Pre-saturated Core Fault Current Limiter (PCFCL) Project

Similar documents
Energy Storage and Distribution

UK Offshore Wind Cost Optimisation: Top Head Mass

Natural Gas Pathway Analysis for Heavy Duty Vehicles

Consumers, Vehicles and Energy Integration (CVEI) project

ETI HDV Marine Programme

Consumers, Vehicles and Energy Integration (CVEI) project

Transport An affordable transition to sustainable and secure energy for light vehicles in the UK

The Smarter Network Storage Project

Transport and Energy Integration

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices

Managing Risks from New Technologies. ENA SHE Conference 2015 Roger Hey 16 April 2015

Introducing Nexans Superconducting Fault Current Limiters (SCFCLs)

Low Carbon Green Growth Roadmap for Asia and the Pacific FACT SHEET

The Electricity Grid Scottish Power Energy Networks Overview

All-Energy 2016, Glasgow. Contributing funding partners:

Integrating Energy Storage into Distribution Networks

Energy from Waste Grid Connections

Battery & Energy Storage

Choosing the Electric Avenue: Unlocking Savings, Emissions Reductions, and Community Bene=its of Electric Vehicles

Decision on Merced Irrigation District Transition Agreement

SMART GRIDS, THE FUTURE OF DISTRIBUTION POWER NETWORK

TWO TECHNOLOGIES, ONE SOLUTION

Metal enclosed capacitor banks: ABBACUS family

fuel cell systems for the automotive sector

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

INCREASING electrical network interconnection is

AEP Ohio Distribution Reliability and Technology Programs

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

26 th Oct Prof. Jeongtae KIM Daejin Univ. KNC Representative

Green Power Feasibility Study Econet Lesotho

Small Scale GTL - Upstream Sector Leads the Way. Gulf Publishing GTL Technology Forum Houston TX July 2014 Iain Baxter Chief Operating Officer

Airbus Alternative Fuels

Application of Cost-Effective Grid-Scale Battery Storage as an Enabler of Network Integration of Renewable Energy

Microgrid solutions Delivering resilient power anywhere at any time

Exceeding the standards with MNS

Review paper on Fault analysis and its Limiting Techniques.

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Smart Grids and Integration of Renewable Energies

March, Status of U.S. Electric Drive Energy Learning Network Webinar. United States Department of Energy

The Power Potential Project A guide to participating

Flexible Distributed Generation. FDG-F Burwell (EPN) May 2017

Smart Mobile Energy: Electric Vehicles and the Energy System

Smart Grid Automation and Centralized FISR

10 years experience of Framework Programmes in Aeronautics

Learning and Legacy Dave A Roberts, EA Technology

15 Nelson-Marlborough Regional Plan

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

Energy storage investment in APAC Energy Storage Strategy Paper

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

CarConnect Balancing Act Conference Thursday 8th September Ben Godfrey Innovation and Low Carbon Networks Engineer Western Power Distribution

California Energy Commission. December 7, 2015

Interconnection System Impact Study Report Request # GI

Fault management for grid automation Advanced fault location solution

Smart Grid 2.0: Moving Beyond Smart Meters

Aviation Fuels & Additives

4-6 October 2016 The NEC, Birmingham, UK. cleanenergylive.co.uk

PRESS RELEASE. Significant fuel savings and rapid payback shown for rail flywheel hybrid technology. 16 June 2015

Aviation Fuels & Additives

Independent Testing Laboratory for High Voltage Equipment

PRODUCT BROCHURE. ABB Ability Wireless Monitor for surge arrester Enabling reliability and availability of power supply

Influencing the Portfolio through the Distribution System Case Study- Pullman, WA

REALIZING INCREASED GRID CAPACITY FOR HIGH PENETRATION OF RENEWABLE GENERATION. TechAdvantage 2015 Orange Country Convention Center Orlando, FL

Merger of the generator interconnection processes of Valley Electric and the ISO;

2015 Grid of the Future Symposium

Commercialized storage solutions for enhanced grid operation

DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System

Optimising battery energy storage systems operation

The Hinkley Point C Project

MVDC link in a 33 kv distribution network

EIB experience in financing smart meter roll-outs

PQstorI One stop solution for energy storage and power quality

Smart EV Managed Charging

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

Investor Open Day 2017 The Olde House, Cornwall, 25 October Scott McGregor, Chief Executive Officer

A Distribution Network Operator s View of Connecting Microgeneration For RegenSW - South Devon College 07 September 2011

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Natasha Robinson. Head of Office for Low Emission Vehicles Office for Low Emission Vehicles. Sponsors

2009 Wind-Diesel Workshop. Microgrid Control System Technology GE Digital Energy, Markham Ontario

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

SAIREC Panel Discussion

Superconducting Fault Current Limiter Project

Electricity Technology in a Carbon-Constrained Future

DG system integration in distribution networks. The transition from passive to active grids

