HIGH WIRE ACT. When the lights went out at Kitimat, it was the cue for Rio Tinto Alcan to embark on one of its most complex engineering feats ever.

Similar documents
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Power Transmission Division Erlangen, April 29, Siemens Completes Installation of Second HVDC Converter Platform for TenneT

TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027

Avalanche Tower LS12-5

Figure 36 The view of the gantry from the stores boat during World War 2.

Planning Advisory Notice

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee

Power Transmission Division Erlangen, April 29, 2014

Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

Western Alberta Transmission Line (WATL) HVDC Project

2012 Water Consumption Statistics Report. Water Services Department

Water Consumption Statistics Report

Job Report. Bosphorus Bridge, Turkey

200 TRIPS THE D 42 MAMMOET WORLD Issue

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD

TERRACE TO KITIMAT TRANSMISSION (TKT)

Air time! AMERICAN CRANES & TRANSPORT. Lift planning. Specialized Lifting. Crane inspections. Ranking North America s top tower crane-owning companies

Variable Speed Limit Pilot Project in BC

LOCAL CLIMATOLOGICAL DATA

LONG RANGE PERFORMANCE REPORT. Study Objectives: 1. To determine annually an index of statewide turkey populations and production success in Georgia.

Q1. The graph shows the speed of a runner during an indoor 60 metres race.

CONTENTS. Key to Access. SUSPENDED PLATFORMS BMU-cradles and MSP s for every type of suspension method.

CHAIN & HOOKS. Proof Coil Chain Grade 28. Transport Chain Grade 70

Word Problems Distance=Rate Time

First published June 2007 Copyright China Trend Building Press Limited

TRACC. Trinity Attenuating Crash Cushion

Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad

PYRTE. Building The Front Axle, Fork and Steering

The Unimog. More Energy whatever the Terrain.

Texas Refinery Corp. of Canada, Limited TIRESEAL

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD

BC Hydro System 2017 Annual Progress Report

INSTALL SERVICE- ENTRANCE SYSTEMS

Hiab XS 377 Range tm

SAE Mini BAJA: Suspension and Steering

How to use the Multirotor Motor Performance Data Charts

National 4/5. Dynamics and Space

Mercedes-Benz Unimog U1200

AND DESIGN FROM CONCEPT. Why did we develop Xenon? Experienced team. Christopher Schmidt


Building and flying a 1930s dream

AVIATION INVESTIGATION REPORT A08P0035 LOSS OF VISUAL REFERENCE / COLLISION WITH TERRAIN

very low it measured only 33in/84cm from ground to the top of the roof but it had two steeply reclined seats and allindependent

Inventing a new type of platform gate

Alberta Speeding Convictions and Collisions Involving Unsafe Speed

YOUR GUIDE TO SAFE SPRING MOTORING

1st Armoured Regiment

welcome to the BC Hydro community open house

CHAPTER 10 FLOATING WHARVES

SOXOS DB7. Words & Pictures: Raquel Bellot

11. Electrical energy tariff rating

In September of 1944 the USAAF's first Helicopter Training School was established at Freeman Field, Seymour, Indiana

Module 4.2 Curves and Hills

BC Hydro System 2016 Annual Progress Report

U.S. Classes 3-8 Used Trucks

CLIMATOLOGICAL SUMMARY

Passenger Dies When Semi-Truck Trailer Hits Cow In Roadway Incident Number: 05KY089

Jake can skate on ice.

Truckee Meadows Fire Protection District Monthly Report

Austin Insulators Inc. Manufacturers of Austin Base & Guy Insulators and Isolation Transformers for Radio Antenna Towers.

Title: Lifting Operations Involving Crane or Gantry Offshore

Could also be a Near Hit

F1 in Schools Champions at Silverstone

Galaxy blue. Signal blue

Ladder Use in Construction Guideline

SAMPLE PAGE. Trains Express Lapbook. Any Age. A Journey Through Learning

Rolling drums while California dreams

Podium Newsletter. February 2010

Construction of the Alcan Highway One of the Top 10 Construction Achievements of the 20th Century

Power Grid & Blackouts. Prof. Ramzy R. Obaid

THE T IN DETAIL

Lesotho Electricity Authority REPORT ON ANALYSIS OF LEC LOAD SHEDDING FOR PERIOD APRIL JULY 2008

FEASIBILITY LAND TRANSPORTATION VENTUS ENERGY. from. covering WIND TURBINE EQUIPMENT PORT OF MOUNT MAUNGANUI TO KAIMAI RANGE SITE. for.

