Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

Similar documents
East. Georgia Integrated Transmission System (ITS) Jointly Planned ITS. Dalton Utilities. GTC (Georgia Transmission Corporation)

East. Georgia Integrated Transmission System (ITS) GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA)

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

Southeastern Regional Transmission Planning Process 10 Year Preliminary Expansion Plan Meeting. June 24, 2009

Southern Company Transmission Active OATT Interconnection Agreements

Table of Contents. Section YEAR EXPANSION PLAN EAST REGION. Section YEAR EXPANSION PLAN WEST REGION

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

2011 SERTP Annual l S E S RTP T P S u S mmit 1

2010 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 9:00 AM 3:00 PM

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting

SERTP nd Quarter Meeting

2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting

West. Coordinated Planning. Coordinated Planning. PS (PowerSouth Energy Cooperative) SMEPA (South Mississippi Electric Power Association)

Southeastern Regional Transmission Planning (SERTP) PRELIMINARY 10 YEAR TRANSMISSION EXPANSION PLANS

Southeastern Regional Transmission Planning (SERTP) PRELIMINARY 10 YEAR TRANSMISSION EXPANSION PLANS

Generation Deactivation Notification Update

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Southeastern Regional Transmission Planning (SERTP)

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Falcon-Midway 115 kv Line Uprate Project Report

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

VACAR 2015 SUMMER PEAK RELIABILITY STUDY

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Sub Regional RTEP Committee - Southern. August 19, 2011

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Appendix B. Summary of Changes to the Year Assessment

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA MEMBERSHIP REPORT

Sub-Regional RTEP Committee PJM South

2016 SPP Transmission Expansion Plan Project List Kansas Projects

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

West. PS (PowerSouth Energy Cooperative) SMEPA (South Mississippi Electric Power Association) Southern Company Transmission

West. PS (PowerSouth Energy Cooperative) SMEPA (South Mississippi Electric Power Association) Southern Company Transmission

MTEP13 SPM #2- Central Region. March 25, 2013

Sub Regional RTEP Committee Mid-Atlantic

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Sub Regional RTEP Committee Western Region ATSI

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

West. Coordinated Planning. PS (PowerSouth Energy Cooperative) SMEPA (South Mississippi Electric Power Association) Southern Company Transmission

Sub Regional RTEP Committee Mid-Atlantic

SPP Notification to Construct

Pacific Gas and Electric Company s Revised 2016 Annual Progress

South Carolina Regional Transmission Planning. Stakeholder Meeting. Web Conference

SERTP Southeastern Regional Transmission Planning

Appendix D Black Hills Project Summary

Sub Regional RTEP Committee Mid-Atlantic

Black Hills Project Summary

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Chapter 7 - Appendix A

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

Sub Regional RTEP Committee Mid-Atlantic

Pacific Gas and Electric Company s 2013 Annual Progress Report

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

Sub Regional RTEP Committee Mid-Atlantic

Gateway South Transmission Project

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

PG&E s 2012 Request Window Proposals

2013 ANNUAL PROGRESS REPORT

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

SPP Notification to Construct

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

APPENDIX E: Project Need and Description

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

Key to Status Fields in the Project List

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

THE AMERICAN LEGION AUXILIARY DEPARTMENT OF GEORGIA

Pacific Gas and Electric Company s Revised 2015 Annual Progress

SPP Notification to Construct

New Jersey State Report

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

Smart Grid Reliability Research

Georgia 24,403 27,238 26,928-2, % -2, %

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Georgia 30,325 26,345 27,946 3, % 2, %

KEY. Key to Status Fields in the Project List

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

South Dakota 890 Study

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transcription:

10 Year Transmission Expansion Plan

Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised due to changes in assumptions. This presentation does not represent a commitment to build for projects listed in the future.

Input Assumptions for 10 Year Expansion Plan

2010 Regional Generation Assumptions Dahlberg Conasauga Hancock CC Rocky Mtn Warren Co Bio McDonough Tenaska Wansley Vogtle Kemper Central AL Piedmont Bio Washington Co CT Moselle Harris CC West Georgia Franklin CC Lee Road Warthen CT SMARR CC SOWEGA McIntosh Baconton East Bainbridge Farley Existing Generation Future Generation

Generation Assumptions for the 2010 Transmission Expansion Planning Process Year Site MW Year Site MW 2010 GTC Dahlberg CT -160 Lee Road CT -100 Rocky Mountain 45 Wansley CC7 572 Warthen CT -600 West GA Gen 150 SoCo Dahlberg CT 292 Exelon Heard CT 942 Franklin 1-559 2011 GTC Dahlberg CT -100 East Bainbridge -72 Franklin 2 625 Lindsay Hill CC 205 McDonough 2 Coal -51 Rocky Mountain 44 Warthen CT 390 PS McIntosh 4 & 5 448 SoCo Farley 1 Uprate 35 Franklin 2-625 Harris 1-627 Wansley CC7-572 McDonough 2 Coal -200

