www. ElectricalPartManuals. com Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers

Similar documents
Advanced Test Equipment Rentals ATEC (2832)

Instructions for VCP-W Simple Electrical Ground & Test Device (SEG&TD) with simplified interlock scheme - bottom terminal set version

Instruction Booklet for the Installation, Operation and Maintenance of Type 5-15 kv VCP-WG Vacuum Circuit Breaker 4000A MiniMod

Instructions for using Functional Test Kit on Digitrip 520 and 1150 family of Power Circuit Breaker Trip Units and Series G and FD MCCB Trip Units

Instruction Booklet IB E. Contents

CM52 Network Protector with Arc Flash Reduction Module

O & M Manual for the EATON Generator Ready Loadcenter

Simple Electrically Operated Ground & Test Device For use in Type VCP-W Switchgear rated up to 15kV, 25 and 40kA UPPER TERMINAL SET VERSION

Digitrip Retrofit System for the ITE LG-3000 (Frameless) Circuit Breaker

TVSS Installation for RLCM/CHGENLC, RLCU, and CHGEN ATSs

CCP2-FLR1-21_ flange-rod operating mechanism

Installation and removal instructions for Series NRX RF fixed breaker three-way Type 32 cable interlock kit

3-way multi-family drawout cable interlock kit - type 32 - RF

Installation Instructions for R-Frame G-Series (RG) 310+ Trip Unit

SECTION MICROPROCESSOR TRIP UNITS FOR LV CIRCUIT BREAKERS. This section is organized as indicated below. Select desired Paragraphs.

Installation Instructions for Interlocking Trip Indicator with Remote Reset for Magnum Low Voltage Circuit Breakers

Magnum Breaker Remote Racking Device (MRR1000)

Digitrip Retrofit System for General Electric AKR/AKRU-6D/7D-30S Series Breakers

Digitrip Retrofit System for the Federal Pioneer 25-H(L)-2, 30-H(L)-2, 30-H(L)-3, and 30-3 Breakers

Installation Instructions for KPS and KPH Circuit Breakers and Molded Case Switches

Digitrip Retrofit System for Allis-Chalmers LA-600 F Electrically Operated Fused Breakers

Cutler-Hammer. Installation Instructions for the Digitrip OPTIM Pole Trip Unit Installation and Operation with L-Frame Series C Circuit Breakers

COOPER POWER SERIES. S.T.A.R. type LVR faulted circuit indicator installation instructions. Fault Indicators MN320005EN

Factory Authorized Mechanism Enhancement (FAME)

Two-way cable interlock kit for Magnum fixed circuit breakers

Removal/installation instructions for Series NRX (IZMX) drawout levering (racking) mechanism

INSPECTOR LINE LOAD SIMULATOR INSTRUCTION MANUAL TASCO, INC.

COOPER POWER SERIES. K-Limiter back-up current-limiting fuse installation instructions. Fusing Equipment MN132010EN

Two-way cable interlock kit for Magnum drawout circuit breakers

www. ElectricalPartManuals. com Digitrip Retrofit System for BBC LKD 8 Breakers IL 33-LK8-2

Reprogramming guide. Power Defense ICCB. Instructional Leaflet IL EN WARNING WARNING. Instructions apply to:

COOPER POWER. SERIES ELF Current-Limiting Dropout Fuse Installation Instructions. Fusing Equipment MN132028EN. Pull ring. Housing

Digitrip Retrofit System for Siemens-Allis RLX-1600 Breakers

Data Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931

COOPER POWER SERIES. Testing a motor capacitor on a voltage regulator procedure instructions. Voltage Regulators MN225064EN

Instructions for installation, operation, and maintenance of medium voltage VC-W MR2 (integral racking)

Instructions for Digitrip Models 220, 520, 520i, 520M, and 520Mi Trip Units for use only in Cutler-Hammer Magnum and Magnum DS Circuit Breakers

Eaton Digitrip RMS and Digitrip OPTIM Trip Units with Types DSII and DSLII Low Voltage Power Circuit Breakers

www. ElectricalPartManuals. com Digitrip Retrofit System for the Westinghouse DA-50 IL 33-DAC-2 WARNING

