TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

Similar documents
SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

UK Power Networks Use of System Charging Methodology

Southern Electric Power Distribution plc. Metering and Data Services Statement. Effective from 1st April Version 1.0

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Key DRAFT OPERATING CODE 2 LEGAL TEXT

Networks. Charges for Connection to the Distribution System Revision 10 Status: Approved. Commercial and Customer Asset Management ESB Networks

STATEMENT OF CHARGES. For Use of. Northern Ireland Electricity Ltd. Transmission System. Applicable from 1 st October 2013

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

Introduction to Charging: Which Parties Pay Which Charges?

NATIONAL GRID ELECTRICITY TRANSMISSION plc THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS

Consolidated Edison Company of New York, Inc.

Guideline for Parallel Grid Exit Point Connection 28/10/2010

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

RSPO PalmTrace - Book and Claim Terms and Conditions

Electricity Transmission network charging

CMP294: National Grid Legal Separation changes to CUSC Section 14. CUSC Modification Proposal Form

Submission on the Wellington Town Belt Bill. Local Government and Environment Select Committee Parliament Buildings Wellington

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

JEA Distributed Generation Policy Effective April 1, 2018

RATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015

INDUSTRIAL HAUL AGREEMENT

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

Research RES LEGAL Grid issues Country: Hungary

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

TRANSMISSION DEVELOPMENT PLAN

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

TERMS AND CONDITIONS

Model Standing Offer for Micro Embedded Generator Basic Connection Services

Large Embedded Generation User Guide A

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

This Distribution Charter explains how PLS distributes collective licensing

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B;

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State

OVERVIEW OF UNIFORM TRANSMISSION RATES

STATUTORY INSTRUMENTS. S.I. No. 160 of 2017

Charging Statement. Charges effective from 1st April / 17

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing.

TUoS Statement of Charges

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE

Merger of the generator interconnection processes of Valley Electric and the ISO;

Good Practices for Grid Connection: European Wind Industry perspective. Iván Pineda EWEA Research Officer Grids and Internal Electricity Market

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

TERMS AND CONDITIONS OF PARKING AT PALMERSTON NORTH AIRPORT

Draft Guidance for generators: Co-location of electricity storage facilities with renewable generation supported under the Renewables Obligation or

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

ANNEX MOTOR VEHICLES AND MOTOR VEHICLES' PARTS. Article 1. General Provisions

APRIL 2011 FINAL RATES

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

Toll Bye-Laws for the

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Addressing ambiguity in how electricity industry legislation applies to secondary networks

University of Alberta

GENERAL TERMS AND CONDITIONS OF EINDHOVEN AIRPORT PARKING FACILITIES Ryanair

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Importing Toyota vehicles into the United Kingdom

Parking Control Bylaw 2014

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Indigo Pipelines Limited. Connection Charges For Individual Domestic Properties

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Derivative Valuation and GASB 53 Compliance Report For the Period Ending September 30, 2015

Explanatory Notes to aid completion of Disclosure Document Template

GC108: EU Code: Emergency & Restoration: Black start testing requirement

Umatilla Electric Cooperative Net Metering Rules

best to you all Gail Carbiener Page 1 of 5

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY

Wholesale Developer Services Charges

City of Palo Alto (ID # 6416) City Council Staff Report

Official Journal of the European Union. (Non-legislative acts) REGULATIONS

Every Disclosure Document issued by a Franchisor Member pursuant to the Code shall comply with the following requirements: -

Official Journal of the European Communities

Decision on ESB Networks Electric Vehicle Pilot

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A

Dublin Airport Chauffeur Code of Conduct Dublin Airport Chauffeurs Code of Conduct. Dublin Airport Parking

Number 10 of 2012 MOTOR VEHICLE (DUTIES AND LICENCES) ACT 2012 ARRANGEMENT OF SECTIONS. 3. Amendment of Part I of Schedule to Act of 1952.

