COOPER POWER SERIES. 200 A loadbreak junction 15 and 25 kv class installation instructions. Loadbreak Connectors MN650015EN

Similar documents
COOPER POWER SERIES. 600 A 15, 25, and 35 kv Class Cleer Loadbreak Bushing Insert Installation Instructions. Loadbreak/Deadbreak Connectors MN650016EN

COOPER POWER SERIES. 200 A Fused Loadbreak Elbow Connector Replacement Fuse Installation Instructions. Fusing Equipment MN132021EN

Effective November 2016 Supersedes February 2012 (S )

Effective November 2016 Supersedes September 1998 (S )

COOPER POWER SERIES. ELSG Full-Range Current-Limiting Fuse Re-Fusing Instructions. Fusing Equipment MN132017EN

COOPER POWER SERIES. Testing a motor capacitor on a voltage regulator procedure instructions. Voltage Regulators MN225064EN

COOPER POWER SERIES. Edison Modular Fuse (EMF) Installation Instructions. Fusing Equipment MN132031EN

COOPER POWER SERIES. UltraSIL polymer-insulated D-73P disconnect switches installation instructions. Switches MN008004EN

Effective June 2016 New Issue

COOPER POWER SERIES. K-Limiter back-up current-limiting fuse installation instructions. Fusing Equipment MN132010EN

COOPER POWER SERIES. High-voltage primary bushings installation instructions. OEM Equipment MN800008EN

COOPER POWER. SERIES ELF Current-Limiting Dropout Fuse Installation Instructions. Fusing Equipment MN132028EN. Pull ring. Housing

COOPER POWER SERIES. QD5 Quik-Drive tap-changer reversing neutral stationary contact asssembly kit A26 installation instructions

COOPER POWER SERIES. Current-Limiting Type NXC (C-Rated) Fuse Installation Instructions. Fusing Equipment MN132014EN

COOPER POWER SERIES. S.T.A.R. Hot line voltage indicator installation instructions. Fault Indicators MN320011EN. Indicator boot.

COOPER POWER SERIES. 600 A 15/25 kv class T-OP II connector assembly installation instructions. Deadbreak Apparatus Connectors MN650048EN

COOPER POWER SERIES. HX-CB loadbreak fuse cutout installation instructions. Fusing Equipment MN132011EN

COOPER POWER SERIES. S.T.A.R. type LVR faulted circuit indicator installation instructions. Fault Indicators MN320005EN

COOPER POWER SERIES. Screened Separable Connectors MN650023EN. Effective October 2016 Supersedes March 2012 (IS )

Effective March 2015 Supersedes S August 2012

COOPER POWER SERIES. Screened Separable Connectors MN650024EN. Effective October 2016 Supersedes March 2012 (IS )

COOPER POWER SERIES. RTE EL-BAY-O-NET FUSE Re-Fusing Instructions. Fusing Equipment MN132024EN

COOPER POWER. SERIES CMU Medium voltage power fuse installation instructions. Fusing Equipment MN132032EN

High-voltage primary bushings installation instructions

COOPER POWER SERIES. KA662R tank-lifting windlass assembly and installation instructions. Recloser Mountings MN280071EN

COOPER POWER SERIES. Fused loadbreak elbow connector installation instructions. Loadbreak Apparatus Connectors MN650014EN

COOPER POWER SERIES. Pad-mounted Switchgear MN285019EN. Effective March 2017 Supersedes February 2007 (S )

COOPER POWER SERIES. KA1169R Closing Coil Transfer-Switch Accessory Operation. Reclosers MN280069EN

COOPER POWER SERIES. Dielectric grease application to recloser cable instructions. Reclosers MN280070EN

COOPER POWER SERIES. Expulsion fuse installation instructions. Capacitors MN230005EN. Effective November 2016 Supersedes November 2001 (S )

Type NR oil switch installation and operation instructions

COOPER POWER SERIES. Types 4H single-phase and 6H three-phase vacuum interrupter conversion kits. Reclosers MN280014EN