Generation Assumptions for the 2010 Transmission Expansion Planning Process Year Site MW Year Site MW GTC Fitzgerald Bio McDonough 1 Coal 55-49 2013 SoCo Central Alabama CC McDonough CC6 885 841 SMEPA Moselle 150 GTC East Bainbridge 78 2012 SoCo Conasauga Farley 2 Uprate -620 35 Lee Road CT SOWEGA 50 90 McDonough 1 Coal -202 McDonough CC4 841 McDonough CC5 841 Piedmont Bio 50 2014 SoCo Warren Co Bio Baconton CT Dahlberg CT Kemper IGCC 100-197 -292 600

Generation Assumptions for the 2010 Transmission Expansion Planning Process Year Site MW Year Site MW GTC Dahlberg CT 300 Dalton Vogtle 4 16 East Bainbridge -78 GTC Vogtle 4 330 2015 Lee Road CT SMARR CC -50 605 2017 MEAG Wansley CC6 Vogtle 4 561 250 SOWEGA -90 SoCo Vogtle 4 504 Washington Co CT 734 Wansley CC6-561 Dalton Vogtle 3 16 GTC Dahlberg CT -300 2016 Vogtle 3 Warthen CT 330-70 MEAG SoCo Vogtle 3 Vogtle 3 250 504

Generation Assumptions for the 2010 Transmission Expansion Planning Process Year Site MW 2018 N/A N/A N/A PS McIntosh 6 187 2019 SoCo Hancock CC1 840 Harris 2-628 2020 SoCo Hancock CC2 840

Generation Assumptions for the 2010 Transmission Expansion Planning Process PTPs preserved through the planning horizon Starting in Year Site MW PTPs ending within the planning horizon Year Site MW 2010 PTP Dahlberg 75 2010 2014 PTP Scherer 3 42 2010 Franklin 535 2010 2014 Miller 164 2010 Harris 1 584 2011 Bowen 50 2010 Hillabee 700 2011 Wansley 155 2010 Scherer 3 235 2015 Miller 103 2010 Scherer 4 850 2010 Lindsay Hill 300 2011 Lindsay Hill 200 2012 Dahlberg 180 2015 Vogtle 103 2016 Vogtle 103

10 Year Transmission Expansion Plan The in-service date of each project is June 1 st of the stated project year unless otherwise specified The need date of each project is the same as the in-service date unless otherwise specified

East Region Georgia Integrated Transmission System (ITS) Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Jointly Planned ITS Southern Company Transmission

Expansion Item ITS-1a Factory Shoals Create a 230 / 115 kv network substation at Factory Shoals. Install one 230 / 115 kv 300 MVA transformer. Tap the Adamsville Douglasville 230 kv line from Buzzard Roost for 230 kv source using existing line. Create a 115 kv network station by breakering up the Douglasville Greenbriar 115 kv line. 2011 ITS-1a

Expansion Item ITS-1b Factory Shoals Install three 230 kv breakers at Buzzard Roost, looping in the Adamsville- Douglasville 230 kv line, with a third terminal serving Factory Shoals. Tap the Adamsville Douglasville 230 kv line from Buzzard Roost for 230 kv source using existing line. 2011 ITS-1b Alleviates the overload of Gordon Road Hightower 115 kv T.L., Adamsville Greenbriar 115 kv T.L. and the Douglasville 230 / 115 kv transformer given various contingencies.

Factory Shoals 2011 ITS-1 Plt. Jack McDonough Douglasville Problem: Loss of the Groover Lake segment of the Douglasville Greenbriar 115kV line overloads the East Point Gordon Rd. Jct Groover Lake 115kV Factory Shoals to Mableton, Jack Mac-West Mar.115 Fact Shls Jct Gordon Rd. to Jack Mac.- West Mar. 115 Gord Rd. Jct 230kV Hightower. Jct Thornton Road Buzzard Roost Solution: Breaker up Buzzard Roost 230kV Add 230kV line Thornton Rd. to Factory Shoals. Add 230/115 autobank and 115 breakers at Factory Shoals. Adamsville Greenbriar Post Road 230kV Boat Rock Bakers Ferry East Point

Expansion Item ITS-2 Arkwright Gordon #1 115 kv Transmission Line Rebuild the Arkwright Gordon #1 115 kv Transmission Line (23.6 miles) with 795 ACSR conductor at 100 C. 2011 ITS-2 This line becomes thermally overloaded given multiple contingencies in 2011.

