Minutes of 6 th Joint Co-ordination Meeting of IPPs granted LTA in ER held on 26.0.20 at CC, POWERGRID. The 6 th meeting of the Joint Co-ordination Committee of IPPs in ER was held at POWERGRID Office, Gurgaon on 26 th May, 20. The list of participants of the meeting is enclosed at Annexure-I. 2. COO (CTU Planning & CE), POWERGRID stated that Minutes of the th meeting of the Joint Co-ordination Committee of IPPs granted LTA in ER held on 2.0.20, were issued vide letter ref. no. C/CTU/E/OA/JCC dated.04.20. As no observations/comments were received on the minutes, the minutes were confirmed as circulated. 3. COO (CTU Planning & CE) mentioned that LTOA/LTA to most of the applicants was granted on the basis of target regions. It is therefore high time that the firm beneficiaries should be finalized at the earliest as the common transmission system required is completed / very close to completion. However till firm beneficiaries are finalized the end links cannot be planned which may lead to constraints in transmission of power. 4. It was also stressed that generation developers should ensure completion of their dedicated lines to match with the commissioning of transmission network in order to prevent bottling up of power. POWERGRID stated that interim arrangements through LILO of existing lines were provided only as a contingency measure and the IPPs need to focus on implementing the final dedicated transmission system. Constraints shall be faced in evacuation of power from the generation projects connected through LILO arrangement, provided as an interim arrangement. Therefore, all the IPPs should expedite the construction of their dedicated line as well as the terminating bays at the Pooling Station.. Representative of Business Development Department (BDD), POWERGRID informed that wherever POWERGRID is implementing terminal line bays on consultancy basis, timely payment to POWERGRID contractor for the same should be made. In case of non-payment, the work of bays awarded to the contractor shall be cancelled and fresh tender of the same shall delay the work by 6 months to year. Towards this, representative of CTU Planning stated that the responsibility of such delay shall lies with the generation developer. Delay in completion of terminating bays shall also delay connection to the pooling station and interim arrangement is liable for removal for efficient grid operation and reliability and security of grid. Page of 3
6. It was further stated that since the construction of transmission line constitutes a very small portion compared to the total investment made by the developers, it is being put on a lesser priority by the generation developers and POWERGRID emphasized the need to change this scenario as it could lead to a bottleneck for transfer of power. 