Fly Rocket Fly: Design Lab Report. The J Crispy and The Airbus A

DECWARE HIGH DEFINITION TOWERS

DIRECT GEAR DRIVE / U-TROUGH / CARRY-IN SWEEPS BIN UNLOADING SYSTEMS PROVEN & DEPENDABLE

WELCOME. Nanaimo Harbour and Gabriola Island Terminal Development Plans (TDPs)

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS

REPORT A-008/2008 DATA SUMMARY

Creating a Lean and Productive Processing Facility

Summary. IEEJ: November 2011 All Rights Reserved. Yu Nagatomi *

Hiab XS 322 Range tm

Train Wreck. A reservoir of good will goes a long way

Building on success - growing the Pilbara. Greg Lilleyman President, Pilbara Operations

Drillsafe Meeting June Sydney. Stena Clyde Start-up in Australia. Ricardo Bueno Drilling Manager- ENI Australia

Hydraulic Slide Starts and Stops

We all put our heads together to try and determine what the facts were. They were as follows:

Live-line transmission lines upgrade projects. First-in-Africa project

ALUMINUM UNDERGROUND ALHIDE 600 VOLT SINGLE LAYER RUGGEDIZED CABLES. grounded in service wired to innovate TM. Black Crosslinked.

TABLE OF CONTENTS SECTION TITLE PAGE NUMBER

AVIATION INVESTIGATION REPORT A07C0148 COLLISION WITH POWER LINE TOWER

REASONABLE FURTHER PROGRESS REPORT FOR THE MONO BASIN PM-10 STATE IMPLEMENTATION PLAN

Green Line LRT: Beltline Segment Update April 19, 2017

Aircraft Maintenance Prof. A.K Ghosh Prof. Vipul Mathur Department of Aerospace Engineering Indian Institute of Technology, Kanpur

Pg 1 Solve each word problem 1. Marie rode her bicycle from her home to the bicycle shope in town and then walked back home. If she averaged 6 miles

British equipment losses at Dunkirk and the post Dunkirk situation

FATAL AND SEVERE RISK PROGRAM

Transcription:

HIGH WIRE ACT When the lights went out at Kitimat, it was the cue for Rio Tinto Alcan to embark on one of its most complex engineering feats ever. 20

Words and pictures by Dwight Magee, Corporate Affairs adviser for Rio Tinto Alcan BC Operations at Kitimat, British Columbia. 21

