Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Similar documents
Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

PSNH INTERCONNECTION REQUEST

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION

Electric Utility Contact Information Indiana Michigan Power

GENERATOR INTERCONNECTION APPLICATION

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

If any further information is required for CHELCO to fulfill its reporting requirements, please let us know.

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Rule 21 Export Submittal Instructions

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

Section 6. Generation Interconnection

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 25 kw)

Application for Interconnection and Net Metering Revision: 1 Revised: November 7, 2017

Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

Form C Renewable Energy Micro-Generation Connection Application Distribution System

Request for Payment Instructions form. Rule 21 Non-Exporting Generators Submittal Instructions

Micro-Generation Connection Application For Connection of Micro-Generation Facilities of 10 kw

Request for Payment Instructions Rule 21 Non-Exporting Generators Submittal Instructions

Please Refer to Attached Sample Form

August 2, 2001 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Municipality Generator Interconnection Application Single Meter Application Part I

Form G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION

Please Refer to Attached Sample Form

APPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

TERMS AND CONDITIONS

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw

APPLICATION Net Energy Metering (NEM2) Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Net Metering Service. Customer Information Package

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Louisville Gas and Electric Company

December 13, This document was filed with the Board of Public Utilities on December 13, It is awaiting final approval by BPU staff.

Interconnection Process for Customer-Owned Generation (QFs)

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

To complete the process for a net metering interconnection, please follow the steps below:

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

New Hampshire Electric Cooperative (NHEC) Introduction to Net Metering

MCCOOK PUBLIC POWER DISTRICT McCook, Nebraska BOARD POLICY NUMBER 488

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Standards, Procedures and Policies for Grid Connection

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota

California PUC Rule 21 Generating. Facility Interconnection Application Guide. Technical Note

Customer Name : Account Number: Customer Service Address (Street, City, State, ZIP Code): Customer Mailing Address: Customer Telephone Number:

Instructions for Completing Oncor s Interconnection Application For Solar PV Projects

Spec Information. Reactances Per Unit Ohms

Duke Energy Carolinas North Carolina Interconnection Request Checklist

Oncor Application for Interconnection of Distributed Generation

West Virginia Net Metering Service. Customer Information Package

To complete the process for a net metering interconnection, please follow the steps below:

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

NET METERING APPLICATION

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Eligible Renewable Generation (ERG) Application INSTRUCTIONS

GENERATOR DATA MAY 10, 2018

Enquiry Form for Micro and Small Generators 5MW and Less

To complete the process for a net metering interconnection, please follow the steps below:

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

MICHIGAN ELECTRIC UTILITY

Synchronous Generators I. Spring 2013

Net Metering Interconnection Requirements

GENERATOR DATA SEPTEMBER 29, 2015

London Hydro Connection Checklist

RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Solar Power Installation Application

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

MICHIGAN ELECTRIC UTILITY

Louisiana Net Metering Service. Customer Information Package

S5L1D-G4 Wdg Technical Data Sheet

Synchronous Generators I. EE 340 Spring 2011

UCM274C - Technical Data Sheet

UCM274H - Technical Data Sheet

HCI634V - Technical Data Sheet

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

Micro Embedded generation

UCDI224F - Technical Data Sheet

REVISED 8/1/2018 SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & WGC INTERCONNECTION AGREEMENT

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Georgia Transmission Corporation Georgia Systems Operations Corporation

Fall 1997 EE361: MIDTERM EXAM 2. This exam is open book and closed notes. Be sure to show all work clearly.

UCI224C - Technical Data Sheet

MICHIGAN ELECTRIC UTILITY

UCDI274J - Technical Data Sheet

Transcription:

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different from Customer Contact Information) Name: Facility Address (if different from above): City: State: Zip Code: Electric Distribution Company (EDC) serving Facility site: Electric Supplier (if different from EDC): Account Number of Facility site (existing EDC customers): Inverter Manufacturer: Model Equipment Contractor Name: 1

Electrical Contractor (if Different from Equipment Contractor): Name: License number: Electric Service Information for Customer Facility Where Generator Will Be Interconnected Capacity: (Amps) Voltage: (Volts) Type of Service: Single Phase Three Phase If 3 Phase Transformer, Indicate Type Primary Winding Wye Delta Secondary Winding Wye Delta Transformer Size: Impedance: Intent of Generation Offset Load (Unit will operate in parallel, but will not export power to EDC) Net Meter (Unit will operate in parallel and will export power pursuant to Illinois Net Metering or other filed tariff(s)) Wholesale Market Transaction (Unit will operate in parallel and participate in PJM or MISO market(s) pursuant to a PJM Wholesale Market Participation Agreement or MISO equivalent) Back-up Generation (Units that temporarily operate in parallel with the electric distribution system for more than 100 milliseconds) Note: Backup units that do not operate in parallel for more than 100 milliseconds do not need an interconnection agreement. 2

