GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT

Similar documents
GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016

Metrolinx Electrification Project

Metrolinx Electrification Project

CREATING CONNECTIONS IN THE CITY OF WATERLOO

Appendix 10. Implementation of Electrification Options. December 2010

CREATING CONNECTIONS IN WATERLOO REGION

CREATING CONNECTIONS IN THE CITY OF KITCHENER

Mississauga Bus Rapid Transit Preliminary Design Project

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

Public Information Centre

Scarborough Transit Planning

CREATING CONNECTIONS IN EAST GWILLIMBURY

Attachment 5 Eglinton West LRT Planning and Technical Update

CREATING CONNECTIONS IN RICHMOND HILL

Mr. Vince Mauceri General Manager Transportation Operations and Technology

PROJECTS $500K AND OVER FOR 2012

CONNECTING THE REGION

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

TORONTO TRANSIT COMMISSION REPORT NO.

Developing Toronto s Transit Network Plan to 2031

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016

CREATING CONNECTIONS IN AURORA

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

GO Transit s deliverable: the 2020 Service Plan

CONNECTING THE REGION

TRANSFORMING THE WAY OUR REGION MOVES

New McNicoll Bus Garage Public Open House

PROJECT BACKGROUND 3

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

CPG is pleased to report the following accomplishments this quarter:

GO RER INITIAL BUSINESS CASE SUMMARY

Metrolinx Electrification Project

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

Welcome. Green Line in Your Community

Proposed Dounreay - Mybster 275 kv / 132 kv

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.

welcome to the BC Hydro community open house

Appendix 6. Electrification Systems Technology Assessment. December 2010

Developing Toronto's Transit Network Plan: Phase 1

Powering Sydney s Future

JCP&L Verbatim Response to Middletown Township s Questions

Confederation Line West Queensway Terrace North. May 27, 2017

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

Welcome to Open House #5 Scarborough Rapid Transit

Proposed Parking Strategy for Existing New Urbanism Areas. Committee of the Whole (Working Session) December 3, 2013

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) PLEASE SIGN IN

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO.

Panel Discussion: Planning for Today and Tomorrow

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims

Yonge Relief Network Study (YRNS)

SCARBOROUGH RAPID TRANSIT ENVIRONMENTAL PROJECT REPORT CHAPTER 2 PROJECT DESCRIPTION. Project Description

F.P.O. Yonge subway extension: concept plan and profile. Langstaff/Longbridge. Royal Orchard Station. Clark Station. Steeles Station.

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

WELCOME. New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA)

Mystic to Woburn Line Project. Town of Winchester Board of Selectmen Lincoln School Auditorium February 11, 2016

Peninsula Corridor Electrification Project (PCEP)

5 New GO Stations in York Region to Support Regional Express Rail

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

INTEGRATED GO RER- SMARTTRACK OPTIONS

City of Palo Alto (ID # 6416) City Council Staff Report

Great Western electrification project Frequently asked questions

Caltrain Modernization EMU Procurement

Green Line LRT: Beltline Recommendation Frequently Asked Questions

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY

Public Information Session June 2, Transportation Planning Section City Planning Division Toronto Transit Commission

Bayshore Station to Moodie Drive LRT Extension Environmental Assessment Studies. Public Meeting 22 March 2017

East Turnaround. Access to Ayreswood Avenue would be restricted to right-in/rightout movements under the proposed Rapid Transit plan.

EX29.1 REPORT FOR ACTION. SmartTrack Project Update and Next Steps SUMMARY

Green Line LRT: Beltline Segment Update April 19, 2017

Bayshore Station to Moodie Drive LRT Extension Environmental Assessment Studies. Advisory Committee Meeting June 2017

Compatibility Between Electric Trains and Electrification Systems

Electromobility for Heavy-Duty Vehicles. Long Beach Convention Center, May 15-17, 2012 ACT Expo 2012

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Passenger Rail Solar Electrification: A Primer. Oregon Department of Transportation Rail Division. June 2009

Etobicoke-Finch West Light Rail Transit (LRT) Planning Study for a Transit Project Assessment

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

Energy Technical Memorandum

GTA West Corridor Planning and EA Study Stage 1

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

Chair and Members, The Etobicoke York Community Council. Mark Sraga, Director and Deputy Chief Building Official

Harlem Avenue between 63 rd and 65 th

SOUTHWEST CALGARY RING ROAD (SWCRR)

Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to

Bohn to Kettle River Transmission Project

South West Wales Best Practice Club with ABC Electrification Swansea 7 th July 2015

