NUCLEAR POWER PLANTS in TURKISH POWER SYSTEM TURKISH DELEGATION

Similar documents
Turkey's Nuclear Power Programme

Georgia Transmission Corporation Georgia Systems Operations Corporation

TURKISH ELECTRICITY NETWORK

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2.

TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Presentation Plan. 1. Introduction. 2. Licensing Procedure in EMRA. 3. Current Situation on Licences

ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC

Generators for the age of variable power generation

Variable speed control of compressors. ABB drives control the compressors of the world s longest gas export pipeline

New 115 kv Disconnect Switches at Bloomsburg MTS

Jemena Electricity Networks (Vic) Ltd

The Electric Power System

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

PowerGen Europe 2014 CIMAC circle

The Swedish Government Inquiry on Smart Grids

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

ABB POWER SYSTEMS CONSULTING

The Romanian Grid a Hub for Regional Electricity Markets in SEE

Vattenfall Capital Markets Day 2009

SET Plan The 10th Year Anniversary Central European Energy Conference 2017

Non-BM Balancing Services Volumes and Expenditure

Consequences on Grid Operation by Decentralized Renewable Power Generators

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

FLEXIBILITY & NUCLEAR ENERGY MANAGEMENT IN FRANCE

15 Nelson-Marlborough Regional Plan

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Electrical grid stability with high wind energy penetration

Implementation of a Wide Area Monitoring System (WAMS) for Austria's Power Grid

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Microgrid Storage Integration Battery modeling and advanced control

Climate change drivers for a single and smart EU grid

Electric vehicles demand forecast. Erwan Hemery and Bruce Smith

Unit Protection System for Pumped-Storage Power Stations

2016 Load & Capacity Data Report

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

TRANSMISSION PLANNING CRITERIA

The Electric Power System

GOLDWIND 2.5MW PERMANENT MAGNET DIRECT-DRIVE (PMDD) WIND TURBINE

Diversifying into Marine Energy. ABB March 2015

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Case study: Utility-scale battery for balancing power in Germany

The Role of Electricity Storage on the Grid each location requires different requirements

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Synchronous condenser solutions siemens.com/energy/facts

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Electricity industry structure and capacity growth trends

Interconnection between Arab countries

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Sensors for hybrid power generation system

26 th Oct Prof. Jeongtae KIM Daejin Univ. KNC Representative

Christian Ohler, ABB Switzerland Corporate Research Physics of Electric Power Systems. ABB Group August 1, 2012 Slide 1

Reliable, economical and safe siemens.com/rail-electrification

Final Written Examination.

C PER. Center for Advanced Power Engineering Research C PER

PSPP AVČE THE FIRST PUMPED STORAGE HIDROPOWER PLANT IN SLOVENIA

Electricity industry structure and key players

Building Collaboration Between East African Nations via Transmission Interconnectors

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

POWER FACTOR IMPROVEMENT CONCEPT FOR LARGE MOTORS

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

ABB Wind Power Solution

Florida Public Service Commission Rule Development Workshop

15 Nelson-Marlborough Regional Plan

Offshore Wind Connections HVDC for Offshore Grids

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Essential Reliability Services From PV Plants

Development of power industry in Russia

Smart Grid: A Building Utility Partnership. Steven T. Bushby Engineering Laboratory

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Smart Grid A Reliability Perspective

Energy Outlook for Asia and the Pacific

Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic

Measuring the Smartness of the Electricity Grid

Impact of Distributed Energy Resources on Transmission System Reliability

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Connecting your business diesel generation

GRID INNOVATION CAUCUS CO-CHAIRS

Small Electrical Systems (Microgrids)

Decision on Merced Irrigation District Transition Agreement

Flexible gas markets for variable renewable generation

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

9 th IFIC Workshop Athens 26 & 27 January 2012

Interconnection System Impact Study Report Request # GI

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

COMMISSION REGULATION (EC)

Energy Saving Practices and Enlightenments in State Grid Corporation of China (SGCC) Dr. Xianzhang LEI, Dr. Yanqiu BI 1st December 2015, COP21, Paris

Electricity System Operator EAD. Difficulties in Grid Planning & Development

Solar-Wind Specific Request for Proposals

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

BSCP31 Trading Unit Application for West Burton A&B Power Stations

Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Transmission Grid Development & Investment Planning on EHV Level in Germany

Tidal lagoon snapshot

Transcription:

NUCLEAR POWER PLANTS in TURKISH POWER SYSTEM TURKISH DELEGATION

Contents I. Turkish Power Grid II. III. IV. NPP Projects in TURKEY Grid Integration Integration to National Grid Code 2

I. Turkish Power Grid NUMBER OF SUBSTATIONS 400 kv: 92 220 kv: 1 154 kv: 566 66 kv: 14 Total 673 Subs. with 124.888 MVA transformer installed capacity. LENGTH OF TRANSMISSION LINES 400 kv: 17.328 km 154 kv: 34.741 km 220 kv: 85 km 66 kv: 509 km 154 & 400 kv UndergroundCable: 296 km Total 52.960 km

