Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Similar documents
Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

MVDC PLUS Managing the future grid

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

PES Cook Islands KEMA Grid Study Final Report

EVENT, DATE. The Smart Grid. Challenges & Solutions. Fahd Hashiesh, Global Business Development Manager, Power Consulting

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Experiences with Wind Power Plants with Low SCR

Krzysztof Rudion. Otto-von-Guericke Universität Magdeburg , Bremerhaven

Chapter 1. Overview of HVDC applications

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA

Enabling the power of wind. Competence and expertise for wind power customers

ABB Group August 27, 2010 Slide 1

Integration of Large Wind Farms into Electric Grids

ABB Wind Power Solution

Power Quality innovative SolutionS for industrial and distribution grids.

Power Conditioning of Microgrids and Co-Generation Systems

Offshore Wind Connections HVDC for Offshore Grids

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

HVDC. TMT&D provides the best and most economical HVDC system.

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

RESEARCH PROJECT VERBUNDNETZSTABIL

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

ABB FACTS Grid connection of Wind Farms

Solar Power Switchgear & Energy Storage Renewable Energy Systems

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems

Essential Reliability Services From PV Plants

HVDC Technology. Phil Sheppard Head of Network Strategy

Targeted Application of STATCOM Technology in the Distribution Zone

Certificate of Conformity self-generation unit

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani

PV Grid Integration Research in the U.S.

Certificate of Conformity self-generation unit

Certificate of Conformity self-generation unit

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Challenges and opportunities in the integration of PV in the electricity distribution networks

ABB November 16, 2016 Slide 1

Renewable Energy Grid Integration and Distributed Generation Specialization Syllabus

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

Guidelines for connection of generators:

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

Regulating life s ups and downs

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Medium Voltage. Power Factor Correction Reactive Compensation Harmonic Filters. Electrical Power Quality Management at its best.

POWER QUALITY SOLUTIONS FOR INDUSTRIAL AND DISTRIBUTION GRIDS. W WW.R EINHAU S EN.COM

ABB POWER SYSTEMS CONSULTING

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Getting Smart Evolution to the Smart Grid April 2008

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Regenerative Utility Simulator for Grid-Tied Inverters

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

Dynamic Reactive Power Control for Wind Power Plants

Cabo Verde s new Renewable-Energy-Friendly Grid Code

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

The Circuit and Control Technology in the Power Conditioner and Converter for Wind Turbine Systems

ECE 421 Project 1, Group 3 HVDC. Brian Beilstein, Robert Germick, James Haney, Alexander Joss, Matt Murphy, Shutang You

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy

TRANSMISSION PLANNING CRITERIA

Agility in energy Ahead of the challenge, ahead of the change

Grid Stability Analysis for High Penetration Solar Photovoltaics

ABB in Wind &Integration of renewables

Session 10 NERC Interconnection Requirements

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors

Synchronous condenser solutions siemens.com/energy/facts

4-Day Power System Analysis, Coordination, System Studies

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

Grid Code Testing of Wind Turbines by VSC-based Test Equipment

ROBERTO BERNACCHI, GLOBAL PRODUCT MANAGER, 16 JUNE 2018 New power infrastructure concept for greener container terminals Creating Stronger, Smarter

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

Distributed Energy Resources

POWER QUALITY SEMINAR OF IRAN, 2 ND MARCH 2017 Power Quality Seminar. Abel-Zhang,Power Quality Center Manager

High speed, closed loop frequency control using PMU measurements for power grids

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

Small Electrical Systems (Microgrids)

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Lösungen zur Spannungsregelung in Verteilernetzen

India Smart Grid Week, 2017

Certificate of Conformity self-generation unit

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Robust Control Technique for Grid-connected Power Conditioner

Abstract. Benefits and challenges of a grid coupled wound rotor synchronous generator in a wind turbine application

Testing procedure for the evaluation of grid compliance of power generating units according to the requirements of the Indian Grid Code

C PER. Center for Advanced Power Engineering Research C PER

HVDC with Voltage Source Converters A Desirable Solution for Connecting Renewable Energies

Transcription:

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1

Characteristics of the Project Parameter Detail Generation Site Ukujima Island Source of Energy Photovoltaic Installed Power 430 MW Voltage at Generation Site 0.4 / 33 kv Point of Common Coupling Ainoura Substation Ainoura S/S 220 kv Network Operator at PCC Kyushu Power & El. Length to PCC Voltage at PCC 65.5 km 220 kv 400 MW 65.5 km Ukujima S/S 約 500m 漁業権境界29 Juli 2014 Page 2