Digitrip RMS and Digitrip OPTIM Trip Units Used with R-Frame Circuit Breakers

www. ElectricalPartManuals. com Digitrip Retrofit System for Allis-Chalmers LA-4000 F Fused Breakers IL 33-A1K-1 WARNING

COOPER POWER SERIES. Dielectric grease application to recloser cable instructions. Reclosers MN280070EN

Transformer Protection

A WARNING. Installation Instructions for KD, HKD, KDC, CKD, CHKD Circuit Breakers I.L. 29C092C

Flush Mount AIN ALPHA Meters. General. Hardware Kit

Digitrip Retrofit System for the General Electric AKR 6D/7D-30/50 and AKRT 6D/7D-50 Series Breakers

SPC-PANEL Simplex, Single Phase Pump Control Panel

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work

COOPER POWER SERIES. Current-Limiting Type NXC (C-Rated) Fuse Installation Instructions. Fusing Equipment MN132014EN

Type DTU De-energized Tap Changer Application, Installation & Selection Guide. IL A Instruction Leaflet Page 1 September, 2003

Type NR oil switch installation and operation instructions

INSP-3 Wiring Inspection Tester

Digitrip Retrofit System for Allis-Chalmers G-25 Breakers

COOPER POWER SERIES. Pad-mounted Switchgear MN285019EN. Effective March 2017 Supersedes February 2007 (S )

COOPER POWER SERIES. Quick Connect Assembly (QCA) Retrofit Kit, General Electric Installation Instructions. Voltage Regulators MN225075EN

Digitrip Retrofit System for BBC LKD 8 Breakers

COOPER POWER SERIES. KA1169R Closing Coil Transfer-Switch Accessory Operation. Reclosers MN280069EN

Effective November 2016 Supersedes September 1998 (S )

Guide for Primary Injection Testing WL Circuit Breakers. Document No. : 11-C

WESTINGHOUSE / CUTLER HAMMER DS POWER BREAKERS

Digitrip Retrofit System for ITE K-3000, K-3000 S, K-4000 and K-4000 S Breakers

Product Overview. Product Identification. Amps One CT Two CTs Three CTs

Magnum breaker remote racking device (MRR1000)

Cutler-Hammer. Installation Instructions for the ND OPTIM 550 PowerNet and/or Zone Interlock Accessories (ICK 550N, ZGK550N, ZGPK550N) I.L.

Instructions for Digitrip Models 520V and 520MCV for use only in Cutler-Hammer Type VCP-T, VCP-TR and T-VAC, T-VACR Circuit Breakers

COOPER POWER SERIES. ELSG Full-Range Current-Limiting Fuse Re-Fusing Instructions. Fusing Equipment MN132017EN

Effective May 2017 Supersedes January 2003 (S )

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

Pump Installation and Service Manual HRS Hydromatic Retractable System

Zone Selective Interlock Module. For GE Circuit Breakers

COOPER POWER SERIES. HX-CB loadbreak fuse cutout installation instructions. Fusing Equipment MN132011EN

DSR1. User s Manual. MarTek Ltd. RAKTEK. Model DSR1. A Portable Device for Remotely Racking DS and DSII-Style Circuit Breakers. 1.0 Arc-blast Hazards

Effective March 2015 Supersedes S August 2012

VCPR. User s Manual. MarTek Ltd. RAKTEK. Model VCPR. A Portable Device for Remotely Racking VCP-Style Circuit Breakers 1.0 Arc-blast Hazards

ProTrip Conversion Kits. For GE Types AK-15, AK-25, and AKU- 25 Low-Voltage Power Circuit Breakers INTRODUCTION. DEH Installation Instructions

High-voltage primary bushings installation instructions

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

dfdf 34.5 kv and 69 kv, Type O Plus C II Condenser Bushings Technical Guide

Cutler-Hammer. Instructions for Potential Transformer and Auxiliary Control Power Disconnecting Means for Use in Ampgard Lineups, 7.2 kv I.B.