7. Agenda for the 6 th JCC meeting was taken-up and the outcome of the same is placed below: of the Generation Projects HIGH CAPACITY TRANSMISSION CORRIDOR I (Phase-I IPPs in Odisha & associated Transmission System) LTOA / LTA Applicant LTOA Quantum (MW) Target Beneficiaries NR WR ER SR Firm beneficiary Sterlite Energy Ltd 400 200 200 0 0 Not attended Not attended 2 GMR Kamalanga Energy Ltd 800 600 0 0 200 300-Haryana 260- Bihar U, 2 & 3 : Apr 3, Nov 3 & Mar 4 U, 2 & 3 : commissioned in Apr 3, Nov 3 & Mar 4 Dedicated / Connectivity line & Strelite-Jharsuguda Pool 400kV D/c line GMR TPS-Angul Pool 400kV D/c (Quad) linecommissioned in Dec 4, GMR TPS- Meramundali 400 kv S/c linecommissioned in Mar Representative not attended JCC, status for progress not submitted since th JCC 3 Navabharat Power Pvt. Ltd 720 46 2 0 0 Navbharat TPS- Angul Pool 400kV D/c line Developer informed that project has been abandoned. They have applied for Page 2 of 3
LTOA / LTA Applicant LTOA Quantum (MW) Target Beneficiaries NR WR ER SR Firm beneficiary Dedicated / Connectivity line & relinquishment and the case pending in CERC. 4 6 7 Monnet Power Company Ltd Jindal India Thermal Power Ltd Lanco Babandh Power Pvt Ltd Ind Barath Energy(Utkal) Ltd 900 300 22 22 0 044 834 20 0 0 800 32 47 0 0 66 266 30 0 0 400-West Bengal Kerala: 9 MW UP: 424MW Rajasthan: 30 MW Tamil Nadu : 00 MW, 2% power- GRIDCO Not attended U- : Mar 4 U-: Dec 6 U- 2 : Feb 7 U-: COD in Apr ; U-2: COD in July U- : Jan 7 U-2 : April 7 U- COD expected in June U-2 COD in Oct Monet TPS-Angul Pool 400kV D/c line Jindal TPS-Angul Pool 400kV D/c line Lanco TPS-Angul Pool 400kV D/c line + 3x00MVA ICT at Angul Pool: Commissioning matching with generation projects Ind barath- Jharsuguda Pool 400kV D/c line: expected by June Representative not attended JCC, status of progress not submitted since 4th JCC. Representative not attended JCC, status of progress not submitted since 4th JCC. Consultancy contract work for line bay work to be signed between LBPL & PGCIL. Petition in Madras High court Subtotal (Odisha) 280 3289 04 60 300 Page 3 of 3
HIGH CAPACITY TRANSMISSION CORRIDOR II (Phase-I IPPs in Jharkhand & associated Transmission System) 2 3 4 LTOA / LTA Applicant Adhunik Power & Natural Resources Limited (2x270 MW) Essar Power (Jharkhand) Ltd. (2x600 MW) Corporate Power Limited Ph-I (2x270 MW) Corporate Power Limited Ph-II (2x270 MW) WBSEDCL (000 MW State surplus) LTOA Quantum (MW) Target Beneficiaries NR WR ER 40 200 0 200 00 400 400 300 Firm beneficiary Tamil Nadu: 00 MW WB : 00 MW Bihar: 70 MW NPCL: 240 MW Jharkhand: 2% U-:Dec 6 U- : April 7 U-2 : July 7 480 240 240 0 Uncertain Uncertain 480 240 240 0 Uncertain Uncertain 000 600 400 0 Not attended Not attended Total 30 680 330 00 Dedicated / Connectivity line & Adhunik TPS- Jamshedpur 400kV D/c line- Essar TPS-Jharkhand Pooling Station 400kV D/c line (Quad) : Commissioning matching with generation projects Corporate TPS- Jharkhand Pooling Station 400kV D/c line Corporate TPS - Ranchi 400kV D/c line 00MW LTA to WB operational.. No Progress. Coal block de-allocated. 2. Re-appraisal of the project being undertaken by lenders Representative not attended JCC, status of progress not submitted since th JCC. Representative not attended JCC, status of progress not submitted since th JCC. Representative not attended JCC, status of progress not submitted since th JCC. Page 4 of 3