High wire act At 10.41 on the evening of March 28, 2007, at Rio Tinto Alcan s aluminium smelter at Kitimat in British Columbia, Canada, the lights went out. At that instant, no one knew why, for certain, but seasoned power control room operators had their immediate suspicions: in a word, avalanche. They turned out to be spot on. The electrical power that feeds the smelter is generated at a remote power station located in Kemano, some 80km away. The transmission line from Kemano begins from more or less sea level but then climbs up over the rugged mountains through the Kildala Pass. The transmission line crests the top of the pass at over 1,500 metres. Annual snowfall of over 8m is the norm and in 2007, around this time, record amounts of snow were being recorded in the region. It was two days before flying weather allowed members of the line crew to carry out a visual inspection of the transmission line from helicopter. From the air, they saw that the word from the control room had been right. A massive avalanche had started at the top of Kildala Pass and raced down the mountain destroying the transmission tower numbered 113R. As the tower went, so did one of the two 300 kv transmission lines from Kemano. The avalanche was so massive in size and force that the transmission tower itself had simply disappeared. The avalanche was thought to have run over 4km in distance and estimates placed its peak depth at 17m. But the damage was done. The team from Operations now had to figure out how to get the power from Kemano back on line and, more importantly, find a permanent avalanche proof solution. The daunting concept that evolved led to the construction of one of the largest catenary systems in the world. In the summer of 2007 workers were able to erect a temporary tower where the old one existed. This tower, although temporary, had to be strong enough to last through a potentially unpredictable winter. Spring was late arriving and the unusually cool weather hindered a rapid melt of the record snow fall from the previous winter. Construction crews hoping to begin work found the going slow and time was of the essence. Each day that the circuit was out of commission meant that Rio Tinto Alcan had to buy electricity to maintain full operations at the aluminum smelter. Despite the odds, crews had the temporary tower in place and returned full power to the smelter on August 22, finishing the work planned for the year. During the time that work was progressing on the construction of the temporary tower engineering, work also began on the permanent solution. A massive length of support cables (the catenary) would stretch 1,100m in a single span between the two mountain peaks of the pass at a height of 1,500m above sea level, supporting the power cables, which march down the pass, at the centre. The 28 cables making up the two strands of the catenary would be suspended 150m above the valley floor, keeping the transmission line well out of The daunting solution that evolved led to the construction of one of the largest catenary systems in the world. Below left, heavy winter snowfall, the norm in the rugged Kildala Pass. Below, crews installing one of the 28 individual cables that make up the catenary system. Right, in suspense crews ready to connect the first conductor onto the new catenary. It took a complete day to raise and connect each conductor. 22

Coming down the mountain Schematic showing the power cables marching down the pass, the new catenary being at the top. The lower catenary was constructed in 1960 when an avalanche destroyed three towers, taking out both circuits.

To allow access for maintenance is a 150m catwalk, complete with its own helicopter landing pad. 24

High wire act Left, at the centre of the catenary, above the maintenance catwalk, is a tiny helicopter pad providing access for men and materials. Below, top, a catenary anchor point on the side of the mountain. Each of the four anchor bases is protected within its own avalanche shed. Centre: steady as she goes all heavy equipment and materials had to be lifted in by helicopter. Bottom: constructive blast. The easiest way to join power line conductors together is with the aid of explosives. Right, photofinish: members of the construction team pose for a celebratory picture. harm s way from any conceivable future avalanche risks. The location of this catenary required special engineering indeed. At the centre of the span, where the cables intersect with the transmission line, would be six insulators and each would weigh ten tonnes, excluding the actual cable it carried. Immediately above, to allow access for maintenance, would be a 150m catwalk, complete with unbelievably its own helicopter landing pad. The first phase of the project consisted of building the four cable anchor points to the side of the mountain. Rock blasting crews and equipment arrived at their work locations daily by helicopter. The anchor area had to be cleared and six holes bored 6m deep into the side of the mountain for each of the four anchor bolts. Wet concrete was flown in continuously from Kitimat to build the actual cement anchors into the side of the mountain. When the bases were completed anchor plates and runners were installed onto each of the four bases. Work next began on pulling the 28 cables 1,000m across the valley. With the cables in place, workers then had to bind each of the seven sets of cables together to form two massive cables across the valley. Next came the the installation of the catwalk in the middle of the suspension. To accomplish this, linemen worked from carts that ran along the length of the cable. Helicopters were used to ferry the 26 catwalk panels into place while workers anchored them to the catwalk. Once the catwalk was put into place the final task was installing the new helicopter landing pad on top of the structure. Raising the conductors from the ground required the use of a cable sling attached from a winch on a tractor over to a ground pulley, up to a pulley on the catenary and back down to the actual conductor. Once the cable was connected the winch was used to lift the conductor, weighing ten tonnes, up to the catenary itself a process that took over an hour each time. During this lifting process the potential stress on the catenary itself was at its greatest: no one was allowed on the catenary until the conductor was lifted into mounting position with the insulators already attached below the catenary. On September 13, just 115 days after the project began, there was much to celebrate. The final conductor had been raised that day and the project had been completed ahead of plan, but, most importantly, the entire project had been completed entirely free of accidents or injuries. No future avalanche in this section of the Kildala Pass will put out the lights at Kitimat. 25