Deploying Smart Wires at the Georgia Power Company (GPC)

Similar documents
2015 Grid of the Future Symposium

Initial Field Trials of Distributed Series Reactors and Implications for Future Applications

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Introduction to PowerWorld Simulator: Interface and Common Tools

Project #148. Generation Interconnection System Impact Study Report

Contingency Analysis

Eskisehir Light Train- Correcting Capacitive

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report GIP-222-FEAS-R3

System Status Briefing

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Application Note. First trip test. A circuit breaker spends most of its lifetime conducting current without any

June Safety Measurement System Changes

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

OPERATING AND MAINTENANCE MANUAL. Primary Current Injection Test Set. 750ADM-H mk2

Clean Energy Series: Technology Insights from University Innovators. Applications Center. Rick Hartlein

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

With Cummins PowerCommand Cloud, you can ensure you are always on.

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

IES GRID FEED-IN LIMITER

APC APPLICATION NOTE #98

Interconnection Feasibility Study Report GIP-226-FEAS-R3

WHITE PAPER. Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard

SECONDARY FUEL TESTING ARRANGEMENTS

Smart Grid Automation and Centralized FISR

Vehicle Diagnostic Logging Device

ACTIVE STATOR - A MORE EFFICIENT DRIVE TRAIN CONCEPT FOR A WIND TURBINE. Dr. Makhlouf Benatmane - Director Business Development

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

A comparison of the impacts of Euro 6 diesel passenger cars and zero-emission vehicles on urban air quality compliance

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB

Improving predictive maintenance with oil condition monitoring.

Smart Grid 2.0: Moving Beyond Smart Meters

MCE TM Product Information 5 kv Electric Motor Analyzer

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD

Renewable Energy Systems 14

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

TachoDrive key + TachoDrive Express software

Breakout Session 1 Report-out presentations

Embracing the Challenge of the Broadband Energy Crisis

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Internal Audit Report. Fuel Consumption Oversight and Coordination TxDOT Internal Audit Division

Electric Power Research Institute, USA 2 ABB, USA

Electric Vehicle Cyber Research

September 2014 Data Release

ABB POWER SYSTEMS CONSULTING

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

TRITON ERROR CODES ERROR CODE MODEL SERIES DESCRIPTION RESOLUTION

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER FLOW SIMULATION AND ANALYSIS

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

April 2014 Data Release

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Industry-Wide Light Duty Hydrogen Vehicle Fueling Protocol up to 70MPa: Created by Math Modeling and Confirmed by System Testing

Dynamic Control of Grid Assets

Background. If It Ain t Broke CASE STUDY

REMOTE SENSING DEVICE HIGH EMITTER IDENTIFICATION WITH CONFIRMATORY ROADSIDE INSPECTION

Targeted Application of STATCOM Technology in the Distribution Zone

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

The Role of Electricity Storage on the Grid each location requires different requirements

2018 Load & Capacity Data Report

Introduction...3. System Overview...3. PDC Control Unit Sensors PDC Button Interfaces Activation of the PDC...

PowerChute TM Network Shutdown in Redundant UPS Configurations

University of Florida Low Cost Solar Driven Desalination

More information at

NZQA registered unit standard version 3 Page 1 of 5. Demonstrate and apply knowledge of electrical machines

Step Motor Lower-Loss Technology An Update

2016 Load & Capacity Data Report

Fluke 438-II Power Quality and Motor Analyzer

Guideline No.: E-07(201501) E-07 TRANSFORMERS. Issued date: October 20,2015. China Classification Society

POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Powerware Master Modbus

Smart Grid A Reliability Perspective

The IAEA does not normally maintain stocks of reports in this series.

Overview. Battery Monitoring

5G V2X. The automotive use-case for 5G. Dino Flore 5GAA Director General

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society

Compatibility of STPA with GM System Safety Engineering Process. Padma Sundaram Dave Hartfelder

Grid Impacts of Variable Generation at High Penetration Levels

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Guideline No.: E-07(201712) E-07 TRANSFORMERS. Issued date: December 26, China Classification Society

2016 Reporting Guide W Sharp Avenue, Spokane, WA POOL (7665)

Welcome to ABB machinery drives training. This training module will introduce you to the ACS850-04, the ABB machinery drive module.

Power System Economics and Market Modeling

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD

Appendix D Black Hills Project Summary

TORONTO TRANSIT COMMISSION REPORT NO.

Building a 21 st Century Electric Grid. February 23, 2018

Installation and User Manual. with RAIN SENSOR.