DANGER. See Wiring Diagrams on page 7 for illustrations of both internal and connection wiring diagrams. WARNING

Zone Selective Interlocking

WEB CONTROL PRODUCTS

VCPR. A Portable Device for Remotely Racking VCP-W Circuit Breakers. User s Manual

COOPER POWER SERIES. High-voltage primary bushings installation instructions. OEM Equipment MN800008EN

www. ElectricalPartManuals. com !tell Cutler-Hammer I.L A WARNING Instructions for Digitrip RMS 510 Trip Unit

COOPER POWER SERIES. 600 A 15/25 kv class T-OP II connector assembly installation instructions. Deadbreak Apparatus Connectors MN650048EN

COOPER POWER SERIES. Electronic control battery testing, charging, and replacement instructions. Reclosers MN280074EN

Firstmate Installation Manual and User's Guide May, 2003

Installation Instructions for R-Frame Circuit Breakers and Molded Case Switches

COOPER POWER SERIES. S.T.A.R. Hot line voltage indicator installation instructions. Fault Indicators MN320011EN. Indicator boot.

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

Users Guide for Ac-sync

COOPER POWER SERIES. 600 A 15, 25, and 35 kv Class Cleer Loadbreak Bushing Insert Installation Instructions. Loadbreak/Deadbreak Connectors MN650016EN

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

WARNING. Instructions for Combination Bypass Isolation and Transfer Switches Amps I.L A FILE APPLICATION SAFETY PRACTICES

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

INSTRUCTION BOOK SYSTEM 2001 GROUNDING EQUIPMENT FOR FAULT LOCATION. W/ High Resistance Neutral Grounding. for use on

Instructions for Digitrip Models 1150 and 1150i Trip Units for use only in Cutler-Hammer Magnum and Magnum DS Circuit Breakers

Installation Instructions for Series C F-Frame 310+ Electronic Circuit Breaker Types FDE, HFDE, FDCE

MAINFRAME HOT RUNNER TEMPERATURE CONTROL SYSTEMS. Instruction Manual

Transcription:

Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers The National Electrical Code makes the following statement regarding ground fault conformance testing: NEC 230-95c The ground fault protection system shall be performance tested when first installed. The test shall be conducted in accordance with approved instructions which shall be provided with the equipment. A written record of this test shall be made and shall be available to the authority having jurisdiction. This document is intended to provide instructions for conformance testing of ground fault systems utilizing type Magnum DS circuit breakers. Although the most common system variations are specifically illustrated, they are also used to form the basis for more complex systems. These instructions may be applied, accordingly, on these systems as well. Refer to order-specific drawings to determine the actual ground fault system supplied. DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. Overall system selectivity and performance of integral ground fault protection equipment can be field tested only by using the high current primary injection method. When testing with this method, the following rules must be followed: 1. Tests are to be conducted by qualified personnel only. 2. The incoming line or source transformer must be disconnected from the switchgear. 3. Loads must be disconnected from the switchgear when testing feeder breaker ground fault. If only the mains or ties are to be tested, all feeder breakers must be open. 4. A single phase high current power supply will be required (approx. 1200A at approx. 2.5V). Flexible jumper cables, equal to the current that will be applied, will also be required. DANGER INSTALLED RATING PLUG SIZE GROUND FAULT PICKUP SETTINGS IN AMPERES ➀ GROUND FAULT PICK-UP VALUES FOR MAGNUM DS BREAKERS. TABLE A RMS 0.25➁ 0.3 ➁ 0.35➁ 0.4 ➁ 0.5➁ 0.6 0.75 1.0 200 50 60 70 80 100 120 150 200 250 63 75 88 100 125 150 188 250 300 75 90 105 120 150 180 225 300 400 100 120 140 160 200 240 300 400 600 150 180 210 240 300 360 450 600 800 200 240 280 320 400 480 600 800 1000 250 300 350 400 500 600 750 1000 1200 300 360 420 480 600 720 900 1200 1600 400 480 560 640 800 960 1200 1200 2000 500 600 700 800 1000 1200 1200 1200 2500 625 750 875 1000 1200 1200 1200 1200 3000 750 900 1050 1200 1200 1200 1200 1200 3200 800 960 1120 1200 1200 1200 1200 1200 4000 1000 1200 1200 1200 1200 1200 1200 1200 5000 1200 1200 1200 1200 1200 1200 1200 1200 ➀➀ TOLERANCES ON PICKUP LEVELS ARE +10% OF VALUES SHOWN. ➁➁ FOR TESTING PURPOSES ONLY: WHEN USING AN EXTERNAL SINGLE PHASE CURRENT SOURCE TO TEST LOW LEVEL GROUND FAULT CURRENT SETTINGS, IT IS ADVISABLE TO USE THE TEST KIT AND ASSOC. ADAPTER. WHEN THE SINGLE PHASE CURRENT IS LOW, IT MAY APPEAR AS IF THE TRIP UNIT DOES NOT RESPOND UNTIL THE CURRENT IS WELL ABOVE THE SET VALUE, LEADING THE TESTER TO BELIEVE THERE IS AN ERROR IN THE TRIP UNIT WHEN THERE IS NONE. THE REASON THIS OCCURS IS THAT THE SINGLE PHASE TEST CURRENT IS NOT A GOOD SIMULATION OF THE NORMAL THREE PHASE CIRCUIT. IF THREE PHASE HAD BEEN FLOWING, THE TRIP UNIT WOULD HAVE BEEN POWERED SUFFICIENTLY. USE THE TEST KIT AND ASSOC. ADAPTER FOR CORRECT TRIP UNIT PERFORMANCE WHEN SINGLE PHASE TESTS ARE MADE. 5. For RMS 520 Digitrip, a test kit and assoc. adapter will be required for each breaker undergoing simultaneous testing. For all other Digitrip types, either an auxiliary power supply module (Cat. No: PRTAAPM) will be required, or the power/relay module must be energized through its breaker secondary terminals. (See Table A Footnote 2). 6. On 4-wire systems, check to ensure that there are no additional grounds on the feeder breaker neutral conductors. OPTIONAL ZONE SELECTIVE INTERLOCKING GROUND FAULT OPERATION Under a ground fault condition, the downstream breaker will send a restraining signal to the upstream breaker. This signal tells the upstream breaker to begin timing (assuming the fault current is above their pickup settings).

