The Grid West project - Summary of the report for the Independent Expert Panel

Similar documents
The Grid Link Project. Summary of the Report for the Independent Expert Panel

TOBIN CONSULTING ENGINEERS

Powering Sydney s Future

Proposed Dounreay - Mybster 275 kv / 132 kv

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY

RENEWABLES INTEGRATION STATUS REPORT

SECONDARY FUEL TESTING ARRANGEMENTS

Chirmorie Wind Farm Grid Connection

Generation Connections Industry Workshop 2017

Oakey Solar Farm Community Consultation

INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM

Decision on Merced Irrigation District Transition Agreement

Shunt reactors Proven history for future success

ABB Services for Low Voltage equipment Your choice, your future

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Transmission Development Plan Draft for Public Consultation

Merger of the generator interconnection processes of Valley Electric and the ISO;

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Public Information Centre

Willingdon Substation Decommission

Decision on ESB Networks Electric Vehicle Pilot

15 Nelson-Marlborough Regional Plan

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

City of Palo Alto (ID # 6416) City Council Staff Report

15 Nelson-Marlborough Regional Plan

PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Eyre Peninsula electricity supply options investigation

TRANSMISSION DEVELOPMENT PLAN

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

JOINT PRESS RELEASE BY MYHSR CORPORATION & SG HSR PTE LTD LAUNCH OF ASSETS COMPANY TENDER FOR THE KUALA LUMPUR SINGAPORE HIGH SPEED RAIL PROJECT

The Power Potential Project A guide to participating

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION

Solar-Wind Specific Request for Proposals

ABB Drive Services Your choice, your future

Submission on the Wellington Town Belt Bill. Local Government and Environment Select Committee Parliament Buildings Wellington

TORONTO TRANSIT COMMISSION REPORT NO.

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

GC108: EU Code: Emergency & Restoration: Black start testing requirement

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

Microgrid solutions Delivering resilient power anywhere at any time

Net Metering Policy Framework. July 2015

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

Generation Connections

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Building Collaboration Between East African Nations via Transmission Interconnectors

Brookfield Renewable Ireland. Response to Review of Connection and Grid Access Policy: Initial Thinking & Proposed Transitional Arrangements

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Eric Johnson, Director, External Affairs, ISO New England

Land Transport Rule Traction Engines [2008]

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State

Rate of Change of Frequency Project Quarterly Report for Q4 2017

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

committee report General Permitted Development Order SPT response to consultation

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Toronto Parking Authority Fleet Vehicle Replacement

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

Accommodating High Levels of Variable Generation. EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009

CUSC Modification Proposal Form CMP270

Discussing the Ratepayer Benefits of EVs On the Electrical Grid

Emerald Reactive Support Alternative Solution Expressions of interest

Security of supply II: Electric Transmission System Reliability

Fuel Mix Disclosure 2016

Bohn to Kettle River Transmission Project

Basic Connection Services Application and Price Guide

Kettle River Transmission Project

GIBRALTAR ERDF OPERATIONAL PROGRAMME POST ADOPTION STATEMENT

Boston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016

It is 5.30 on a winter s evening...

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee

TRANSMISSION PLANNING CRITERIA

PROJECT BACKGROUND 3

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 1 TO THE REQUEST FOR INFORMATION FOR THE

Comhairle Cathrach Chorcaí Cork City Council

CMP294: National Grid Legal Separation changes to CUSC Section 14. CUSC Modification Proposal Form

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

GEODE Report: Flexibility in Tomorrow s Energy System DSOs approach

Addressing ambiguity in how electricity industry legislation applies to secondary networks

Incentives and Opportunities Signalled by Transmission Charges in Scotland. Iain Wright 03 September 2018

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Smart EV Managed Charging

GRID INNOVATION CAUCUS CO-CHAIRS

ABB Wind Care Service Offering

National Seniors Association 18 October 2010 Jo Benvenuti David Stanford

Smart Grid, Long term planning for a sustainable energy system, from source to socket

The Swedish Government Inquiry on Smart Grids

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

Pilbara Undergrounding Program Smart Grid Opportunities November 2009 DMS#

The Role of Electricity Storage on the Grid each location requires different requirements