Challenges: Project Internal Design General Considerations The installed capacity of 400MW is identically to kinds of conventional Power Plants The project s Character of a Power Plant and therefore the meaning for the existing Japanese Transmission System requires the consideration of appropriate technical solutions concerning The use of applications according to the State of the Art The fulfillement of the criteria for the reliability of power supply The knowledge of specifics for the Japanese Transmission system (e. g. JEAC) The application of international experiences for the grid connection of Renewables The electrical phenomena caused by the long submarine cable connection Two Issues are the main Challenge concerning the Planning Process: - A technical-economical Green-Field Structure for the Network at Ukujima - The Identification of the optimal HV power transmission technology! 29 Juli 2014 Page 3

Challenges: Project Internal Design Green-Field Network Planning Baseline Design PV Farm 400MW Internal PV-DC network 10Tkm Invertertstations 217 pcs. 434 Inverter 1000kVA each Network 33kV 150km - Radial MV network structure - max 18 Stations per MV-String - max 630 A per String - only Load-break switches Substation 220kV 2 x 250 MVA Submarine Cable 220kV 65km cross section 1.600 mm² Al General Structure of the internal MV Network 33 kv A B C D 29 Juli 2014 Page 4

Challenges: Project Internal Design Power Transmission Technology to Ainoura HVDC vs. HVAC LCC- / CSC-Technology *1 - Use Since early 1950 Not applicable for Ukujiima! - Requires connection of two active power networks at both sides of the link Applicable for Ukujiima! - Use of AC technology for long distances on- and offshore is well approved and experienced VSC-Technology *2 - Use since 1999 Applicable for Ukujiima! - Contrary to LCC, can be applied for linking isolate networks, like remote islands For both technologies practical experiences are available *1 Line Commutated Current-Sorced Converter *2 Voltage Source Commutated 29 Juli 2014 Page 5

Challenges: Project Internal Design Int l HV Power Transmission Experiences VSC - HVDC HVAC Other worlwide applications besides Germany / Europe are available for both technologies as well! Conclusion for the UMSP project The power to be transmitted The length of connection 400 MW 65 km Both Technologies - HVAC and HVDC are applicable! 29 Juli 2014 Page 6

Challenges: Project Internal Design Optimal HV Power Transmission Technology Advantages HVDC Independent control of Active and Reactive Power Disadvantages More expansive than HVAC Cost Break-even >70km; lower losses will not compensate higher investment costs Space problems for the placement of the landside converter station Extreme long lead time HVAC Most economical solution considering CAPEX + OPEX Expected influences to the existing transmission system 220kV More References Separate System Studies are necessary 29 Juli 2014 Page 7

Challenges: Project Internal Design Need and Content of System Studies The Main System Study Issues due to the influence of the existing transmission system by a long distance HVAC cable are: I. Power Quality Analysis Impedance-Frequency-Curve and Harmonics 200 Impedance [Ohm] 150 Z=f(f) with UMSP Displacement of the Resonance due to the long HVAC cable Z=f(f) without UMSP II. Electromagn. Transient Analysis Voltage Drops, Surge Resonances and Harmonics during switching processes Zero-miss currents during normal and disturbed network conditions 0 0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 Frequency [Hz] Effects of the Cable Discharge to the existing equipment (e. g. breakers) Lower Harmonic Resonances during a Fault Current 100 50 29 Juli 2014 Page 8

Challenges: Project Internal Design Powerful System Analysis Software PowerFactory DIgSILENT, Germany Load Flow analysis and Short-Circuit Analysis (IEC 60909, ANSI C37, IEC 61363, complete method, multiple faults, DC Short-Circuit calculation according to IEC 61660 and ANSI/IEEE 946) Optimal Power Flow (OPF): Reactive power optimization and economic dispatch Protection Functions: Time-Overcurrent Protection and Distance Protection; comprehensive relay library with relay models suitable for steady-state, RMS and EMT calculations Voltage stability analysis: PQ and QV curves; P-, Q-, I- and V-measurement models, consideration of load flow constraints, verification of system observability Cable Sizing: Automatic cable sizing and cable reinforcement optimization Basic MV/LV Network Analysis: Feeder Analysis Tool, Radial Feeder Tool, Backbone Calculation Power Quality and Harmonic Analysis Harmonic Load Flow and Filter Analysis: Various harmonic distortion indices, Multiple harmonic injections Flicker Analysis: Flicker Assessment (IEC 61400-21), Flicker Meter (IEC 61000-4-15) Impedance-Frequency-Curve: Balanced and unbalanced network model Stability Analysis Functions (RMS): balanced/unbalanced, multi-phase AC networks, DC networks, simulation of any kind of faults or events + Electromagnetic Transients (EMT): FACTS, HVDC interconnections, power electronic devices 29 Juli 2014 Page 9

Challenges: Project Internal Design Outcome of the System Studies The Main Outcome of the System Studies is: Definition of measures for a secure and stable operation under undisturbed conditions Fulfilment of the Grid Code requirements acc. to JEAC 9701 Definition of Countermeasures for the specific electrical phenomena due to longdistance submarine cables (e. g. harmonic filters, surge arresters) Definitions for the setting of the Protection Devices Challenges Chances Input System Study Output Constrution Contribution to a Stable Operation of the Transmission System 29 Juli 2014 Page 10