Application to Amend Net Metering Service under RS Appendix B. Revised RS 1289 Clean and Black-lined

THE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Risk Management of Rail Vehicle Axle Bearings

Application of claw-back

Guidance for generators: Co-location of electricity storage facilities with renewable generation supported under the Renewables Obligation or Feed-in

PEAK LOAD CAPACITY AGREEMENT XXXX/2017. Customer Oy. and. Finextra Oy

Number 22 of 2001 MOTOR VEHICLE (DUTIES AND LICENCES) ACT, ARRANGEMENT OF SECTIONS. Section 1. Interpretation.

CHAPTER 2 HOW TO APPLY FOR ELECTRICITY

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

SSE Guide to the Energy Industry. Guide

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

TRANSPORT ACT 1985 APPLICATION FOR A SECTION 19 SMALL BUS (MINIBUS) PERMIT (9 to 16 passenger seats)

ECOMP.3.A EUROPEAN UNION. Brussels, 12 December 2018 (OR. en) 2018/0220 (COD) PE-CONS 67/18 ENT 229 MI 914 ENV 837 AGRI 596 PREP-BXT 58 CODEC 2164

Distribution Charging Update

RENEWABLES INTEGRATION STATUS REPORT

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company

Generation Connections Industry Workshop 2017

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO WESTERN POWER DISTRIBUTION (SOUTH WEST) PLC S ELECTRICITY DISTRIBUTION SYSTEM

SYNOPSIS OF PROPOSED GEORGIA DEPARTMENT OF PUBLIC SAFETY RULES CHAPTER TRANSPORTATION NETWORK COMPANIES AND TAXI SERVICES

Transcription:

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008

TABLE OF CONTENTS Page 1 Introduction... 2 2 Charging Methodology Objectives... 4 3 Connection Charging Methodology... 5 4 Connection Assets... 7 5 Least Cost Technically Acceptable Connection Design... 8 6 Cost Allocation Rules for Shared Assets... 9 7 Application Fees... 10 8 Bonds and Credit Cover... 11 9 Disconnection, de-energisation and decommissioning charges... 13 10 Contact details... 14 11 Definitions...15 Appendix A - System Asset / Connection Asset Boundary Illustrations... 17

1 INTRODUCTION 1.1 EirGrid plc. ( EirGrid ) is a State owned company and is the Transmission System Operator for the Republic of Ireland. EirGrid is authorised to operate the Transmission System to transmit electricity in the State by means of a licence issued by The Commission for Energy Regulation (the CER ), under Section 14(1)(e) of the Electricity Regulation Act, 1999 (hereinafter referred to as the Act ), as inserted by Regulation 32 of the European Communities (Internal Market in Electricity) Regulations 2000 (hereinafter referred to as SI 445 of 2000 ) and subject to conditions set out in the licence. 1.2 Under its Transmission System Operator Licence EirGrid is responsible for operating the Transmission System in the Republic of Ireland, a system consisting of some 6,200 circuit kilometres of 110kV, 220kV and 400kV overhead line and underground cable with a maximum demand of about 5,200MW. 1.3 EirGrid is the only party entitled to offer terms to enter into a Connection Agreement (or to amend an existing Connection Agreement) for connection (or modification of an existing connection) to the Transmission System at entry or exit points on the in the Republic of Ireland for access to the All Island Transmission Networks. Such terms are offered following receipt by EirGrid of an application containing all such information as EirGrid may reasonably require for the purpose of formulating the terms of the offer. 1.4 In accordance with Condition 5 of its licence, EirGrid, in co-operation with the Northern Ireland System Operator, has prepared and obtained the CER s approval for a statement setting out the basis upon which charges will be made for connection to the Transmission System and this statement is published to meet that obligation. 1.5 This statement includes: 1.5.1 a schedule listing those items (including the carrying out of works and the provision and installation of electric lines or electrical plant or meters) of significant cost liable to be required for the purpose of connection to the Transmission System for which connection charges may be made or levied and including (where practicable) indicative charges for each such item and (in other cases) an explanation of the methods by which and the principles on which such charges will be calculated; 1.5.2 the methods by which and the principles on which any charges will be made in respect of extension or reinforcement of the Transmission System and as applicable All-Island Transmission Networks rendered necessary or appropriate by virtue of providing such connection to the Transmission System; 1.5.3 the methods by which and the principles on which connection charges will be made in circumstances where the electric lines or electrical plant to be installed are of greater size or capacity than that required for use of system by the party seeking connection; 1.5.4 the methods by which and the principles on which any charges (including any capitalised charge) will be made for maintenance and repair required of electric lines, electrical plant or meters provided and installed for making a connection to the Transmission System; 1.5.5 the methods by which and the principles on which any charges will be made for the provision of special metering or telemetry or data processing equipment by Page 2

