STATE OF MICHIGAN Prevailing Wages PO Box Lansing, MI Informational Sheet: Prevailing Wages on State Projects

Similar documents
Official 2016 Prevailing Wage Rates for State Funded Projects

Official 2017 Prevailing Wage Rates for State Funded Projects

State of Michigan Official Request #: Requestor: Project Description: Project Number: Grand Traverse County

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

SEWER AND WATERMAIN CONSTRUCTION

Fair Wage Office 18 th Floor, West Tower, City Hall FAIR WAGE SCHEDULE * I.C.I. WORK

Backhoe & Hoe Ram (under 3/4 Yd.) $26.11 $34.81 $ Backhoes & Hoe Ram (3 Yds & Over) $26.44 $35.25 $44.06

FAIR WAGE SCHEDULE Sewer and Watermain

St. Cloud State University St. Cloud, MN

SEWER AND WATERMAIN CONSTRUCTION

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

T.A.T Minimum Wage Scale

GREASE TIME RATE SINGULARLY OPERATED MACHINES

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

SCHEDULE B Building Construction WAGE SCHEDULE: LOCAL 138 INTERNATIONAL UNION OF OPERATING ENGINEERS. EFFECTIVE DATE JUNE 1, 2017 to MAY31, 2018

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

All Users of the City of Denver Prevailing Wage Schedules

Highway and Heavy Master Job Classifications OLD versus NEW

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

FAIR WAGE SCHEDULE Road Building

*Due to the shift of $1.00 from H&W to Pension below is the corrected rates for 6/1/17 APPENDIX 1

General Decision Number: MN /04/2011 MN15. State: Minnesota. Construction Type: Highway

General Decision Number: MN /15/2012 MN10. Superseded General Decision Number: MN State: Minnesota. Construction Type: Highway

Heavy/Highway. OPERATING ENGINEERS LOCAL NO. 825 WAGES & FRINGE BENEFITS EFFECTIVE JULY 1, 2017 through DECEMBER 31, 2017

FAIR WAGE SCHEDULE HEAVY CONSTRUCTION

Heavy/Highway. OPERATING ENGINEERS LOCAL NO. 825 WAGES & FRINGE BENEFITS EFFECTIVE JULY 1, 2014 through DECEMBER 31, 2014

Roadway Erosion Control 2017 CONTRACT NO ADDENDUM NUMBER ONE

ATTACHMENT A. Construction Project Safety Checklist

JULY 2018 WAGE BULLETIN

State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone PO Box 44540, Olympia, WA

Meredith Creme, Associate Human Resource Professional

General Decision Number: AZ /22/2013 AZ8. Superseded General Decision Number: AZ State: Arizona. Construction Type: Highway

CERTIFICATE. I, Marilyn L. Banks, DO HEREBY CERTIFY THAT I am the Town. of the City of Champaign Township Clerk in and for the Town of the City of

On-the-Job Training Program. Overview of Training Programs

ATTACHMENT 13 DAVIS-BACON WAGE DETERMINATION (HIGHWAY) NUEX Bldg Luke AFB Temporary Lodgin Facility. 20 June 2014

FEMA's Schedule of Equipment Rates

FEMA's Schedule of Equipment Rates

Hennepin County Transportation Department ADDENDUM

B JACK KOCSIS, JR., CHIEF EXECUTIVE OFFICER

Prevailing Wage Rates for Will County effective August 15, 2018

County Trade Job Classification Wage Holiday Overtime Notes

Hennepin County Transportation Department ADDENDUM

Schedule of Equipment Rates

Why? Faster To reduce the duration of the process

MERCER COUNTY PREVAILING WAGE ORDINANCE FOR

CITY OF MONTICELLO PIATT COUNTY, ILLINOIS AN ORDINANCE ENACTING THE ILLINOIS PREVAILING RATE OF WAGES FOR PUBLIC WORKS NO

Instructions for filling out the Equipment for Hire Registration Form (Other than Dump Trucks)

NSRBA 2017 EQUIPMENT DESCRIPTION. Purchase Price 2017 Monthly Rental % Monthly Rate Hourly Rate Daily Rate

KENDALL COUNTY PREVAILING WAGE RATES EFFECTIVE JUNE 5, Base Wage

General Decision Number: OR /06/2013 OR17. Superseded General Decision Number: OR State: Oregon. Construction Type: Residential

BIDDING REQUIREMENTS Addendum No. 2. June 21, Southern Illinois University School of Medicine Springfield, IL PROSPECTIVE BIDDERS

U.S. Department of Labor Wage Determinations

Modification Number Publication Date 0 04/01/ /23/2016 * SUMN /01/2014

LABOR COMMISSIONER'S EXHIBITS

REACHING ACROSS ILLINOIS LIBRARY SYSTEM (RAILS) Prevailing Wage Ordinance ORDINANCE NO

Dr. Mike Riggle Board of Education. Dr. R.J. Gravel. Date: Monday, May 21, Resolution Establishing the Prevailing Wage Rates for FY

ADDENDUM NUMBER ONE PART ONE, VOL. 1 CONTRACT DOCUMENTS

Executive Committee Item EX33.2, adopted as amended, by City of Toronto Council on July 16, 17, 18 and 19, 2013 CITY OF TORONTO BY-LAW

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD. Filed with the secretary of state on

NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF EAST PEORIA, TAZEWELL COUNTY, ILLINOIS, THAT:

CONSTRUCTION and OFF ROAD EQUIPMENT

I, CHIKE EROKWU, DO HEREBY CERTIFY THAT

ADDENDUM ADDENDUM NO.: 02. Mt. Greenwood Elementary School Annex II Site Preparation PROJECT NO.: CONTRACT NO.: DATE OF ISSUE: September 5, 2017