Arkwright Gordon #1 115 kv T.L. 2011 ITS-2 Arkwright Gordon

Expansion Item ITS-3 Kraft McIntosh 230 kv T.L.s Rebuild 16 miles along the Kraft McIntosh Black and White 230 kv T.L.s with 1622 ACCR/TW. 2012 ITS-3 The loss of either Kraft McIntosh 230 kv T.L. will overload the parallel 230 kv T.L.

Kraft McIntosh 230 kv T.L.s 2012 ITS-3 The loss of one Kraft McIntosh 230 kv T.L. overloads the parallel 230 kv line. McIntosh Reconductor the Kraft McIntosh 230 kv Black & White transmission lines with 1622 ACCR/TW. Kraft

Expansion Item ITS-4 McIntosh Blandford Meldrim 230 kv T.L.s Reconductor 18.2 miles along the McIntosh Blandford Meldrim Black and White 230 kv T.L.s. 2014 ITS-4 The loss of either McIntosh Meldrim 230 kv T.L. will overload the parallel 230 kv T.L.

McIntosh Blandford Meldrim 230 kv T.L.s 2014 ITS-4

Expansion Item ITS-5 Boulevard 230 / 115 kv Substation Install a 230 / 115 kv transformer at the existing Boulevard 115 kv substation. Rebuild the Boulevard Dean Forest 115 kv double circuit line with 2-795 ACSR at 230 kv specifications. Operate one circuit at 115 kv and the other at 230 kv. 2015 ITS-5 The loss of one of the Deptford Kraft 115 kv T.L.s causes the other line to become overloaded.

Boulevard 230 / 115 kv Substation 2015 ITS-5

Expansion Item ITS-6a East Walton 500 / 230 kv Project Construct a new 500 /230 kv Substation at East Walton. Construct a new Rockville 500 kv Switching Station. Construct a new 500 kv T.L. from the new Rockville 500 kv Switching Station to the new East Walton 500 / 230 kv substation. Construct 230 kv T.L. from East Walton to Jacks Creek 2015 ITS-6a

Expansion Item ITS-6b East Walton 500 / 230 kv Project Construct a new 230 kv T.L. from East Walton to the new Bostwick Switching Station. Construct a new 230 kv T.L. from Bethabara to East Walton. 2015 ITS-6b The loss of the Klondike Scherer 500 kv T.L. will thermally overload the Klondike O Hara 500 kv T.L.

East Walton 500 / 230 kv Project 2015 ITS-6

Expansion Item ITS-7 Sharon Springs 230 / 115 kv Substation Install a 230 / 115 kv transformer at the existing Sharon Springs 115 kv distribution substation. Construct a new 6.6 mile, 230 kv transmission line from Cumming to Sharon Springs (1351 ACSR at 100 ºC. 2015 ITS-7 The loss of the Hopewell Brandywine segment of the Hopewell Suwanee 115 kv T.L. overloads the Suwanee Old Atlanta Road segment of the line and vice versa.

Sharon Springs 230 / 115 kv Substation 2015 ITS-7

Expansion Item ITS-8 Center Primary Commerce 115 kv T.L. Reconductor 16.2 miles of 115 kv T.L. from Center Primary to Commerce Primary. 2016 ITS-8 The loss of the 230 / 115 kv transformer at Middle Fork causes the Center Primary Commerce Primary 115 kv T.L. to become overloaded.

Center Primary Commerce 115 kv T.L. 2016 ITS-8

Expansion Item ITS-9 Goshen Waynesboro 115 kv T.L. Reconductor 18.7 miles along the Goshen Waynesboro 115 kv T.L. with 1033 ACSR. 2016 ITS-9 The loss of the Wilson Waynesboro 230 kv T.L., with Hatch Unit #1 offline, will overload the Goshen Waynesboro 115 kv T.L.

Goshen Waynesboro 115 kv T.L. 2016 ITS-9 Goshen The loss of the Wilson Wayensboro 230 kv T.L. causes the Goshen Waynesboro 115 kv T.L. to become overloaded Reconductor the Goshen Waynesboro 115 kv T.L. (18.7 miles) with 1033 ACSR Waynesboro

Expansion Item ITS-10 Thomson Primary Vogtle 500 kv T.L. Construct a 500 kv line from Plant Vogtle to the new Thomson Primary 500 / 230 kv substation. 2016 ITS-10 This project is to support the expansion of Plant Vogtle.

