Double earth fault in a PSP during back to back launching sequence

Similar documents
ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

34 th Hands-On Relay School

Large Air Cooled Generator Failure

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

Excitation systems for high power synchronous generators with redundant configurations

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

2015 WDC Disturbance and Protection Standards Overview

Unit Protection System for Pumped-Storage Power Stations

Short Term Course On Hydropower Development Engineering (Electrical) for Teachers of Polytechnics in Uttarakhand L33-2

Comprehensive Technical Training

INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)

Electrical Systems - Course 135 COMPOSITE ELECTRICAL PROTECTIVE SCHEMES: PART II

INDEX Section Page Number Remarks

9. Examples of hydro energy conversion

Service and Rehabilitation Electrical Power Systems

ECEg439:-Electrical Machine II

Unified requirements for systems with voltages above 1 kv up to 15 kv

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Washington, DC Area Low Voltage Disturbance

INTER PLANT STANDARD STEEL INDUSTRY SPECIFICATION FOR STATIC EXCITATION CONVERTORS FOR SYNCHRONOUS MOTORS (FIRST REVISION)

Sulzer Dowding & Mills

GE Energy. Variable Frequency Transformers Grid Inter-tie

DESIGN CONSIDERATIONS FOR APPLICATION OF SHUNT CAPACITORS IN HEAVY HATER PLANT (TUTICORIN)

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

INTER PLANT STANDARD - STEEL INDUSTRY THYRISTOR CONVERTORS FOR ARMATURE AND FIELD OF MAIN DRIVE MOTORS. Corresponding IS does not exist

9.1.4 Troubleshooting of Faults in LCD Screen

The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions

Turbogenerators. With Top Performance for Steam and Gas Applications. Specifically tailored 4-pole Synchronous Turbogenerators

Inspection Testing Repair

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

CAST RESIN TRANSFORMERS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco

Centro América Application of EMI Diagnostics to Diesel Generators

Power Systems Trainer

HVDC. TMT&D provides the best and most economical HVDC system.

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

INSTALLATION MANUAL. Instructions, precautions, suggestions for installing and servicing resin transformers in full compliance with safety rules

CHAPTER 3 CAUSES AND EFFECTS OF ELECTRICAL FAULTS

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

MAGNETIC MOTOR STARTERS

Excitation system is of Static Silicon Excitation System, including excitation transformer, thyristors, and AVR.

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

INDUCTION MOTOR. There is no physical electrical connection to the secondary winding, its current is induced

Generator. Jason S DiSanto. 6B Users Conference San Antonio, TX June 19-22, 2017

Christian Ohler, ABB Switzerland Corporate Research Physics of Electric Power Systems. ABB Group August 1, 2012 Slide 1

REVELSTOKE - 1 YEAR DOWN. Applied to Equipment Instruction Number R Class-Group Generate Date: 11 March 2004

Lecture 20: Stator Control - Stator Voltage and Frequency Control

Configuration of a generator

Hydro Generators Poles

Standards, Procedures and Policies for Grid Connection

Safe, fast HV circuit breaker testing with DualGround technology

SERVICE SHOP NOTES. Use ohmmeter to check the resistance between the leads.

Electrical Theory. Generator Theory. PJM State & Member Training Dept. PJM /22/2018

B-03 ELECTRICIAN TRAINING SKILL DEVELOPMENT GUIDE

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Guidelines for connection of generators:

Innovators in Protection Technology Moulded Case Circuit Breaker Instruction Manual

AC MOTOR TYPES. DESCRIBE how torque is produced in a single-phase AC motor. EXPLAIN why an AC synchronous motor does not have starting torque.

World s Largest Air-cooled Turbogenerator in operation

Protection of Power Electronic Multi Converter Systems in AC and DC Applications

Evaluation of a Gearbox s High-Temperature Trip

SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS.

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

Motor Protection. Voltage Unbalance & Single-Phasing

Historical Development

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

Sub:EE6604/DESIGN OF ELECTRICAL MACHINES Unit V SYNCHRONOUS MACHINES. 2. What are the two type of poles used in salient pole machines?