EirGrid for the purposes of enabling any party which is bound to comply with the Grid Code to comply with its obligations in respect of metering thereunder, or for the performance by EirGrid of any service in relation thereto; 1.5.6 the methods by which and principles on which any charges will be made for disconnection from the Transmission System and the removal of electrical plant, electric lines and ancillary matters following disconnection; and 1.5.7 such other matters as shall be specified in directions issued by the CER from time to time. 1.6 This statement is reviewed, in co-operation with the Northern Ireland System Operator, at least once in every year in order that the information set out shall continue to be accurate in all material respects. 1.7 Any revisions will be made with the approval of the CER. 1.8 A copy of this statement can be obtained from EirGrid s website at www.eirgrid.com. 1.9 Details on the processes to be followed in applying for a connection to the Transmission System can also be found at this website. 1.10 Expressions used in this statement have the definitions given to them in the EirGrid Connection Agreement unless otherwise defined herein and shall be construed accordingly. Terms which are capitalised and in bold type are defined in section 11 of this document. 1.11 Parties being connected to the system will be required to enter into a Connection Agreement with EirGrid setting down the terms and conditions which will apply in providing a connection. In the event of any inconsistency with this statement and the Connection Agreement, the Connection Agreement will take precedence. 1.12 Where the party seeking a connection to the Transmission System is not satisfied with the terms offered and agreement with EirGrid cannot be reached within a reasonable time, either party may request a determination of any of the terms and conditions of connection by the CER. Page 3

2 CHARGING METHODOLOGY OBJECTIVES 2.1 The connection charging methodology is designed to ensure: 2.1.1 the recovery of the appropriate proportion of the costs directly or indirectly incurred (or to be incurred) in carrying out the works, extension or reinforcement in question and in providing, installing, maintaining and repairing (and, following disconnection, removing) the electrical lines, electrical plant, meters, special metering, telemetry, data processing equipment or other items in question; 2.1.2 the methodology promotes efficient use of the transmission system by ensuring that charges are cost reflective and that possible anomalies are minimised; 2.1.3 the recovery of a reasonable rate of return on the capital represented by such costs; 2.1.4 that charges and allocation methods are based on clear and transparent rules that avoid arbitrariness and limit administrative overheads: and 2.1.5 that EirGrid does not unduly discriminate between any parties or class or classes of parties. Page 4

3 CONNECTION CHARGING METHODOLOGY 3.1 In order to calculate connection charges, EirGrid categorises assets as either Connection Assets or System Assets. 3.2 In connecting to the Transmission System a new User s connection offer may be to connect to either Connection Assets or to System Assets, and the connection charge payable will vary in each circumstance. 3.3 Any party wishing to enter into a Connection Agreement (or to amend an existing Connection Agreement) for connection (or modification of an existing connection) at entry or exit points on the Transmission System will be required to pay for: 3.3.1 the estimated cost of new Connection Assets; 3.3.2 a proportion of the estimated cost of any new Connection Assets which are to be shared with others who are connecting simultaneously, if any; 3.3.3 a proportion of the cost of any existing Connection Assets to be shared with other Users who are already connected, if any; 3.3.4 the estimated cost of decommissioning transmission assets resulting from the new or modified connection, if any; and 3.3.5 certain pass-through costs which will be set out in the offer of connection. For example, any environmental planning costs, any costs incurred in acquiring planning consents, any costs incurred in complying with any conditions of planning consents, any external legal costs, any costs incurred in seeking, obtaining and paying for wayleaves or easements and certain costs relating to land conditions and civil works. 3.4 As part of the connection offer, EirGrid will provide the estimated connection charge, identifying the costs of the main items of expenditure in the Offer Letter. The Applicant will pay this amount irrespective of the outturn cost, subject to any price adjustment mechanism(s), referred to in section 3.3.5 above, specifically set out in the Offer Letter. 3.5 Connection Charges will contain elements covering engineering costs and in some circumstances a reasonable rate of return on the capital involved as appropriate. 3.6 For connection offers where the connection works are completed over a significant period of time after the acceptance of the connection offer, the connection charge may be adjusted in line with the Consumer Price Index or in line with another appropriate index, such as a London Metal Exchange price index. Any price adjustment mechanism will be set out in the Offer Letter. 3.7 The work to be done and the connection charge payable will inevitably depend on the requirements of the party seeking the connection and on the planning and security standards applicable and on any other relevant matters. 3.8 Where an Applicant wishes to connect to a part of the Transmission System that is planned to be constructed, as set out in the Forecast Statement, and the Applicant s connection requires that those works must be advanced or altered, the Applicant will be liable to pay for any incremental costs incurred by deviating from the original plan, whether for Connection Assets or System Assets, including any advancement costs. Page 5