JOB POSTING Service Worker I Open: Tuesday, November 21, 2017 through Friday, December 22, 2017

ADDENDUM #1 MARCH 20, 2017 COUNTY PROJECT S.A.P

DEPARTMENT OF FINANCE & OPERATIONS Wilmette Public Schools ACTION ITEM. Date: June 27, Superintendent. Gail F. Buscemi Business Manager

Defense Logistics Agency Troop Support. Construction and Equipment. Heavy Equipment Procurement Program HEPP. Customer Handbook March 2017

NOW, THEREFORE BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE NORTH RIVERSIDE PUBLIC LIBRARY, COUNTY OF COOK, STATE OF ILLINOIS, AS FOLLOWS:

BUILDING AND CONSTRUCTION GENERAL ON-SITE AWARD 2010

Bev Quinn. Govemor. Acting Director. August 31,2017. Bruce Rauner

Whatcom County Invitation to Bid Bid #17-09

ESSEX COUNTY OFFICE OF THE MANAGER

Fleet Replacement Budget Scenarios DPW City of Milwaukee, Fleet Services February, 2010

ILLINOIS DEPARTMENT OF LABOR

LABOR RELATIONS BULLETIN

Union Pacific Pay Rates July 1, 2018

Transcription:

RICK. SNYDER GOVERNOR STATE OF MICHIGAN Prevailing Wages PO Box 30476 Lansing, MI 48909 517-284-7800 Informational Sheet: Prevailing Wages on State Projects REQUIREMENTS OF THE PREVAILING WAGES ON STATE PROJECTS ACT, PUBLIC ACT 166 OF 1965 The State of Michigan determines prevailing rates pursuant to the Prevailing Wages on State Projects Act, Public Act 166 of 1965, as amended. The purpose of establishing prevailing rates is to provide minimum rates of pay that must be paid to workers on construction projects for which the state or a school district is the contracting agent and which is financed or financially supported by the state. By law, prevailing rates are compiled from the rates contained in collectively bargained agreements which cover the locations of the state projects. The official prevailing rate schedule provides an hourly rate which includes wage and fringe benefit totals for designated construction mechanic classifications. The overtime rates also include wage and fringe benefit totals. Please pay special attention to the overtime and premium pay requirements. Prevailing wage is satisfied when wages plus fringe benefits paid to a worker are equal to or greater than the required rate. State of Michigan responsibilities under the law: The department establishes the prevailing rate for each classification of construction mechanic requested by a contracting agent prior to contracts being let out for bid on a state project. Contracting agent responsibilities under the law: If a contract is not awarded or construction does not start within 90 days of the date of the issuance of rates, a redetermination of rates must be requested by the contracting agent. Rates for classifications needed but not provided on the Prevailing Rate Schedule, must be obtained prior to contracts being let out for bid on a state project. The contracting agent, by written notice to the contractor and the sureties of the contractor known to the contracting agent, may terminate the contractor's right to proceed with that part of the contract, for which less than the prevailing rates have been or will be paid, and may proceed to complete the contract by separate agreement with another contractor or otherwise, and the original contractor and his sureties shall be liable to the contracting agent for any excess costs occasioned thereby. Contractor responsibilities under the law: of all prevailing rates Every contractor and subcontractor shall keep an accurate record showing the name and occupation of and the actual wages and benefits paid to each construction mechanic employed by him in connection including certified payroll, as used in the industry, with said contract. This record shall be available for reasonable inspection by the contracting agent or the department. Each contractor or subcontractor is separately liable for the payment of the prevailing rate to its employees. The prime contractor is responsible for advising all subcontractors of the requirement to pay the prevailing rate prior to commencement of work. The prime contractor is secondarily liable for payment of prevailing rates that are not paid by a subcontractor. A construction mechanic shall only be paid the apprentice rate if registered with the United States Department of Labor, Bureau of Apprenticeship and Training and the rate is included in the contract. Enforcement: A person who has information of an alleged prevailing wage violation on a state project may file a complaint with the State of Michigan. The department will investigate and attempt to resolve the complaint informally. During the course of an investigation, if the requested records and posting certification are not made available in compliance with Section 5 of Act 166, the investigation will be concluded and a referral to the Office of Attorney General for civil action will be made. The Office of Attorney General will pursue costs and fees associated with a lawsuit if filing is necessary to obtain records. (10/15) Page 1 of 1

RICK. SNYDER GOVERNOR STATE OF MICHIGAN Prevailing Wages PO Box 30476 Lansing, MI 48909 517-284-7800 Informational Sheet: Prevailing Wages on State Projects General Information Regarding Fringe Benefits Certain fringe benefits may be credited toward the payment of the Prevailing Wage Rate: o If a fringe benefit is paid directly to a construction mechanic o If a fringe benefit contribution or payment is made on behalf of a construction mechanic o If a fringe benefit, which may be provided to a construction mechanic, is pursuant to a written contract or policy o If a fringe benefit is paid into a fund, for a construction mechanic When a fringe benefit is not paid by an hourly rate, the hourly credit will be calculated based on the annual value of the fringe benefit divided by 2080 hours per year (52 weeks @ 40 hours per week). The following is an example of the types of fringe benefits allowed and how an hourly credit is calculated: Vacation Dental insurance Vision insurance Health insurance Life insurance Tuition Bonus 401k Employer Contribution Total Hourly Credit 40 hours X $14.00 per hour = $560/2080 = $31.07 monthly premium X 12 mos. = $372.84 /2080 = $5.38 monthly premium X 12 mos. = $64.56/2080 = $230.00 monthly premium X 12 mos. = $2,760.00/2080 = $27.04 monthly premium X 12 mos. = $324.48/2080 = $500.00 annual cost/2080 = 4 quarterly bonus/year x $250 = $1000.00/2080 = $2000.00 total annual contribution/2080 = $.27 $.18 $.03 $1.33 $.16 $.24 $.48 $.96 $3.65 Other examples of the types of fringe benefits allowed: Sick pay Holiday pay Accidental Death & Dismemberment insurance premiums The following are examples of items that will not be credited toward the payment of the Prevailing Wage Rate o Legally required payments, such as: Unemployment Insurance payments Workers Compensation Insurance payments FICA (Social Security contributions, Medicare contributions) o Reimbursable expenses, such as: Clothing allowance or reimbursement Uniform allowance or reimbursement Gas allowance or reimbursement Travel time or payment Meals or lodging allowance or reimbursement Per diem allowance or payment o Other payments to or on behalf of a construction mechanic that are not wages or fringe benefits, such as: Industry advancement funds Financial or material loans (10/15) Page 1 of 1