EE042: Practical Power System Protection for Engineers & Technicians

Grounding Of Standby & Emergency Power Systems

BRUSHLESS EXCITERS FOR TURBINE GENERATORS

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Transformer Protection

Ford Scorpio 95+ Charging System

T5S4P3 Synchronous Condensers Application. Mr. Marco Schenone Mr. Sandro Tuscano Mr. Alessandro Oldrati

Small wonder. Station service voltage transformers for small power requirements

Switchgear Arrangement, Torque Requirements, Insulation Systems & Maintenance Intervals. Mike Schmaderer

R250 A.V.R. Installation and maintenance R250 0V E+ E- VOLT STAB FREQ. & L.A.M. CONFIG. 50Hz. 47.5Hz. 57Hz LAM 1 13% 2 25% OFF LAM OFF 9

VOLUME: IIIC SCHEDULE IIIC/4 11 KV AND 3.3 KV SWITCHGEARS

CHAPTER 1 INTRODUCTION

T-Line Generator Control, Protection and Monitoring

Signal Power Supply Monitoring & Restoration

TURBO GENERATORS BEST QUALITY FOR THERMAL POWER PLANTS

Dual Power. Protection. Protection

Electric Motor Controls BOMA Pre-Quiz

Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.)

FUJI HEAVY INDUSTRIES LTD.

CHAPTER 4 PROTECTION REQUIREMENTS

MCE TM Product Information 5 kv Electric Motor Analyzer

FINITE-ELEMENT ANALYSIS OF ACCIDENTAL ENERGIZING OF AN OFF-LINE TURBOGENERATOR*

An Introduction to Completing a NERC PRC Study

OPERATING AND MAINTENANCE MANUAL. Primary Current Injection Test Set. 750ADM-H mk2

Sectionalizing. Rick Seeling. Pete Malamen. Introduction Philosophy. Three Phase Reclosers High-Side Protection Specific Applications

Make : BHEL / Siemens Type : THDF 115/ Reference Standard : IEC 60034

The Case for Hybrid Generator Grounding

Research and Reviews: Journal of Engineering and Technology

Modular Standardized Electrical and Control Solutions for Fast Track Projects

SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL ELECTRICAL MACHINES

High Voltage Generators. TM21-TG Series. 2-Pole Air Cooled Turbine Generator Up to 80,000 kw (107,000 HP)

Transcription:

Double earth fault in a PSP during back to back launching sequence Jean-Louis DROMMI EDF Hydro Engineering Center, France Pump Storage Scheme, back to back launching Electricité de France Hydro Department operates monitors and maintains a fleet of more than 1000 machines totaling 20 000 MW+ Among these, 5000MW are pump storage schemes commissioned in the 1980s to help balancing nuclear power. In recent years, these units, thanks to their flexibility, are being operated with very high duty and high cycling, some being started 6 times per day. The motor generators being used in these PSP are of synchronous type and are no longer started with direct switching to the grid since this very brutal sequence led to quick rotor ageing. Hence, EDF went for softer launching sequences, either using poney motor, static frequency converter or back to back. The scheme involved in this case study uses back to back launching mode. The PSP is equipped with generators driven by Pelton turbine that are used as driving units and with motor generator connected to a pump turbine which are the driven units. Each of these units is rated 170MVA with stator voltage being 15.5kV. The back to back launching sequence includes the following steps: - Both stator windings of driving and driven units are connected together through an IPB and breaker - Both field windings are energized - The driving unit is then ramped up to speed with its turbine - The driven unit rotor follows the same speed ramp up - The driven unit is synchronized to the grid (speed controlled by driving unit and voltage controlled by its AVR) - The driven unit beaker is closed to grid - The driving unit is disconnected from driven unit Insulation failures during launching sequence During back to back sequence, the protection scheme has to be elaborated so as to protect both units from electrical faults. The units are equipped with stator earth fault, differential, overvoltage, overcurrent tripping relays. Since both stators are connected, the circuit is protected against earth fault with the driven unit relay; the driving unit star point is open. As a matter of fact, a fault occurred during this launching sequence and the following protection were activated: 09:48:29.640 Driving U Stator earth fault 09:48:00.600 Driving U Rotor earth fault 09:47:58.960 Driving U Generator CO2 emission 09:47:58.920 Driving U Field breaker open 09:47:58.800 Driving U Grid breaker open 1