HIGH CAPACITY TRANSMISSION CORRIDOR III (Phase-I IPPs in Sikkim) 2 3 4 6 7 LTOA / LTA Applicant Teesta Urja Ltd. / PTC (Teesta-III) (6x200 MW) Lanco Energy Pvt. Ltd. (Teesta-VI) (4x2 MW) DANS Energy Pvt. Ltd. (Jorethang) (2x48) JAL Power Corporation (Rangit-IV) (3x40 MW) Madhya Bharat Power Corpn Ltd. (Rongnichu) (2x48 MW) Gati Infrastructure Ltd (Chuzachen) (2x49. MW) Gati Infrastructure Bhasmey Power Pvt. Ltd. (Bhasmey) (2x2. MW) LTOA Quantum (MW) Target Beneficiaries Firm beneficiary NR WR ER 200 840 0 44 Punjab:340 MW Haryana :200MW U.P.:200 MW Rajasthan:00MW Sikkim:44MW U-: Dec ; followed by other units with 20 days gap U-: April 6 U2,3,4,,&6: progressively by July 6 00 0 00 0 Apr, 206 Not attended 96 48 48 0 Oct, 204 U- & 2: July 20 6 6 88 96 6 40 0 60%- WBSEDCL; 40%-TPTCL U-/2/3: COD by May-June 6. U-: Jun 8; U-2: July 8 Not attended Not attended 99 69 30 0 36 0 Total 262 09 69 232 COD - Dec 7 U & 2: COD- Dec 7 Dedicated / Connectivity line & Teesta III - Kishanganj 400kV D/c (Quad) line : Commissioning matching with generation project Teesta VI- Rangpo 220 kv Conductor line Jorethang - New Melli 220kV D/c line- Expected by Mar 6 Rangit IV - New Melli 220kV D/c lineexpected by Dec Rongnichu-Rangpo 220kV D/c Zebra conductor line Chuzachen-Rangpo 32kV D/c Zebra Conductor line LILO of one ckt of Chuzachen - Rangpo 32kV D/c (Zebra) line at Bhasmey Representative not attended JCC, status of progress not submitted since th JCC. Interim arrangement being made through connection of one ckt of New Melli- Rangpo line at Jorethang. Requested for revision of LTA Target region as follows: ER-72 MW; WR- 24 MW; NR-24 MW Construction of bays pending. CTU re-iterated that LTA cannot be started unless bays are constructed Page of 3
Other Generation Projects Granted Connectivity & LTA Generation Projects granted LTOA/LTA LTOA / LTA Applicant Shiga Energy Pvt. Ltd. (Tashiding) (2x48. MW) LTOA Quantum (MW) Target Beneficiaries NR WR ER SR 97 48. 48. 0 0 Firm beneficiary U- & 2 : March 7 2 NTPC Ltd. (Darlipalli) 793. 0 0 793. 0 Not attended 3 4 Orissa Power Generation Company Ltd. Sneha Kinetic Power Projects Ltd (Dikchu) 600 200 200 0 200 Not attended 96 48 48 0 0 Total 86. 296. 296. 793. 200 Dedicated / Connectivity line & Tashiding -Legship 220kV D/c line Commissioning matching with generation project Darlipalli-Jharsuguda 76 kv D/c line OPGC-Jharsuguda 400 kv D/c line with Triple snowbird conductor : Under TBCB, d by Jul 7 Dikchu- Dikchu Pool 32 kv D/c Moose conductor/ HTLS line LTA Agreement to be signed Page 6 of 3
of the Associated Transmission System Transmission System under the Scope of POWERGRID: HIGH CAPACITY TRANSMISSION CORRIDOR I (Phase-I IPPs in Odisha & associated Transmission System) Transmission System for Phase- generation projects in Odisha - Part-A Angul Pooling Station Jharsuguda Pooling Station 76kV 2xS/c line Jan, / Mar, Mar ( commissioned)/ Jun 2 LILO of Rourkela Raigarh 400kV D/c at Jharsuguda Pooling station 3 LILO of Meramundali Jeypore 400kV S/c line at Angul pooling station 4 LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling station Establishment of 2x00 MVA, 76/400kV Pooling Station at Mar, 20 Jharsuguda 6 Establishment of 4x00MVA, 76/400kV Pooling Station at Angul Mar, 20 Transmission System for Phase- generation projects in Odisha - Part-B 2 Establishment of 76kV switching station at Dharamjaygarh / near Korba LILO of Ranchi WR Pooling near Sipat 76kV S/c line at Dharamjaygarh / near Korba Page 7 of 3