Statement of Expected Price Trends

Measuring the Smartness of the Electricity Grid

EUCL AMI Project Experience Share

GC108: EU Code: Emergency & Restoration: Black start testing requirement

Transcription:

The Grid West project - Summary of the report for the Independent Expert Panel

1. Glossary Glossary AC AC is a type of electrical current, in which the direction of the flow of electrons switches back and forth at regular intervals or cycles. An Bord Pleanála Ireland s independent national planning authority. Assets All substations and electricity transmission lines that form the transmission network. ESB owns the transmission network, and EirGrid operates it. Capacity The amount of electricity that can be safely transferred on the system or a circuit. CER ( the regulator ) The Commission for Energy Regulation. The CER is Ireland s independent energy regulator with a range of economic, customer and safety functions. Circuit The overhead line or underground cable linking two substations. For example, the Moneypoint Dunstown 400kV circuit. DC Direct current (DC) is electrical current which flows consistently in one direction. Demand The amount of electrical power that consumers take from the network. This is often expressed as peak demand, which is the largest amount of power used in a given period. Distribution Network Our high-voltage transmission network supplies power to the distribution network. This lower voltage network delivers power to households and businesses. In Ireland, the ESB owns and ESB Networks Ltd operates the distribution network. Generator A facility that produces electricity. Generators use a variety of sources to generate power. This can include coalfired power plants, gas fired power plants and wind farms. Kilovolt (kv) Operating voltage of electricity transmission equipment. One kilovolt is equal to one thousand volts. The highest voltage on the Irish transmission system is 400kV. Megavolt-ampere (MVA) is the unit used for power in an electrical line or cable. In direct current (DC) circuits, this product is equal to the real power in watts. Megawatt (MW) A unit of measurement for the amount of power produced by a generator or transported on the transmission grid. The rating of high voltage direct current (HVDC) circuits is generally quoted in MW. For ease of comparison, we use a unity power factor and displayed the rating in MVA. This allows for a better comparison with the high voltage alternating current (HVAC) options. Present Value All lifecycle costs including construction, maintenance and electrical losses etc. over the assumed 50 year life of the asset are shown as a single equivalent value today. Reinforcement Increasing the capacity of the existing electricity transmission network. We do this by building new lines or cables, or by uprating existing ones. Renewable generation The generation of electricity using renewable energy, such as wind, solar, tidal and biomass. Substation A set of electrical equipment used to step high-voltage electricity down to a lower voltage. We use substations to create lower voltages to safely deliver power to small businesses and homes. Transmission line A high-voltage power line running at 400kV, 220kV or 110kV on the Irish transmission system. The high-voltage allows delivery of bulk power over long distances with minimal power loss. Transmission Network or Grid This is a network of around 6,500 km high-voltage power lines, cables and substations. It links generators of electricity to the distribution network. EirGrid operates Ireland s transmission network. Voltage Voltage is a measure of electric potential. It is like pressure in a water system. The Grid West project EirGrid s Report for the Independent Expert Panel Page 2

