Examination of alternative mining methodologies that have the potential to increase productivity at the mine site

Similar documents
Abstract. General N BANDA

Stationary & Semi-mobile crushing solutions Primary gyratory stations

MacKellar EPSA Capability Statement

EFFECT OF TRUCK PAYLOAD WEIGHT ON PRODUCTION

4800XPC. Electric Mining Shovel Product Overview

Haul & Load Practical Cost Reduction Volvo Construction Equipment

Mining. We set your business in motion Automation solutions and electrical equipment for open-pit mining and bulk-material handling

Ronnie van Eeden. Senior Mining Engineer. Overview

Mode of Presentation

Industrial Solutions. RollSizer. The different way of crushing.

MASTER OF SCIENCE IN ENGINEERING

QA Mobile Crushing & Screening. Stu Gamble - Sandvik

Draglines. Product Line

Main product assortment includes:

Glencore Xstrata Westside Story Mine Closure and Rehabilitation. Neil Rae Operations Manager

APPLICATION guide book

Cat MINI HYDRAULIC EXCAVATORS

Material Transport System DesignFest Problem

Hydraulic power is the key to the utility of many excavators.

Tenova TAKRAF Expertise in Open Cast Mining Technology

Sandvik VSI Crushers new CV200 series

H-E Parts Mining Solutions Capabilities

Applied Data Science, Big Data and The PI System

Quarterly Stakeholder Call

USE OF MOBILE EQUIPMENT IN OPEN PIT LIGNITE MINES PROFEN AND ZWENKAU 1. Bryan J. Evans and Monta W. Zengerle 2

Appendix E3. Open Pit Pioneering and Pre-production

ALL TERRAIN TRANSPORTERS WORLDWIDE HEAVY TRANSPORTATION AND LIFTING

Highwall Mining System

HW300. Highwall Mining System

Wear Protection ESCO Kwik-Lok Application Guide for Crushing and Conveying P6001UWS01L0312

Power stability for manufacturers

Industrial Solutions. Gyratory crushers. State-of-the-art technology with throughput rates of up to 14,000 t/h

THE MINER S BEST FRIEND.

Terex Mining Investor Meeting Dortmund, Germany

Loading and Hauling. Håkan Gustafsson David Nus Martin Mattsson

Quarterly Stakeholder Call

Mobile solutions in Action. A world leader in mobile screening and crushing

Jose Moschioni, ABB Mining Sweden, 2016 ABB Mine to Market How to improve efficiency and safety. ABB Group February 19, 2016 Slide 1

Our Company AUSWASTE

August 22 nd, Highwall Mining in India: extending mineable reserves a presentation for CMPDI.

INDEX BUCKETS - Available Components - Typical Bucket - Bucket Construction

Make sellable and reusable products on site

Technical Test Theory Wheeled Loading Shovel A21

Minto North Access Design

MMD SIZERS THE MMD GROUP OF COMPANIES

Appendix 4-2-C Project Air Emissions Inventory

ABB in cement manufacturing. From quarry to dispatch and from plant to enterprise

REFIT OF AN ELECTRIC SHOVEL OR DRAGLINE - A COST SAVING ALTERNATIVE BETWEEN FREQUENT REPAIRS AND THE PURCHASE OF A NEW MACHINE

Maintaining frictional resistance on mine road surfaces. Presented by Cres Bulger Inspector Of Mines (Qld)

Copyright Statement FPC International, Inc

ABB in Mining & Mineral Processing Business Unit Mining

Toronto Parking Authority Fleet Vehicle Replacement

The Uralmashplant Joint-Stock Company is the leading Russian supplier of plants and machinery for oil-and- gas production and mining sectors, as well

LD Parex TM Aromatics Complex: Lowest Cost of Production for PX Technology

CRUSHING, FEEDER & SCREENING EQUIPMENT

Case Study. Creative Lighting Company

MMD SIZERS THE MMD GROUP OF COMPANIES

Gas-insulated medium-voltage switchgear. For the mining industry. Answers for energy.

compact bucket wheel excavator SRs(H) /2.0 TENOVA. innovative solutions for metals and mining

Hydraulic excavator noise control case study as part of a comprehensive mitigation plan of an integrated open-pit coalmine and powerplant