3.9 Charges for connection will include an element to provide for the operation and maintenance costs of the connection, known as the Ongoing Service Charge. The Ongoing Services Charge shall be advised to the User prior to energisation, is payable annually and is subject to appropriate indexation or adjustment. 3.10 The connection charge is normally payable in full in advance of energising the connection. Where a connection is to be commissioned or constructed in phases, payments will be reflective of those phases or key milestones, with full payment details set out in the Offer Letter. 3.11 Where the User is a load User, the charges payable shall be in accordance with approved CER policy which is 50% of the applicable charges subject to section 5.4. Page 6

4 CONNECTION ASSETS 4.1 Connection Assets are: 4.1.1 those assets, which are installed to enable the transfer of the Maximum Export Capacity (MEC) or the Maximum Import Capacity (MIC) of the User s facility, to or from, as appropriate, the Transmission System for the term of the Connection Agreement in accordance with the Grid Code and Transmission and Distribution System Security and Planning Standards, subject to subparagraph 4.2; and 4.1.2 those assets which are installed as a result of the User s effect on fault current levels on the transmission system at the transmission node to which the User connects, but does not include any assets installed at any location other than the transmission node to which the User connects. 4.2 In deciding which assets are required to enable the transfers referred to in subparagraph 4.1.1, power flows other than those to or from the User are disregarded. 4.3 Assets which are not Connection Assets are System Assets and the costs of these assets are recovered through use of system charges. 4.4 Connection Assets may include, as appropriate: 4.4.1 the circuit(s), or those parts of the circuit(s), required to connect the User to the existing Transmission System; 4.4.2 in addition to assets required under sub-paragraph 4.4.1, any new circuit(s) or enhanced circuit(s) required pursuant to sub-paragraph 4.1.1; 4.4.3 the circuit bay(s) required by the User; 4.4.4 an appropriate proportion of common plant (busbars, land, buildings, protection and other common services) associated with the connection, which may or may not provide benefits to another user and, for the avoidance of doubt, this also includes an appropriate proportion of a system station; 4.4.5 any upgraded existing protection or communication equipment required as a direct result of the connection but not changes or additions to protection systems at remote substations (including the provision of communication channels); and 4.4.6 metering, telemetry or data processing equipment supplied by EirGrid. 4.5 Figures 1 through 10 in Appendix A illustrates Connection Asset / System Asset boundaries under a number of circumstances. Page 7

5 LEAST COST TECHNICALLY ACCEPTABLE CONNECTION DESIGN 5.1 EirGrid s design objective is to make connection offers on the basis of the Least Cost Technically Acceptable or LCTA design. The Least Cost Technically Acceptable connection is the connection which: 5.1.1 complies with the Transmission and Distribution System Security and Planning Standards; and 5.1.2 complies with any other applicable standard, regulation and code; and 5.1.3 takes into account committed developments on the Transmission System including retrials from the system; and 5.1.4 is the least overall cost; 5.2 It is likely that EirGrid will evaluate a number of design options before deciding on the preferred design for a new or modified connection to the Transmission System. In doing so, there may be occasions where the preferred design is not the LCTA connection. 5.3 Where EirGrid does not proceed with the LCTA connection, whether new or modified, to accommodate a User or a group of Users then that User will only be required to pay for the estimated cost of the LCTA connection. 5.4 Where an Applicant requests a connection offer on the basis of a design which is more expensive than the LCTA connection then the Applicant will be required to pay the estimated cost of providing both the Connection Assets and additional System Assets, if any, required by the Applicant s preference. Page 8

