NETWORK. Annex AC. Aurizon Network Ballast Fouling, 4 March 2013

Similar documents
Management of Ballast Fouling in the Central Queensland Coal Network

Shoulder Ballast Cleaning Effectiveness

Shoulder Ballast Cleaning Effectiveness

TITLE: Drainage, Better Drainage, and More Drainage PRESENTER: DARRELL D. CANTRELL CANTRELL RAIL SERVICES, INC VICE PRESIDENT ENGINEERING

Coal Dust Frequently Asked Questions

TE-II (10CV63) Ballast

Sustainable Rail Strategy The Value of Quality

Materials and Trackbed Design for Heavy Haul Freight Routes : Case Study. By Dr Matthew Brough

PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION

Class 1 Crushed rock ballast for use primarily on main line track. Class 2 Crushed rock ballast for use only on other than main line track.

JRC EFFECTS OF BALLAST DEGRADATION ON PERMANENT DEFORMATION BEHAVIOR FROM LARGE-SCALE TRIAXIAL TESTS

The Use of Falling-Weight Deflectometers in Determining Critical Velocity Problems. Craig Govan, URS, Trackbed Technology

Submission on the 2013 Blackwater Electric Traction Pricing DAAU Anglo American Metallurgical Coal Pty Ltd

Senate Standing Committees on Economics 27 June 2014 PO Box 6100 Parliament House CANBERRA ACT 2600 By

THE INFLUENCE OF BALLAST FOULING ON TRACK SETTLEMENT

Monitoring of switches & crossings (turnouts) and tracks

To support the amended claim, please find attached the amended Capex Expenditure amounts, by Project, as Appendix A. Please note:

The major roadways in the study area are State Route 166 and State Route 33, which are shown on Figure 1-1 and described below:

Erol Tutumluer, Yu Qian, Youssef Y.M.A. Hashash, and Jamshid Ghaboussi

UPDATE OF TTCI S RESEARCH IN TRACK CONDITION TESTING AND INSPECTION. Dingqing Li, Randy Thompson, and Semih Kalay

Technology and maintenance of tracks at ÖBB

Transportation Engineering II UNIT - I

Shaping the Future of Railway Industry Student Engagement Event 20 th September 2016

Study on System Dynamics of Long and Heavy-Haul Train

Management of Clearances

Safety Sense Ballast Under Cutter

1) The locomotives are distributed, but the power is not distributed independently.

Simulation of railway track maintenance trains at MATISA

Safe Work Instruction

CER/EIM Position Paper Ballast Pick-up due to Aerodynamic Effects. October Version 1.0

EME2 Pavement and mix design. Laszlo Petho, Pavements Manager Fulton Hogan.

15 Nelson-Marlborough Regional Plan

Speed Limit on Railway Curves. (Use of SuperElevation on Railways)

EMGA Mitchell McLennan Pty Limited (EMM) has been engaged to complete quarterly attended noise

PREDICTION OF BALLAST RETURN FROM HIGH OUTPUT BALLAST CLEANERS (HOBC)

Interim Report into Cement Train Derailment at the Suir River Viaduct On 07/10/03

Buffer Stops and Restraining Devices for Dead End Tracks

PROPEX The exceptional choice for sustainable erosion control to replace hard armour

FUEL EFFICIENCY CASE STUDY

ECONOMIC AND FINANCIAL ANALYSIS

METHODOLOGY FOR THE SELECTION OF SECOND HAND (RELAY) RAIL

NUMERICAL ANALYSIS OF LOAD DISTRIBUTION IN RAILWAY TRACK UNDER WHEELSET

Research Brief. Simulation and verification of results from 125mph current collection modelling for two pantographs. T841 - January 2011.

Comparing Total Mine Airflow Requirements using a comprehensive new approach vs. traditional method(s)

RM 900 VB. STRABAG The Group. STRABAG Rail GmbH. STRABAG Rail GmbH

Road Condition Assessment and Road Contributions Study. 270 Grants Road, Somersby. June 2015 Our Ref: SY140135

Prerequisites for Increasing the Axle Load on Railway Tracks in the Czech Republic M. Lidmila, L. Horníček, H. Krejčiříková, P.

