BREAKER FAILURE PROTECTION

Similar documents
Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

The X, Y, and Z of Circuit Breaker Control

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

Dual Power. Protection. Protection

Breaker-failure protection RAICA

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Testing Breaker Failure Schemes

Solid Dielectric, Three Phase Reclosers CATALOG VS11

Logic Description. For: 115 kv Line Panel Standard Design One Breaker Normal Length Line Panel with New Panels at All Ends

Cost Benefit Analysis of Faster Transmission System Protection Systems

Burns & McDonnell ISU Senior Design Project 2010/2011

IEEE Guide for the Design of Low Voltage AC and DC Auxiliary Systems for Substations

Transformer Protection

POWER SESSION. DP3 Class Power System Solutions for Dynamically Positioned Vessels

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Case Study on On EHV Circuit Breaker Flashover NTPC-SINGRAULI

Sectionalizing. Rick Seeling. Pete Malamen. Introduction Philosophy. Three Phase Reclosers High-Side Protection Specific Applications

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Application Note RESIDUAL BUS MAIN-TIE-MAIN AUTOMATIC TRANSFER SCHEME USING THREE GE 850 RELAYS

Solid Dielectric, Independent Pole Operated Reclosers Catalog O-vst16

S&C TripSaver II. Cutout-Mounted Recloser. For enhanced lateral circuit protection at 15 kv and 25 kv

Breaker Failure Protection PSRC K2 WG

Paralleling Equipment

Outdoor Distribution (15 kv through 25 kv) S&C Fault Tamer Fuse Limiter

EE 741 Over-voltage and Overcurrent. Spring 2014

16kA Solid Dielectric, Triple Option Reclosers Catalog VLT12

S&C Fault Tamer Fuse Limiter. Outdoor Distribution (15 kv through 25 kv)

www. ElectricalPartManuals. com Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers

RUS accepted Catalog O-vst18

Circuit breaker interlocking and operation requirements SIEMENS

1. Take the cover off the relay, taking care to not shake or jar the relay or other relays around it.

Improving Breaker Failure Protection for Generator Applications

MOLDED CASE CIRCUIT BREAKER BASICS. David Castor, P.E.

Advanced Protective Relay Training

Tolerance-Based Time-Current Coordination

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

Data Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

PRODUCT / TEST MANUAL 2L9K2 BATTERY EARTH FAULT RELAY

The Case for Hybrid Generator Grounding

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

ADHERING TO UTILITY INTERCONNECTION STANDARDS MAY NOT GUARANTEE DG SECURITY Wayne G. Hartmann Beckwith Electric Co., Inc. Product Manager, Protection

Breaker failure relay REB 010

Experiences in a Motor Protection Retrofit

C. Figure 1. CA-16 Front View Figure 2. CA-16 Rear View

Islanding of 24-bus IEEE Reliability Test System

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

Functional Overview and Operating Principles for the AR-OH and AR360 Overhead AutoRANGER Fault Indicators

MODEL 422 Submersible Pump Controller

Use of Circuit Breaker Position Indication in Breaker Failure Protection

Solid Dielectric, Three Phase Reclosers Catalog O-vs18

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Appendix C. Interval Every 2 Year. Functional Test Weekly Monthly Quarterly. Semi. Every 3. Engineering Studies

Motor Protection Application Considerations

Zone Selective Interlocking

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Close-Open (Short-Circuit) Time Results Interpretation

Fusesaver specification form

A21M. Introduction: Functional Overview: Key Protection & Control Functions:

3.0 Radial Distribution Systems

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

Seabrook Substation Reliability Improvement Project

Solid Dielectric, Triple Option Reclosers Catalog O-vlt14

6/4/2017. Advances in technology to address safety. Thomas A. Domitrovich, P.E., LEED AP VP, Technical Sales Eaton

34 th Hands-On Relay School

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

White Paper. Ground Fault Application Guide. WL Low Voltage Power Circuit Breakers

This specification describes the minimum requirements for a hoist maintenance safeguard (HMS) system for mine hoists.