COOPER POWER SERIES. 600 A 15 kv and 25 kv class BT-TAP connector system installation instructions. Deadbreak Apparatus Connectors MN650004EN

COOPER POWER SERIES. 600 A 15/25 kv class BOL-T and separable splice connector assembly installation instructions

COOPER POWER SERIES. Surge arrester interchangeable fuse cutout combination installation instructions. Surge Arresters MN235004EN

Effective May 2017 Supersedes December 2004 (S )

COOPER POWER SERIES. 600 A 35 kv class BT-TAP connector system installation instructions. Deadbreak Apparatus Connectors MN650003EN

COOPER POWER SERIES. KA146W5 single pole-mounting hanger; KA146W2 tank lifting windlass assembly and installation instructions. Reclosers MN280039EN

COOPER POWER SERIES. Electronic control battery testing, charging, and replacement instructions. Reclosers MN280074EN

COOPER POWER SERIES. KA716L7001 adjustable control valve kit for Types L, E, 4E, V4E, and V4L reclosers installation and adjustment instructions

COOPER POWER SERIES. Mercury switch to microswitch retrofit kit KA349WE installation instructions. Reclosers MN280022EN

Effective May 2017 Supersedes January 2003 (S )

COOPER POWER SERIES. Quick Connect Assembly (QCA) Retrofit Kit, General Electric Installation Instructions. Voltage Regulators MN225075EN

S Voltage Regulators GENERAL. Contents. Acceptance and Initial Inspection. Handling and Storage. Standards

COOPER POWER SERIES. Manually-Operated M-Force Switch Installation and Operation Instructions. Switches and Disconnects MN008003EN

S Fault Indicators. S.T.A.R. Type TPR Faulted Circuit Indicator Installation Instructions. Contents INSTALLATION PROCEDURES

Figure 1. Kearney Type HX cutout.

COOPER POWER SERIES. Types D and DV recloser installation instructions. Reclosers MN280030EN

COOPER POWER SERIES. Instructions for oil-filled, single-phase overhead distribution transformers. Distribution Transformers MN201003EN

S Voltage Regulators PRODUCT INFORMATION GENERAL. Contents. Acceptance and Initial Inspection. Handling and Storage

S Voltage Regulators PRODUCT INFORMATION GENERAL. Contents. Acceptance and Initial Inspection. Handling and Storage.

S Voltage Regulators GENERAL. PRODUCT INFORMATION Introduction. Contents. Acceptance and Initial Inspection. Handling and Storage.

COOPER POWER SERIES. Metal-enclosed capacitor banks installation instructions. Power Capacitors MN230010EN

Factory Authorized Mechanism Enhancement (FAME)

COOPER POWER SERIES. Metal-enclosed, pad-mounted capacitor banks installation instructions. Power Capacitors MN230009EN

This Kit Is for Use with Types RE, RVE, WE, WVE, VWE, VWVE27, and VWVE38 Reclosers.

600 A 28 kv class Cleer loadbreak connector system

ELB ES. Product Installation Instructions

ELB ELB

25 kv class fused loadbreak elbow connector

600 A 15 kv class Cleer loadbreak connector system

200 A 25 kv and 28 kv class loadbreak elbow connector with optional integral jacket seal-canadian Edition

200 A 15 kv class loadbreak elbow connector with optional integral jacket seal

600 A 15 and 25 kv class Cleer grounding elbow

Removal/installation instructions for Series NRX (IZMX) drawout levering (racking) mechanism

Two-way cable interlock kit for Magnum fixed circuit breakers

200 A 25 and 28 kv class POSI-BREAK loadbreak elbow connector with optional integral jacket seal-canadian Edition

GWI Rev. 1 October 2007 Supersedes Rev. 0 Dated February 2004

CCP2-FLR1-21_ flange-rod operating mechanism

Instructions for VCP-W Simple Electrical Ground & Test Device (SEG&TD) with simplified interlock scheme - bottom terminal set version

Two-way cable interlock kit for Magnum drawout circuit breakers

Reprogramming guide. Power Defense ICCB. Instructional Leaflet IL EN WARNING WARNING. Instructions apply to:

200 A 15 kv class loadbreak elbow connector with optional integral jacket seal-canadian Edition

COOPER POWER SERIES. RVAC Fluid-insulated Vacuum Switchgear; Installation, Operation, and Maintenance Instructions. Switchgear MN285005EN

Instruction Booklet IB E. Contents

3-way multi-family drawout cable interlock kit - type 32 - RF

COOPER POWER SERIES. Type MOST Fluid-Insulated Switchgear; Installation, Operation, and Maintenance Instructions

COOPER POWER SERIES. VFI tester operating instructions. Underground Distribution Switchgear MN285001EN

Installation Instructions 15/25/35kV, 600/900 AMPERE

600 A 15 kv class T-OP II deadbreak connector

Edison modular fuse, vault application products

Installation Instructions for Interlocking Trip Indicator with Remote Reset for Magnum Low Voltage Circuit Breakers

Installation and removal instructions for Series NRX RF fixed breaker three-way Type 32 cable interlock kit

Installation Instructions For Motor Control Center (MCC) Units

600 A 25 kv class BT-TAP deadbreak connector

600 A 35 kv class separable splices

600 A 35 kv class BT-TAP deadbreak connector

Two-position sidewall (horizontal) and cover (vertical) mounted loadbreak switches

COOPER POWER SERIES. Types VWE, VWVE27, VWVE38X, WE, WVE27, and WVE38X; threephase electronically controlled; installation and operation instructions

Effective October 2016 Supersedes January 2014 (S )

COOPER POWER SERIES. Externally fused block banks installation instructions. Capacitors MN230004EN

200 A and 600 A, 15, 25, and 35 kv junction bars for separable connectors

Grounding equipment COOPER POWER SERIES. Temporary Connections CA325004EN. Contents

600 A 15 and 25 kv class deadbreak accessories, tools, and replacement parts

Raychem CSJA Safety Instructions. Safety Instructions. Customer Service. Kit Contents. Installation Instructions

Vacuum Circuit Breaker (Vehicle)

Instruction Booklet for the Installation, Operation and Maintenance of Type 5-15 kv VCP-WG Vacuum Circuit Breaker 4000A MiniMod

Loadbreak Apparatus Connectors

100 A externally operated one-, twoand three-phase tap-changer switch

Installation Instructions for KPS and KPH Circuit Breakers and Molded Case Switches

Transcription:

Loadbreak Connectors MN650015EN Effective December 2015 Supersedes S500-15-1 October 2013 COOPER POWER SERIES 200 A loadbreak junction 15 and 25 kv class installation instructions

DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY The information, recommendations, descriptions and safety notations in this document are based on Eaton Corporation s ( Eaton ) experience and judgment and may not cover all contingencies. If further information is required, an Eaton sales office should be consulted. Sale of the product shown in this literature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agreement between Eaton and the purchaser. THERE ARE NO UNDERSTANDINGS, AGREEMENTS, WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY, OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT BETWEEN THE PARTIES. ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON. THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES. In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or otherwise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to damage or loss of use of equipment, plant or power system, cost of capital, loss of power, additional expenses in the use of existing power facilities, or claims against the purchaser or user by its customers resulting from the use of the information, recommendations and descriptions contained herein. The information contained in this manual is subject to change without notice. ii 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015

Contents SAFETY INFORMATION Safety information...iv PRODUCT INFORMATION Introduction...1 Acceptance and initial inspection...1 Handling and storage...1 Quality standards...............................................................................1 EQUIPMENT REQUIRED 200 A loadbreak junction only kit...2 200 A loadbreak junction with stainless steel bracket kit...2 200 A loadbreak junction with u-straps...2 TOOLS REQUIRED Tools required...2 INSTALLATION INSTRUCTIONS Loadbreak junction with stainless steel bracket....2 Loadbreak junction with u-straps...3 OPERATING INSTRUCTIONS Loadmake operation...4 Fault close...4 Loadbreak operation....4 MOUNTING CONFIGURATIONS Dimensional drawing...5 15 kv dimensional information...5 25 kv dimensional information....5 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015 iii