State of Michigan DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS MICHIGAN OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION MARTHA B. YODER DIRECTOR OVERTIME PROVISIONS for MICHIGAN PREVAILING WAGE RATE COMMERCIAL SCHEDULE 1. Overtime is represented as a nine character code. Each character represents a certain period of time after the first 8 hours Monday thru Friday. Monday thru Friday Saturday Sunday & Holidays Four 10s First 8 Hours 4 9th Hour 1 5 10th Hour 2 6 Over 10 hours 3 7 8 9 Overtime for Monday thru Friday after 8 hours: the 1st character is for time worked in the 9th hour (8.1-9 hours) the 2nd character is for time worked in the 10th hour (9.1-10 hours) the 3rd character is for time worked beyond the 10th hour (10.1 and beyond) Overtime on Saturday: the 4th character is for time worked in the first 8 hours on Saturday (0-8 hours) the 5th character is for time worked in the 9th hour on Saturday (8.1-9 hours) the 6th character is for time worked in the 10th hour (9.1-10 hours) the 7th character is for time worked beyond the 10th hour (10.01 and beyond) Overtime on Sundays & Holidays The 8th character is for time worked on Sunday or on a holiday Four Ten Hour Days The 9th character indicates if an optional 4-day 10-hour per day workweek can be worked between Monday and Friday without paying overtime after 8 hours worked, unless otherwise noted in the rate schedule. To utilize a 4 ten workweek, notice is required from the employer to employee prior to the start of work on the project. 2. Overtime Indicators Used in the Overtime Provision: H - means TIME AND ONE-HALF due X - means TIME AND ONE-HALF due after 40 HOURS worked D - means DOUBLE PAY due Y - means YES an optional 4-day 10-hour per day workweek can be worked without paying overtime after 8 hours worked N - means NO an optional 4-day 10-hour per day workweek can not be worked without paying overtime after 8 hours worked 3. EXAMPLES: HHHHHHHDN - This example shows that the 1½ rate must be used for time worked after 8 hours Monday thru Friday (characters 1-3); for all hours worked on Saturday, 1½ rate is due (characters 4-7). Work done on Sundays or holidays must be paid double time (character 8). The N (character 9) indicates that 4 ten-hour days is not an acceptable workweek at regular pay. XXXHHHHDY - This example shows that the 1½ rate must be used for time worked after 40 hours are worked Monday thru Friday (characters 1-3); for hours worked on Saturday, 1½ rate is due (characters 4 7). Work done on Sundays or holidays must be paid double time (character 8). The Y (character 9) indicates that 4 ten-hour days is an acceptable alternative workweek. LARA is an equal opportunity employer. Auxiliary aids, services and other reasonable accommodations are available, upon request, to individuals with disabilities. Wage and Hour Program 530 W. Allegan P.O. BOX 30476 LANSING, MICHIGAN 48909 www.michigan.gov/wagehour Phone : (517) 284-7800

ENGINEERS - CLASSES OF EQUIPMENT LIST UNDERGROUND ENGINEERS CLASS I Backfiller Tamper, Backhoe, Batch Plant Operator, Clam-Shell, Concrete Paver (2 drums or larger), Conveyor Loader (Euclid type), Crane (crawler, truck type or pile driving), Dozer, Dragline, Elevating Grader, End Loader, Gradall (and similar type machine), Grader, Power Shovel, Roller (asphalt), Scraper (self propelled or tractor drawn), Side Broom Tractor (type D-4 or larger), Slope Paver, Trencher (over 8 digging capacity), Well Drilling Rig, Mechanic, Slip Form Paver, Hydro Excavator. CLASS II Boom Truck (power swing type boom), Crusher, Hoist, Pump (1 or more 6" discharge or larger gas or diesel powered by generator of 300 amps or more, inclusive of generator), Side Boom Tractor (smaller than type D-4 or equivalent), Tractor (pneu-tired, other than backhoe or front end loader), Trencher (8 digging capacity and smaller), Vac Truck. CLASS III Air Compressors (600 cfm or larger), Air Compressors (2 or more less than 600 cfm), Boom Truck (non-swinging, non-powered type boom), Concrete Breaker (self-propelled or truck mounted, includes compressor), Concrete Paver (1 drum, ½ yard or larger), Elevator (other than passenger), Maintenance Man, Mechanic Helper, Pump (2 or more 4" up to 6" discharge, gas or diesel powered, excluding submersible pump), Pumpcrete Machine (and similar equipment), Wagon Drill Machine, Welding Machine or Generator (2 or more 300 amp or larger, gas or diesel powered). HAZARDOUS WASTE ABATEMENT ENGINEERS CLASS I Backhoe, Batch Plant Operator, Clamshell, Concrete Breaker when attached to hoe, Concrete Cleaning Decontamination Machine Operator, Concrete Pump, Concrete Paver, Crusher, Dozer, Elevating Grader, Endloader, Farm Tractor (90 h.p. and higher), Gradall, Grader, Heavy Equipment Robotics Operator, Hydro Excavator, Loader, Pug Mill, Pumpcrete Machines, Pump Trucks, Roller, Scraper (self-propelled or tractor drawn), Side Boom Tractor, Slip Form Paver, Slope Paver, Trencher, Ultra High Pressure Waterjet Cutting Tool System Operator, Vactors, Vacuum Blasting Machine Operator, Vertical Lifting Hoist, Vibrating Compaction Equipment (self-propelled), and Well Drilling Rig. CLASS II Air Compressor, Concrete Breaker when not attached to hoe, Elevator, End Dumps, Equipment Decontamination Operator, Farm Tractor (less than 90 h.p.), Forklift, Generator, Heater, Mulcher, Pigs (Portable Reagent Storage Tanks), Power Screens, Pumps (water), Stationary Compressed Air Plant, Sweeper, Water Wagon and Welding Machine. CLASS IV Boiler, Concrete Saw (40HP or over), Curing Machine (self-propelled), Farm Tractor (w/attachment), Finishing Machine (concrete), Firemen, Hydraulic Pipe Pushing Machine, Mulching Equipment, Oiler (2 or more up to 4", exclude submersible), Pumps (2 or more up to 4" discharge if used 3 hrs or more a day-gas or diesel powered, excluding submersible pumps), Roller (other than asphalt), Stump Remover, Vibrating Compaction Equipment (6 wide or over), Trencher (service) Sweeper (Wayne type and similar equipment), Water Wagon, Extend-a-Boom Forklift.