The Grid West project Report for the Independent Expert Panel Foreword:... page 3 About this document :... page 4 Chapter 1 about EirGrid :... page 6 Chapter 2 - Summary & Layout of the Report for the Independent Expert Panel :... page 7 Chapter 3 - Grid West project need :... page 8 Chapter 4 - Technology Options for the Grid West project :... page 9 Chapter 5 - A fully underground HVDC solution :... page 10 Chapter 6 - A fully overhead 400kV solution :... page 11 Chapter 7 - a 220kV overhead line with partial undergrounding :... page 12 Chapter 8 - Analysis of options :... page 13 What will happen next? :... page 19 Foreword It is EirGrid s responsibility to ensure Ireland has the electricity transmission infrastructure it needs. We develop the grid to help Ireland remain competitive. Our work also fosters economic growth, attracts new investment and supports indigenous jobs. We must do this without placing too great a burden on communities, or too high a cost on industry. Our goal is to always find a fair balance between these factors. We recently published Your Grid, Your Views, Your Tomorrow. This draft document outlines our strategy for the development of the transmission grid, which is shaped by three key pillars: open engagement with communities; making the most of new technologies; getting more capability from the existing grid before we build new transmission infrastructure. We have sought your feedback on our draft strategy. We will reflect the themes and issues you provide in our final strategy which we will publish later this year. In the case of the Grid West project, we outlined the need to add capacity for high-voltage transmission in the west of Ireland. We must now consider the best solution to meet this need. As part of this process, we undertook a detailed analysis of underground and overhead options. We submitted these studies to a Government-appointed Independent Expert Panel (IEP) earlier this year. The Panel responded to the Minister for Communications, Energy and Natural Resources with a positive opinion. They assessed that our report was complete and fair. We are now publishing this report the Grid West report for the Independent Expert Panel. This summary is designed to sit sideby-side with the report as an overview of the key points. We have presented our work in a neutral way which is easy to assess. We will be consulting with the public later this year on all options for the Grid West project. This will help us select a preferred solution for the project. Fintan Slye Chief Executive EirGrid Plc. July 2015 The Grid West project EirGrid s Report for the Independent Expert Panel Page 3

About this document The full report for the Independent Expert Panel is a detailed, technical document. This summary follows the same outline as the full report, including an overview and analysis of each option. This summary is a shortened version of the report. The chapters listed from page six onwards, directly correspond to the chapters of the Report for the IEP and should be read as a synopsis of each of the chapters. The main report contains a detailed overview of each option: a HVDC underground cable; a 400kV overhead line; a 220kV overhead line with partial use of underground alternating current cable. Each chapter outlines the routespecific solution that EirGrid and our consultants considered. Chapter 1 - an introduction that explains EirGrid s role, the Grid West project and the role of the Independent Expert Panel; Chapter 2 - a summary that contains a full synopsis of each chapter and the main comparison points for each of the options; Chapter 3 - an outline of the need for the Grid West project. This explains why new transmission infrastructure is required in the west of Ireland; Chapter 4 - this chapter details three options, and explains how they compare to national, European and international best practice. First, we describe how each option meets The Grid West project EirGrid s Report for the Independent Expert Panel Page 4

About this document the need. We then explain how we can integrate each option into the network. Finally, we detail the infrastructure required for each option; Chapter 5 this chapter covers the first option, which is a direct current fully underground cable; Chapter 6 this chapter covers the second option, which is a 400kV fully overhead line including 8km of underground cable. The underground section is part of an existing lower voltage circuit, close to Flagford; cable. This includes the 8km close to Flagford and a potential for a further 22km underground. The maximum amount of 220kV cable that can be undergrounded in the region is 30km; Chapter 8 is a a side-by-side summary of the analysis for each of the options, in table format; Chapter 9 outlines the next steps. Chapter 7 this chapter covers the third option, which is a 220kV overhead line with partial use of underground The Grid West project EirGrid s Report for the Independent Expert Panel Page 5

Chapter 1- About EirGrid This chapter gives an overview of the role of EirGrid, the need for the Grid West project and the role of the Independent Expert Panel. It is EirGrid s responsibility to ensure Ireland has the electricity transmission infrastructure it needs. We work to ensure there is enough electricity for industry to prosper, and for employment to grow. We also keep the electricity transmission grid secure and reliable. The grid carries high-voltage electricity from where it is generated, to where it is needed. Industrial or high-tech companies connect directly to the transmission grid, as they use large amounts of electricity. Homes and small businesses get their electricity from the lower-voltage distribution network. Why are we developing the Grid West project? In 2008, the Commission for Energy Regulation (CER) established a process to regulate how renewable energy generators can connect to the grid. This process, called Gate 3 also determines how EirGrid must respond to these applications to connect to the grid. In the north Mayo region, renewable generation companies asked for connections of 647MW in total. At this stage, 400MW of connection agreements are signed. For the balance, approximately 200MW of connection offers are outstanding and 47MW have lapsed. We assessed the existing network in north Mayo to see if it could carry the power from these extra connections. We determined that the existing 110kV network, even if upgraded, could not do so. The network even when upgraded can only accommodate approximately 200MW of generation. Anything beyond this will need a high voltage transmission circuit, either overhead or underground. Grid West is our name for this new circuit. This project will connect more renewable energy to the national grid, which will help meet our 2020 targets. It will also reinforce the transmission network in the west, and support economic development in the region. Background to the Independent Expert Panel In January 2014, the then Minister for Communications, Energy and Natural Resources Mr Pat Rabbitte TD established an Independent Expert Panel. The IEP ensured that information we submitted on overhead and underground options was neutral and easy to compare. They also checked that our analysis covered the environmental, technical and economic factors they asked us to consider. The Grid West project EirGrid s Report for the Independent Expert Panel Page 6