09:47:58.640 Driving U Différential protection 09:47:58.520 Driving U Excitation thyristor fuse melt 09:47:58.480 Driven U Stator earth fault The inspection undertaken after the fault showed several damages on the driving unit stator and rotor, but no damage on the driven unit at all, even though the insulation resistance of the driven unit circuit was almost zero. On the driving unit both stator and rotor were severely damaged. On the stator, a partial melt down of one stator bar was found and the adjacent core clamping finger had also partially melted. The stator core showed several hits on the lamination Two rotor poles were damaged, showing zero insulation resistance and interturn faults. The rotor earthing brush had melted. Melted iron was also found on upper bracket gland seal bearing cover. On the driven unit side, the stator winding was meggered on its own and showed high insulation resistance values; whereas the IPB duct meggering showed poor values. These IPB ducts being in a humid ambient, with some water dripping, the insulators had surface contamination. Cleaning the insulators and blowing dry air in the IPB ducts and gallery were undertaken, eventually the insulation resistance of IPB was restored and the unit could be put back on line in a matter of days. The set of pictures below show the damages suffered by the driving unit: Damaged stator Melted stator bar and finger 2

Melted finger and melted lamination Impact on stator winding One of the many impacts on core Faulty pole being removed 3

Pole 1 with arcing evidence between winding and body Pole 2 with interturn fault Most likely failure scenario Among the various scenario that were built to explain the fault sequence, the most probable one involves a double earth fault, one in each generator (the driving and the driven one). The fault was very likely triggered in the driving unit where a forgotten foreign object must have impacted the stator winding. A screw driver end was later found in the bottom of the generator end windings. Simultaneously, the driven unit IPB had a very poor insulation resistance because of heavy moisture in the IPB gallery. The IPB insulation was found to be almost zero after the fault and resumed to several megohms after 2 day drying. Hence, as the first earth fault resulted in a voltage potential increase of the neutral side and a potential increase to phase to phase voltage of the phases, the latent IPB fault broke down resulting in a double earth fault on two different phase of the electrical circuit. Whereas the single earth faults currents are limited thanks to neutral impedance, a double earth fault (identical to a phase to phase fault) is only limited by the fault path resistance which is rather low and leads to very high current and important damages. Let s note that the damages were not as severe as a phase to phase fault with the generators connected to the grid since the short circuit power was in this case moderate. The almost instantaneous variation of stator current induced a very important voltage on the rotor side, which led to arcing between the 2 poles (input and output poles) and rotor body. The voltage surge was strong enough to damage inter turn insulation on one pole. Repairs The repairs that were required on the driving unit we rather extensive and removing was a relevant question but it would lead to a very long outage as the thrust bearing is above the rotor (5 to 6 weeks for mechanical works alone). Hence after checking in details the feasibility, repairs have been performed with the rotor in the stator. 3 poles were removed to give access to the stator and provide working space for the winders. Spare Roebel bars were available at the plant, therefore the melted stator bar was replaced with a spare one. 4

Repairing he melted core clamping finger and part of the lamination was more of a challenge. The shape had to be rebuilt with glass fiber and epoxy bonding. And the pressure function and the proper lamination insulation had also to be secured. This was achieved using conic wedges inserted in between lamination. As an extra safety against hot spot, a thermocouple was placed in the repaired area to check the core operating temperature. A specific heat run test was carried out for this purpose. The core impacts were ground and checked with El Cid for any stray current. clamping finger repair The two faulty rotor poles were removed. One coil had to be replaced with the spare coil, the second one was cleaned from arcing dust and recovered perfect insulation resistance including interturn insulation. On the driven unit side, no extensive work was required. Only, the IPB ducts had to be cleaned and dryed to recover an acceptable insulation resistance. Eventually, 5 weeks after the fault, repair was complete and the driving unit resumed service. The commissioning tests included: rotor insulation resistance (500Vdc), stator insulation resistance (5kVdc), stator high pot (30kVdc), voltage ramp up, heat run of core, back to back start. Lessons learnt: The units described above failed due to the conjunction of several causes that taken individually would not have harmed the equipment so much. It may be noted that the triggering fact, which could have been avoided, is the presence of a foreign object left in the generator. Such an event shows how important it is to check and double check the tool box completion, the generator cleanliness and to work with empty pockets. The second factor is linked to heavy moisture in the IPB gallery. It shows the importance of housekeeping and drying in the electrical galleries, rooms and shafts. Water droplets have to be kept away from electrical components, sheds or drainage pipes have to be implemented to prevent insulation loss. Ultimately, this event showed the importance of an adequate protection scheme to disconnect power during any operating sequence. 5