State of Michigan WHPWRequest@michigan.gov Lenawee County Official 2015 Prevailing Wage Rates for State Funded Projects Page 1 of 31 Asbestos & Lead Abatement Laborer Asbestos & Lead Abatement Laborer MLDC 10/30/2015 $40.75 $54.34 $67.93 H H H X X X X D Y 4 ten hour days @ straight time allowed Monday-Saturday, must be consecutive Asbestos & Lead Abatement, Hazardous Material Handler Asbestos and Lead Abatement, Hazardous AS207 10/30/2015 $40.75 $54.25 $67.75 H H H X X X X D Y Material Handler 4 ten hour days @ straight time allowed Monday-Saturday, must be consecutive Boilermaker Boilermaker BO85 3/28/2008 $47.24 $70.27 $93.29 H H H H H H H D N 1st 6 months $30.47 $45.11 $59.75 2nd 6 months $31.22 $46.24 $61.25 3rd 6 months $39.72 $58.99 $78.25 4th 6 months $40.47 $60.11 $79.75 5th 6 months $41.22 $61.24 $81.25 6th 6 months $42.73 $63.51 $84.27 7th 6 months $44.23 $65.75 $87.27 8th 6 months $45.74 $68.02 $90.29 Page 1 of 31

Page 2 of 31 Bricklayer Bricklayer BR9-3-BL 5/8/2015 $45.23 $58.80 $72.37 H H H H H H H D Y 4 10s allowed M-F Saturday 0-749 hours $34.37 $42.51 $50.65 750-1499 hours $35.73 $44.55 $53.37 1500-2249 hours $37.09 $46.59 $56.09 2250-2999 hours $38.45 $48.63 $58.81 3000-3749 hours $39.80 $50.65 $61.51 3750-4499 hours $41.16 $52.69 $64.23 4500-5249 hours $42.52 $54.73 $66.95 5250-6000 hours $43.87 $56.76 $69.65 Carpenter Floor layer CA1004FL 10/14/2015 $40.16 $51.34 $62.52 X X H H H H H D Y Saturday 1st Year $31.22 $37.93 $44.64 2nd Year $33.45 $41.28 $49.10 3rd Year $35.69 $44.64 $53.58 4th Year $36.81 $46.32 $55.82 Page 2 of 31

Page 3 of 31 Carpenter CA1004J 10/14/2015 $42.27 $54.47 $66.66 X X H H H H H D Y Four 10s allowed Monday-Thursday. Friday make up day for inclement weather. Hours worked on Friday except for inclement weather make up shall be paid at time and one half. Saturday 1st Year $32.51 $39.82 $47.14 2nd Year $34.95 $43.48 $52.02 3rd Year $37.39 $47.14 $56.90 4th Year $38.61 $48.98 $59.34 Cement Mason Cement Mason - 4 10s allowed M-F; Pointer, BR9-3-CM 4/14/2015 $44.02 $56.62 $69.22 X X H X X X H D Y Cleaner, Caulker 750-1499 hours $36.46 $45.28 $54.10 1500-2249 hours $37.72 $47.17 $56.62 2250-2999 hours $38.98 $49.06 $59.14 3000-3749 hours $40.24 $50.95 $61.66 3750-4499 hours $41.50 $52.84 $64.18 Cement Mason PL886-CM 6/26/2014 $44.31 $61.13 $77.95 H H D H H D D D Y 4 tens allowed M-Th, Friday makeup day 1st 6 months $32.08 $42.78 $53.49 2nd 6 months $34.80 $46.86 $58.93 3rd 6 months $37.52 $50.94 $64.37 4th 6 months $38.87 $52.97 $67.07 5th 6 months $40.23 $55.01 $69.79 6th 6 months $41.59 $57.05 $72.51 Page 3 of 31