Chapter 2 - Summary & Layout of the Report for the Independent Expert Panel This chapter contains a summary of the entire report and the main analysis criteria for each of the options under the headings: technical, environmental and economic. The report is presented in three parts: the background and consideration of the need and technology options (chapter 1-4); chapters 5, 6 and 7 are stand-alone assessments of the underground and overhead options and a summary of options. The next steps are outlined in chapters 8 & 9. 1. Introduction 2. Summary 3. Grid West Project Need 4. Technology Options for the Grid West Project 5. HVDC Underground Cable Option 6. 400kV HVAC Overhead Line Option 7. 220kV HVAC Overhead Line Option Description of Option Route Selection Substation sites Environmental Analysis Technical Analysis Economic Analysis Description of Option Route Selection Substation sites Environmental Analysis Technical Analysis Economic Analysis Description of Option Route Selection Substation sites Environmental Analysis Technical Analysis Economic Analysis 8. Summary of Options 9. Next Steps The Grid West project EirGrid s Report for the Independent Expert Panel Page 7

Chapter 3 - Grid West project need Having explained the background to the Grid West project in Chapter 1, in this chapter we explain why the project is needed. Introduction New energy generation proposed in north Mayo will drive the need for a new high-voltage transmission circuit. This is because the existing grid cannot accommodate the proposed volume of extra power. What factors were considered? When developing the grid, we engage closely with the Department of Communications, Energy and Natural Resources to ensure we are aligned with its energy strategy, and that our plans deliver for the entire country now and in the years ahead. In developing solutions for Grid West we considered our statutory obligations as Transmission System Operator (TSO), the upcoming Government policy on energy and the Gate process - the CER s approach to the connection of generators. We also considered the capacity of the existing transmission network and the quantity of generation seeking to connect. Future needs were also considered in terms of additional generation that might seek to connect to the transmission grid and additional demand growth in the region. The Grid West project EirGrid s Report for the Independent Expert Panel Page 8

Chapter 4 - Technology options for the Grid West project In this chapter we outline the three technology options we considered, how a Transmission System Operator goes about selecting the various technology options and the factors that determine this. The specific nature, extent and location of any project determines the most appropriate technology. No single technology or mix of technologies is appropriate for every transmission infrastructure project. Also, transmission technology develops over time. Because of this, we continually review new developments to identify their potential. When developing any new transmission project, we have three main technology decisions to make: whether to use Alternating Current (AC) or Direct Current (DC); what transmission voltage to use; the appropriate use of overhead or underground technology. Using AC and DC technology Ireland s transmission grid uses high voltage alternating current (AC). This is comparable to other European and international grids. Where we need to transfer power over long distances, we also use high voltage direct current (HVDC). To integrate a HVDC solution with the electricity grid requires converting HVAC to HVDC, or the other way round. We do this in converter substations at each end of a circuit. Transmission voltage The decision as to what transmission voltage is used is based on two factors. The first of these is the required power capacity for the new circuit which we measure in Megavolt amperes (MVA). The second factor is the specification of the transmission network at the point of connection. How did we determine the suitability of underground cables for the Grid West project? We carried out technical studies for the Grid West project. These confirmed that a fully underground solution is only possible using HVDC. We developed an underground solution that uses HVDC along the route and connects back into the AC transmission grid via converter stations at either end. In another study, we confirmed it was possible to use an AC underground cable for a maximum of 30km, if we use a lower voltage of 220kV, rather than 400kV. This study allowed us to develop Option 3 - the partial underground option. This uses 8km of the possible 30km underground cable near Flagford. This minimises extra wires in the approach to the Flagford substation. No location was selected for the remaining 22 km of AC cable available. We developed three comprehensive, detailed and route-specific studies to analyse the fully underground and the overhead technology options. The Grid West project EirGrid s Report for the Independent Expert Panel Page 9