Page 2 The downstream breaker should then clear the fault. If the downstream breaker fails to trip, the upstream breaker will then time out and clear the fault condition. If the fault condition is located between the upstream breaker and the downstream breaker, the downstream breaker will not sense the fault and no restraining signal will be sent. The upstream breaker will then trip at its minimum time band, regardless of the time setting. The pickup and time delay settings on the main, tie, and feeder breakers must be selectively coordinated. Note: If individual breaker testing is performed with the breaker withdrawn from the test or connected positions, terminals B8 & B9 must be jumpered to obtain time delay by use of secondary defeat adapter 8779C02G05. RMS FIELD TESTING OF OPTIONAL ZONE INTERLOCKING The following is a general procedure to check the zone interlocking functions and wiring. Primary injection is not required for this test. Drawout breakers must be in the test or connected position. The breakers must not be energized except control power. For RMS 520, use a Test Kit for each trip unit to obtain control power. See Test Kit instructions. For all other Digitrip RMS trip units, use an Auxiliary Power Module to power the trip units. The APM is powered from a 120VAC receptacle, the power cord plugs into a jack on the front of the trip unit. Auxiliary power module is required. The Digitrip RMS green status LED should be flashing. Preliminary: For ease of testing, make the following settings. They should be turned back to the desired settings after testing is complete. Make these settings on both the downstream and upstream trip units: ➀ ➀ Test Amps = GFT Ground Fault Pick-up = 0.35 Ground Fault Time = 0.5 TEST 1 Self-Interlocked Feeders Verify each feeder breaker trips with time delay when self-interlocked. Push test pushbutton and release to start the test. The breaker should trip with time delay. Push reset on Digitrip and reclose breaker. Do this for each feeder breaker and verify delayed tripping occurs. NOTE: Self-interlocking is defined as the feeder breaker having a jumper installed on secondary contacts B8 and B9. When this jumper is installed, it allows the ground fault time delay to operate at the trip unit setting. Without this jumper, the ground fault time delay will always revert to the minimum time setting (0.1) regardless of the trip unit setting. The self-interlocked jumpers should only be on the furthest downstream breakers in the zone interlock scheme. TEST 2 No Delay Trip On Upstream Breakers (Normally mains and ties) Verify that each upstream breaker will trip with no time delay (minimum setting 0.1), when not receiving a restraint signal from a downstream breaker. Push test pushbutton and release to start the test. The breaker should trip without any time delay (minimum setting 0.1). Push reset on Digitrip and reclose breaker, repeat test for each upstream breaker. TEST 3 Delayed Trip Verify that restraint signal sent by a downstream breaker to an upstream breaker does cause a time delay trip. For Digitrip RMS 520, use the Test Kits to initiate simultaneous ground faults for both an up- and downstream breaker. The upstream breaker should trip with a 0.5 sec delay. For all other Digitrip trip units, choose a feeder adjacent to the main or tie that is to be tested. Push test pushbuttons on both breakers and release them simultaneously. The upstream breaker should trip with a 0.5 sec delay. ➀ Procedure is written for trip units which include an integral test feature. For trip units that do not have an integral test panel, use a Digitrip Test Kit for each breaker to initiate a ground fault trip. Follow Test Kit instructions to initiate a trip.