Newmarket GO Station Mobility Hub Study. Open House #1 MAY 18, 2017

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

4.0 TIER 2 ALTERNATIVES

Appendix F-1 Description of the Long-Term Alternatives

Confederation Line West Alignment Improvement. September 21, 2016

Transcription:

GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT ASSESSMENT PROCESS Public Meeting Round #3 June July 2017

What We ve Done - Electrification 15 public meetings held as part of Consultation Round #1 - February/March 2016. Summary Report posted online. 13 public meetings held as part of Consultation Round #2 - November 2016. Summary Reports posted online. Completed Environmental Impact Assessment Studies. Draft Reports posted online. Prepared Draft Environmental Project Report. Held numerous meeting with municipalities, stakeholders, and utilities. Ongoing engagement with regulatory authorities, indigenous communities and community groups.

Benefits of Electrification A faster, more attractive service: o Electric trains can accelerate faster and stay at top speed for longer, saving time for customers. o By attracting additional riders, frequent electric train service reduces road congestion and reduces greenhouse gas emissions from automobiles. o Regenerative braking puts energy back into the system. A more efficient, reliable service: o More frequent service reduces reliance on scheduled trips and increases the number of available seats. o Lower operating and maintenance train costs; we can offer more trips with electric service than diesel service. Other supporting benefits: o Reductions in rail greenhouse gas emissions, which form a minor part of the regional emissions total. o Improved local air quality. GREENHOUSE GASES ANNUAL DAILY TRAFFIC CONGESTION CLEAN AIR DAILY NOISE FROM TRAINS RIDERSHIP DAILY IMPROVED FREQUENCY / QUICKER TRIPS

Electrification Project Scope Union Station Rail Corridor UP Express Union Station to Don Yard Layover. o No Traction Power Facilities. Lakeshore West Corridor From just west of Bathurst St. (Mile 1.20) to Burlington GO Station. o 2 Hydro One Taps, 2 Traction Power Substations, 2 Switching Stations. o Mimico 25kV Feeder Route. Kitchener Corridor Highway 427 to Bramalea. o 1 Paralleling Station. o Bramalea 25kV Feeder Route. Barrie Corridor Parkdale Junction to Allandale GO Station. o 1 Hydro One Tap, 1 Traction Power Substation, 1 Switching Station, 2 Paralleling Stations. o Allandale 25kV Feeder Route. Stouffville Corridor Scarborough Junction (off Lakeshore East Corridor) to Lincolnville GO Station. o 1 Hydro One Tap, 1 Traction Power Substation, 2 Paralleling Stations. o Scarborough 25kV Feeder Route. Lakeshore East Corridor Don Yard Layover to Oshawa GO Station. o 1 Hydro One Tap, 1 Traction Power Substation, 2 Switching Stations, 1 Paralleling Station. o Scarborough 25kV Feeder Route. By the numbers: Approximately 250 kms of corridor to be electrified, including: 5 Hydro One Tap Locations 5 Traction Power Substations 5 Switching Stations 6 Paralleling Stations 4 25kV Feeder Routes 1. The portion of the Kitchener Corridor from Strachan Ave. to the airport spur (at Highway 427) was previously assessed/approved as part of the Metrolinx UP Express Electrification EA (June 2014).

Power Supply Hydro One Metrolinx and Hydro One are co-proponents for the Electrification Transit Project Assessment Process. Electrical power will be supplied by Hydro One s power grid through tap connections from existing 230kV transmission lines and transformer stations. The infrastructure required for the five Hydro One Tap connections (e.g., new towers, transformers) are being assessed as part of the TPAP. How the System Will Work Traction power substations transform the voltage from 230kV to the appropriate voltage (25 kv). Distribution of power along rail corridors via Overhead Contact System (OCS), feeders and gantries. To ensure reliable power supply, switching stations and paralleling stations are needed.

Traction Power Supply Transmission Tap Structures The point at which electric power is tapped from the existing Hydro One power source. 230kV Transmission Connections New tap structures will draw electrical power from Hydro One s existing 230kV grid. From there, the power will be routed to new Metrolinx Traction Power Substations via 230kV high voltage connections routes (either aerial or underground). Traction Power Substation (TPS) A facility that transforms the utility supply voltage from 230kV to 25kV for distribution to the trains via Overhead Contact System (OCS). Approximate minimum footprint required: 75m x 50m (plus access road). Gantries The 25 kv feeder wires from the TPS will be connected to the OCS with the help of gantries. The main gantry (also referred to as the catenary feeding gantry) is the one parallel to the track.