6 COST ALLOCATION RULES FOR SHARED ASSETS 6.1 Where a new User connects to the Transmission System by making use of existing Connection Assets which have been funded by an existing User, the new User will be charged a proportion of the value of equivalent new Connection Assets shared with the existing User. 6.2 If the existing User connected within the preceding ten years then the existing User will be entitled to receive a partial rebate of the original connection charge from EirGrid, calculated in accordance with sub-paragraph 6.3. 6.3 The rebate will take into account: 6.3.1 the original cost of the assets; 6.3.2 depreciation; 6.3.3 annual indexation of the cost of the assets at CPI; 6.3.4 the per MW share of the utilisation of the shared assets; and 6.3.5 the connection charge received from the new User 6.4 In addition to the charges for use of the shared Connection Assets the new User will be required to make a payment to EirGrid in respect of reasonable administrative expenses. 6.5 Where a number of Users connect simultaneously and jointly make use of Connection Assets each User will be charged a proportion of the estimated cost of the shared Connection Assets, calculated on a per MW share of the utilisation of the shared Connection Assets. Page 9

7 APPLICATION FEES 7.1 An Applicant seeking a connection offer will be required to pay a fee to enable EirGrid to recover the costs of producing the connection offer. The fee is published as Tariff Schedule COP1 in the EirGrid Statement of Charges published on the EirGrid website 1. 1 http://www.eirgrid.com/eirgridportal/desktopdefault.aspx?tabid=use%20of%20system&treelinkmodid=1445&tree LinkItemID=48 Page 10

8 BONDS AND CREDIT COVER 8.1 An Applicant seeking to connect to the Transmission System must provide security in the form of a number of bonds which are designed to protect other Users of the system. Detailed requirements are set out in sub-paragraphs 8.2-8.4. 8.2 Connection Charges Bond 8.2.1 A User must post a Connection Charges Bond by the Consents Issue Date. This bond will cover any costs incurred during construction of the connection which are not covered under the payments made by the User. The bond will be drawn down should the User decide not to proceed to completion. The Connection Charges Bond is released upon completion of the connection and final charge payment. 8.3 Maximum Export Capacity Bond and Maximum Import Capacity Bond 8.3.1 Because of limited capacity on the Transmission System, capacity bonds are required of Applicants to ensure that Applicants seek only an offer solely based their MIC or MEC requirement and that the Applicant is not seeking to hoard capacity or to reserve additional capacity for later development of their facilities. 8.3.2 A generation User will require an MEC Capacity Bond and a load User will require an MIC Capacity Bond. 8.3.3 Once the generator has demonstrated to the satisfaction of EirGrid that it has passed the Capacity Test then the capacity bond is returned. However if the generator has not passed the Capacity Test by the date specified in the Connection Agreement then EirGrid is entitled to draw down on the MEC Capacity Bond. 8.3.4 The value of the MEC Capacity Bond is determined in accordance with formulae set out in the General Conditions of the Connection Agreement. 8.3.5 EirGrid shall be entitled to draw down under the MIC Capacity Bond under the terms of the Connection Agreement including where the User terminates the Connection Agreement and/or fails to pay for the appropriate loss in TUoS revenue. 8.3.6 A load User s MIC Capacity Bond is determined in accordance with formulae set out in the General Conditions of the Connection Agreement. The User is required to maintain an MIC Capacity Bond for two years. 8.3.7 EirGrid shall be entitled to draw down under the MEC Capacity Bond under the terms of the Connection Agreement including where the User terminates the Connection Agreement and/or fails to meet the Capacity Test and/or fails to submit a Capacity Certificate. 8.4 Decommissioning and Reinstatement Bond 8.4.1 A User must maintain a Decommissioning and Reinstatement Bond for the duration of their Connection Agreement to cover potential costs arising out of the decommissioning of Connection Assets and reinstatement. 8.4.2 The Decommissioning and Reinstatement Bond is released in the event that the Page 11

assets are not decommissioned. Where the assets are to be decommissioned, the Decommissioning and Reinstatement Bond is released when the Decommissioning and Reinstatement Charge noted in s. 9.2 has been paid by the User. Page 12