DCF8 DCF4 DCF2 DCF7 DCF5 DCF3 DCF1 DCF6 No part of this document may be reproduced or transmitted in any form or stored in any retrieval system of any nature without the written permission of Patrick J. Tobin & Co. Ltd. as copyright holder except as agreed for use on the project for which the document was originally issued. Chapter 5 - A fully underground HVDC option In chapter 5 we discuss the HVDC underground option in further detail and outline the environmental, technical and economic analysis of this option. This option has the capacity to carry of 500MVA of power. To investigate this solution, we first identified thirty-one potential underground routes in conjunction with the relevant local authority departments and the National Roads Authority. Then, we selected a preferred route from north Mayo to Flagford. This option needs a new 110kV substation, and a 500MVA converter station in north Mayo. It requires a second converter station at the Flagford end and new equipment at the existing Flagford substation. A fully underground high voltage direct current (HVDC) solution SB3A Underground Route Option Scale 1:60,000 Underground Route Option Scale 1: 60,000 U l s t e r Legend Town/Village!. Existing Flagford Substation SB2 Moygownagh Sligo!. Emerging Preferred Underground Route Option Indicative route for underground cable - 220 kv HVAC from DCF7 to Flagford (Underground Route Option) Indicative Underground route to alternative substation location Preferred Converter Station location DCF7 (1km diameter) S l i g o L e i t r i m C o. C a v a n Preferred North Mayo Converter station Location Option 1/ Substation Location SB2 Alternative Proposed Converter Station Location Crossmolina Ballina Tobercurry 0 2.5 5 10 Knockmore Kilometres M a y o Foxford Killasser Lough Mask Swinford Maamturks Charlestown Boyle A MAY-2015 Issued G.F S.T. Issue Date Description By Chkd. Client: Carrick-on-Shannon Ballaghaderreen!. Project: THE GRID WEST PROJECT Castlebar Kiltimagh Tibohine Frenchpark R o s c o m m o n Title: HVDC Underground Cable Route Option Scale @ A0: 1:100,000 Castlerea Strokestown Prepared by: Checked: Date: G.Fil S.Tinnelly May 2015 Project Director: B.Downes Claremorris Consulting, Civil and Structural Engineers, Market Square, Castlebar, Co. Mayo, Ireland. tel: +353-(0)1-8030406 fax:+353-(0)1-8030409 e-mail: info@tobin.ie www.tobin.ie G a l w a y L o n g f o r d Ordnance Survey Ireland Licence No EN 0016015 Ordnance Survey Ireland and Government of Ireland Figure 29 A Environment We assessed that the main environmental impact from the cable route would be during the construction phase. We also considered the visual impact of the two converter stations required for this option. Technical This technology, whilst proven internationally, is more common in installations requiring long distances or underwater connections. An underground HVDC cable solution has limited flexibility in providing for future connections and higher capacity. Present Value Cost 476.8 million. Underground Option Meets the Need Present Value Construction Longevity and Flexibility Amount of Undergrounding 476.8m 3 years Limited Full The Grid West project EirGrid s Report for the Independent Expert Panel Page 10