Page 4 of 31 Drywall Drywaller PL886-DR 6/26/2014 $40.52 $53.22 $65.92 X X H X X X H D Y 1st 6 months $27.82 $34.17 $40.52 2nd 6 months $29.09 $36.08 $43.06 3rd 6 months $30.36 $37.98 $45.60 4th 6 months $32.90 $41.79 $50.68 5th 6 months $30.86 $40.39 $49.91 6th 6 months $35.44 $45.60 $55.76 7th 6 months $37.98 $49.41 $60.84 8th 6 months $39.25 $51.32 $63.38 Drywall Taper PT-22-D 10/28/2015 $45.16 $58.69 $72.21 H H D H D D D D Y Four 10s allowed Monday-Thursday Friday make-up day for bad weather or holidays First 3 months $31.63 $38.39 $45.15 Second 3 months $34.34 $42.45 $50.57 Second 6 months $37.04 $46.51 $55.97 Third 6 months $39.75 $50.57 $61.39 4th 6 months $41.10 $52.59 $64.09 Page 4 of 31

Page 5 of 31 Electrician Teledata Journeyman Installer Technician EC-8 9/30/2014 $40.00 $60.00 $80.00 H H H H H H H D Y Four tens may be worked any 4 consecutive days Monday thru Friday. comment Four tens may be worked any four consecutive days Monday thru Friday 1st Period $19.83 $29.75 $39.66 2nd Period $22.87 $34.31 $45.74 3rd Period $32.75 $49.13 $65.50 4th Period $34.20 $51.30 $68.40 5th Period $35.65 $53.48 $71.30 6th Period $37.10 $55.65 $74.20 Inside Wireman EC-8-IW 9/30/2014 $56.00 $84.00 $112.00 H H H X H H H D Y Four consecutive 10 hour days may be worked at the straight time rate of pay Mon-Fri. Any day except Sunday when work cancelled due to weather conditions Period 1 $22.46 $33.69 $44.92 Period 2 $26.61 $39.92 $53.22 Period 3 $33.01 $49.52 $66.02 Period 4 $37.60 $56.40 $75.20 Period 5 $42.20 $63.30 $84.40 Period 6 $46.81 $70.22 $93.62 Teledata Cable Puller EC-8-TC 9/29/2011 $13.37 $20.06 $26.74 H H H H H H H D Y Four tens may be worked any 4 consecutive days Monday thru Friday. Make up day allowed Page 5 of 31

Page 6 of 31 Elevator Constructor Elevator Constructor Mechanic EL-44 2/4/2015 $77.53 $122.30 D D D D D D D D Y comment 4 10s allowed M-Th 1st year $55.41 $80.03 2nd year $60.33 $89.43 3rd year $62.79 $94.13 4th year $67.71 $103.53 Elevator Constructor Mechanic EL-85 4/8/2013 $70.77 $116.32 D D D D D D D D Y comment 4 tens allowed M-TH 1st year $50.27 $75.32 2nd year $54.83 $84.44 3rd year $57.10 $88.98 4th year $61.66 $98.10 Glazier Glazier GL-357 10/28/2015 $48.10 $66.84 $85.58 H H H H H H H D Y If a four 10 hour day workweek is scheduled, four 10s must be consecutive, M-F. 1st 6 months $33.07 $44.30 $55.52 2nd 6 months $34.58 $46.57 $58.54 3rd 6 months $37.58 $51.07 $64.54 4th 6 months $39.09 $53.33 $67.56 5th 6 months $40.59 $55.58 $70.56 6th 6 months $42.09 $57.83 $73.56 7th 6 months $43.59 $60.08 $76.56 8th 6 months $46.60 $64.59 $82.58 Page 6 of 31

Page 7 of 31 Heat and Frost Insulator Spray Insulation AS25S 3/5/2007 $20.14 $29.14 H H H H H H H H N Heat and Frost Insulator and Asbestos Worker Heat and Frost Insulators and Asbestos Workers AS45 7/1/2008 $48.05 $71.74 $95.42 H H H H H H H D Y 1st period $22.62 $33.60 $44.56 2nd period $24.08 $35.78 $47.48 3rd period $29.93 $44.56 $59.18 4th period $31.40 $46.77 $62.12 5th period $32.87 $48.97 $65.06 6th period $34.34 $51.17 $68.00 7th period $39.00 $58.16 $77.32 8th period $40.46 $60.35 $80.24 9th period $41.93 $62.55 $83.18 10th period $43.40 $64.76 $86.12 Subdivision of county Twps of Blissfield, Clinton, Deerfield, Fairfield, Macon, Ogden, Palmyra, Raisin, Ridgeway, Riga and Tecumseh Heat and Frost Insulator and Asbestos Worker AS47 3/11/2013 $44.40 $58.76 $73.12 H H H H H H H D Y 4 ten hour work days shall be either Monday thru Thursday or Tuesday thru Friday Friday for missed time during M-Th 4 ten schedule 1st year $25.78 $32.96 $40.14 2nd year $29.50 $38.11 $46.73 3rd year $33.22 $43.27 $53.32 4th year $36.95 $48.44 $59.93 5th year $40.68 $53.61 $66.53 Subdivision of county Twps of Adrian, Cambridge, Dover, Franklin, Hudson, Madison, Madina, Rollen, Rome, Seneca and Woodstock Page 7 of 31

Page 8 of 31 Ironworker Ironworker IR-55 10/7/2014 $49.24 $73.86 $98.48 H H D H D D D D Y Four tens allowed M-Th. Friday for inclement weather 1st year $25.04 $37.56 $50.08 2nd year $40.50 $60.75 $81.00 3rd year $43.42 $65.13 $86.84 4th year $46.33 $69.50 $92.66 Metal Fence & Guard Rail IR-55-MF 10/8/2015 $39.87 $59.81 $79.74 H H D H H H H D Y Four tens allowed M-Th Friday for inclement weather 1st year $19.57 $29.36 $39.14 2nd year $33.87 $50.81 $67.74 3rd year $35.87 $53.81 $71.74 4th year $37.87 $56.81 $75.74 Pre-engineered Metal Building IR-55-PE 8/1/2013 $43.17 $64.76 $86.34 H H D H D D D D Y Four tens allowed M-Th Friday for inclement weather 1st year $21.55 $32.33 $43.10 2nd year $36.09 $54.13 $72.18 3rd year $38.45 $57.67 $76.90 4th year $40.81 $61.21 $81.62 Page 8 of 31