Page 3 4 POINT GROUND FAULT TERMINAL BLOCK 1 2 1 CONNECT TO AND TO ON 4 POINT GF TERMINAL BLOCK 2 FOR RESIDUAL SENSING. 4 POINT GROUND FAULT TERMINAL BLOCK 1 2 5 WINDING CURR. XFMR. PRIMARY CURRENT SENSORS OUTPUT WINDING FIG. 1 CONNECTION DIAGRAM FOR MAGNUM DS RESIDUAL GROUND FAULT PRIMARY CURRENT SENSORS FIG. 2 CONNECTION DIAGRAM FOR MAGNUM DS SOURCE GROUND FAULT 22 20 18 17 19 21 15 FLUX TRIP 14 DEVICE 1 CONNECT TO AND TO ON 4 POINT GF TERMINAL BLOCK 2 FOR RESIDUAL SENSING. 4 3 RMS CONNECT TO ON 4 POINT GF TERMINAL BLOCK FOR SOURCE GROUND AND ZERO SEQUENCE SENSING. 18 20 22 21 19 17 15 FLUX TRIP 14 DEVICE 4 3 RMS CONNECT TO ON 4 POINT GF TERMINAL BLOCK FOR SOURCE GROUND AND ZERO SEQUENCE SENSING.

Page 4 3 WIRE ØA, 3 WIRE BREAKER WITH RESIDUAL GROUND FAULT ØB, ØC, 3 WIRE LOAD FIG. 3 SINGLE LINE DIAGRAM OF 3W DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. BREAKER STATUS APPLY 1Ø INSTALL POWER TO JUMPER FROM RESULTS REMARKS CLOSED A1 & G1 A2 & G1 TIMES OUT AND TRIPS REPEAT THE ABOVE TEST FOR B PHASE & C PHASE. NOTE: If the above test does not pass, utilize Integral Test Panel ➀ on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. FOR LARGE SEE FIG. 2 ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing. ØA, ØB, A1 B1 C1 A2 B2 C2 ØC, DISCONNECTED FROM LOAD DANGER FIG. 4 THREE LINE DIAGRAM INDICATING TEST POINTS G1 EQUIPMENT GROUND BUS

Page 5 4 WIRE ØA, ØB, ØC, NEUT. 4 WIRE LOAD 4 WIRE BREAKER WITH RESIDUAL GROUND FAULT ( )N ( )G C1 C4 C5 FIG. 5 SINGLE LINE DIAGRAM OF 4W DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. BREAKER STATUS APPLY 1Ø INSTALL POWER TO JUMPER FROM RESULTS REMARKS CLOSED A1 & N1 A2 & N2 NO TRIP POLARITY CHECK FOR NEUTRAL SENSOR CLOSED A1 & G1 A2 & G1 TIMES OUT AND TRIPS FIG. 6 THREE LINE DIAGRAM INDICATING TEST POINTS REPEAT THE ABOVE TEST FOR B PHASE & C PHASE, EXCEPT NEUTRAL SENSOR POLARITY CHECK IS ONLY REQUIRED. ON ONE PHASE. NOTE: If any of the above tests do not pass, utilize ➀ Integral Test Panel on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. If No Trip test fails, reverse secondary connections at neutral sensor and repeat test. If test still fails, check that connections on breaker are per figure 1. FOR LARGE SEE FIG. 2 ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing. D9 0 ØA, ØB, ØC, N A1 B1 C1 A2 B2 C2 DANGER N1 N2 DISCONNECTED FROM LOAD G1 EQUIPMENT GROUND BUS NEUTRAL SENSOR