Under Sleeper Pads on the Ofoten Line

TABLE OF CONTENTS 6 MEDIUM-TERM COAL MARKET REPORT 2012

Lateral Resistance Characteristics of Sleepers in Railway Ballasted Tracks from Laboratory Model Tests

Special edition paper

Discipline: Engineering (Track & Civil) Category: Code of Practice. Clearances. Section 7. Applicability. ARTC Network wide.

Challenge G: An even more competitive and cost efficient railway. Improving ballast tamping process

GLADIATOR. GLADIATOR Telescopic Steel Covers

Kingdom of Cambodia. Ministry of Public Works and Transport. Ministry of Rural Development WORKSHOP ON

Port of Vancouver Schedule 1 Rail Engineering, Operations, and Safety Review Final Report Prepared for: HDR

Accelerated Pavement Tester

Please note: This guideline has been updated according to the BPP extension requirements.

FRONTAL OFF SET COLLISION

Traffic Micro-Simulation Assisted Tunnel Ventilation System Design

STANDARD OPERATING PROCEDURE. Standard Operating Procedure No: SOP-001 Version Number: 1.1. Vari-Stem blast hole stemming plug

Maintenance - the key driver of railway infrastructure costs

Final Report. Solar feed in tariff for regional Queensland for

EMaSM. Analysis of system response

Enterprise Services, General Manager Technical Standards. Track and Civil Code of Practice Section 7 Clearances Technical Note ETD-07-01

NOW INTEGRATED WITH MLM DESIGNED FOR VAV DIFFUSER SYSTEMS LINEAR CHARACTERISTICS NO REGULAR MAINTENANCE REQUIRED PRESSURE SENSOR AND CONTROLLERS

CEMA position on draft braking regulation, 4 June 2008 ENTR/F1/ /rev16

Spillage from a semi-buried jet fuel tank 30 December, 2005 Sainte-Marie [Reunion Island] France

NEOBALLAST SEEKING FOR THE BALLAST OF THE FUTURE

A Guide to Key Railroad Terminology for the Northeast Corridor

Technical support to the correlation of CO 2 emissions measured under NEDC and WLTP Ref: CLIMA.C.2/FRA/2012/0006

Construction Emissions Estimates ICTF Modernization Project Long Beach, California

ENVIRONMENTAL IMPACT STATEMENT

ONYX 360. Rolling PDC cutter

Interrelation between Wavelengths of Track Geometry Irregularities and Rail Vehicle Dynamic Properties

Rolling resistance as a part of total resistance plays a

Tool 3-2 Rope pump installation check list for quality control, 3 rd Edition August 2016 Rope Pump INSTALLATION checklist for quality control A A1 Des

RECOMMENDATIONS REGARDING HIGHER AXLE MASS LIMITS FOR AXLES FITTED WITH WIDE BASE TYRES

The criteria of choice for new High Speed fleet

Field test for the comparison of LNG static and dynamic mass measurement methods

REDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS

Railway Engineering: Track and Train Interaction COURSE SYLLABUS

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Introduction. Cent re-bearing longitudinal movement in transitions due to track twist loads; \ 1

BUSINESS BREAKFAST SEMINAR LEONARD M. MAKWINJA CHIEF EXECUTIVE OFFICER. December 10, 2018

Permissible Track Forces for Railway Vehicles

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Applicable standards in HS Infrastructure subsystem TSI (2008/217/EC)

EUROPEAN UNION AGENCY FOR RAILWAYS Annex 1 006REC1025 V 1.0

The development of a differential for the improvement of traction control

Optimisation of Rolling Stock Wheelset Life through Better Understanding of Wheel Tyre Degradation

Proposal for draft amendments to ECE Regulation No. 13

Automated Lubrication Yields Concrete Results

The following section summarises the present conditions related to transportation for the proposed development of the Matimba B Power Station:

Field investigation on variation of rail support modulus in ballasted

Multilayer Energy Dissipating Inlet Column in Center-Feed Clarifiers 1

TRAFFIC IMPACT ASSESSMENT PART OF AN ENVIRONMENTAL IMPACT ASSESSMENT FOR THE KEBRAFIELD ROODEPOORT COLLIERY IN THE PULLEN S HOPE AREA

Using OpenTrack to determine the electrical load on the network

Cost-Benefit Analysis of Options for Certification, Validation and Monitoring and Reporting of HDVs

Development of long life structural asphalt

Transcription:

NETWORK Annex AC 4 March 2013 Aurizon Network Ballast Fouling,

Overview of the problem Ballast is the material that is laid on the rail bed under the sleepers, providing stability and drainage to the track structure. It is an essential structural component of the track as it transfers the loads of the train through the sub-ballast and formation. The interlocking properties of the shape of the ballast rock also provide track stability by reducing the lateral, horizontal and vertical movement of the rail track. Ballast is graded stone material where the voids between stones also allow for the drainage of water from the track. It can deteriorate in a number of ways, including crushing by the loads borne by the track infrastructure. One key source of deterioration is the fouling of the ballast. Fouling occurs from a number of sources including natural attrition of the ballast itself, external contaminants such as dust, sand and dirt either blown or falling into ballast, the infiltration of underlying layers into the ballast and through foreign contaminants such as coal. The retention of fine particles in the ballast can trap water and lubricate it, which can eventually compromise the track stability. This also reduces the service life of the ballast and increases the frequency of maintenance interventions. Figure 1 shows a diagram of the interactions that cause ballast contamination and illustrates the dynamic and interrelated nature of the various elements. Figure 1: Ballast fouling interrelationships The ballast therefore needs to be cleaned to remove these particles in order to restore the elasticity and draining properties of the ballast. Ballast cleaning machines remove the accumulated dirt, coal and broken ballast, before the rail bed is topped up with new ballast.

Figure 2 shows in an alternative cause and event layout the causes for Ballast contamination. Figure 2: Ballast fouling interrelationships (Cause and Event layout) While the causes of coal fouling are primarily driven by factors that are not within the direct control of the below rail network provider (i.e. through spillage from wagons), it bears most of the costs (i.e. as the entity required to maintain the ballast). The management of this externality is a feature of all coal networks around the world, including by the Class 1 railroads in the United States. Aurizon Network has been working collaboratively with supply chain participants to invest in technologies and modify operating practices to substantially reduce coal spillage within the rail corridor under its Coal duct Management Plan. In Australia (and in most other jurisdictions), coal is hauled in open top wagons. One of the key sources of coal loss is when coal falls out of the wagon. This could occur due to wind erosion or and/or load settling and displacement in transit. Coal spillage from wagons can be from: Parasitic coal on external parts of the wagon due to poor loading practice Coal blown from the top of the wagon Coal falling through the doors Coal ploughed from loading or unloading facilities. Figure 3 shows an example of the network where ballast has been contaminated with coal spillage. Figures 4 and 5 shows evidence of the build up of parasitic coal on a wheel bogie and on a wagon.

Figure 3: Ballast contaminated with coal spillage Figure 4: Example of parasitic coal on a wheel bogie

Figure 5: Example of parasitic coal on a wagon To better manage this issue of ballast fouling, Aurizon Network have analysed 1170 km of Ground Penetrating Radar data on the Central Queensland Coal Network which represents the most highly trafficked tracks on the four systems including the North Coast Line, Central Line, Rocklands to Burngrove, Hay Point to Goonyella and the Oaky Creek Branch. This represents about 80% of the ballast cleaning requirements of the network. The Science Behind Fouling Levels for Intervention Aurizon Network intervention level for ballast cleaning is 30% PVC (Percentage Void Contamination). This has been derived empirically based on original research and with consideration of the limitations of other fouling measurements and intervention limits adopted by other railways. The 30% PVC represents that the voids (comprising of the clean ballast profile) are 30 % filled with contaminant. Empirically this equates to 100mm depth of competent ballast below the sleeper. Traditionally the fouling index has been based on the mass of fines in the ballast profile as a proportion of the total mass. Consequently it is sensitive to the specific gravity (s.g.) of the contaminants and this can vary wildly along a track length let alone between different railways with various operating parameters and product mix. This is the main reason Aurizon Network has developed a fouling index based on PVC which is not reliant on the s.g. of the contaminant but is dependent on other physical properties of the contaminant such as hydraulic conductivity, moisture content and load bearing competence. The closest comparisons on intervention limits can be made with the Coal Lines of the South African Railways (Transnet). The axle load, operating parameters and product is most similar to the Central Queensland Coal Network. Transnet intervention limit for their coal line is defined as the Critical Fouling Point and set in accordance with the depth of the competent ballast below the sleeper so that perfectly clean ballast corresponds to the full depth of clean ballast and is 0%. At depth of clean ballast of 70 mm below sleeper the ballast is deemed fully fouled at 100%. By fully fouled it is meant the ballast is no longer performing competently so that the intervention limit is set at 70 to 75%. In the context of our Central Queensland Coal Network ballast depth of 300mm the critical fouling point would equate to 120 mm competent ballast below the sleeper. This is very similar to the empirically defined Central Queensland Coal Network intervention mentioned above and based on 30% PVC. The University of Illinois has carried out strength tests of coal fouled ballast collected from the BNSF Powder River Basin lines. They report that the lowest shear strength of foul ballast occurs at fouling index of 25% by weight of ballast at 35% moisture content. This condition occurs when the ballast voids are completely full. That is to say the performance of the fouled ballast at this level is no better than wet coal dust at 35% moisture content. At moisture saturation the situation is worse. The coal lacks any strength by way of soil suction and has lower shear strength so that track is quite unstable.