UNITED STATES DEPARTMENT OF LABOR MINE SAFETY AND HEALTH ADMINISTRATION Metal and Nonmetal Mine Safety and Health REPORT OF INVESTIGATION

Selection of Shaft Hoisting or Decline Trucking for Underground Mines

FLSmidth s Fuller-Traylor Crushers

Background. Whitepaper May Emerson Reliability Consulting. Michael Whittaker, Emerson Process Management

2a. Excavating and Lifting

National Aluminium Company Limited TRAFFIC RULES AND PROCEDURES

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Liebherr machines in use worldwide in the quarry industry

MELBOURNE: BRISBANE: Ph : Fax : Ph : Fax :

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

mining sector and look to grow our business through strategic investments and co-operation agreements leveraging off our existing infrastructure.

Application of Surface Miner today and future development

The Renewable Energy Market Investment Opportunities In Lithium. Prepared by: MAC Energy Research

Digital Adrenaline For Your Subaru Forester X, XS 2.5

CPCS renewal test factsheet

Dump Point Safety. Vehicle concerns and Additional Points. Jonathan Hall, PE Tech Support, A&CC, M&ESD

Digital Adrenaline For Your Lamborghini Gallardo Superleggera

Stora Enso Helping Stora Enso achieve big energy savings

Building a 21 st Century Electric Grid. February 23, 2018

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your Peugeot

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your Jaguar S-Type R 4.

P. & I. Pascoe Limited

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your MG ZT 220 S 2.

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your BMW 335i E92 3.

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your BMW 116i 2.

HW300. Highwall Mining System

EE064D: Circuit Breakers & Switchgears: Design, Testing, Commissioning, Maintenance, Repair & Troubleshooting

Customised Mining Buckets

SUPER LONG FRONTS. n Zaxis 200LC-3, Zaxis 240LC-3, Zaxis 270LC-3, and Zaxis 350LC-3

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your Skoda Octavia 2.

Technological Viability Evaluation. Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens

Digital Adrenaline For Your Aston Martin DB9 6.0 V12

Smarter Washing Solutions S130 RINSER

Drive system for high pressure grinding rolls Increased roller life and productivity

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your Mercedes-Benz ML63

minerals & aggregates

Production Efficiency. Selective Products from specific locations

LHD Vehicles. Product Line

Powerchip Australia Pty. Ltd. Phone : (03) Fax : (03) Digital Adrenaline For Your Honda Prelude Si 2.

A powerful retrofit ABB drive retrofits extend life cycle of shovels and draglines

Transcription:

Examination of alternative mining methodologies that have the potential to increase productivity at the mine site Keith Whitchurch PT SMG Consultants

SMG Consultants Who are we? SMGC has been consulting internationally for over 44 years with a staff of highly experienced and accredited full-time professionals. Consultants cover a comprehensive range of disciplines, and their international experience covers most types of mining and minerals

Founded 1966 Australian operation sold to GHD Mid 2009 Independent Jakarta Headquartered Consulting group

A slight change in Title Examination of alternative mining methodologies that have the potential to increase productivity at YOUR mine site

THE FOCUSING QUESTION which mining options on the basis of improved costs and productivities and reduced risks should be applied to your project?

Mining Methods Focus on Overburden Conventional Loader and Truck Excavator to Semi Mobile crusher Excavator to Mobile Crusher Bucket wheel to Conveyor Dozer to conveyor Dozer to Final spoil Dragline

Loader and Truck

Mining Technique - Truck Shovel Trucks can haul from anywhere in pit direct to waste

Dimension 1 Type of Excavator CONVENTIONAL HYDRAULIC EXCAVATOR OR ELECTRIC SHOVEL / TRUCK ON WASTE Options Large excavator (26 cu m) Large electric shovel (48 cu m) Dependent qualities Diesel power Trailing cable; ground pressure 2 Bench layout Bench height Panel dimensions Time between minor relocations Time between major relocations 3 Size of Truck Cat 777 / Komatsu HD785 (100t) Cat 785 (136t) Cat 789 (177t) Cat 793 (218t) Ground pressure Tyre availability

CONVENTIONAL LARGE EXCAVATOR / TRUCK Known methodology Minimum Capex by Client Contractor owns equipment Ease of changes in production rate Expected production = ~ 9 Mbcmpa per fleet Large fleet size for high production rates No leverage to reduce operating costs