Page 6 MAIN BKR. LOAD POWER TRANSFORMER ØA, ØB, ØC BREAKER STATUS APPLY 1Ø INSTALL SINGLE ENDED, 3 WIRE SYSTEM 2 LOAD FIG. 7 SINGLE LINE DIAGRAM OF SWITCHGEAR DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. S POWER TO JUMPER FROM RESULTS REMARKS CLOSED OPEN A1 & G1 A2 & G2 MAIN TIMES OUT AND TRIPS FOR BREAKER GROUND FAULT TEST REFER TO PAGE 4 REPEAT THE ABOVE TEST FOR B PHASE & C PHASE FIG. 8 THREE LINE DIAGRAM INDICATING TEST POINTS NOTE: If the above test does not pass, utilize Integral Test Panel ➀ on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. FOR LARGE SEE FIG. 2 ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing. 2 Zone interlocking not wired A1 B1 C1 A2 B2 C2 MAIN DANGER G1 G2 EQUIPMENT GROUND BUS BUS 1

Page 7 MAIN BKR. 4 WIRE BREAKER STATUS APPLY 1Ø INSTALL NEUT. DISC. LINK ( )N ( )G POWER TRANSFORMER ( )N ( )G C1 C4 C5 D9 0 ØA, ØB, ØC NEUT. SINGLE ENDED, 4 WIRE RESIDUAL SYSTEM 2 3 WIRE C1 C4 C5 D9 0 4 WIRE LOAD 3 WIRE LOAD FIG. 9 SINGLE LINE DIAGRAM OF SWITCHGEAR DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. S POWER TO JUMPER FROM RESULTS REMARKS CLOSED OPEN A1 & N1 A2 & N2 NO TRIP POLARITY CHECK FOR NEUTRAL SENSOR CLOSED OPEN A1 & G1 A2 & G2 MAIN TIMES OUT AND TRIPS FOR BREAKER GROUND FAULT TEST REFER TO PAGES 4 & 5 A1 B1 C1 N1 MAIN FOR LARGE A2 B2 C2 N2 SEE FIG. 2 4W G2 EQUIPMENT GROUND BUS REPEAT ALL OF THE ABOVE TESTS FOR B PHASE & C PHASE, EXCEPT NEUTRAL SENSOR POLARITY CHECK IS ONLY REQUIRED ON ONE PHASE. NOTE: If any of the above tests do not pass, utilize Integral Test Panel ➀ on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. If No Trip test fails, reverse secondary connections at neutral sensor and repeat test. If test still fails, check to verify that connections on breaker are per figure 1. ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing. 2 Zone interlocking not wired BUS 1 G1 NEUTRAL SENSOR NEUTRAL DANGER FIG. 10 THREE LINE DIAGRAM INDICATING TEST POINTS

Page 8 DOUBLE ENDED, 4 WIRE SYSTEM, 2 SINGLE POINT GROUNDING T CONNECTION MAGNUM DS POWER TRANSFORMER POWER TRANSFORMER MAIN BKR. 52-2 MAIN BKR. TIE BKR. 52-T ØA, ØB, ØC ØA, ØB, ØC NEUT. NEUT. NEUT. SENSOR TIE BKR. 52-T NEUT. SENSOR MAIN BKR. 52-2 3 WIRE TN M2N M2G ( )N NEUT. SENSOR MAIN BKR. 3 WIRE ( )N ( )G 4 WIRE 2 1 TG M1G M1N 2 1 1 2 ( )G 4 WIRE 52-T 33-52-T 52-T a a M1GA M1NA 4 WIRE LOAD 4 WIRE LOAD 3 WIRE LOAD 3 WIRE LOAD M2NA M2GA TNA TGA * MAIN BKR. TIE BKR. 52-T MAIN BKR. 52-2 C1 C4 C5 D9 0 C1 C4 C5 D9 0 C1 C4 C5 D9 0 C1 C4 C5 D9 0 C1 C4 C5 D9 0 C1 C4 C5 D9 0 C1 C4 C5 D9 0 FIG. 11 SINGLE LINE DIAGRAM OF SWITCHGEAR NO OTHER GROUNDING OF NEUTRAL BUS SHOULD BE MADE UPSTREAM OR DOWNSTREAM FROM THIS POINT. BREAKER CELL SWITCH SHOWN WITH BREAKER IN THE TEST OR DISCONNECT POSITION. 2 Zone interlocking not wired