Traction Power Distribution Switching Station (SWS) Switching stations are traction power facilities that are required approximately mid-way between Traction Power Substations in order to split the electrical sections. Paralleling Station (PS) This type of traction power facility contains an autotransformer which helps support the OCS voltage in the electrified system. Feeder Routes Feeders are cables/wires that carry power from a Traction Power Facility to the OCS via gantries. These will be routed either aerially or underground in duct banks. Feeder routes will be used where it is not possible/feasible to locate a TPS directly adjacent to Hydro One infrastructure, or where a TPS is not located in close proximity to the Metrolinx rail corridor.

Overhead Contact System (OCS) OCS is a series of overhead wires which supply electricity to the electric trains. Power is supplied to the train through the pantograph which makes contact with the OCS. OCS is supported by cantilever and portal structures. Maximum distance between OCS supports is approximately 65 m. Cantilevers: one foundation required Portals: foundations to be installed on either side of tracks

Bridge Modifications Bridge Barriers Barriers are required on overhead bridges to ensure safety of the energized equipment; height of the barrier is approximately 2 metres; barrier will extend beyond any electrified wire(s) running under the bridge to ensure safety. OCS Attachments Used for support of OCS wires in situations with restricted clearance such as tunnels and overhead bridges. Vertical clearance In instances where overhead bridges do not meet the vertical clearance requirements for electrification engineering solutions being explored including: raise or replace the bridge, lowering the tracks, or modifying OCS to fit within the existing clearance / opening (if possible). Other Bridge Modifications Minor bridge modifications (e.g., flash plates) will be required on some bridges to ensure that the electrification system passes safely underneath the bridge.

Electromagnetic Fields (EMF) / Electromagnetic Interference (EMI) Effects & Mitigation As per Health Canada: On a daily basis, we are exposed to electric and magnetic fields (EMFs) generated by household wiring, lighting, and electrical appliances. EMFs are invisible forces that surround electrical equipment, power cords and power lines. You cannot see or feel EMFs. Every time you use electricity and electrical appliances, you are exposed to EMFs at extremely low frequencies. EMFs are strongest when closest to the source. As you move away from the source, the strength of the fields fades rapidly. Based on the EMI/EMF assessment completed as part of the TPAP, no adverse EMI effects are anticipated due to the installation/operation of the electrified GO Transit system. Magnetic Field Strength in milligaus (mg) Electrified Railways in North America and Europe Magnetic Field Strength measured approximately 18 m from rail Right-of-Way North America (Example A) North America (Example B) Europe Avg. Max. Avg. Max. Avg. Max. 3.4mG 21.7mG 1.9-4.5mG 11.4mG 1.7 7.2mG 8.7 24mG Mitigation Measures to be considered: Further testing and verification will be carried out during the detailed design phase once the rolling stock is established. Confirm background EMI/EMF measurements during detailed design; Implement an Electromagnetic Compatibility (EMC) Control Plan; Grounding and shielding measures.

Electrification TPAP Next Steps 2016 Stakeholder Engagement Baseline data collection Impact Assessment Public Meetings Round # 1 Public Meetings Round # 2 2017 Notice of Commencement Public Meetings Round # 3 Notice of Completion Statement of Completion 2018-2025 Procure Design and Build

Share Your Thoughts Online: www.gotransit.com/electrification E-mail: electrification@metrolinx.com Phone: 416.869.3200 Comment forms: Please fill out a comment form and leave it with the project team. We want to hear from you! Join the conversation:

Allandale Tap/Traction Power Substation The Allandale Tap location has been revised since November 2016 based on further discussion with Hydro One and advancements in engineering design. Previous site is being carried as an alternative siting location; final site and configuration will be determined during detailed design. Revised site is currently zoned Light Industrial, General Commercial and Highway Industrial. Vegetation communities not considered sensitive or significant and effects from facility installation/construction can be mitigated. Mitigation measures may include: work timing outside the breeding bird season, installation and maintenance of sediment and erosion controls, detailed Species at Risk surveys during detailed design. No cultural heritage features were identified on the site. A portion of the site requires a Stage 2 Archeological Assessment.