2015 WDC Disturbance and Protection Standards Overview

TRANSMISSION PLANNING CRITERIA

EE042: Practical Power System Protection for Engineers & Technicians

Application of Undervoltage Protection to Critical Motors

TIME REQUIREMENT GUIDE (TRG)

4-Day Power System Analysis, Coordination, System Studies

School of Electrical and Information Engineering. ELEC High Voltage. University of Sydney. Dr Keith Mitchell. Engineering

Application Note CTAN #127

Universal Interconnection Technology Technology Roadmap Workshop. Associated Barriers to Distributed Generation

GENERATOR & SINGLE-FUNCTION PROTECTION

AP1000 European 7. Instrumentation and Controls Design Control Document

DIP SWITCH BASED EARTH LEAKAGE RELAY (ELR) WITH CORE BALANCE CURRENT TRANSFORMER (CBCT / ZCT) EL SERIES

Solid Dielectric, Single Phase Recloser

Intelligence in Substation Automation

* With I-Option card only (C. T. connection) Basic connections with isolated contacts

Transfer switch OTEC open or delayed transition

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guidelines for connection of generators:

SALES PRESENTATION FOR RELAYS, CONTACTORS & MOTOR STARTER TESTING EQUIPMENTS

PGE POWER SYSTEMS SEMINAR SERIES

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Power Quality and Protective Device Coordination: Problems & Solutions Part 1 Undersizing of Utility Main Service Transformers

AutoLink Frequently Asked Questions

Transcription:

29 th Annual HANDS-ON RELAY SCHOOL March 12-16, 2012 BREAKER FAILURE PROTECTION Brent Carper, PE Protection & Integration Engineer brent.c@relayapplication.com

OUTLINE Protection System Failures and Breaker Failures BF Protection versus BF Relaying BF Relay Schemes and Logic Special BF Situations BF Setting Calculation Exercise Impacts from Changing Technology Testing and Maintenance of BF Schemes Primary Reference: C37.119-2005 IEEE Guide for Breaker Failure Protection of Power Circuit Breakers

PROTECTION FAILURE Protection System Failures Relay failure Settings failure Control system failure CT/PT failure Battery system failure Catastrophic control house failure (fire) Breaker Failures Fails to trip Trips too slow Fails to interrupt fault current Fails to interrupt load current Flashover when open Fails to close Auxiliary contact problems Catastrophic failure

Breaker Failure Protection versus Breaker Failure Relaying

BREAKER FAILURE PROTECTION BY COORDINATION T A B

BREAKER FAILURE PROTECTION BY COORDINATION T A B

BREAKER FAILURE PROTECTION BY COORDINATION T A B

BREAKER FAILURE PROTECTION BY COORDINATION T A B

BREAKER FAILURE PROTECTION BY COORDINATION T A B Advantages: Simple No extra equipment Simple No risk of misoperation Ultimate protection. Covers ALL failures, not just Breaker Failure (failure of breaker, relay, settings, controls and wiring, battery, etc.) Disadvantages: Slow May not be possible for the backup relaying at [A] to see all faults Conclusions: Common practice for Distribution, but typically not sufficient for Transmission. There is Breaker Fail Protection even though there is not Breaker Fail Relaying. Breaker failure protection is built-in to good protection practices.

BREAKER FAILURE PROTECTION BY COORDINATION T A B 1 2 T M 3 4 5

BREAKER FAILURE PROTECTION BY COORDINATION T A B 1 2 T M 3 4 5 [A] can probably back up [B] and see a minimum fault all the way at the end of the line. [M] may not be able to fully back up the feeder breakers for an end of line fault. Example: Assume 200A load per feeder section, and 800A minimum fault current at the end of line. [A] has 400A max load and needs to pickup on an 800A fault. [M] has 1000A max load, so it cannot be set to pickup on an 800A fault.