! SAFETY FOR LIFE Safety for life! SAFETY FOR LIFE Eaton meets or exceeds all applicable industry standards relating to product safety in its Cooper Power series products. We actively promote safe practices in the use and maintenance of our products through our service literature, instructional training programs, and the continuous efforts of all Eaton employees involved in product design, manufacture, marketing, and service. We strongly urge that you always follow all locally approved safety procedures and safety instructions when working around high voltage lines and equipment, and support our Safety For Life mission. Safety information The instructions in this manual are not intended as a substitute for proper training or adequate experience in the safe operation of the equipment described. Only competent technicians who are familiar with this equipment should install, operate, and service it. A competent technician has these qualifications: Is thoroughly familiar with these instructions. Is trained in industry-accepted high and low-voltage safe operating practices and procedures. Is trained and authorized to energize, de-energize, clear, and ground power distribution equipment. Is trained in the care and use of protective equipment such as flash clothing, safety glasses, face shield, hard hat, rubber gloves, clampstick, hotstick, etc. Following is important safety information. For safe installation and operation of this equipment, be sure to read and understand all cautions and warnings. Hazard Statement Definitions This manual may contain four types of hazard statements: DANGER Indicates a hazardous situation which, if not avoided, will result in death or serious injury. WARNING Indicates a hazardous situation which, if not avoided, could result in death or serious injury. CAUTION Indicates a hazardous situation which, if not avoided, could result in minor or moderate injury. CAUTION Indicates a hazardous situation which, if not avoided, could result in equipment damage only. Safety instructions Following are general caution and warning statements that apply to this equipment. Additional statements, related to specific tasks and procedures, are located throughout the manual. DANGER Hazardous voltage. Contact with hazardous voltage will cause death or severe personal injury. Follow all locally approved safety procedures when working around highand low-voltage lines and equipment. G103.3 WARNING Before installing, operating, maintaining, or testing this equipment, carefully read and understand the contents of this manual. Improper operation, handling or maintenance can result in death, severe personal injury, and equipment damage. G101.0 WARNING This equipment is not intended to protect human life. Follow all locally approved procedures and safety practices when installing or operating this equipment. Failure to comply can result in death, severe personal injury and equipment damage. G102.1 WARNING Power distribution and transmission equipment must be properly selected for the intended application. It must be installed and serviced by competent personnel who have been trained and understand proper safety procedures. These instructions are written for such personnel and are not a substitute for adequate training and experience in safety procedures. Failure to properly select, install or maintain power distribution and transmission equipment can result in death, severe personal injury, and equipment damage. G122.3 iv 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015

Product information Introduction Eaton's Cooper Power series 200 A, 15 and 25 kv Class loadbreak junction provides two, three, or four 8.3/14.4 kv loadbreak interfaces that are internally bused together and meet all requirements of IEEE Std 386-2006 standard, Separable Insulated Connector Systems. Loadbreak junctions are used in pad-mounted apparatus, underground vaults, and other apparatus to sectionalize, establish loops, taps, or splices, and to facilitate apparatus changeouts. WARNING High voltage. All associated apparatus must be de-energized during any hands-on installation or maintenance. Failure to comply may result in death, severe personal injury and equipment damage. CAUTION High voltage. The 200 A Loadbreak Junction is designed to be operated in accordance with normal safe operating procedures. These instructions are not intended to supersede or replace existing safety and operating procedures. The loadbreak junction should be installed and serviced only by personnel familiar with good safety practices and the handling of high-voltage electrical equipment. Read this manual first Read and understand the contents of this manual and follow all locally approved procedures and safety practices before installing or operating this equipment. Additional information These instructions cannot cover all details or variations in the equipment, procedures, or process described nor provide directions for meeting every possible contingency during installation, operation, or maintenance. For additional information, contact your Eaton representative. Acceptance and initial inspection Each loadbreak junction is in good condition when accepted by the carrier for shipment. Upon receipt, inspect the shipping container for signs of damage. Unpack the loadbreak junction and inspect it thoroughly for damage incurred during shipment. If damage is discovered, file a claim with the carrier immediately. Handling and storage Be careful during handling and storage of the loadbreak junction to minimize the possibility of damage. If the loadbreak junction is to be stored for any length of time prior to installation, provide a clean, dry storage area. Quality standards ISO 9001 Certified Quality Management System 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015 1