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

INTRODUCTION TO SMART GRID

In Bulgaria by. Continental Wind Bulgaria EOOD

Transportation Electrification Public Input Workshop. August 3, 2016

The Future of Electrification

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

Energy Systems of the Future Emad Ghaly, CEO Siemens Egypt. Unrestricted Siemens Technologies S.A.E. 2018

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION

Toshiba s Smart Grid technologies and solutions for MV/LV grid

Submission to the Transport and Public Works Committee s inquiry into the operations of toll roads in Queensland

Building the Business Case for Energy Storage

Transcription:

Pre-saturated Core Fault Current Limiter (PCFCL) Project 9 th October 2014 Nick Eraut, Project Manager Energy Storage & Distribution 2014 Energy Technologies Institute LLP The information in this document is the property of Energy Technologies Institute LLP and may not be copied or communicated to a third party, or used for any purpose other than that for which it is supplied without the express written consent of Energy Technologies Institute LLP. This 2014 information Energy is given Technologies in good faith based Institute upon the latest LLP information - Subject available to to notes Energy on Technologies page 1Institute LLP, no warranty or representation is given concerning such information, which must not be taken as establishing any contractual or other commitment binding upon Energy Technologies Institute LLP or any of its subsidiary or associated companies.

WHAT IS A FAULT CURRENT? WHY DOES IT MATTER?

Network Faults Faults within electrical power systems are inevitable equipment failures (cables, transformers, switchgear, etc), often due to old age external factors such as lightning strikes, overloading, digging through cables, etc Consequences of faults cause very high electrical currents lead to high electrical, thermal and mechanical stresses on distribution system equipment closing a CB onto a fault risks exceeding mechanical stress limit opening a CB during a fault risks exceeding switchgear opening limit personnel safety risks if switchgear fails, particularly during switching

The Fault Level Challenge UK energy policy More generation sources being connected in distribution networks As more renewable energy sources are connected to the UK distribution system (Distributed Generation), fault current levels increase CHP systems typically have fault contribution of 5-8 x rating PV typically 1-1.2 x rating Wind depends on system design Increased fault levels Existing equipment ratings becoming exceeded Substantial infrastructure investment Major operational restrictions Inability to connect new generation Networks are reaching fault current rating limits e.g. 20% of UKPN s London network has high fault levels (>95% of rating)

Consequences Conventional (passive) techniques to manage these fault currents introduce additional cost and negative impact on operational complexity, power quality, power system stability, reliability and security of supply A significant number of new DG projects do not proceed as a consequence, and fault current levels are becoming a major barrier to the widespread deployment of low-carbon distributed generation Also a major barrier to smart distribution networks with increased operational efficiency, flexibility, reliability and resilience Conventional (Passive) Fault Current Management Techniques Switchgear reinforcement Network splitting & reconfiguration Passive current limiting reactors & high impedance transformers Sequential switching Connecting DG at higher voltages Standard approach requiring high investment in most cases; also assumes switchgear exists at required ratings Low cost but leads to operational restrictions, and often lower power quality Comparatively low cost but introduces voltage drops and much increased steady-state losses Higher operational complexity, not fail-safe so a higher risk solution Increased connection infrastructure investment Active Fault Current Limiters (FCLs) will provide a credible, commercially acceptable means of overcoming these barriers

GridON s FCL Technology Removes fault level constraints without costly network upgrades Enables more distributed generation, with shorter connection times and reduced costs Enables smart networks with increased efficiency, flexibility, reliability and resilience Faster implementation than switchgear replacement Fully scalable for use at all distribution and transmission voltages Provides: Instantaneous, self-triggering response to network faults (without reliance on sensors or other components) Immediate recovery following clearance of a fault without network interruption, and suppression of multiple consecutive faults (allowing use in incomer applications) Enhanced fault limiting capability relative to other pre-saturated core fault current limiters Breakthroughs in design remove the need for superconducting components and associated cryogenic systems Inherent cost-effectiveness, ease of installation, reliability and minimal maintenance requirements GridON s is the first such fully tested, commercially viable, non-superconducting pre-saturated core fault current limiter GridON partnered with Australian-based Wilson Transformer Company for detailed design, manufacture and test

PROJECT OVERVIEW

Project Aims Having selected a potentially world-leading second-generation FCL technology (GridON s PCFCL), develop this FCL to the point at which it meets the genuine needs of distribution network operators (which no product has to date achieved) Assess and demonstrate performance in service for two years Define the Commercialisation Pathway, incorporating all aspects of further technical developments, supply chain planning, unit price development, etc to achieve a fully commercialised product Thereby, accelerate the commercialisation and deployment of FCLs in significant numbers on UK distribution networks Impact By removing constraints on the network operation, this will enable smart distribution networks with improved operation, flexibility and efficiency, and will remove key technical and commercial barriers to the installation of large quantities of low-carbon distributed generation and energy storage all of which are essential if the Government s 2050 targets are to be met