Page 9 of 31 Laborer Journeyperson - building and heavy construction L499-A 7/16/2015 $35.11 $46.19 $57.27 X X H H H H H D Y craft laborer, portable concrete mixer operator, air, electric or gasoline tool operator, hot dope carrier, tar kettle tender, gasoline vibrators, concrete gas buggies, concrete saw, signal person and top person on sewer, caisson construction (open cut work), concrete shoveler, car pusher, and bottom person (on sewer work). Demolition laborer, 3" pumps & below, jobsite clean-up, deep cleaning, jackhammer operators, burner, crock layer, caisson worker, tunnel mucker and tunnel miner, welder, mason tender, mortar mixer, scaffold builder, forklift operator (masonry only), helper and te nder on work customarily performed by laborers and all laborers working for masonry contractors and plasterer tenders. Saturday 0-1,000 hours $29.57 $37.88 $46.19 1,001-2,000 hours $30.68 $39.55 $48.41 2,001-3,000 hours $31.79 $41.21 $50.63 3,001-4,000 hours $34.00 $44.53 $55.05 High Burner L499D 7/16/2015 $36.11 $47.69 $59.27 X X H X X H H D N A 4-10 work week must run 4 consecutive days between Monday and Friday. All hours worked on Saturday except as an inclement weather make-up day, must be paid @ time & Saturday Ground burner L499J 7/16/2015 $35.61 $46.94 $58.27 X X H X X H H D N Saturday Page 9 of 31

Page 10 of 31 Laborer - Hazardous Class A - performing work in conjunction with LHAZ-Z4-A 11/7/2014 $34.71 $49.13 $63.54 H H H H H H H D Y site preparation and other preliminary work prior to actual removal, handling, or containment of hazardous waste substances not requiring use of personal protective equipment required by state or federal regulations; or a laborer performing work in conjunction with the removal, handling, or containment of hazardous waste substances when use of personal protective equipment level "D" is required. 4 10s allowed M-Th or T-F; inclement weather makeup day Friday 0-1,000 work hours $29.25 $40.94 $52.62 1,001-2,000 work hours $30.34 $42.57 $54.80 2,001-3,000 work hours $31.44 $44.22 $57.00 3,001-4,000 work hours $33.62 $47.49 $61.36 Class B - performing work in conjunction with LHAZ-Z4-B 11/7/2014 $35.71 $50.63 $65.54 H H H H H H H D Y the removal, handling, or containment of hazardous waste substances when the use of personal protective equipment levels "A", "B" or "C" is required. 4 10s allowed M-Th or T-F; inclement weather makeup day Friday 0-1,000 work hours $30.00 $42.06 $54.12 1,001-2,000 work hours $31.14 $43.77 $56.40 2,001-3,000 work hours $32.29 $45.50 $58.70 3,001-4,000 work hours $34.57 $48.92 $63.26 Page 10 of 31

Page 11 of 31 Laborer Underground - Tunnel, Shaft & Caisson Class I - Tunnel, shaft and caisson laborer, LAUCT-Z2-1 10/30/2014 $35.67 $47.07 $58.47 X X X X X X X D Y dump man, shanty man, hog house tender, testing man (on gas), and watchman. 0-1,000 work hours $30.52 $39.35 $48.17 1,001-2,000 work hours $31.55 $40.90 $50.23 2,001-3,000 work hours $32.58 $42.44 $52.29 3,001-4,000 work hours $34.64 $45.53 $56.41 Class II - Manhole, headwall, catch basin LAUCT-Z2-2 10/30/2014 $35.76 $47.21 $58.65 X X X X X X X D Y builder, bricklayer tender, mortar man, material mixer, fence erector, and guard rail builder 0-1,000 work hours $30.58 $39.44 $48.29 1,001-2,000 work hours $31.62 $41.00 $50.37 2,001-3,000 work hours $32.66 $42.56 $52.45 3,001-4,000 work hours $34.72 $45.65 $56.57 Page 11 of 31

Page 12 of 31 Class III - Air tool operator (jack hammer man, LAUCT-Z2-3 10/30/2014 $35.86 $47.36 $58.85 X X X X X X X D Y bush hammer man and grinding man), first bottom man, second bottom man, cage tender, car pusher, carrier man, concrete man, concrete form man, concrete repair man, cement invert laborer, cement finisher, concrete shoveler, conveyor man, floor man, gasoline and electric tool operator, gunnite man, grout operator, welder, heading dinky man, inside lock tender, pea gravel operator, pump man, outside lock tender, scaffold man, top signal man, switch man, track man, tugger man, utility man, vibrator man, winch operator, pipe jacking man, wagon drill and air track operator and concrete saw operator (under 40 h.p.). 0-1,000 work hours $30.66 $39.56 $48.45 1,001-2,000 work hours $31.70 $41.12 $50.53 2,001-3,000 work hours $32.74 $42.68 $52.61 3,001-4,000 work hours $34.82 $45.80 $56.77 Class IV - Tunnel, shaft and caisson mucker, LAUCT-Z2-4 10/30/2014 $36.02 $47.60 $59.17 X X X X X X X D Y bracer man, liner plate man, long haul dinky driver and well point man. 0-1,000 work hours $30.78 $39.74 $48.69 1,001-2,000 work hours $31.83 $41.32 $50.79 2,001-3,000 work hours $32.88 $42.89 $52.89 3,001-4,000 work hours $34.97 $46.02 $57.07 Page 12 of 31