Equipment required 200 A loadbreak junction only kit includes Loadbreak Junction Silicone Grease Instruction Sheet 200 A loadbreak junction with stainless steel bracket kit includes Loadbreak Junction with Frontplate (assembled). See Figure 1. Stainless Steel Pivot Support Legs and Assembly Hardware. See Figure 2. Stainless Steel Mounting Feet and Assembly hardware. See Figure 3. Silicone Grease Instruction Sheet Figure 2. Pivot support leg. 200 A loadbreak junction with U-straps Loadbreak Junction U-straps with Assembly Hardware Silicone Grease Instruction Sheet Tools required 5/16" Wrench Figure 3. Mounting feet. Installation instructions Loadbreak junction with stainless steel bracket Step 1. Using supplied 5/16" hardware, attach mounting feet to pivot support legs. NNote: Refer to mounting configurations and dimensions on page 5. FRONTPLATE Figure 1. Loadbreak junction assembled to frontplate. 2 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015

Step 2. Using supplied 5/16" hardware, loosely attach pivot support/mounting feet assembly to back of frontplate and place assembly against the mounting surface (Figure 4). Step 6. Using supplied drain wire clamps, connect bracket to ground. (Drain wire clamps accommodate two wires up to 1/0 stranded [3/8" dia.].) Step 7. Remove protective shipping caps from junction interfaces. Clean and using supplied silicone grease, apply a thin layer of lubricant to the junction interfaces and mating accessory. Loadbreak junction with U-straps Figure 4. Pivot support/mounting feet assembled to frontplate. Adjust the brackets for proper alignment and mark their location on the mounting surface. Step 3. After mounting location has been marked, detach pivot support/mounting feet assembly from frontplate. Using 1/2" hardware (not supplied), mount pivot support/ mounting feet assembly on mounting surface according to location marks made in Step 2. Step 4. With pivot support/mounting feet assembly secure, using supplied 5/16" hardware, mount frontplate with junction to pivot support/mounting feet. Step 5. Adjust frontplate to desired angle. Tighten all bolts securely (Figure 5). Figure 6. Stainless steel U-strap. Step 1. Position loadbreak junction against mounting plate of apparatus and hold in place. Step 2. Place one supplied U-strap (Figure 6) between each post of the loadbreak junction and using the supplied 5/16" hardware attach U-straps to apparatus mounting plate, securing the loadbreak junction in place. IMPORTANT In applications where the junction is mounted without a stainless steel bracket, the mounting U-straps or the semi-conductive jacket of the junction must be grounded by an alternate means. Step 3. Tighten bolts securely. Figure 5. Frontplate angle adjustment. 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015 3

Step 4. Remove protective shipping caps from junction interfaces. Clean and using supplied silicone grease, apply a thin layer of lubricant to the junction interfaces and mating accessory. WARNING High Voltage. All unused junction interfaces must be covered with a insulated protective cap before energization. Do not use plastic shipping caps for this purpose. Failure to comply may result in death, severe personal injury and equipment damage. CAUTION The operator should always use personal protective equipment (insulated gloves, clampstick and eye protection) whenever operating the elbow. The operator should always be in the best possible operating position, providing firm footing and enabling a secure grasp of the clampstick, while maintaining positive control of the elbow before, during and immediately after operation. If there is any question regarding the operator s operating position, de-energize the elbow before operation. The operator should not be looking directly at the connector during the moment of circuit interruption or connection. Operating instructions Do not connect two different phases of a multiple-phase system. Before closing a single-phase loop, make certain both ends of the loop are the same phase. Loadmake operation 1. Area must be clear of obstructions or contaminants that would interfere with the operation of the loadbreak elbow. 2. Securely fasten a clampstick to the pulling eye. 3. Place the loadbreak elbow over the bushing, inserting the white arc follower of the probe into the bushing until a slight resistance is felt. 4. Immediately thrust the elbow onto the bushing with a fast, firm, straight motion, with sufficient force to latch the elbow to the bushing. 5. Push again on the elbow with the clampstick, and then pull gently to make sure that it is secure. Fault close 1. It is not recommended that operations be made on known faults. 2. If a fault is experienced, both the elbow connector and the bushing must be replaced. Loadbreak operation 1. Securely fasten a clampstick to the pulling eye. 2. Without exerting any pulling force, slightly rotate the connector clockwise to break surface friction between the elbow and bushing. 3. Withdraw the connector from the bushing with a fast, firm, straight motion, being careful not to place the connector near a ground plane. 4. Place connector on an appropriate accessory device, following the operating instructions for that accessory. 5. Place an insulated protective cap with drain wire attached to system ground on any exposed energized bushing using a clampstick. 4 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015