Noise & Vibration Assessment A Noise and Vibration Study was undertaken as part of the GO Rail Network Electrification TPAP to examine the noise & vibration effects of future electrified RER service levels. When is mitigation required? There are two key protocols in place that Metrolinx follows: The 1995 draft Transit Noise and Vibration Protocol from the Ontario Ministry of Environment and Climate Change (MOECC)/GO; and The 2013 Noise Guideline (NPC-300) from the MOECC (applies to stationary noise sources including train stations, e.g., announcements at the station) Noise The 1995 draft MOEE/GO Transit Noise Protocol stipulates that: Mitigation must be considered if the project is expected to cause a 5 db increase or greater in the average noise (referred to as Leq ) relative to the existing noise level or the MOE objectives of 55 dba for daytime and 50 dba for night-time Noise mitigation is required if it is administratively, operationally, economically and technically feasible Noise barriers are considered technically feasible if they can reduce noise by at least 5 db. Mitigation measures were investigated for all receptors with a significant adjusted noise impact (i.e., 5 db increase or greater) in accordance with the MOEE/GO Draft Protocol

Noise & Vibration Assessment Vibration There are many factors that influence vibration levels, including: Soil type and conditions Rail condition Wheel condition Speed of vehicle Weight of vehicle Suspension system of vehicle Track bed (concrete, ballast, etc.) Distance between source and receiver Vibration protocols in place: The Ontario Ministry of Environment and Energy (MOEE) and GO Transit have a Draft Protocol for Noise and Vibration Assessment that Metrolinx follows. The Protocol indicates that if vibration levels of any project exceed the higher of the existing vibration level, or 0.14 mm/s by 25% or more, vibration mitigation needs to be investigated. Measuring Vibration: Vibration is measured in terms of particle velocity in millimetres per second (mm/s). Vibration can be felt by humans at levels as low as 0.10 mm/s and building damage (cosmetic or structural) occurs at levels about 50 times higher than this around 5 mm/s.

Potentially Impacted Heritage Properties Provincially Important Heritage: Union Station (Toronto) Credit River Bridge (Mississauga) Aurora GO Station (Aurora) Locally Important Heritage: Islington Avenue Bridge (Toronto) Markham GO Station (Markham) Maple GO Station (Vaughan) Newmarket GO Station (Newmarket) Bradford GO Station (Bradford West Gwillimbury) Sixteen Mile Creek and Cross Avenue Bridge (Oakville) Bronte Creek Bridge (Oakville) Highland Creek Bridge (Toronto) Humber River Bridge (Toronto) Credit River Bridge Aurora GO Station

Cultural Heritage Cultural Heritage Screening Report Prepared to identify known or potential cultural heritage resources (CHRs) that may be affected by Electrification. Cultural Heritage Evaluation Reports (CHERs) Based on the CHIA, CHERs conducted to confirm cultural heritage value of potential CHRs and to identify associated heritage attributes. Heritage Impact Assessments (HIAs) Undertaken where there are any impacts to known Provincial Heritage Properties (PHPs) or Provincial Heritage Properties of Provincial Significance (PHPPS). 10/06 Properties (Provincial Heritage Properties of Provincial Significance) are properties found to have cultural heritage value or interest of provincial significance as evaluated using the criteria found in Ontario Heritage Act O. Reg. 10/06. 9/06 Properties are properties of cultural heritage value or interest as evaluated using the criteria found in Ontario Heritage Act O. Reg. 9/06 (local significance). Modifications to Heritage Properties 1.OCS attachments (GO Stations and bridges) 2.Flash plate attachments (bridges) 3.Bridge barriers (overhead bridges)

Archaeology Assessments A Stage 1 Archaeological Assessment (Impact Assessment) was prepared to describe the results of all background research and property inspection fieldwork conducted. Prior to construction or other site alteration Stage 2 Archaeological Assessments will be completed, where recommended. Mitigation Measures Mitigation will be based on the results of the Stage 2 assessments and will be determined through further Stage 3 archaeological assessment and subsequent Stage 4 mitigation assessments, if required. Stage 2 Archaeological Assessments will be completed for the following sites as part of the TPAP, where possible and where Permission to Enter (PTE) access is granted: Burlington Tap/TPS Bramalea PS Allandale Tap Gilford PS Barrie Rail Corridor West of Minet s Point Road in the City of Barrie Scarborough Tap/TPS Unionville PS Durham SWS Stouffville Corridor, Scarborough 25 kv Feeder Route, view from Eglinton Avenue East bridge looking Northwest Stage 2 Archaeological Assessments have already been completed for the following sites: Mimico Tap/TPS Newmarket SWS Lincolnville PS Based on the results of the completed Stage 2 Archaeological Assessments, no further assessment is required. Barrie Corridor, view from Mapleview Drive crossing looking Northwest