ELECTRIC SHOVEL / TRUCK Larger bucket size Larger bench height (20m) for decreased bench moves Minimum Capex by Client Contractor owns equipment Ease of changes in production rate Expected production = ~18 Mbcmpa per fleet Uncommon methodology to Indonesia Ground conditions shovel prone to bogging ramification of wiping out cable reeler Needs larger trucks to realise produciton gains again ground conditions Electric shovels require operational discipline respect for cables; correct gradients on benches; correct blasting Limited leverage to reduce operating costs

Excavator to Semi Mobile Crusher

Excavator to Semi Mobile Crusher

Spreader Generation 1 & 2 Generation 1 Goonyella 7,000tph? Generation 2 Mae Moh, Thailand 20,000tph

Spreader Generation 3 and 4 Generation 3 Low Profile Spreader With track shiftable conveyors Generation 4 RAHCO system Fully mobile spreader conveyor (MSC)

Trucks can haul to crushers from anywhere in pit or haul direct to waste Mining Technique - Truck to Crusher

EXCAVATOR OR SHOVEL TO IN-PIT CRUSHING (ON WASTE) Dimension 1 Type of Excavator Options Large excavator (26 cu m) Large electric shovel (48 cu m) Dependent qualities Diesel power Trailing cable; ground pressure 2 Bench layout Bench height Panel dimensions Time between minor relocations Time between major relocations 3 In-pit crusher system Semi-mobile crusher Mobile crusher Bandwagon to feed pit conveyor Crusher rates Conveyor rates No. of pit conveyors No. of spreaders

Dictated by design capacity Same as for Loader/Truck Loading Type

DIGGER TO TRUCKS TO SEMI-MOBILE CRUSHER TO CONVEYOR Proven methodology in tropics (e.g. Mae Moh) Multiple installations give high production rates Expected production of 2 x 5000 tph crushers = ~ 25 Mbcmpa Potential to reduce operating costs Flexibility in trucks feeding from RL of +/- 20 to 30m from crusher level More flexible than full conveyor system Able to divert diggers to alternate work areas while coal / IB being extracted Able to divert trucks to lower levels when system is out-of-action Degree of Capex by Client Initial installation locks in production rate High Capex to increase production Optimum for large working area Requires balance of upper / lower pit production Failure of one component in continuous system stops upper pit production Less flexible than total truck system Geotechnical failure = catastrophic

Mobile Crusher Generation 1 & 2 O&K Generation 1 Ulan MMD / P&H Generation 2 Goonyella Tertiary Overburden

Mobile Crusher Generation 3 Krupp Generation 3a China Generation 3b Clermont Mantakraf / Abon

Excavator to Mobile Crusher

Excavator to Mobile Crusher

Mining Technique - Combination System System can only operate efficiently in large interburdens

DIGGER TO MOBILE CRUSHER TO CONVEYOR Multiple installations give high production rates Expected production of 1 x 5 000 tph crusher = ~ 12 Mbcmpa (fed by L996 excavator) Potential to reduce operating costs by eliminating trucks Unproven methodology in tropics Degree of capex by Client High capex (incl. 4 x conveyors) Initial installation locks in production rate No flexibility Needs large working area Unable to work system in coal / IB zones Requires balance of upper / mid-level / lower pit production Needs mid-level system such as semi-mobile crusher fed by trucks Failure of one component in continuous system stops production Bogging of tracks of mobile crusher Geotechnical failure = catastrophic

Bucket wheel excavator to Conveyor

Bucket wheel excavator to Conveyor

Bucket wheel excavator to Conveyor

Mining Technique - Combination System System can only operate efficiently in large interburdens

BUCKET WHEEL EXCAVATOR TO CONVEYOR Dimension 1 Type of Excavator Options Compact unit Design to specific site Dependent qualities Dig rate anything to 3 000 bcm/hr Ground pressure 2 Bench layout Bench height Panel dimensions Time between minor relocations Time between major relocations 3 Materials handling system 4 x conveyors Bandwagon to feed pit conveyor Spreader Conveyor rates No of pit conveyors No. of spreaders