Generator & Prime Mover Data ENERGY SOURCE (Hydro, Wind, Solar, Process Byproduct, Biomass, Oil, Natural Gas, Coal, etc.): ENERGY CONVERTER TYPE (Wind Turbine, Photovoltaic Cell, Fuel Cell, Steam Turbine, etc.): GENERATOR SIZE: NUMBER OF UNITS: TOTAL CAPACITY: kw or kva GENERATOR TYPE (Check one): kw or kva Induction Inverter Synchronous Other Requested Procedure Under Which to Evaluate Interconnection Request 1 Please indicate below which review procedure applies to the interconnection request. The review procedure used is subject to confirmation by the EDC. Level 2 Lab-certified interconnection equipment with an aggregate electric nameplate capacity less than or equal to 2 MW. Lab certified is defined in 466.30 (Application fee is $100.00 plus $1.00 per kw). Level 3 Distributed generation facility does not export power. Nameplate capacity rating is equal to less than or equal to 50KW if connecting to area network or equal to or less than or equal to 10 MW if connecting to a radial distribution feeder. (Application fee amount is $500.00 plus $2.00 per kw). Level 4 Nameplate capacity rating is less than or equal to 10 MW and the distributed generation facility does not qualify for a Level 1, Level 2 or Level 3 review or, the distributed generation facility has been reviewed but not approved under a Level 1, Level 2 or Level 3 review. (Application fee amount is $1,000 plus $2.00 per kw, to be applied toward any subsequent studies related to this application). 1 Note: Descriptions for interconnection review categories do not list all criteria that must be satisfied. For a complete list of criteria, please refer to 83 Ill. Admin. Code Part 466, Electric Interconnection. 3

Distributed Generation Facility Information Estimated Commissioning Date: List interconnection components/system(s) to be used in the Distributed Generation Facility that are lab certified. Component/System NRTL Providing Label & Listing 1. 2. 3. 4. 5. Please provide copies of manufacturer brochures or technical specifications Energy Production Equipment/Inverter Information: Synchronous Induction Inverter Other Rating: kw Rating: kva Rated Voltage: Volts Rated Current: Amps System Type Tested (Total System): Yes No; attach product literature For Synchronous Machines: Note: Contact EDC to determine if all the information requested in this section is required for the proposed distributed generation facility. Manufacturer: Model No. Version No. Submit copies of the Saturation Curve and the Vee Curve Salient Non-Salient Torque: lb-ft Rated RPM: Field Amperes: at rated generator voltage and current and % PF over-excited Type of Exciter: Output Power of Exciter: Type of Voltage Regulator: Locked Rotor Current: Amps Synchronous Speed: RPM Winding Connection: Min. Operating Freq./Time: Generator Connection: Delta Wye Wye Grounded 4

Direct-axis Synchronous Reactance (Xd) ohms Direct-axis Transient Reactance (X'd) ohms Direct-axis Sub-transient Reactance (X"d) ohms Negative Sequence Reactance: ohms Zere Sequence Reactance: ohms Neutral Impedance or Grounding Resister (if any): ohms For Induction Machines: Note: Contact EDC to determine if all the information requested in this section is required for the proposed distributed generation facility. Manufacturer: Model No. Version No. Locked Rotor Current: Amps Rotor Resistance (Rr) ohms Exciting Current Amps Rotor Reactance (Xr) ohms Reactive Power Required: Magnetizing Reactance (Xm) ohms VARs (No Load) Stator Resistance (Rs) ohms VARs (Full Load) Stator Reactance (Xs) ohms Short Circuit Reactance (X"d) ohms Phases: Single Three-Phase Frame Size: Design Letter: Temp. Rise: O C. Reverse Power Relay Information (Level 3 Review Only) Manufacturer: Relay Type: Model Number: Reverse Power Setting: Reverse Power Time Delay (if any): Additional Information For Inverter Based Facilities Inverter Information: Manufacturer: Model: Type: Forced Commutated Line Commutated Rated Output Watts Volts Efficiency % Power Factor % Inverter UL1547 Listed: : Yes No 5

DC Source / Prime Mover: Rating: kw Rating: kva Rated Voltage: Volts Open Circuit Voltage (If applicable): Volts Rated Current: Amps Short Circuit Current (If applicable): Amps Other Facility Information: One Line Diagram attached: Plot Plan attached: Yes Yes Customer Signature I hereby certify that all of the information provided in this Interconnection Request Application Form is true. Applicant Signature: Title: Date: An application fee is required before the application can be processed. Please verify that the appropriate fee is included with the application: Amount EDC Acknowledgement Receipt of the application fee is acknowledged and this interconnection request is complete. EDC Signature: Date: Printed Name: Title: Please mail completed application to: MidAmerican Energy Company Attn: Private Generation P.O. Box 4350 Davenport, IA 52808-9986 Fax: 563-336-3568 Email: PrivateGeneration@midamerican.com 6