3 Jharsuguda Pooling Station Dharamjaygarh / near Korba (WR) 76kV D/c 4 Establishment of 76/400kV Pooling Station at Jabalpur Dharamjaygarh / near Korba Jabalpur Pooling Station 76kV D/c July Jun, 20 line 6 Jabalpur Pooling Station Jabalpur 400 kv D/c (high capacity) line Transmission System for Phase- generation projects in Odisha - Part-C Jabalpur Pooling Station Bina 76kV D/c line 2 Bina Gwalior 76kV S/c (3rd circuit) 3 Gwalior - Jaipur 76kV S/c line (2nd circuit) Jun, 20 Aug 4 Jaipur - Bhiwani 76kV S/c line Feb, 20 June Transmission System under the Scope of Private Sector: Establishment of 2x00MVA, 76/400kV Bhopal Pooling Station 2 Jabalpur Pool Bhopal Indore 76kV S/c 3 Bhopal New substation Bhopal (M.P.) 400kV D/c (high capacity) Page 8 of 3
Transmission System under the Scope of POWERGRID: HIGH CAPACITY TRANSMISSION CORRIDOR II (Phase-I IPPs in Jharkhand & associated Transmission System) Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A- 2 Establishment of 400kV GIS Pooling Station (Jharkhand Pool) near Essar and Corporate generation projects. Ranchi - Gaya 400 kv D/c (Quad) line via pooling station proposed near Essar / Corporate generation projects Mar, 20 Mar, 20 Dec Dec Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A-2 Sep Ranchi New (76/400kV S/s) - Dharamjaygarh / near Korba 76kV S/c Mar, 20 2 2x00 MVA, 76/400 kv New GIS substation at Varanasi Jun, 20 Sep 3 Gaya - Varanasi 76kV S/c Jun, 20 Sep 4 Varanasi - Balia 76 kv S/c line Jun, 20 Sep Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-B New 2x00 MVA, 76/400 kv substation at Kanpur Jun, 20 Sep 2 Varanasi Kanpur 76 kv D/c Jun, 20 Sep Page 9 of 3
3 Kanpur Jhatikra 76 kv S/c Jun, 20 Dec 4 Kanpur (76/400kV) - Kanpur (Existing) 400kV D/C (Quad) Jun, 20 Sep 400kV connectivity for new 76/400kV S/s at Varanasi Varanasi - Sarnath (UPPCL) 400kV D/c (quad) LILO of Sasaram - Allahabad 400kV line at Varanasi Opening of LILO of one ckt of Sasaram - Allahabad 400kV D/c line at Sarnath Jun, 20 Sep Transmission System under the Scope of Private Sector: Dharamjaygarh Jabalpur 76kV D/C line (2nd line) Sep As per CEA Report of Apr Transmission System under the Scope of POWERGRID: HIGH CAPACITY TRANSMISSION CORRIDOR III (Phase-I IPPs in Sikkim) Transfer of power from generation projects in Sikkim to NR/WR (Part-A) 2 3 Establishment of New 2x3 MVA, 400kV sub-station at Kishanganj LILO of Siliguri (Existing) Purnea 400kV D/c line(quad) at new pooling station Kishanganj LILO of Siliguri (Existing) Purnea 400kV D/c line (on which reconductoring is being carried out) at Kishanganj with higher capacity (quad) conductor Jun, 20 Jun, 20 Jun, 20 June June June Page 0 of 3
4 LILO of Siliguri Dalkhola 220kV D/c line at new pooling station Kishanganj LILO of Gangtok-Melli 32kV S/c line upto Rangpo, where Chuzachen-Rangpo 32kV D/c would be connected so as to form Chuzachen-Gangtok and Chuzachen-Melli 32kV S/c lines. Jun, 20 June Transfer of power from generation projects in Sikkim to NR/WR (Part-B) Establishment of 400/220/32kV (400/220kV, 6x0 MVA, Single Phase transformers and 220/32kV, 3x00MVA) Gas Insulated Substation at Rangpo Jan, 20 2 Establishment of 220kV Gas Insulated switching station at New Expected by May Jan, 20 Melli