CoP1 at the time of construction. The 400kV banking compound busbars are connected by two 400kV cable circuits to NGET s 400kV substation busbars. CoP1 meters are located on the two 6.6kV circuits within the site connecting the two sides of the battery system to the main CCGT unit 1 and unit 3 boards. Lifetime meter dispensation D/478 permits battery meters at lower voltage within the site, with compensation to the HV side of the 400kV transformers. CCGT module 1 and 3 BM Unit (T_WBURB 1 and T_WBURB 3) aggregation rules subtract the relevant battery BM Unit meter readings from the boundary metering to represent the relevant CCGT module. CCGT module 2 BM Unit (T_WBURB 2) is not connected to the low voltage system within the site, and is aggregated from its 400kV boundary meters alone. Ie. T_WBURB 1 (CCGT) = unit 1 boundary flow battery unit 41 flow T_WBURB 3 (CCGT) = unit 3 boundary flow battery unit 43 flow Confirmation from each Lead Party of their intention to be associated with a single Trading Unit The applicant, EDF Energy (Thermal Generation) Ltd, is the registrant for all the BM Units. Confirmation of its agreement for the Trading Unit is attached (attachment 6). Page 3 of 6

Full description of Metering Systems See the description of metering given within Full description of nominated BM Unit(s) above. BSCP20 registration forms have not been included, but can be provided on request. Full description of points of measurement of electrical flow See the description of metering given earlier within Full description of nominated BM Unit(s). Line diagrams showing electrical connections and energy flows at nominated BM Unit(s) Attachment 7 is a simple line diagram showing the plant, electrical connections, BM Units, settlement metering locations and typical flow directions at the West Burton Power Stations. The actual flows vary according to which items of plant are operating. Line diagrams showing location of Metering Systems Attachment 7 is a simple line diagram showing the plant, electrical connections, BM Units, settlement metering locations and typical flow directions at the West Burton Power Stations. Evidence that assets & equipment are capable of transmitting or distributing the quantity of Electricity to be transmitted or distributed at the nominated BM Unit(s) See extracts from NGET Bilateral Connection Agreements, attachments 4 (WBA) and 5 (WBB). Confirmation from the Transmission Company that the metering arrangements are compatible To be confirmed. Supporting evidence from associated BSC Parties (as appropriate) All the BM Units are registered to EDF Energy (Thermal Generation) Ltd. The only other directly associated BSC Parties are National Grid, and Western Power Distribution (WPD) who have separate distribution feeds from the 132kV substation. WPD take power from the 132kV busbar at the National Grid substation, from which West Burton A station demand is also taken (and may be used as part of a difference metering arrangement for the East Midlands _B GSP Group). This is not directly relevant to the Trading Unit status of the West Burton BM Units. Class 2 only Evidence of Dedicated Assets Not applicable. Page 4 of 6

Class 3 only Evidence of Contiguous Assets Not applicable. Class 6 only Other evidence having regard to the criteria set out in BSC The arrangement is equivalent to a Class 1(B) Trading Unit as in the BSCP31 line diagram (pasted below) in all respects except that there are two power stations and the auxiliary generating units at West Burton A and the battery BM Units at West Burton B are connected to the respective unit/station boards. This is a normal configuration at many existing large power station Trading Units. We think the arrangement should be a Class 1 Trading Unit, but it could be a Class 6 Trading Unit if the line diagram arrangement (attachment 7) is considered materially different from that in the BSCP31 line diagram (pasted below). Page 5 of 6

Attachments 1 This document, supporting evidence for BSCP31 Trading Unit Application for West Burton A&B Power Stations 2 Map of West Burton site showing National Grid assets. 3 NGET West Burton Substation Assets Diagram (from West Burton B Connection Agreement) 4 Extract from West Burton A NGET Connection Agreements showing entry capacities. 5 Extract from West Burton B NGET Connection Agreement showing entry capacities. 6 EDF Energy (Thermal Generation) Ltd director s confirmation of Trading Unit application. 7 Simple Line diagram showing the plant, electrical connections, BM Units, settlement metering locations and typical flow directions at the West Burton Power Stations. Page 6 of 6