9 DISCONNECTION, DE-ENERGISATION AND DECOMMISSIONING CHARGES 9.1 Where a User wishes a connection to be de-energised, EirGrid will arrange to deenergise the connection. No charge will be made for this service if carried out during normal working hours and following reasonable notice except, as provided by agreement. 9.2 On termination of the Connection Agreement the User shall be liable for the estimated cost of decommissioning the Connection Assets, removing the Connection Assets from the connection site and making good the condition of the connection site. 9.3 In the event that the assets are not decommissioned or the site is not reinstated no decommissioning or reinstatement charges, as appropriate, will be payable by the User. Page 13

10 CONTACT DETAILS 10.1 Should you require any further details about the information contained in this document or if you have any comments on how this document might be improved please contact our charging representative at the address below. 10.2 As stated previously in the document, additional information on the connection process can be obtained at EirGrid s website www.eirgrid.com. Contact details: Customer Relations EirGrid plc. 27 Lower Fitzwilliam Street Dublin 2 Tel: +353 1 702 6642 Fax: +353 1 702 6040 email: info@eirgrid.com Page 14

11 DEFINITIONS All-Island Transmission Networks Applicant means the Transmission System and the NI Transmission System taken together; means a party, or group of parties as appropriate, who has applied for an offer of terms to enter into an agreement with EirGrid in respect of connection to the Transmission System at entry or exit points on the transmission system but has not yet signed that agreement; Connection Assets as defined in sub-paragraph 4.1; Consents means any one or more, as the context requires, of planning and other statutory consents, wayleaves, easements, or other interests in, or rights over, land, or any other consents, approvals, route approvals or permissions of any kind required for the purposes of the Connection Agreement (including a Users's generation authorisation or licensing arrangements but excluding fuel supply consents, if applicable) granted or issued without any appeals period, unacceptable conditions, judicial review or other legal proceedings pending; Consents Issue Date means the date on which both EirGrid and the User have obtained the Consents relating to the works for the Connection Assets and the User s facility and which they are obliged to use prudent and commercial endeavours to obtain; Forecast Statement means the statement of that name prepared in accordance with Section 38 of the Electricity Regulation Act, 1999; Grid Code means the code of that name drawn up in accordance with Section 33 of the Electricity Regulation Act, 1999; Least Cost Technically as defined in sub-paragraph 5.1; Acceptable or LCTA Northern Ireland Transmission System Operator or NI TSO Northern Ireland Transmission System or NI Transmission System means the Transmission System Operator for Northern Ireland as authorised by means of a licence issued by The Department of Enterprise, Trade and Investment, under Article 10(1)(b) of the Electricity (Northern Ireland) Order 1992; means the system of electric lines operated by the NI TSO and comprising high voltage lines and electrical plant and meters used for conveying electricity from a generating station to a substation, from one generating station to another, and from one substation to another within Northern Ireland; System Assets as defined in sub-paragraph 4.3; Transmission and Distribution System Security and Planning Standards Transmission System means the standards referred to in Condition 16 of EirGrid s Transmission System Operator Licence or until such a document is approved by the CER, this shall mean the Transmission Planning Criteria as defined in the Grid Code; means the ESB Transmission System as defined in the Connection Agreement; Page 15

Transmission System Operator Licence User A licence issued by The Commission for Energy Regulation (the CER ), under Section 14(1)(e) of the Electricity Regulation Act, 1999 (hereinafter referred to as the Act ), as inserted by Regulation 32 of the European Communities (Internal Market in Electricity) Regulations 2000 (hereinafter referred to as SI 445 of 2000 ); means a party, or a group of parties as appropriate, who has entered into an agreement with EirGrid in respect of connection to the Transmission System at entry or exit points on the transmission system. Page 16

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 APPENDIX A - SYSTEM ASSET / CONNECTION ASSET BOUNDARY ILLUSTRATIONS Figure 1 Looped Connection Station Existing circuits are sufficient to carry generator output User pays the cost of all assets noted in red including the cost of line removal ~ Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed Page 17