Consortium Members & Key Subcontractors

Plan Overview Stage 1: FCL Device Design & Build (including design, build & test of small-scale prototype) SG 1 FCL commissioning actually achieved, and subsequent stages therefore running, approx 3 months ahead of this schedule. Stage 2: FCL Device Testing SG 2 FCL shipping FCL Commissioning SG 3 Stage 4: Demonstration first year SG 4 Stage 5: Demonstration second year SG 5 Decommissioning and post-site testing Stage 6 SG 6 2011 2012 2013 2014 2015 2016

1MVA Prototype Development Prior to project, technology initially developed and tested only at bench-top scale First stage of project included development of 1MVA Prototype (i.e. 1/10 th power rating) Fully designed, built and tested

Main 10MVA FCL Device Learning from 1MVA prototype incorporated into development of 10MVA FCL Device Thoroughly tested in WTC s factory and then at an independent, third-party short-circuit test laboratory (more than 50 fault tests)

Test Results (extract) Site worst case prospective fault level (4.36kA single phase fault) 30% initial peak limitation as required 55% steady state RMS limitation

Newhaven Town Substation (at outset) Newhaven Town Substation (33/11kV Primary substation), East Sussex, UK Plan for site works to include new flood defences (under a parallel UKPN project) as well as plinth for FCL and complete new switchroom building for future site flexibility

Newhaven Electrical Schematic GT2 60MVA Peacehaven 33kV / Newhaven ERF GT1 60MVA G2 06 05 61 12 10 11 09 07 G1 Newhaven Grid 33kV LEGEND Seaford 132kV 33kV 11kV T2 10MVA T1 10MVA T3 10MVA 53 61 15 14 FCL 52 60 51 13 Newhaven Town 11kV

Newhaven Town Construction: Dec 2012

FCL Shipment from Australia to Newhaven

FCL Installation

FCL Installed

Newhaven Town Construction: June 2013

Commissioning FCL commissioned into service at Newhaven in May 2013

OPERATIONAL EXPERIENCE

Network Faults Since the winter storms died out, five network fault events have been experienced by the FCL to date (on three separate days) All were cable faults, three on UKPN s network, two on the nearby connected private network at Newhaven Docks 5 faults during first 15 months of site operation, follow more than 50 tests in lab: FCL performed reliably and exactly to specification Faults limited by up to 46% (this varies with exact nature of fault) Network and its protection systems behaved as expected Example test data:

Second Year of Operation Operational Review and Stage Gate held 22 nd May 2014, at end of 1 st year of demonstration Demonstration very successful to date Crucially, demonstrated perfect reliability throughout the first year of operation, under both normal and fault conditions, even through the winter s extreme weather conditions Fault limiting on each occasion exactly as specified and designed Proceed with planned 2 nd year of demonstration (to mid 2015) Site reconfigured to run all three transformers in parallel an improvement in customers security of supply that was impossible without the FCL The FCL is making a real difference to the supply security at the site by allowing the additional transformer operation without exceeding the site fault level limits (Low Carbon Project Manager, UKPN)

Plans for Post-Demonstration Testing At completion of 2 nd year of operation (mid 2015), FCL will be removed from Newhaven site Minor site reconfiguration works Further testing of FCL at independent test facility, potentially including: Limited disassembly and inspection to assess condition Further characterisation tests Testing to establish ultimate FCL capability limits (potentially destructive testing)

EXPLOITATION

Commercial Position for FCL Sales by GridON Demonstration: provides real evidence of benefits of FCLs to network operators, generators and others justifies confidence to deploy GridON s commercially-available FCLs now as part of business-as-usual activities Launch event at start of operation well attended by DNOs and other stakeholders Press releases issued at kick-off, at launch event, and in July after first year of operation First GridON FCL sale: to WPD for LCN FlexDGrid project FlexDGrid is a 17 million project which will revolutionise the power network in Birmingham. The WPD initiative will use ground-breaking new solutions to accommodate more low carbon generation across the city, reducing power cuts and helping Birmingham reduce its carbon emissions. GridON receiving sustained interest in further potential sales worldwide for both distribution and transmission applications

Other Planned Activities A number of activities planned to maximise deployment volumes and speed Market Analysis Supporting development of FCL standards Potential opportunities for further work Opportunities to support next development steps targeted engineering to reduce unit size, weight & cost, (across product range and of particular importance for distribution applications) Transmission application demonstration Engagement with key stakeholders DNOs, TSOs, consultancies & engineering contractors, finance and investment companies, government & regulators, local authorities, academic networks, etc

Further Information Further information available: 2 press releases FCL information sheet GridON s data sheet other resources on request Contacts: Nick Eraut Project Manager ESD nicholas.eraut@eti.co.uk +44(0)1509 202022 Phil Proctor Programme Manager ESD phil.proctor@eti.co.uk +44(0)1509 202063 Yoram Valent Chief Executive Officer, GridON yvalent@gridon.com +972(3)731 1183

PCFCL building on project success

Registered Office Energy Technologies Institute Holywell Building Holywell Park Loughborough LE11 3UZ For all general enquiries telephone the ETI on 01509 202020. For more information about the ETI visit www.eti.co.uk For the latest ETI news and announcements email info@eti.co.uk The ETI can also be followed on Twitter @the_eti