Page 9 DANGER DANGER DOUBLE ENDED, 4 WIRE SYSTEM, SINGLE POINT GROUNDING T CONNECTION MAGNUM DS DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. B3 A3 C3 N3 N1 A1 B1 C1 B4 A4 C4 N4 N2 G1 G2 EQUIPMENT GROUND BUS NEUTRAL NEUTRAL A2 B2 C2 BUS 2 BUS 1 DISCONNECTED FROM LOAD (OR OPEN) FIG. 12 THREE LINE DIAGRAM INDICATING TEST POINTS DISCONNECTED FROM LOAD (OR OPEN) BREAKER STATUS APPLY 1Ø INSTALL 52-T 52-2 S POWER TO JUMPER FROM RESULTS REMARKS CLOSED OPEN CLOSED OPEN A1 & N1 A2 & G2 MAIN TRIPS IF NO TRIP, CHECK CONN. AT "" AND "" CLOSED CLOSED OPEN OPEN A1 & N1 A2 & G2 TIE 52-T TRIPS, THEN MAIN TRIPS CLOSED CLOSED OPEN OPEN A1 & N1 A4 & G2 TIE 52-T TRIPS CLOSED OPEN CLOSED OPEN A3 & N3 A4 & G2 MAIN 52-2 TRIPS OPEN CLOSED CLOSED OPEN A3 & N3 A4 & G2 TIE 52-T TRIPS, THEN MAIN 52-2 TRIPS OPEN CLOSED CLOSED OPEN A3 & N3 A2 & G2 TIE 52-T TRIPS FOR BREAKER TEST REFER TO PAGES 4 & 5 REPEAT ALL OF THE ABOVE TESTS FOR B PHASE & C PHASE NOTE: If any of the above tests do not pass, utilize Integral Test Panel ➀ on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing.

Page 10 DOUBLE ENDED, 4 WIRE SYSTEM, MODIFIED RESIDUAL GROUND FAULT POWER TRANSFORMER POWER TRANSFORMER * * M1G M2G MN MN NEUT. SENSOR MAIN BKR. 52-2 NEUT. SENSOR MAIN BKR. MAIN BKR. 52-2 MAIN BKR. TIE BKR. 52-T ØA, ØB, ØC ØA, ØB, ØC NEUT. NEUT. MN NEUT. SENSOR TIE BKR. 52-T MN ( )N ( )G 4 WIRE 3 WIRE M1G M2G 3 WIRE ( )N ( )G 4 WIRE 52-2 52-T a a a 4 WIRE LOAD 3 WIRE LOAD 3 WIRE LOAD 4 WIRE LOAD MAIN BKR. TIE BKR. 52-T MAIN BKR. 52-2 C1 C4 C5 C1 C4 C5 C1 C4 C5 C1 C4 C5 C1 C4 C5 C1 C4 C5 0 D9 C1 C4 C5 FIG. 15 SINGLE LINE DIAGRAM OF SWITCHGEAR M2GA TG M1GA MAIN AND TIE BREAKERS MUST HAVE THE SAME FRAME AND SENSOR RATINGS, AND ONE OF THE THREE MUST BE NORMALLY OPEN. NO OTHER GROUNDING OF NEUTRAL BUS SHOULD BE MADE DOWNSTREAM FROM THESE TWO POINTS. TO DO SO WILL DEFEAT THE GROUND FAULT PROTECTION. POLARITY MUST BE AS SHOWN. 2 Zone interlocking not wired