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

TEPCO NUCLEAR SAFETY REFORM PLAN PROGRESS REPORT 1 ST QUARTER FY 2014 EXECUTIVE SUMMARY

Transcription:

Deploying Smart Wires at the Georgia Power Company (GPC) January, 2015

Contents Executive Summary... 3 Introduction... 4 Architecture of the GPC Installations... 5 Performance Summary: Long-term Test... 6 PowerLine Guardian TM Uptime and Mode of Operation... 6 Communications Robustness... 8 Installation Impact on the Power System... 8 Conclusion... 9 Oakland, CA 94612 2

Executive Summary Since its founding, Smart Wires has been a leader in developing power flow control solutions for the transmission network. The technology, which is designed and manufactured in the United States, offers its customers a unique solution to improve the flexibility of their existing transmission networks and meet the challenges of the coming utility paradigm. In 2009, Southern recognized the game-changing potential of this technology and joined the Smart Wire Focus Initiative (SWFI) a consortium of utilities within the National Electric Energy Testing Research and Applications Center (NEETRAC) to develop performance requirements for the PowerLine Guardian TM, previously known as the Distributed Series Reactor. Collaborating closely, Smart Wires and Southern successfully completed the installation of 33 PowerLine Guardian units spread across two transmission lines in March of 2013. The initial Smart Wires installations at GPC were deployed to demonstrate the power flow control and real-time sensing capabilities of Smart Wires technology. This report describes the architecture of the Installations, performance over a 16-month test period (4/1/2013 7/31/2014), and power system impacts. The Installations met or exceeded the objectives over the 16-month test. The units exceeded project requirements and were available 99.1% of the time to respond to operator commands to control power flow or transmit sensed data. The injected inductive impedance of the Installations varied from zero to full nameplate capability and many stages in-between. On average, the units were dispatched to inject 75% of the nameplate impedance. As of October 2014, the Installations had been in continuous operation for 19 months, had demonstrated a statistically significant impact on power flow, and had been 100% available to control power flow using local control. Oakland, CA 94612 3

Introduction PowerLine Guardians were installed on two GPC lines in March 2013, the Grady Moreland and Grady West End 115 kv transmission lines. Following installation, use case testing was performed to ensure the Installations were functioning in accordance with modeled expectations. Starting in April 2013, the Installations were operated by GPC for a 16-month test and performance was evaluated. The objective of the Installations was to demonstrate the reliability of the power flow control and real-time sensing capabilities of Smart Wires technology, and mitigate overload during N-1 contingency without using the prior solution (a permanently online air core reactor). The lines are shown in Figure 1. Figure 1: Map of the GPC installations and neighboring lines Oakland, CA 94612 4

Architecture of the GPC Installations The Smart Wires system is an end-to-end system to control power flows and measure the state of the transmission system. Figure 2 shows the communication layer of the end-to-end system. Components of the system include: PowerLine Guardian TM Changes line impedance by an incremental amount and measures the state of the transmission asset. Typically deployed en masse and distributed along the transmission line. Cellular Enabled PowerLine Guardian TM (Guardian+) Serves as a PowerLine Guardian and communication bridge between the fleet of PowerLine Guardians and the PowerLine Commander TM. PowerLine Commander TM Performs a suite of services, which include Energy Management System (EMS) interface, data aggregation, archival, operator logging, and alert generation. Each PowerLine Guardian is able to operate in one of four modes standby mode, monitoring mode, injection mode, and in extremis. In standby mode, the unit is unable to change modes or communicate as the line current is insufficient to power the units. In monitoring mode, full telemetry and communications is enabled while the secondary of the unit is shorted and negligible impedance is injected into the line. In injection mode, the magnetizing impedance of the transformer is injected into the line. During in extremis, the unit protects itself from conditions that are outside of the set of allowable operating conditions (i.e. fault-inducted current). Figure 2: Overview of Smart Wires communications layer For the GPC Installations, GPC accesses PowerLine Commander TM through a web-interface. The operator GUI is shown in Figure 3, with each green dot representing a unit in monitoring mode and each red dot indicating a unit in injection mode. The operator may put all units in monitoring mode via the All Stop button or put all units into injection mode using the Max Inject button. Alternatively, the operator may apply one of the pre-defined Oakland, CA 94612 5

Set Point configurations, allowing units to self-determine the mode based on local conditions such as conductor temperature or current. PowerLine Commander TM may also be used to monitor the state of each Installation in total or individual assets. Figure 3: PowerLine Commander TM GUI Performance Summary: Long-term Test For the long-term test, the Installations were operated from 4/1/2013 through 7/31/2014 in Standby, Set Point, Max Inject and All Stop configurations. From April through July 2013 with the exception of the Use Case testing, the Installations were operated exclusively with roughly 50% of the modules in injection mode. From July onward, the Installations were operated with all units in injection mode. Upon completion of the 16 month test, summary statistics were generated to characterize uptime, usage type, and robustness of the communications system. As of October 24, 2014, the Installations continued to be in use by GPC. PowerLine Guardian TM Uptime and Mode of Operation Summary statistics for the period of the Long-term test are presented below. 1. Period of Record: 1.1. 4/1/2013 through 7/31/2014 Oakland, CA 94612 6

