French - Russian Chamber of Commerce and Industry PPP & Innovation Christian Heurtebis Paris,
VINCI Concessions - Six areas of activity 2
Locations in Europe 3
Locations around the world 4
The A19: An important East - West Link in France Caracteristics 101 km 2x2 lanes 3 interchanges A10, A77 et A6 1 Viaduct of 1 km 8 500 vehicles/day (2010) 5
Only 4 years between contract concession signature and opening Only 4 years between contract signature and opening Five processes were conducted simultaneously : Archaeological excavations Land Acquisition Stakeholder Engagement / Public Consultation Project Design Start of construction Illustrates the soundness and effectiveness of the all inclusive concessionaire-designer-builderoperator business model. 6
Eco-motorway: Environmental, Safe and User-friendly Environment: it goes far beyond French regulations New motorways are not so popular anymore in France Very early, the Concessionnaire started discussions with the different stakeholders : the government the local authorities the environmental associations the agricultural world the roadside residents The spirit of partnership was essential to build acceptance for this new motorway. 7
Attractive and welcoming rest areas The first Contribute to the relaxation and to the rest of the customers Encourage the customers to take more frequent and more regular breaks 8
Use of I-Phone and mobile internet Virtual VMS on I-Phone Use of GPS coordinates of terminals Display personalized messages to customers (in relation to events occurring downstream) Collaborative Information Possibility for customers to report and share events Services on the areas Consultation of the services and fuel cost Assessment of the services on areas by customers 9
A86 Project Second ring road A86 First ring road Periphérique Paris
A86 Project 11
Cross Section Doubling the link-up s capacity Diversification of the interchanges with surface roads Significant reduction of each interchange s surface Reduced impact on the environment Increased safety Clearance : 2,55 m Maximum height of vehicles : 2 m
Designed for peaceful driving 13
Underground interchange A86 / A13
A sustainable project Project Location : Paris «Green Belt» area Surface traffic lightened by 15% Architecture design and aboveground facility location blends into landscape Minimized above-ground facilities while maintaining safety Air quality observatory Noise reduction
Traffic Management No congestion allowed inside the tunnel Traffic control on entrances and exits, and inside the tunnel Automatic Incident Detection Variable message signs Customer Assistance Patrol FM radio override 16
Moscow St Petersburg (Km 15 Km 58) Key elements Concession contract for 31 years Financing, design, construction and operation of a 43 km highway starting from the Moscow ring road PPP project with foreign investment Motorway project based on European technical requirements, performance and standards Environmental management laboratory Socio-economic objectives Develop the link between the two capitals / Bring Moscow closer to Sheremetyevo Airport / Reduce congestion on the M10 / Improve traffic northwest of Moscow 17
Innovative solutions Cast in situ reinforced concrete barrier on the separating strip 18
Innovative solutions Equipment & Systems - Traffic Control Center 19
Parkings - New generation
Parkings- Operation Support Center Communicate with customers Parking equipment remote control Solve errors remotely KPI s to plan maintenance work
Airport - Notre-Dame-des-Landes (Nantes) Key Features: first energy positive airport in France optimised flight and taxiing time thanks to the configuration of the runways and the terminal fuel savings 22
Allianz Riviera Nice Stadium 23
Allianz Riviera Nice Stadium Program: 35 000 seats stadium with high sustainable development standards 30 000 m² of retail and commercial spaces 5 500 m² for the «Sports National Museum Eco-district with more than 500.000 m² for housing A Tramway line with 2 stations to be built for the stadium 24
Allianz Riviera Nice Stadium 25
Thank you for your attention Christian Heurtebis Christian.heurtebis@vinci-concessions.com Mobile : + 7 916 222 92 62 26