BWE TO CONVEYOR Proven methodology in tropics (e.g. Jorong; Bukit Asam) Single installation for high production rates Expected BWE production up to 1 x 3 000 bcm/hr = ~ 18 Mbcmpa Potential to reduce operating costs by eliminating trucks Degree of capex by Client High capex (incl. 4 x conveyors) Initial installation locks in production rate No flexibility Needs large working area Unable to work system in coal / IB zones Requires balance of upper / mid-level / lower pit production Needs mid-level system such as semimobile crusher fed by trucks Failure of one component in continuous system stops production Suited to material blasting? stickiness? Geotechnical failure = catastrophic

Push Dozer to Mobile Crusher

Push Dozer to Mobile Crusher

Mining Technique - Combination System System can only operate efficiently in large interburdens

DOZER TO FEEDER TO CONVEYOR (ON WASTE) Dimension 1 Type of Excavator 2 Bench layout 3 Materials handling system Options Dozer D11R Carry Dozer Komatsu 575 Super Dozer Bench height Panel dimensions Size & capacity of Stammer breaker / feeders 4 x conveyors Dependent qualities Dig rate est. 450 to 500 bcm/hr per dozer Time between minor relocations Time between major relocations Bandwagon to feed pit conveyor Spreader Conveyor rates No of pit conveyors No. of spreaders

DOZER TRAP TO CONVEYOR Single installation for high production rates Expected dozer trap production of 2.5 to 3 Mbcmpa per dozer Potential to reduce operating costs by eliminating trucks Relatively cheap capex and opex of dozers compared to other continuous systems Dozers may be used on other tasks during system outages Unproven methodology in tropics Degree of capex by Client High capex (incl. 4 x conveyors) Initial installation locks in production rate No flexibility Needs large working area Unable to work system in coal / IB zones Requires balance of upper / mid-level / lower pit production Needs mid-level system such as semi-mobile crusher fed by trucks Failure of one component in continuous system stops production Suited to material able to increase face height beyond 25m? Geotechnical failure = catastrophic

Push Dozers To Final spoil

Push Dozers To Final spoil

Example Dozer Method X Section Truck Spoil Dozer Spoil Mined out Dozer Truck Shovel Blast Dozer Pass and Then Truck Shovel Pass Truck Spoil Dozer Spoil Mined out Dozer Truck Shovel

Example Dozer Method X Section Dozer Pushes Ramp through Blast at Panel Truck Spoil Dozer Spoil Mined out Dozer Truck Shovel Prestrip mined and hauled cross pit Truck Shovel Truck Spoil Dozer Spoil Mined out Dozer

Example Dozer Method X Section Dozer Push to Final Leaves Highwall Wedge Truck Shovel Truck Spoil Dozer Spoil Dozer Shovel Truck Clears Highwall Wedge and Low wall rehandle Rehandle Wedge Highwall Wedge Truck Shovel Truck Spoil Dozer Spoil

DOZER PUSH TO FINAL Expected dozer production of 2.5 to 3 Mbcmpa per dozer Relatively cheap capex and opex of dozers compared to other systems Dozers may be used on other tasks Unproven methodology in Indonesia Needs large working area Requires highly disciplined approach Unable to work system in coal / IB zones Requires truck/loader support Geotechnical failure Application limited by deposit geometry/geology Bulk dozer push requires specially rained operators

Dragline

Dragline

Truck Shovel Prestrip

Blast Top Pass

Dozer Push Top Pass to Form Bench

Dragline to bench

Dragline Removes First Pass Truck Shovel mines Coal

Blast Second Pass

Dragline chops Highwall and extends bench

Dragline sits on bench and removes remainder of second pass

DRAGLINE Single installation for high production rates Expected 14Mbcm to 25Mbcm pa Potential to reduce operating costs by eliminating trucks Very low opex Not impacted by Rain Very long asset life > 30 years Unproven methodology in Indonesa Degree of capex by Client High capex Initial installation locks in production rate No flexibility Needs large working area Limited application by deposit geometry/geology Unable to work system in coal / IB zones Generally needs a prestrip system Exposure to failure of a single unit Modern high productivity spoil side operations unlikely due to geotechnical constraints Geotechnical failure = catastrophic

WHICH ONE IS FOR YOU? which mining options on the basis of improved costs and productivities and reduced risks should be applied to your project?