2. Definition of Participating Units: 33 of 33 PowerLine Guardians available at beginning of the 16-month test. 31 of 33 PowerLine Guardians available at end of the 16-month test (95%). Units 2MH and 58MB categorized as unavailable. 3. Results: 3.1. Percentage of time that participating units were available to change modes via remote command and/or send data (periods for which the conductor current was below the PowerLine Guardian minimum current level have been excluded from the set of potential available periods): Average across both Installations: 99.071% Minimum for any given PowerLine Guardian: 89.749% Maximum for any given PowerLine Guardian: 99.998% 3.2. Percentage of time that participating units were available to change modes via local command (periods for which the conductor current was below the PowerLine Guardian minimum current level have been excluded from the set of potential available periods): 100% 3.3. Number of times a unit entered injection mode: Total across both Installations: 5631 Average for any given PowerLine Guardian: 170.6 Minimum for any given PowerLine Guardian: 15 Maximum for any given PowerLine Guardian: 518 3.4. Number of hours the units were in injection mode: Total across both Installations: 282,347 unit-hours Average for any given Guardian: 8556 unit-hours Minimum for any given PowerLine Guardian: 2741 unit-hours Maximum for any given PowerLine Guardian: 9665 unit-hours 3.5. Number of hours the units were in monitoring mode: Total across both Installations: 95,623 unit-hours Oakland, CA 94612 7

Average for any given PowerLine Guardian: 2898 unit-hours Minimum for any given PowerLine Guardian: 1999 unit-hours Maximum for any given PowerLine Guardian: 5464 unit-hours. Unit 2MH was removed from service and NEETRAC was chosen to perform a failure analysis on the unit in the presence of GPC and SW representatives. After detailed examination of the failed unit and telemetry data, it was determined that the primary cause of failure was related to the electrical connection between the two halves of the secondary winding. The PowerLine Guardian was redesigned to reduce the likelihood of a future failure. The redesigned unit was then tested extensively at NEETRAC and other laboratories. Communications Robustness Regular status polling was executed by each PowerLine Guardian+ to determine the status of each local PowerLine Guardian. The robustness of PowerLine Guardian to PowerLine Guardian+ communications is determined by comparing the frequency of polling errors to polling attempts. This calculation does not assess the robustness of backhaul communications between the PowerLine Guardian+ units and the Operation Center. 1. Results: 2.1 Attempted communications events over this period: 4.53 x 10 7 2.2. PowerLine Guardian polling errors: 3.93 x 10 4 2.3. Percentage packet loss over the period: < 0.0087 % 2. Conclusions: One packet was lost for every 1153 status inquires generated by the PowerLine Guardian+. When considering the outbound and inbound messages required for an exchange, one packet was lost out of 2306 packets. As expected, some errors resulted during normal maintenance activities such as firmware updates. Installation Impact on the Power System The impact on the power system was not significant enough to identify via analysis of a limited number of power flow cases extracted from the GPC state estimator. Instead a statistical test was performed to determine if the Installations impacted the power system and quantify the magnitude of the impacts. Data for the statistical test were extracted from all available Max Inject and All Stop events for each Installation. During a Max Inject event, injected inductance of each phase was changed from zero to maximum over the Oakland, CA 94612 8

course of a few minutes. During an All Stop event, the inverse occurred. For each Max Inject event, the phase current measurements were sampled at the last time step the Installation inductance was zero and the first time step the inductance reached its maximum value. For each All Stop event, the phase current measurements were derived at the last time step the Installation inductance was at maximum and the first time step the inductance reached zero. For each Installation, two groups of records were populated. The first group (no injection) contains all measurements before transmission of the Max Inject command and all measurements after the All Stop had been confirmed. The second group (max injection) contains all measurements after the Max Inject command had been confirmed and all measurements before transmission of the All Stop command. For the Grady Moreland Installation, the no injection records have a mean current 1.25% higher than the max inject records. The null hypothesis that the two means are statistically equal was tested at a significance level of 0.05 using a one-side paired t-test. The result of the t-test supports rejection of the null hypothesis, suggesting that the mean current of the no injection records is statistically higher than the mean current of the max inject records sample. Thus, the statistical test supports the conclusion that the Grady Moreland Installation lowered line current when operated in Max Inject. For the Grady West End Installation, the no injection records have a mean current 2.83% higher than the max inject records. The null hypothesis that the two means are statistically equal was tested at a significance level of 0.05 using a one-side paired t-test. The result of the t-test supports rejection of the null hypothesis, suggesting that the mean current of the no injection records is statistically higher than the mean current of the max inject records sample. Thus, the statistical test supports the conclusion that the Grady West End Installation lowered line current when operated in Max Inject. In conclusion, the statistical test demonstrates a high certainty that the Installations had the expected effect on power flows. On average, switching the state of all units simultaneously changed the current flow by 7.5 A and 6.3 A per phase for the Grady Moreland and Grady West End Installations respectively. This corresponds to a change in flow of 1.5 MVA and 1.3 MVA respectively or approximately 100 kva and 70 kva per unit respectively. The Installations would provide more control capability if additional units are added. Conclusion The GPC Installations demonstrated the intended capabilities, namely power flow control and real-time sensing. On average over the 16 month test, the Installations were operated at 75% of nameplate impedance in injection mode. Guardian to PowerLine Guardian+ communications were successful over 99.991% of the time. Across the set of instances where the entire Installation was switched from monitoring to injection mode or vice versa, the average impact on power flow was 1.5 MVA and 1.3 MWA for the Grady Moreland and Grady West End Installations respectively. As of October 2014, the Installations had been in continuous operation for 19 months. Oakland, CA 94612 9