No part of this document may be reproduced or transmitted in any form or stored in any retrieval system of any nature without the written permission of Patrick J. Tobin & Co. Ltd. as copyright holder except as agreed for use on the project for which the document was originally issued. Chapter 6 - A fully overhead 400kV option In chapter 6 we discuss the fully overhead 400kV option in further detail and outline the environmental, technical and economic analysis of this option. This option has the capacity to carry 1,580MVA of HVAC electricity. This solution includes replacing 8km of an existing 220kV overhead line with 220kV underground cable. This would take place on the approach to the existing Flagford substation. This option also needs a new 110kV substation in north Mayo and some new equipment at the existing Flagford substation. A fully overhead 400kV high voltage alternating current (HVAC) solution Overhead Line Option Scale 1:60,000 SB3A Ulster Legend Town/Village!. Existing Flagford Substation SB2 Indicative 400kV Overhead Line Route Option Indicative Overhead Line Route to alternative substation location Moygownagh Sligo Indicative Route of the Underground section of the existing Flagford to Srananagh 220kV line (Overhead Line Option) Preferred North Mayo Substation Location SB2 Alternative Proposed North Mayo Substation Location SB3A Leitrim Co.Cavan Sealing End Compound Location (Line Cable Interface Station 1Km Diameter) Moygownagh Crossmolina Ballina Sligo Tobercurry 0 2.5 5 10 Kilometres Knockmore Foxford Mayo Killasser Lough Mask Swinford Maamturks Charlestown Boyle A MAY-2015 Issued G.F S.T. Issue Date Description By Chkd. Client: Carrick-on-Shannon Castlebar Kiltimagh Ballaghaderreen Tibohine Frenchpark!. Project: THE GRID WEST PROJECT Title: Roscommon 400kV Overhead Line Route Option Scale @ A0: 1:100,000 Castlerea Strokestown!. Prepared by: Checked: Date: G.Fil S.Tinnelly May 2015 Project Director: B.Downes Claremorris Galway Consulting, Civil and Structural Engineers, Market Square, Castlebar, Co. Mayo, Ireland. tel: +353-(0)1-8030406 fax:+353-(0)1-8030409 e-mail: info@tobin.ie Overhead Line Option www.tobin.ie Scale 1:60,000 Longford Ordnance Survey Ireland Licence No EN 0016015 Ordnance Survey Ireland and Government of Ireland Figure 30 A Environment The most significant impact of this option is the visual impact on landscape due to overhead wires and substations. Technical This is a flexible option, and offers the most potential for future expansion and reinforcement. Overhead Option Meets the Need Present Value Construction Longevity and Flexibility 222.1m 3.5 years Good Present Value Cost 222.1 million. Amount of Undergrounding * 8km undergrounding of an existing lower voltage circuit. 8km* The Grid West project EirGrid s Report for the Independent Expert Panel Page 11

No part of this document may be reproduced or transmitted in any form or stored in any retrieval system of any nature without the written permission of Patrick J. Tobin & Co. Ltd. as copyright holder except as agreed for use on the project for which the document was originally issued. Chapter 7 - a 220kV overhead line with partial undergrounding In chapter 7 we discuss the 220kV overhead line option with partial undergrounding in further detail and outline the environmental, technical and economic analysis of this option. This option has the capacity to carry 600MVA of HVAC electricity. For comparison, we assessed this option using the proposed overhead 400kV route. This option includes 8km of 220kV underground cable into the existing Flagford substation. It also allows for up to 22km of 220kV underground cable on the proposed overhead route, which is the maximum of underground AC cable available in the region. This option requires a new 110kV gas insulated substation in north Mayo, and new equipment at the existing Flagford substation. A 220kV alternating current overhead line with partial use of underground AC cable Overhead Line Option Scale 1:60,000 SB3A Ulster Legend Town/Village!. Existing Flagford Substation SB2 Indicative 220kV Overhead Line Route Option Indicative Overhead Line Route to alternative substation location Moygownagh Sligo Indicative Route of the Underground section of the existing Flagford to Srananagh 220kV line (Overhead Line Option) Preferred North Mayo Substation Location SB2 Alternative Proposed North Mayo Substation Location SB3A Leitrim Co.Cavan Sealing End Compound Location (Line Cable Interface Station 1Km Diameter) Moygownagh Crossmolina Ballina Sligo Tobercurry 0 2.5 5 10 Kilometres Knockmore Foxford Mayo Killasser Lough Mask Swinford Maamturks Charlestown Boyle A MAY-2015 Issued G.F S.T. Issue Date Description By Chkd. Client: Carrick-on-Shannon Castlebar Kiltimagh Ballaghaderreen Tibohine Frenchpark!. Project: THE GRID WEST PROJECT Title: Roscommon 220kV Overhead Line Route Option Scale @ A0: 1:100,000 Castlerea Strokestown!. Prepared by: Checked: Date: G.Fil S.Tinnelly May 2015 Project Director: B.Downes Claremorris Galway Consulting, Civil and Structural Engineers, Market Square, Castlebar, Co. Mayo, Ireland. tel: +353-(0)1-8030406 fax:+353-(0)1-8030409 e-mail: info@tobin.ie Overhead Line Option www.tobin.ie Scale 1:60,000 Longford Ordnance Survey Ireland Licence No EN 0016015 Ordnance Survey Ireland and Government of Ireland Figure 31 A Environment We assessed what the main environmental impact from the cable route would be during the construction phase. We also considered the visual impact of the two converter stations required for this option. Technical The technology is well proven in Ireland and is in line with international best practice. An underground HVAC cable solution has some flexibility, and can provide for future reinforcement. Partial Underground Option Meets the Need Present Value 207.4m 249m Construction Longevity and Flexibility Amount of Undergrounding 3.5 years Moderate Maximum of 30km for the region Present Value Cost 207.4m 249m* *These values are a range of costs, the ultimate cost of which will be determined by the extent of partial undergrounding on this option. The Grid West project EirGrid s Report for the Independent Expert Panel Page 12