HOW DO WE DECIDE WHAT IS BEST IN YOUR DEPOSIT

Decision Criteria Starting List by consensus Capital Cost Operating Cost Exposure to escalation of Operating Costs Practicality degree of compatibility with this site Mining complexity Risk of technical failure % of production applicable to the method Operating hours per year Material conditions (as applied to impact on method) Timing of implementation (lead time) Availability of technology and parts Local Skills Geotechnical stability / consequences of failure Acceptability to international banks for finance Hydrology consequences of water inflow

Weightings determined independently and pooled Weighting 1 = unimportant, 10 = important SMGC Contractor SMGC Client Average Description of Criteria weighting weighting weighting weighting Weighting Capital cost (size of capital cost) 10 7 10 5 8.0 Operating cost (indicative relativity for method) 10 10 10 10 10.0 Exposure to escalation of Operating Costs 6 5 7 5 5.8 Practicality - degree of compatibility to TOP site 10 10 10 10 10.0 Boxcut (implications of external dumps) 2 2 8 5 4.3 Mining Complexity 7 7 8 2 6.0 Risk of Technical Failure 7 7 7 5 6.5 % of Production Applicable to method 2 5 6 1 3.5 Operating hours per year 5 4 7 1 4.3 Material Conditions (as applied to impact on method) 8 3 7 2 5.0 Timing of Implementation / lead time 4 2 2 1 2.3 Availability of Technology and Parts 6 1 6 1 3.5 Local Skills (degree where lack of skill = high probability of failure?) 3 2 7 2 3.5 Geotechnical - Consequences if geotech failure 7 5 7 1 5.0 Acceptability to International Banks 10 2 9 5 6.5 Hydrology - Consequences on method of water inflow 7 2 8 1 4.5

8 10 5.8 10 6.0 6.5 3.5 4.3 5.0 2.3 3.5 3.5 5.0 5.0 4.5 Capital Cost Operating Cost Exposure to escalation of Operating Costs Practicality degree of compatibility with this site Mining complexity Risk of technical failure % of production applicable to the method Operating hours per year Material conditions (as applied to impact on method) Timing of implementation (lead time) Availability of technology and parts Decision Criteria Rank From 1 to 10 average of participants Local Skills (degree whereby lack of skill = high probability of failure Geotechnical stability / consequences of failure Acceptability to international banks for finance Hydrology consequences of water inflow

Raw Scores per Option Determined by technical analysis (SMGC) HE / shovel HE / shovel Dozer to Dozer push; Hydraulic Electric Front End to Truck to to fully Bucket feeder Dragline; combination Excavator Shovel Loader Semi-mobile mobile Wheel to breaker to proportion excavator Description of Criteria to Trucks to Trucks to Trucks Crusher Crusher Conveyor Conveyor of waste & trucks Capital cost (size of capital cost) 3 2 3 1 1 1 1 1 3 Operating cost (indicative relativity for method) 1 1 1 3 3 3 3 3 1 Exposure to escalation of Operating Costs 1 1 1 2 3 3 3 3 1 Practicality - degree of compatibility to TOP site 3 2 1 3 3 1 3 2 2 Boxcut (implications of external dumps) 3 3 3 1 1 1 1 3 3 Mining Complexity 3 2 2 2 1 1 2 1 1 Risk of Technical Failure 3 2 2 3 2 1 2 1 2 % of Production Applicable to method 3 3 2 3 3 2 2 1 3 Operating hours per year 3 3 3 3 2 2 2 3 3 Material Conditions (as applied to impact on method) 3 2 1 2 2 1 3 2 3 Timing of Implementation / lead time 3 2 3 1 1 1 1 1 3 Availability of Technology and Parts 3 2 2 2 2 2 3 2 3 Local Skills (degree where lack of skill = high probability of failure?) 3 2 3 2 2 2 2 1 3 Geotechnical - Consequences if geotech failure 3 2 3 1 1 1 1 1 3 Acceptability to International Banks 3 2 3 1 1 1 1 1 3 Hydrology - Consequences on method of water inflow 3 2 2 1 1 1 1 1 3