Page 13 of 31 Class V - Tunnel, shaft and caisson miner, drill LAUCT-Z2-5 10/30/2014 $36.28 $47.99 $59.69 X X X X X X X D Y runner, keyboard operator, power knife operator, reinforced steel or mesh man (e.g. wire mesh, steel mats, dowel bars) 0-1,000 work hours $30.98 $40.04 $49.09 1,001-2,000 work hours $32.04 $41.63 $51.21 2,001-3,000 work hours $33.10 $43.22 $53.33 3,001-4,000 work hours $35.22 $46.40 $57.57 Class VI - Dynamite man and powder man. LAUCT-Z2-6 10/30/2014 $36.59 $48.45 $60.31 X X X X X X X D Y 0-1,000 work hours $31.21 $40.38 $49.55 1,001-2,000 work hours $32.28 $41.99 $51.69 2,001-3,000 work hours $33.36 $43.61 $53.85 3,001-4,000 work hours $35.51 $46.84 $58.15 Class VII - Restoration laborer, seeding, LAUCT-Z2-7 10/30/2014 $28.86 $36.86 $44.85 X X X X X X X D Y sodding, planting, cutting, mulching and topsoil grading and the restoration of property such as replacing mail boxes, wood chips, planter boxes and flagstones. 0-1,000 work hours $25.41 $31.68 $37.95 1,001-2,000 work hours $26.10 $32.72 $39.33 2,001-3,000 work hours $26.79 $33.76 $40.71 3,001-4,000 work hours $28.17 $35.82 $43.47 Page 13 of 31

Page 14 of 31 Landscape Laborer Landscape Specialist includes air, gas, and diesel LLAN-Z2-A 10/13/2015 $28.25 $39.04 $49.82 X X H X X X H D Y equipment operator, skidsteer (or equivalent), lawn sprinkler installer on landscaping work where seeding, sodding, planting, cutting, trimming, backfilling, rough grading or maintenance of landscape projects occurs. Sundays paid at time & one half. Holidays paid at double time. Skilled Landscape Laborer: small power tool LLAN-Z2-B 10/13/2015 $24.05 $32.74 $41.42 X X H X X X H D Y operator, lawn sprinkler installers' tender, material mover, truck driver on when seeding, sodding, planting, cutting, trimming, backfilling, rough grading or maintaining of landscape projects occurs Sundays paid at time & one half. Holidays paid at double time. Marble Finisher Marble Finisher BR1-MF 10/20/2014 $43.48 $54.29 $65.10 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $19.04 $25.12 $31.20 Level 2 $20.24 $26.92 $33.60 Level 3 $27.01 $33.96 $40.90 Level 4 $28.47 $36.14 $43.82 Level 5 $29.99 $37.84 $45.70 Level 6 $31.61 $39.86 $48.10 Level 7 $33.30 $41.59 $49.87 Level 8 $34.79 $43.48 $52.17 Page 14 of 31

Page 15 of 31 Marble Mason Marble Mason BR1-MM 10/17/2014 $50.29 $64.51 $78.72 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $25.14 $32.65 $40.15 Level 2 $28.20 $36.49 $44.78 Level 3 $33.41 $41.97 $50.53 Level 4 $36.15 $45.66 $55.17 Level 5 $38.42 $48.17 $57.92 Level 6 $42.07 $53.56 $65.05 Level 7 $42.74 $54.38 $66.02 Level 8 $43.67 $55.78 $67.88 Operating Engineer Crane with boom & jib or leads 120' or longer EN-324-A120 10/28/2015 $57.86 $75.50 $93.13 X X H H D D D D Y comment Double time after 12 hours M-F Crane with boom & jib or leads 140' or longer EN-324-A140 10/28/2015 $58.68 $76.73 $94.77 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Crane with boom & jib or leads 220' or longer EN-324-A220 10/28/2015 $58.98 $77.18 $95.37 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Crane with boom & jib or leads 300' or longer EN-324-A300 10/28/2015 $60.48 $79.43 $98.37 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Page 15 of 31

Page 16 of 31 Crane with boom & jib or leads 400' or longer EN-324-A400 10/28/2015 $61.98 $81.68 $101.37 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Compressor or welding machine EN-324-CW 10/28/2015 $47.01 $59.22 $71.43 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Forklift, lull, extend-a-boom forklift EN-324-FL 10/28/2015 $54.32 $70.19 $86.05 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Fireman or oiler EN-324-FO 10/28/2015 $45.98 $57.68 $69.37 X X H H D D D D Y Work in excess of 12 per day M-F shall be paid at double time. Regular crane, job mechanic, concrete pump EN-324-RC 10/28/2015 $57.00 $74.21 $91.41 X X H H D D D D Y with boom Work in excess of 12 per day M-F shall be paid at double time. Regular engineer, hydro-excavator, remote EN-324-RE 10/28/2015 $56.03 $72.75 $89.47 X X H H D D D D Y controlled concrete breaker Work in excess of 12 per day M-F shall be paid at double time. 0-999 hours $45.00 $56.71 $68.41 1,000-1,999 hours $46.67 $59.22 $71.75 2,000-2,999 hours $48.78 $62.38 $75.97 3,000-3,999 hours $50.02 $64.24 $78.45 4,000-4,999 hours $51.69 $66.75 $81.79 5,000-5,999 hours $53.36 $69.24 $85.13 Page 16 of 31