LILO of Teesta III Kishanganj 400kV D/c line (quad, Teesta III 3 Kishanganj 400kV D/c line to be constructed through JV route) at Rangpo 4 Rangpo New Melli 220kV D/c line (with twin Moose conductor) Feb, 20 Expected by May LILO of Gangtok-Rangit 32kV S/c line at Rangpo and termination of Gangtok-Rangpo/Chujachen and Melli Rangpo/Chujachen 32kV lines (constructed under part-a through LILO of Gangtok- Melli 32kV S/c line upto Rangpo) at Rangpo sub-station 6 LILO of Teesta V Siliguri 400kV D/c line at Rangpo 7 Kishanganj Patna 400kV D/c (quad) line Jun 20 June Page of 3
Annexure-I List of Participants in the 6 th Joint Co-ordination Committee Meeting of IPPs granted LTA in ER held on 26.0.20 Name Designation Organisation E-mail. Ravinder Gupta Director Central Electricity Authority ravindergupta_cea@rediffmail.com 2. Seema Gupta COO (CTU-Plg & CE) Power Grid Corporation of India Ltd. sgupta@powergridindia.com 3. N K Jain GM (Commercial) Power Grid Corporation of India Ltd. nkjain.cc@gmail.com 4. Ashok Pal AGM (CTU-Plg) Power Grid Corporation of India Ltd. ashok@powergridindia.com. D N Rozekar DGM-CTU (Plg) Power Grid Corporation of India Ltd. drozekar@powergridindia.com 6. P Saraswat DGM (Commercial) Power Grid Corporation of India Ltd. sarswat@powergridindia.com 7. S K Varshney Asst. GM (commercial) Power Grid Corporation of India Ltd. skvarshney@powergridindia.com 8. Rajesh Verma C Manager (CTU-Plg) Power Grid Corporation of India Ltd rverma@powergridindia.com 9. Ramchandra Asst. GM ( CTU-Plg) Power Grid Corporation of India Ltd ramachand@powergridindia.com 0. A.K. Dixit Asst. GM (BDD) Power Grid Corporation of India Ltd akdixit@powergridindia.com. Anil Kumar Meena DCDE (CTU-Plg) Power Grid Corporation of India Ltd. anilsehra@powergridindia.com 2. Devika Jay Engineer-CTU (Plg) Power Grid Corporation of India Ltd. devikajay@powergridindia.com 3. K Jyoth Kumar Officer- CTU (Plg) Power Grid Corporation of India Ltd. jyoth@powergridindia.com 4. Mahendra Prajapati Engineer (CMG) Power Grid Corporation of India Ltd mprajapati@powergridindia.com Page 2 of 3
Name Designation Organisation E-mail. Kumar Sanjeev EET (CMG) Power Grid Corporation of India Ltd kumarsanjeev@powergridindia.com 6. Ajaya Kumar Nathani Head- Transmission GMR Kamalanga Energy Ltd ajaya.nathani@gmargroup.com 7. Rishu Garg AM- Transmission GMR Kamalanga Energy Ltd rishu.garg@gmrgroup.com 8. K C Agrawal VP PTC India Ltd kcagrawal@ptcindia.com 9. Ravi Shankar Manager PTC India Ltd ravi.shankar@ptcindia.com 20. Anusha Kakar Engineer Teesta Urja Ltd anusha.k@teestaurja.com 2. J Mohapatra Director Ind Barath Energy (Utkal) Ltd mohapatraj6@gmail.com 22. R Jarard Kishore Ind Barath Energy (Utkal) Ltd kishore@ibpil.com 23. Rajesh Sharma Sr. Manager Gati Infra Pvt. Ltd r.sharma@gatiinfra.com 24. Devesh Gautam Manager Gati Infra Pvt. Ltd devesh.gautam@gatiinfra.com 2. M R Jhala GM (Commercial) Lanco Babadh Power Ltd mahavir.jhala@lancogroup.com 26. T Nagendra Rao M.D. DANS Energy nagedrarao@dansenergy.com 27. P C Sharma Presindent DANS Energy pravin.sharnma@dansenergy.com 28. Nukala Kishore Manager DANS Energy nukala.kishore@dansenergy.com 29. Sandeep Sahay Deputy Head- (Comm) Essar Power Ltd sandeep.sahay@essar.com Page 3 of 3