Page 11 DANGER DOUBLE ENDED, 4 WIRE SYSTEM, MODIFIED RESIDUAL GROUND FAULT DANGER DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. DO NOT ATTEMPT TO TEST THIS EQUIPMENT WHILE IT IS ENERGIZED. DEATH OR SEVERE PERSONAL INJURY COULD RESULT. TURN OFF ALL POWER SUPPLYING THIS EQUIPMENT AND CHECK FOR VOLTAGE BEFORE TESTING. B4 A4 C4 N4 N1 A1 B1 C1 MAIN 52-2 MAIN B5 A5 C5 N5 N2 A2 B2 C2 FOR LARGE SEE FIG. 2 NEUTRAL G1 G2 EQUIPMENT GROUND BUS TIE 52-T NEUTRAL BUS 1 FOR LARGE SEE FIG. 2 BUS 2 FOR LARGE SEE FIG. 2 DISCONNECTED FROM LOAD (OR OPEN) FIG. 16 THREE LINE DIAGRAM INDICATING TEST POINTS DISCONNECTED FROM LOAD (OR OPEN) BREAKER STATUS APPLY 1Ø INSTALL 52-T 52-2 S POWER TO JUMPER FROM RESULTS REMARKS CLOSED OPEN CLOSED OPEN A1 & N1 A2 & N2 NO TRIP POLARITY CHECK FOR MAIN NEUTRAL SENSOR CLOSED CLOSED OPEN OPEN A1 & N1 A4 & N4 NO TRIP POLARITY CHECK FOR TIE 51-T NEUTRAL SENSOR CLOSED OPEN CLOSED OPEN A3 & N3 A4 & N4 NO TRIP POLARITY CHECK FOR MAIN 52-2 NEUTRAL SENSOR CLOSED OPEN CLOSED OPEN A1 & N1 A2 & G2 MAIN TRIPS CLOSED CLOSED OPEN OPEN A1 & N1 A4 & G2 TIE 52-T TRIPS CLOSED OPEN CLOSED OPEN A3 & N3 A4 & G2 MAIN 52-2 TRIPS OPEN CLOSED CLOSED OPEN A3 & N3 A2 & G2 TIE 52-T TRIPS FOR BREAKER TEST REFER TO PAGES 4 & 5 REPEAT ALL OF THE ABOVE TESTS FOR B PHASE & C PHASE NOTE: If any of the above tests do not pass, utilize Integral Test Panel ➀ on Digitrip Unit to verify correct trip unit operation. If trip unit tests properly, check to see if incoming lines and loads are disconnected and that test power supply and jumper connections are correct. If No Trip test fails, reverse secondary connections at neutral sensor and repeat test. If test still fails, check connections to Breaker at points B4 thru B9. ➀ For Digitrip trip units without an integral test panel, use a Digitrip Test Kit for trip unit testing.

Page 12 GROUND FAULT TEST RECORD FORM TEST DATE CIRCUIT BREAKER NO. RESULTS TESTED BY Ground Fault Test Record should be retained by those in charge of the building s Electrical Installation in order to be available to the authority having jurisdiction.

Page 13 GROUND FAULT TEST RECORD FORM TEST DATE CIRCUIT BREAKER NO. RESULTS TESTED BY Ground Fault Test Record should be retained by those in charge of the building s Electrical Installation in order to be available to the authority having jurisdiction.

Page 14 Printed in U.S.A./CCI This instruction booklet is published solely for information purposes and should not be considered all inclusive. If further information is required, you should consult Cutler-Hammer. Sale of product shown in this literature is subject to terms and conditions outlined in appropriate Cutler-Hammer selling policies or other contractual agreement between the parties. This literature is not intended to and does not enlarge or add to any such contract. The sole source governing the rights and remedies of any purchaser of this equipment is the contract between the purchaser and Cutler-Hammer. NO WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY, OR WARRANTIES ARISING FROM COURSE OF DEALING OR USAGE OF TRADE, ARE MADE REGARDING THE INFORMATION, RECOMMENDATIONS AND DESCRIPTIONS CON- TAINED HEREIN. In no event will Cutler-Hammer be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or otherwise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to damage or loss of use of equipment, plant or power system, cost of capital, loss of power, additional expenses in the use of existing power facilities, or claims against the purchase or user by its customers resulting from the use of the information, recommendations and descriptions contained herein. Cutler-Hammer 221 Heywood Road Arden, NC 28704