Raw Scores per Option Determined by technical analysis (SMGC) HE / shovel HE / shovel Dozer to Dozer push; Hydraulic Electric Front End to Truck to to fully Bucket feeder Dragline; combination Excavator Shovel Loader Semi-mobile mobile Wheel to breaker to proportion excavator to Trucks to Trucks to Trucks Crusher Crusher Conveyor Conveyor of waste & trucks 24 16 24 8 8 8 8 8 24 10 10 10 30 30 30 30 30 10 5.75 5.75 5.75 11.5 17.25 17.25 17.25 17.25 5.75 30 20 10 30 30 10 30 20 20 12.75 12.75 12.75 4.25 4.25 4.25 4.25 12.75 12.75 18 12 12 12 6 6 12 6 6 19.5 13 13 19.5 13 6.5 13 6.5 13 10.5 10.5 7 10.5 10.5 7 3.5 3.5 10.5 12.75 12.75 8.5 12.75 8.5 8.5 8.5 12.75 12.75 15 10 5 10 10 5 15 10 15 6.75 4.5 6.75 2.25 2.25 2.25 2.25 2.25 6.75 10.5 7 7 7 7 7 10.5 7 10.5 10.5 7 10.5 7 7 7 7 3.5 10.5 15 10 15 5 5 5 5 5 15 19.5 13 13 6.5 6.5 6.5 6.5 6.5 19.5 13.5 9 9 4.5 4.5 4.5 4.5 4.5 13.5 234 173 169 181 170 135 177 156 206 1 5 7 3 6 9 4 8 2

Comments on Ranking Ranking 1: Conventional hydraulic excavator and trucks has been ranked as the highest or equal highest in 14 of the 16 categories. Such systems benefit from flexibility and simplicity, low total capital cost and acceptability to international banks. The only negative aspects are high operating cost and likelihood of future increases in those costs. Ranking 2: The second choice is a variation of the top ranking, with dozer assist to conventional hydraulic excavator and trucks. This system scored similarly in most categories as the conventional use of hydraulic excavator and trucks; but lost points from the additional complexity and probability of technical failure. Ranking 3: The third choice is the loading mechanism of an hydraulic excavator or electric shovel dumping to a semi-mobile crusher. This system gains in terms of operating cost criteria; but loses against capital costs, size of boxcut to establish, the degree of complexity added by a conveyor spreader system and the related issue of acceptance to international banks. Ranking 4: The fourth option is waste moved by a fleet of dozers pushing to a lowcapital cost but high throughput feeder-breaker to a conveyor system. Such a system scores well on operating cost and practicality to the thick overburden task at this project. The dig side of a dozer operation is not affected by rain; the dozer faces could be designed in excess of 20m to decrease the frequency of system moves, and the method handles poor material conditions. The downside would be the high capital cost of conveyors and spreader, size of boxcut to establish and the degree of complexity added by a conveyor spreader system.

Ranking 5: Waste mining up to 50Mbcm per year with a fleet of large front-end-loaders is a poor option on both practical and technical grounds. These machines would not be able to match the superiority of hydraulic excavators for production time or ability to handle the soft ground conditions Ranking 6: The ranking of the waste systems has eliminated the concept of the fully-mobile MMD-style crusher being fed directly by an hydraulic excavator or electric shovel. Again this option scored highly on the operating cost factor. It suffered on non-suitability to the pit geometry due to high inherent system capacity (to match peak production later in mine life); need for frequent moves down 20m high benches and resultant low work hours per year; high capital costs; size of boxcut to establish; the degree of complexity added by a conveyor spreader system and the related issue of acceptance to international banks. Ranking 7: The option of electric shovel to trucks loses against the hydraulic excavator in the two aspects of complexity (relating to the need to design, plan and maintain procedures associated with the electric cables and substation) and in material conditions (being the consequences of machine bogging with resultant damage to rear cable reel). Ranking 8: The dragline option has been ruled out on the basis of poor technical application. The concept of a single large and unique (to Indonesia) dragline operation with the responsibility of all coal exposure task would be a high risk option with multiple areas for failure (such as high degree of complexity; poor material stability under the machine; lack of local skills and discipline vital to successful dragline application). Ranking 9: The ranking of the waste systems has eliminated the BWE which scored highly on one factor only (cost). It scored badly on material conditions (due to the likely presence of soft sticky material in small buckets); and on all other criteria.

Conclusions These conclusions are for this example project only Options 1 to 3 are Conventional Hydraulic excavator to truck Dozer assist of Conventional Hydraulic excavator to truck Hydraulic excavator or Electric shovel to fully mobile in pit crusher/conveyor These 3 options require further detailed study

Conclusions A range of options are open The best option depends on a wide range of factors The best option for someone else's project is not necessarily the best option for your project There is no substitute for in country experience in guiding this decision making process

Thank You