IEEE EXAMPLE B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE PROPER CLEARING B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE PROPER CLEARING B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE BREAKER FAILURE B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE BREAKER FAILURE B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE REMOTE BACKUP B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE REMOTE BACKUP B C A 3 4 A 1 2 5 6 C 7 8 Advantages: Completely independent of Substation B. Disadvantages: Slow system instability Slow voltage dips Wide area outage May not be possible for the backup relay to see all faults

IEEE EXAMPLE B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE BREAKER FAILURE RELAYING B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE BREAKER FAILURE RELAYING B C A 3 4 A 1 2 5 6 C 7 8

IEEE EXAMPLE BREAKER FAILURE RELAYING B C A 3 4 A 1 2 5 6 C 7 8 BFR on breaker [3] detects breaker failure condition BFR trips a Lockout relay Lockout relay (86) trips breakers [2], [5], and [7] Lockout relay blocks close of [2], [5], and [7] What else? Transfer Trip to breaker [4] Cancel reclose of [4]

BREAKER FAILURE RELAYING Z1 Z2 67 G Z2 67 G 50 62 01 BFI 87B 86B trip all bkrs on bus 86BF DTT/RC to remote bkrs trip all adjacent bkrs

BREAKER FAILURE RELAYING P B 87B BFI BFI 50 62 BFI 86B 86BF

BREAKER FAILURE RELAYING 1 2 3 87B 87B BF 1 B BF 2 P B BF 3 P

BREAKER FAILURE LOGIC 1. Basic Breaker Failure Scheme 2. 50BF Torque Control 3. Breaker Re-Trip Logic 4. BFI Control Timer 5. BFI Seal-In 6. Minimal Current Scheme 7. Timer Bypass Scheme 8. Dual Timer Scheme 9. Special Schemes

BASIC BREAKER FAILURE SCHEME Four Parts to a Breaker Failure Scheme: Fault Detector (50) or other Failure Detectors Initiator Circuit (BFI) Logic and Timers (62) Output Circuit (BFT)

50BF TORQUE CONTROL

BREAKER RE-TRIP LOGIC

BFI CONTROL TIMER

BFI SEAL-IN

MINIMAL CURRENT SCHEME

TIMER BYPASS SCHEME Note: This logic is for illustrative purposes only. Not intended as a complete scheme. The timer bypass scheme should be supervised by a fault detector, which may not be compatible with torque controlled 50BF.

EXAMPLE BE1-50BF LOGIC

DUAL TIMER SCHEMES Use fast BF timer for multi-phase faults (L-L, L-L-G, 3P) Use slower BF timer for single-phase faults (SLG) Multi-phase faults have larger impact on system stability, and may require fast breaker failure times. Single-phase faults are more common. Dual timer allows fast BFT for the multi-phase fault, but keeps the security of a slower BFT for the most common fault scenario.

SPECIAL SCHEMES Voltage differential Frame leakage detection Breaker differential IPO breakers Redundant breakers

BF SETTINGS Logic Fault or Current Detector Pickup Other Breaker Failure Detectors Set Timers

CALCULATING BF SCHEME TIMERS FAULT PROPER OPERATION FAULT CLEARED CRITICAL CLEARING TIME CALCULATED BY STUDY MAX CRITICAL CLEARING TIME BY COMPANY POLICY NORMAL CLEARING TIME PROTECTIVE RELAY OPERATE TIME BREAKER OPERATE TIME 50FD RESET MARGIN BFI INPUT P/U BF TIMER SETTING 50FD P/U BFR OUTPUT RELAY TIME 86BF OPERATE TIME TT CHANNEL TIME LOCAL BACKUP BREAKER OPERATE TIME REMOTE END BACKUP BREAKER OPERATE TIME CONTROL TIMER SETTING