I. Turkish Power Grid ENERGY CONSUMPTION FORECASTED VALUES PEAK DEMAND ENERGY DEMAND YEAR MW GROWTH (%) GWh GROWTH (%) 2015 44260 4,6 287310 6,0 2016 46630 5,4 302700 5,4 2017 49100 5,3 318710 5,3 2018 51940 5,8 337130 5,8 2019 54970 5,8 356830 5,8 2020 58160 5,8 377490 5,8 2021 61260 5,3 397660 5,3 2022 64490 5,3 418590 5,3

I. Turkish Power Grid INSTALLED CAPACITY & PEAK LOAD 2012 Installed Capacity: 57,071 GW Consumption: 241,9 TWh Peak Load: 39.045 MW 2013 Installed Capacity: Consumption: 64.044 MW 245,48 TWh 2.759,6; 4% 6.297,6; 10% 20.269,9; 32% NATURAL GAS COAL IMPORTED COAL Peak Load: 38.274 MW HYDRO 22.289; 35% 3.912,6; 6% 8.515,2; 13% WIND OTHER

I. Turkish Power Grid INSTALLED CAPACITY 2014 6.326,2; 9,3% 3.380,2; 5% 21.172,5; 31% 23.322,6; 34,2% 5.462,6; 8% 8.571,7; 12,5% NATURAL GAS COAL IMPORTED COAL HYDRO WIND OTHER FUEL TYPE INSTALLED POWER (MW) NATURAL GAS 21.172,5 COAL 8.571,7 IMPORTED COAL 5.462,6 HYDRO 23.322,6 WIND 3.380,2 OTHER 6.326,2 TOTAL 68.235,9 Installed capacity is 68.235 MW by 31 August 2014. 6

II. NPP Projects in TURKEY Akkuyu NPP Project Contractor: ROSATOM Estimated Cost: 20 billion US $ Reactor Type: VVER-1200 (AES-2006) Number of Units: 4 Units (1200 MW each) Operation Time: 60 years Akkuyu Site Mersin 7

II. NPP Projects in TURKEY Sinop NPP Project Sinop Site IGA signed (May 3, 2013) HGA negotiation continuing MHI, Itochu, GDF Suez and EUAS (%30-49) EUAS has been recognised as founder Site evaluation studies are being done 8

III. Grid Integration Akkuyu NPP is planned to be in operation in 2020-2023 four unit respectively Sinop NPP is planned to be in operation in 2023-2024 for units I-II and in 2027-2028 for units III-IV In 2022, total energy and peak power demand of Turkish Grid is expected ~418TWh & ~64GW Akkuyu NPP is expected to operate at 90% capacity factor, which will provide ~9% of annual energy demand and will support 7.5% of peak power in 2022. 9

III. Grid Integration GRID INTEGRATION- AKKUYU CASE Near region with large electricity demand Konya Antalya Mersin-Adana # of 400kV, 6 single circuit transmission line is necessary for grid connection of Akkuyu NPP, totally ~1000km. 4 of 6 lines are approved in TEİAŞ s official investment plan and site studies has been started. Lines will be tendered in 2014. Remaining two lines will be contracted later. 10

III. Grid Integration GRID INTEGRATION- AKKUYU CASE 400kV Connections of Akkuyu NPP Afyon Afyon 99km Konya 223km Yeşilhisar S.Şehir 356km Komet NGCCPP 85km Aksa NGCCPP 148km 170km Serbest bölge Varsak 76km Oymapınar HPP Antalya Ermenek HPP NGCCPP, Natural Gas Combined Cycle Power Plant HPP, Hydro electric Power Plant Akkuyu 4x1200MW Off-site power 154kV Grid Mersin 11

III. Grid Integration GRID INTEGRATION- AKKUYU CASE Konya Antalya Adana-Mersin 12

III. Grid Integration GRID INTEGRATION- Sinop CASE İstanbul-İzmit Near region with large electrcity demand Ankara Principle grid integration study is started. Existing grid; which is very weak in Sinop site; line routes, new substations are being evaluated. Draft studies shows that Sinop Project requires more grid investment than Akkuyu NPP does due to lack of big demand center and ongoing coal fired power plants in the same area 13

III. Grid Integration GRID INTEGRATION- Sinop CASE İstanbul-İzmit Ankara 400kV, ~1400km transmission line is necessary to provide secure and reliable grid connection of Sinop NPP 14

IV. Integration to National Grid Code Frequency control in grid code Every generation unit which has a 50 MW installed capacity or above has to contribute to Primary Frequency Control. Every generation unit which has a 100 MW installed capacity or above must be able to contribute to secondary control according to their ancillary service agreement anytime their contribution is needed. (Min 5% of Installed Capacity) 15