Chapter 8 - Analysis of options In this chapter, we compare the work conducted in each of the three previous chapters. We present this work in tables, side-by-side. The tables show the environmental, technical and economic considerations for each option. The darker the colour, the more significant the impact, difficult to reduce effects of impact, greater the risk of occurrence or more likely to occur. The lighter the colour the less significant the impact, easier to reduce the effects of impact, lower the risk of occurrence or less likely it is to occur. More significant impact Difficult to reduce effects of impact Greater risk of lower but sustained effects after reduction More Likely Less significant impact Greater potential to reduce effects of impact Less risk of lower but sustained effects after reduction Less Likely Example of how to review the table. The Grid West project EirGrid s Report for the Independent Expert Panel Page 13

The following tables give more detail on the analysis of each option. They show how the options rate under the headings of Environmental, Technical and Cost. SUMMARY OF ENVIRONMENTAL ASSESSMENTS Option 1 Option 2 High Voltage Direct Current (HVDC) Underground Cable 400kV High Voltage Alternative Current (HVAC) Overhead Line CRITERIA Significance of Impact/Effect Ease of Mitigation Likelihood of Residual Effect (following mitigation) Significance of Impact/Effect Ease of Mitigation Likelihood of Residual Effect (following mitigation) Biodiversity, flora and fauna Soil Landscape and Visual Cultural Heritage Settlements and Communities Climatic Factors Material Assets Recreation and Tourism Noise 1 Water 2 Air Quality 2 Traffic and Noise 2 Table 1 Environmental Analysis of Options Notes: 1. During operation 2. During construction More significant impact Difficult to reduce effects of impact Greater risk of lower but sustained effects after reduction More Likely Less significant impact Greater potential to reduce effects of impact Less risk of lower but sustained effects after reduction Less Likely The Grid West project EirGrid s Report for the Independent Expert Panel Page 14

3 Chapter 8 - Analysis of options Option 3 220kV Overhead Line with 8km of Underground Cable 220kV HVAC Overhead Line with a maximum of 30km of Underground Cable Significance of Impact/Effect Ease of Mitigation Likelihood of Residual Effect (following mitigation) Significance of Impact/Effect Ease of Mitigation Likelihood of Residual Effect (following mitigation) CRITERIA Biodiversity, flora and fauna Soil Landscape and Visual Cultural Heritage Settlements and Communities Climatic Factors Material Assets Recreation and Tourism Noise 1 Water 2 Air Quality 2 Traffic and Noise 2 The Grid West project EirGrid s Report for the Independent Expert Panel Page 15