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 2 Looped Station with enhanced connection circuit(s) Both of the existing circuits require enhancement to carry the generator output User pays the cost of assets noted in red including enhanced circuits in red/black and the cost of line removal Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ Page 18

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 A third circuit is needed in addition to the existing circuits to carry the output of the generator User pays the cost of assets noted in red including the additional circuit and the cost of line removal Figure 3 Looped Station with an additional connection circuit Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ Page 19

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 4 Looped Station with an additional connection circuit and enhanced connection circuits In addition to a third circuit, both of ~ the existing circuits requires enhancement to carry the generator output User pays the cost of assets Customer s Equipment noted in red including enhanced Connection Assets circuits in red/black and the cost Enhanced Circuits of line removal Existing System Assets New System Assets Removed Page 20

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Existing circuits are sufficient to carry the generator output A third circuit is added as part of system reinforcements related to the User connecting to the system The User pays the cost of assets noted in red and the cost of line removal only The User is rebated for use of the connection assets by the system based on an appropriate share of the shared assets noted in light green (e.g. 2 4 bays x shared cost). Figure 5 Looped Station with an additional system circuit Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ Page 21

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 6 Existing Looped Station with an additional system circuit Existing connection station, where ~ the existing circuits were sufficient to carry generator output at the time of connection A third circuit is added as part of Customer s Equipment an unrelated system Connection Assets reinforcement Enhanced Circuits The User is rebated based on a Existing System Assets per bay share of the shared New System Assets assets noted in green at the CPI Removed indexed original cost of the assets less depreciation (e.g. 2 4 bays x [indexed cost depreciation]). Page 22

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 6 New Looped Station with 2 Users connecting simultaneously Existing circuits are sufficient to carry the output of both generators A B Each pays for their own ~ ~ connection bay and line to their HV Trafo bushing Each pays their per MW of MEC share of the cost of the Loop Customer s Equipment Station and the cost of line Connection Assets removal the Shared Assets in Enhanced Circuits light green. For example: if A is Existing System Assets 50 MW and B is 25 MW then A pays 50 75 x shared cost and B New System Assets pays 25 75 x shared cost Removed Page 23

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 7 Tail Fed Station from a new Looped Station Existing circuits are sufficient to carry the output of the 2nd generator and the 1st generator Each pays the cost of a connection bay and line to their HV Trafo bushing 2nd generator pays the cost of a Tail Station Each pays their per MW of MEC share of the cost of the Loop Station and the cost of line removal the Shared Assets in light green. For Example: if A is 50 MW and B is 25 MW then A pays 50 75 x shared cost and B pays 25 75 x shared cost Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed A ~ ~ B Page 24

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 8 Tail Fed Station from existing shared Looped Station Existing circuits were sufficient for the output of the two original generators; A, 50MW and B, 25MW. A ~ B ~ For a third user; C, 75MW, a 3rd line into the station is required to carry the generator s output User C pays for connection assts noted in light blue (bay, line to their HV Trafo bushing and 3rd line). User C pays their per MW of MEC share of the Shared Assets in light green as though these were new assts. For example 75 150 x shared as new. Users A and B are rebated based on ther per MW of MEC share of the CPI indexed original cost of the shared assets less depreciation. For example 25 150 and 50 150 x [indexed shared cost depreciation]. Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ C Page 25

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 Figure 9 Deviation from LCTA by the TSO LCTA is a Tail Fed Station from an existing station For system reasons the TSO prefers to connect the User using a loop station at a different point The User pays based on the cost of the LCTA connection noted in yellow Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ LCTA Page 26

EirGrid Transmission Connection Charging Methodology Statement 14 th March2008 LCTA to connect the user is a looped station and a third circuit, instead of enhancements to existing circuits which were more expensive. The User elects to proceed with enhancements to existing circuits as they believe the new circuit will be extremely difficult to obtain planning consents User pays the cost of the option selected over the LCTA: A new looped station, line removal costs, and the cost of the circuit enhancements the assets noted in red and red/black but not the third line highlighted in yellow Figure 10 Deviation from LCTA by the User Customer s Equipment Connection Assets Enhanced Circuits Existing System Assets New System Assets Removed ~ Page 27