IV. Integration to National Grid Code Primary frequency regulation (PFR): Primary frequency reserve of 1%Рnom Power change is to take place within 30 seconds, whereas achievement of 100% of the required power with ±%10 tolerance rate Power change can be max15 minutes Taking into account plant safety dead band value determined by TEİAŞ and power plant operator Primary control is a prerequisite for connection to the grid. (EUR, 2001) 16

IV. Integration to National Grid Code Secondary frequency regulation (SFR): Purpose: To keep the system frequency close to the nominal value (50 Hz). To restore interchange with the other countries at the scheduled value. Participation on secondary control is based on agreement between the grid operator and the electricity production company. The secondary control is central control. (Manuel or Automatic.) 17

IV. Integration to National Grid Code Why joining Secondary Frequency control not preferable for NPP Owner? Can not utilize the fuel best economic way Unstable reactor power Change in burn up Increase in radioactivity Earlier refueling period Increase in waste No operating VVER joining SFC Automatic AGC signal 18

IV. Integration to National Grid Code In which circumstances NPPs cant join SFC? The standart fuel cycle length is 4 years. 18-20 months long fuel operation is possible along with the fuel operation as per the standart fuel cycle. The length between refuelings is 18 months Grid Code First 40 days LIMITED maneuvering % 3 Pr/min %1 Pr/min %60-%80 (~400 days) of the fuel cycle It is supposed the NPP takes part in the secondary regulation of frequency at the following parameters: Minimum volume of reserve capacity for the nuclear power plants shall be 5% of Nnom; LIMITED maneuvering At the end of fuel cycle Capacity reduction/increase rate within the range of 1% to 5% Nnom/min. 19

IV. Integration to National Grid Code In which circumstances NPPs cant join SFC? Other limitations; the operation modes of Akkuyu turbine plant will be provided in the following frequency bands Frequency band (Hz) Maximal operation duration for every single case Maximal operation duration for full service life 51,5 f 52,5 10 minutes (new grid code) 50,5 51,5 60 minutes 4 hours 49 50,5 unrestricted unrestricted 48,5-49 60 minutes 100 hours 48 48,5 20 minutes 100 hours 47,5-48 10 minutes 4 hours 20

IV. Integration to National Grid Code Secondary Frequency Control solution; Change in grid code: Nuclear Power Plants must join secondary frequency control at most %5 of nominal power with the increase or decrease rate of %1 to %5 per minute. Nuclear power plants must have the capability to increase or decrease power at the rate of %1 when they are able to join SFC Taking into account safe operation conditions power plant operator and TEİAS will agree on which circumstances and period s nuclear power plant can or cannot join SFC. Capabilities will be determined during grid connection tests and those periods will be in grid usage agreement. 21

IV. Integration to National Grid Code Other changes in Grid Code; Number of lines: Regardless of total power and unit number nuclear power plants will connect the grid with N-2 criteria. (it was N-1 for all power plants) 22

IV. Integration to National Grid Code Other changes in Grid Code; Power Output: Old New Units should have the capacity to satisfy rated power output between 0.85 power factor of overexcited operation and 0.95 power factor of underexcited operation. Nuclear Power Units should have the capacity to satisfy rated power output between 0.9 power factor of overexcited operation and 0.95 power factor of underexcited operation. 23

IV. Integration to National Grid Code Other changes in Grid Code; Power Output: Reasons: the lower the power factor the larger will be the generator (economical reason,) similar design generators with lower power factor have lower efficiency, similar design generators with lower power factor have lower Short Circuit Ratio (SCR): SCR will be < 0.5 if Power Factor is < 0.90, a value of reactive power of large generator has big influence on the power system in that it can change the system s voltage. As excess of the reactive power in the system can increase system s voltage and lead to failure of outstanding electrical equipment, the reactive power in the system shall be definitely limited. 24

IV. Integration to National Grid Code Excitation sytem static or brushless? Grid Code : If the unit is exposed to a drastic voltage change, the excitation control system whose output is controlled by the automatic voltage regulator, should be able to reach lower and upper voltage limits of the generator warning winding in no longer than 50 milliseconds. This is only satisfied by static excitation system; Brushless excitation system advantages : High reliability and lifetime operational capability of the excitation technical features Absence of slip rings and brush gear, no need for an additional third bearing, extreme compactness and shorter shaft line and foundation table. With this system there are immanent high dynamic performances and efficient contribution to the grid stability. (Particularly in case of long grid fault). As there are no carbon brushes the maintenance effort is considerable lower. Reduced sizes of excitation transformer, commutation equipment, and current leads. TEİAŞ confirmed that Akkuyu NPP can use Brushless excitation system without change in grid code. 25

26 THANK YOU

II. NPP Projects in TURKEY THE MANOEUVRING CAPABILITY OF THE VVER 1200 Akkuyu NPP Project 27

VVER 1200 CRITICAL ELEMENTS FOR LOAD FOLLOWING (orange arrow) 28 Mokhov&Pedshibiakin, 2010