SUMMARY OF TECHNICAL ASSESSMENTS Option 1 Option 2 Option 3 High Voltage Direct Current (HVDC) Underground Cable 400kV High Voltage Alternating Current (HVAC) Overhead Line 220kV HVAC Overhead Line with 8km of Underground Cable 220kV HVAC Overhead Line with a maximum of 30km of Underground Cable Compliance with all relevant safety standards Compliance with system reliability and security standards The average failure rates during normal operation, average repair times and availabilities of the main elements of each option The expected impact on reliability of supply of unavailability of the development Implementation timelines The extent to which future reinforcement of, and/ or connection to, the transmission network is facilitated Risk of untried technology Compliance with good utility practice More difficult High Risk Less difficult Low Risk Table 2 Technical Analysis of Options * Note: The rating of HVDC circuits is generally quoted in MW, however for ease of comparison we have assumed unity power factor and displayed the rating in MVA, to enable a better comparison with the HVAC options. The Grid West project EirGrid s Report for the Independent Expert Panel Page 16

3 Chapter 8 - Analysis of options SUMMARY OF COST ASSESSMENTS Option 1 Option 2 Option 3 High Voltage Direct Current (HVDC) Underground Cable 400kV High Voltage Alternative Current (HVAC) Overhead Line 220kV HVAC Overhead Line with 8km of Underground Cable 220kV HVAC Overhead Line with a maximum of 30km of Underground Cable Present Value Present Value Present Value Present Value ITEM ( M) ( M) ( M) ( M) Pre-Engineering Costs 16.1 16.1 16.1 16.1 Project Implementation Costs Overhead Line 7.5 100.2 84.5 62.8 Stations 120.9 38.5 33.4 33.4 Underground Cable 145.6 15.5 15.5 58.3 Reactive Compensation 0.0 3.6 3.6 13.4 Other 47.0 17.6 15.9 14.4 Project Life-Cycle Costs Cost of Losses 9.0 6.1 16.0 14.5 O&M 65.2 2.1 2.2 2.9 Decommissioning & Replacement 3.9 0.0 0.0 0.0 Cost to SEM from Development Unavailability (Reliability) Cost of Unplanned Outages 11.0 0.1 0.1 3.8 Cost of Planned Outages 11.6 4.2 4.2 10.5 Contingency Cost Provisions Pre-Engineering Costs 0.4 0.4 0.4 0.4 Project Implementation Costs 32.1 17.5 15.3 18.2 O&M 6.5 0.2 0.2 0.3 Decommissioning & Replacement 0.0 0.0 0.0 0.0 TOTAL 476.8 222.1 207.4 249.0 The Grid West project EirGrid s Report for the Independent Expert Panel Page 17

TRANSMISSION SYSTEM 400, 275, 220 AND 110kV JANUARY 2015 Transmission system in the west of Ireland TRANSMISSION SYSTEM HVDC 400, 275, 220 AND 110kV JANUARY 2015 KILLHILL HVDC KILLHILL KILLHILL EAST-WEST INTERCONNECTOR Over time, patterns of power-flow across the transmission network will change. This can happen when there is significant growth in demand, or when new generators request a connection to the grid. As is the case with other infrastructure, electricity transmission assets have a finite lifespan. Our grid - like road, water or telecommunication networks - requires on going upgrades and refurbishment. EAST-WEST INTERCONNECTOR The Grid West project EirGrid s Report for the Independent Expert Panel Page 18 EAST-WEST INTERCONNECTOR

What will happen next? We are publishing the Report for the Independent Expert Panel for people to consider the work we have done. Separately, we are finalising our other consultation commitments including our new approach to consultation. This work will be complete in the autumn. We will then consult with people on the options and how we propose to select one that is preferred. The report is available online at www.eirgridprojects.com/projects/gridwest/ and can be viewed at our information offices: The Square, Ballaghaderreen, Co. Roscommon Bury Central, Bury Street, Ballina, Co. Mayo Unit 2, Mercantile Plaza block C, Carrick-on-Shannon, Co. Leitrim You can contact the project team for more information through any of the following channels: Telephone: LoCall 1890 940 802 Email: gridwest@eirgrid.com Website: www.eirgrid.com/projects/gridwest Post: EirGrid, PO Box 98, An Post Delivery Service Unit, Quarrypoint Business Park, Castlebar, Co. Mayo. The Grid West project EirGrid s Report for the Independent Expert Panel Page 19

Feedback The Grid West project EirGrid s Report for the Independent Expert Panel Page 20