CALCULATING BF SCHEME TIMERS FAULT PROPER OPERATION FAULT CLEARED CRITICAL CLEARING TIME CALCULATED BY STUDY MAX CRITICAL CLEARING TIME BY COMPANY POLICY NORMAL CLEARING TIME PROTECTIVE RELAY OPERATE TIME BREAKER OPERATE TIME 50FD RESET MARGIN BFI INPUT P/U BF TIMER SETTING 50FD P/U BFR OUTPUT RELAY TIME 86BF OPERATE TIME TT CHANNEL TIME LOCAL BACKUP BREAKER OPERATE TIME REMOTE END BACKUP BREAKER OPERATE TIME CONTROL TIMER SETTING

EXERCISE

IMPACT OF CHANGING TECHNOLOGY Digital Relay BF Protection: Faster, Better, Cheaper, More Solved transient stability problems previously unsolvable Better protection against wide-area and cascading outages Protect against all breaker failure modes, not just one or two Can be more secure if designed well Most utilities moving away from Stand-Alone BF Relays Some utilities (not many) are reversing the trend and going back to stand alone Breaker Failure Relays Reduce misoperations unscheduled maintenance tests Use longer maintenance cycles for BF protection systems

IMPACT OF CHANGING TECHNOLOGY P B 87B BFI BFI 50 62 BFI 86B 86BF

IMPACT OF CHANGING TECHNOLOGY P B 87B BFI BFI BF BFI 86B 86BF

IMPACT OF CHANGING TECHNOLOGY P B 87B BFI BFI BF BF BFI 86B 86BF

IMPACT OF CHANGING TECHNOLOGY P B 87B BF BFI BF BFI 86B 86BF

IMPACT OF CHANGING TECHNOLOGY P B BF BFI 87B BFI BFI BF BF 86B 86BF

IMPACT OF CHANGING TECHNOLOGY 1 2 3 87B 87B BF 1 B BF 2 P B BF 3 P

IMPACT OF CHANGING TECHNOLOGY 1 2 3 BF 1 87B 87B BF 3 BF 1 B BF 2 BF 1 P BF 2 BF 2 B BF 3 BF 2 P BF 3

IMPACT OF CHANGING TECHNOLOGY Digital Relay Timing and Logic Precise timing eliminates relay misoperations due to calibration drift Precise timing and logic allows reducing design margins Digital Relay I/O Sensitive BFI inputs (transients, DC grounds) Solid state relay outputs (sneak circuits) Digital Relay Protective Elements Used to be limited to a 50FD Now we can use 50L and other sensitive detectors that may pick up a lot Solution: Consider using other elements to help add Security, not just Sensitivity (negative sequence, voltage elements, synch check and frequency elements, etc.)

IMPACT OF CHANGING TECHNOLOGY Challenges from Complexity Elaborate/exotic BF logic Wide variety of BF schemes, even in the same model of relay at the same utility May have more than one BF scheme in a single relay May have more than one BF scheme for single breaker Solution: Engineering Standardization Solution: Documentation (written setting descriptions, logic diagrams, and test plans) Challenges with Integrated BF May not be able to disable all BFI s May not be able to disable all BFT s Trend is to completely eliminate all hardwired BFT and lockout relays (IEC 61850) Solution: Design with test switch to relay input that disables the BFI and/or BFT. Especially important for BFTT or 61850.

TESTING AND MAINTENANCE OF BREAKER FAILURE PROTECTION Challenges with BF Protection Difficult to test intentionally Easy to test unintentionally

TESTING AND MAINTENANCE OF BREAKER FAILURE PROTECTION There is a difference between testing the BF Relay and testing the BF Relaying System Many utilities perform maintenance testing of the BF Relay, but are not testing the entire Breaker Failure Protection System. Good maintenance practices (and NERC compliance requirements) are to test the Protection System: Maintenance program for the BF Relay Maintenance program for CT s/pt s Maintenance program for the Battery and DC system Maintenance of the BFR Protection System must include: Rolling lockout relays and tripping breakers Best practice: simultaneous functional test (clear the bus)