AURIZON In 2005 BNSF reported track instability due to ballast fouling as a cause of two derailments on Powder River Basin coal lines. This fouling index for coal fines of 25% by weight should be compared with the European intervention limit of 30 % which if applied to a coal fouling situation would be totally intolerable due to the low specific gravity of coal. The European intervention limit is applicable in a particular context which appears to be where the fouling material is of similar specific gravity to the source ballast. It is set at the limit at which surface water is prevented from draining away and corresponds to a critical rainfall rate of 1 mm per hour. Given that the rainfall rates commonly experienced in the Central Queensland Coal Network are far in excess of 10mm/ hr this intervention limit would appear to have no relevance to the Central Queensland Coal Network circumstance. The University of Wollongong have carried our hydraulic conductivity tests on coal fouled ballast from Australian Railways and shows that the hydraulic conductivity of 0.5 mm/s of coal fouled ballast at around 30 % PVC is equivalent to a fouling index of 7% fouling byweight of coal. Putting this into the European context the hydraulic conductivity of 0.5 mm/s is similar to ballast fouled with sand at the intervention level of 30% by weight of ballast. Moisture in the track structure has a deleterious effect and shortens life of ballast and formation. Foul ballast retains moisture at high levels and impedes the flow of water away from the track and formation. Formation repair is costly and typically exceeds $1,500,000 per kilometre compared with ballast cleaning costs. Formation repairs of one kilometre require suspension of traffic for up to five days which is not a sustainable approach without significant additional infrastructure. Forecasts for a total of 2200 track km of the Network and have been computed by applying an average fouling rate. al carried on a further 1030 km medium to low trafficked lines based on forecast tonnages. There are a he Network that are single mine spurs and balloon loops carrying low tonnage which have little impact on e period to 2019. The exception is some of the older mine balloon loops that have been considered in the - forecasts of undercutting other than by Ballast Undercutting Machine works. The Maintenance Effort if coal fouling was not an issue, that is the natural degradation of the aggregate. The methodology for determining the long term forecast for Ballast Undercutting Machine work relies on ballast fouling rates for each km of the track and applying these to the forecast coal tonnages for Draft Access Undertaking. Beyond this period a 5% pa tonnage increase is applied. Where rates of fouling are not able to be determined because of insufficient historical information or other reason a default average of 5% PVC per 100 Mnt is applied. Other Undercutting Works The areas inaccessible to the Ballast Undercutting Machine will continue to be fouled and an accumulated deficit will mount unless a method of foul ballast removal can be deployed for turnouts and adjacent track at production levels that match available possession windows. Included in this work are mine balloon loops Forecasts are that the equivalent of----per annum of this type of undercutting work will be required --- expected in s~ loops The Network Maintenance Renewal Plan 2012/13 this ~ includes funding for these types of work alon with some s ecific ca ital fundin. This work will need to be combined with the abili to attend to approximately On the Blackwater System in particular, there is a high incident of isolated short lengths of undercutting that will require undercutting not suited to the Ballast Undercutting Machine works. UT 4 Maintenance Submission - Appendices 20130304 - AURIZON.

AURIZON Some more detailed analysis of this is required to quantify but may be assumed that:- The Network has aroun~y fouled mainline turnouts requiring attention immediately. Half of these are on the heavily trafficked Goonyella System. The Ground Penetratin Radar record covers around p.a. lliliiliiiilf nsidered then it is estimated aroun UT 4 Maintenance Submission - Appendices 20130304 - AURIZON.