Chances: Stability of Transmission Systems Stability Criteria The Operator of the Transmission System (TSO) is responsible for the keep of it s Stability! Power System Stability Frequency Stability Voltage Stability Rotor Angle Stability * Stability of the Actice Power Balance Stability of the Reactice Power Balance Small Signal Stability Large Signal (Transient Stability) Generation U Balanced Reactive Power Area Unbalanced Reactive Power Area TSO System Frequency Demand U min Safe Operation Area CriticalOperation Area Impossible Operation Area ** P max P * Not in Scope ** Source: EirGrid 29 Juli 2014 Page 11

Chances: Stability of Transmission Systems Stability Requirements to Generating Units The Main International Requirements to Generating Units including Renewables are: Criterion Description of the Requirement Stability Type Frequency range Normal operation 47.5 Hz f r50hz 51.5 Hz or 57.0 Hz f r60hz 61.8 Hz (Europe 48.5 Hz f r50hz 50.5 Hz) Voltage range Normal operation between 80% U r 120 % (Europe 80% U r 120 %) Frequency Voltage JEAC 9701 Active Power Control Active Power Control within a given Frequency Range Frequency --- Reactive Power Control Possibility to meet a given P-Q-diagram independently to voltage changes (P-Q-diagram in a voltage band) Voltage Fault Ride- Through Stable connection during network faults within a give time-frame; (not in JEAC: injection of a reactive current) Voltage Information exchange Online transfer for the value of active power and possibility for its reduction by the grid operator Frequency Control system Voltage, reactive power or power factor control Voltage 29 Juli 2014 Page 12

Chances: Stability of Transmission Systems Stability Requirements to Generating Units Detailed Requirements to Renewables according to JEAC 9701-2012: Active Power Control No specific requirements regarding the control of the active power due to frequency deviations Reactive Power Control Power Factor between 0.9 lag and 0.95 lead (systems point of view) No specific requirements regarding the infeed of a reactive current during 0.9 lag 200 +Q150 100 50 P Max 0 400-350 -300-250 -200-150 -100-50 0 50 100 P [MW -P +P -50-100 0.95 lead -Q -150-200 Q [Mvar] Lagging 0.85 Fault-Ride-Through Not disconnection during a voltage drop down to 20% U r over 0.3 sec Reversion to 80% of U r within 0.1 s after clearence of the external network failure Voltage Level [p. u.] 110 100 90 80 70 60 50 40 30 After March 2017 Before March 2017 Achievement of the origin voltage after 1.5 sec 20 10 0-0.10 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 Time [s] 29 Juli 2014 Page 13

Chances: Stability of Transmission Systems Stability Requirements to Generating Units Ability for Stability Support by the INVERTERS of the UMSP in Comparison to JEAC 9701 Criterion According to JEAC 9701-2012 Additional Ability Active Power (AP) Control Reactive Power Control Full Compliance to JEAC Normal Operation in the range 57.0 Hz f r60hz 61.8 Hz Full Compliance to JEAC P Max Reverse Power Flow 0.9 lag 0-400 -350-300 -250-200 -150-100 -50 0 50 P [MW] 1-50 0.95 lead Q [Mvar] 200 Non-Reverse Power Flow 150 100 50-100 0.85 lag AP Reduction starting from a Setpoint (e. g. 50.2Hz); The Gradient of the Power Reduction in MW/Hz must be Defined by the TSO P P ref Active Power Setpoint f f n i Droop f f n Fault-Ride- Through -150 Full Compliance to JEAC Injection of a Reactive Current during the external network fault Additional support for the Voltage at the PCC 29 Juli 2014 Page 14

Chances: Stability of Transmission Systems Capabilities of the Renewables Assets Summarize: How UMSP is able to meet stability requirements of JEAC? Criterion Description Inverter - Cability according to JEAC 9701 Add. Ability Active Power Control Normal operation 57.0 Hz f r60hz 61.8 Hz AP Variation during Frequency deviations Reactive Power Control Fault-Ride-Through Normal operation between 80% U r 120 % 0.9 lag cosφ 0.9 lead Not Disconnection; Voltage Recovery Reactive Current injection during FRT UMSP is able to meet the Stability requirements by JEAC AND to provide additional services for the keep of the stability! 29 Juli 2014 Page 15

Please don t hesitate to ask any questions at any time Contact: Photovolt Development Partners GmbH Kurfuerstendamm 136, D-10711 Berlin Joerg Zillmer Peter Gerstmann Principal Consultant Managing Director Phone: +49 1736095034 Phone: +49 30 375926711 email: zillmer@pvdp.eu email: gerstmann@pvpd.eu 29 Juli 2014 Page 16

Chances: Stability of Transmission Systems Capabilities of Renewables Assets P / kva 1 3 2 f / Hz 29 Juli 2014 Page 17