Thomson Primary Vogtle 500 kv T.L. 2016 ITS-10 Thomson Primary Construct new Thomson - Vogtle 500 kv T.L. (50 miles) Vogtle

Expansion Item ITS-11 Corn Crib 230 / 115 kv Substation Construct the Corn Crib 230 / 115 kv substation, looping the Thomaston Yates 230 kv T.L. and the Thomaston Yates 115 kv T.L.. Terminate the Yates Newnan #3 Junction Transmission Line at Corn Crib. 2017 ITS-11 The loss of either end of the Thomaston Yates 115 kv T.L. will overload the opposite end. This project also provides voltage support along the Thomaston Yates 115 kv T.L.

Corn Crib 230 / 115 kv Substation 2017 ITS-11

Corn Crib 230 / 115 kv Substation 2017 ITS-11 Corn Crib Thomaston Yates Newnan Primary

Expansion Item ITS-12 Dorchester 230 kv Project Construct a 45 mile 230 kv T.L. from Dorchester to West Brunswick. Install a second 230 / 115 kv transformer and 230 kv capacitor bank at Dorchester. Reconductor Dorchester Little Ogeechee 230 kv T.L. 2017 ITS-12 This project is to alleviate multiple thermal overloads for various contingencies in the Savannah, Georgia area.

Dorchester 230 kv Project 2017 ITS-12 Little Ogeechee Dorchester The loss of the McCall Road Thalmann 500 kv T.L. causes multiple 115 kv transmission lines in the Hinesville area to exceed their thermal ratings West Brunswick Construct the Dorchester West Brunswick 230 kv T.L. Install a 2 nd 400 MVA 230 / 115 kv transformer at Dorchester. Construct the Dorchester Walthoursville 115 kv line section. Reconductor the Dorchester Little Ogeechee 230 kv T.L. with 2-1351 ACSR.

Expansion Item ITS-13 Lawrenceville Winder 230 kv T.L. Rebuild approximately 15.3 miles along the Lawrenceville Winder 230 kv T.L. with 1351 ACSS at 170 ºC. 2017 ITS-13 The loss of the Norcross end of the Lawrenceville Norcross 230 kv T.L. will overload the Lawrenceville Old Freeman Mill section of the Lawrenceville Winder 230 kv Transmission Line.

Lawrenceville Winder 230 kv T.L. 2017 ITS-13

Expansion Item ITS-14 South Metro Phase-III Project Rebuild the existing O'Hara Bonanza Hampton McDonough 115 kv T.L. with double circuit with ACSR 1351 at 230 kv specifications. Create a new 230 kv circuit from O'Hara to McDonough and add a 230 / 115 kv, 400 MVA transformer at McDonough Construct a 115 kv T.L. between the Peeksville and Ingram substations. Project alleviates multiple thermal overloads in the metro Atlanta area. 2018 ITS-14

South Metro Phase III Project 2018 ITS-14 O Hara McDonough Hampton Ingram Peeksville

Expansion Item ITS-15 South Coweta Yates 115 kv Transmission Line Reconductor approximately 19 miles consisting of multiple sections of the South Coweta Yates 115 kv T.L. 2018 ITS-15 For the loss of either end of the South Coweta Yates 115 kv T.L., with Yates Unit #3 offline, sections of the South Coweta Yates 115 kv T.L. become overloaded.

South Coweta Yates 115 kv T.L. 2018 ITS-15

Expansion Item ITS-16 Hopewell McGrau Ford 2 nd 230 kv Line Construct a second 230 kv Transmission Line between McGrau Ford and Hopewell. 2018 ITS-16 This project alleviates thermal overloads on the Norcross Ocee 230 kv T.L. and provides additional voltage support for the North Georgia area.

Hopewell McGrau Ford 2 nd 230 kv 2018 ITS-16 McGrau Ford Construct a second 230 kv T.L. between McGrau Ford and Hopewell Hopewell Solution needed to provide voltage support in the North Georgia area and serve load growth between the Hopewell and Norcross substations

Expansion Item ITS-17 Branch West Milledgeville 230 kv T.L. Bundle the Branch West Milledgeville 230 kv T.L. with 2-1351 ACSR at 100 ºC. 2019 ITS-17 With Hatch Unit #1 offline, the loss of the Bonaire Scherer 500 kv T.L. causes the Branch West Milledgeville 230 kv T.L. to become overloaded.

Branch West Milledgeville 230 kv T.L. 2019 ITS-17

Expansion Item ITS-18 East Walton South Hall 500 kv Transmission Line Construct a 500 kv T.L. from South Hall to East Walton. 2020 ITS-18 Required to support generation expansion in the central Georgia area.

East Walton South Hall 500 kv T.L. 2020 ITS-18 South Hall Construct a 500 kv line from the South Hall 500 / 230 kv substation to the East Walton 500 / 230 / 115 kv substation. This project is required to support the expected generation expansion plan in the Wallace Dam area. East Walton

Questions?