Mounting configurations S7 S9 A B M4 E MIN. MAX. CONFIGURATION 3* MIN. MAX. CONFIGURATION 2* MIN. MAX. CONFIGURATION 1* Dim. 15 kv 25 kv E 3.25" (83 mm) 4.0" (102 mm) S7 0.75" (19 mm) 0.75" (19 mm) S9 4.38" (111 mm) 4.38" (111 mm) S10 6.77" (172 mm) 8.34" (212 mm) S11 9.20" (234 mm) 10.77" (274 mm) M4 See Table 15 kv See Table 25 kv S10 Figure 7. Dimensional drawing (15 kv shown) shows mounting configurations. S11 Table 1. 15 kv Dimensional Information Physical M4 Mounting Dimensions in./mm Dimensions Configuration Configuration in./mm 1 2 Number of Interfaces 2 3 4 Configuration 3 A B Min. Max. Min. Max. Min. Max. 12.5 6.0 10.8 14.4 7.2 10.8 3.6 7.2 (318) (152) (274) (366) (183) (274) (91) (183) 19.6 9.2 14.7 18.3 11.1 14.7 7.4 11.1 (498) (234) (373) (465) (282) (373) (188) (282) 22.9 12.4 17.9 21.5 14.3 17.9 10.7 14.3 (582) (315) (455) (546) (363) (455) (272) (363) Configuration 1. Both feet turned out. Configuration 2. One foot turned out, one in. Configuration 3. Both feet turned in. Table 2. 25 kv Dimensional Information Physical M4 Mounting Dimensions in./mm Dimensions Configuration Configuration in./mm 1 2 Number of Interfaces Configuration 3 A B Min. Max. Min. Max. Min. Max. 2 14.2 6.7 11.9 15.6 8.0 11.7 4.2 7.8 (361) (170) (302) (396) (203) (297) (107) (198) 3 23.0 10.7 16.8 20.4 12.9 16.5 9.0 12.6 (584) (272) (427) (518) (328) (419) (229) (320) 4 27.0 14.7 20.8 24.4 16.9 20.5 13.0 16.6 (686) (373) (528) (620) (429) (521) (330) (422) Configuration 1. Both feet turned out. Configuration 2. One foot turned out, one in. Configuration 3. Both feet turned in. 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015 5

This page intentionally left blank. 6 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015

This page intentionally left blank. 200 A LOADBREAK JUNCTION 15 AND 25 KV CLASS INSTALLATION INSTRUCTIONS MN650015EN December 2015 7

! SAFETY FOR LIFE Eaton 1000 Eaton Boulevard Cleveland, OH 44122 United States Eaton.com Eaton s Cooper Power Systems Division 2300 Badger Drive Waukesha, WI 53188 United States Eaton.com/cooperpowerseries 2015 Eaton All Rights Reserved Printed in USA Publication No. MN650015EN Rev 0 (Supersedes S500151Rev 2) Eaton is a registered trademark. All trademarks are property of their respective owners. For Eaton's Cooper Power series product information call 1-877-277-4636 or visit: www.eaton.com/cooperpowerseries.