Page 17 of 31 Operating Engineer - DIVER Diver/Wet Tender/Tender/Rov Pilot/Rov Tender GLF D 4/2/2014 $52.80 $79.20 $105.60 H H H H H H H D N Operating Engineer - Marine Construction Diver/Wet Tender, Engineer (hydraulic dredge) GLF-1 2/12/2014 $65.00 $84.85 $104.70 X X H H H H H D Y Make up day allowed Subdivision of county all Great Lakes, islands therein, & connecting & tributary waters Crane/Backhoe Operator, 70 ton or over Tug GLF-2 2/12/2014 $63.50 $82.60 $101.70 X X H H H H H D Y Operator, Mechanic/Welder, Assistant Engineer (hydraulic dredge), Leverman (hydraulic dredge), Diver Tender Holiday pay = $120.80 per hour, wages & Make up day allowed Subdivision of county All Great Lakes, islands therein, & connecting & tributary waters Friction, Lattice Boom or Crane License GLF-2B 2/12/2014 $64.50 $84.10 $103.70 X X H H H H H D Y Certification Holiday pay = $123.30 Make up day allowed Subdivision of county All Great Lakes, islands, therein, & connecting & tributary waters Deck Equipment Operator, Machineryman, GLF-3 2/12/2014 $59.30 $76.30 $93.30 X X H H H H H D Y Maintenance of Crane (over 50 ton capacity) or Backhoe (115,000 lbs or more), Tug/Launch Operator, Loader, Dozer on Barge, Deck Machinery Holiday pay = $110.30 per hour, wages & Make up day allowed Subdivision of county All Great Lakes, islands therein, & connecting & tributary waters County: Statewide Page 17 of 31

Page 18 of 31 Deck Equipment Operator, GLF-4 2/12/2014 $53.60 $67.75 $81.90 X X H H H H H D Y (Machineryman/Fireman), (4 equipment units or more), Off Road Trucks, Deck Hand, Tug Engineer, & Crane Maintenance 50 ton capacity and under or Backhoe 115,000 lbs or less, Assistant Tug Operator Holiday pay = $96.05 per hour, wages & fringes Make up day allowed Subdivision of county Operating Engineer Steel Work All Great Lakes, islands therein, & connecting & tributary waters Forklift, 1 Drum Hoist EN-324-ef 10/26/2015 $58.91 $77.25 $95.58 H H D H H H D D Y Crane w/ 120' boom or longer EN-324-SW120 10/26/2015 $61.61 $81.30 $100.98 H H D H H H D D Y Crane w/ 120' boom or longer w/ Oiler EN-324-SW120-O 10/26/2015 $62.61 $82.80$102.98 H H D H H H D D Y Crane w/ 140' boom or longer EN-324-SW140 10/26/2015 $62.79 $83.07 $103.34 H H D H H H D D Y Crane w/ 140' boom or longer W/ Oiler EN-324-SW140-O 10/26/2015 $63.79 $84.57$105.34 H H D H H H D D Y Boom & Jib 220' or longer EN-324-SW220 10/26/2015 $63.06 $83.47 $103.88 H H D H H H D D Y Crane w/ 220' boom or longer w/ Oiler EN-324-SW220-O 10/26/2015 $64.06 $84.97$105.88 H H D H H H D D Y Page 18 of 31

Page 19 of 31 Boom & Jib 300' or longer EN-324-SW300 10/26/2015 $64.56 $85.72 $106.88 H H D H H H D D Y Crane w/ 300' boom or longer w/ Oiler EN-324-SW300-O 10/26/2015 $65.56 $87.22$108.88 H H D H H H D D Y Boom & Jib 400' or longer EN-324-SW400 10/26/2015 $66.06 $87.97 $109.88 H H D H H H D D Y Crane w/ 400' boom or longer w/ Oiler EN-324-SW400-O 10/26/2015 $67.06 $89.47$111.88 H H D H H H D D Y Crane Operator, Job Mechanic, 3 Drum Hoist & EN-324-SWCO 10/26/2015 $61.25 $80.76 $100.26 H H D H H H D D Y Excavator 0-999 hours $48.54 $62.19 $75.84 1,000-1,999 hours $50.50 $65.13 $79.76 2,000-2,999 hours $52.45 $68.06 $83.66 3,000-3,999 hours $54.39 $70.96 $87.54 4,000-4,999 hours $56.35 $73.91 $91.46 5,000 hours $58.29 $76.82 $95.34 Crane Operator w/ Oiler EN-324-SWCO-O 10/26/2015 $62.25 $82.26$102.26 H H D H H H D D Y Compressor or Welder Operator EN-324-SWCW 10/26/2015 $53.80 $69.58 $85.36 H H D H H H D D Y Page 19 of 31

Page 20 of 31 Hoisting Operator, 2 Drum Hoist, & Rubber Tire EN-324-SWHO 10/26/2015 $60.61 $79.80 $98.98 H H D H H H D D Y Backhoe Oiler EN-324-SWO 10/26/2015 $52.39 $67.47 $82.54 H H D H H H D D Y Tower Crane & Derrick where work is 50' or D EN-324-SWTD50 Y 10/26/2015 $62.34 $82.39$102.44 H H D H H H D more above first level Tower Crane & Derrick 50' or more w/ Oiler D EN-324-SWTD50-O Y 10/26/2015 $63.34 $83.89$104.44 H H D H H H D where work station is 50' or more above first Operating Engineer Underground Class I Equipment - Backfiller Tamper, Backhoe, EN-324A2-UC1 10/14/2014 $50.03 $64.42 $78.80 H H H H H H H D Y Batch Plant Operator, Clamshell, Concrete Paver 2 drums or larger, Conveyor Loader Euclid type, Crane (crawler, truck type or pile driving), Dozer, Dragline, Elevating Grader, endloader, gradall, grader, hydro excavator, power shovel, roller asphalt, scraper selfpropelled or tractor drawn, side boom tractor, slip form paver, slope paver, trencher over 8 ft. digging capacity, well drilling rig, concrete pump 0-999 hours $40.60 $50.67 $60.74 1,000-1,999 hours $42.04 $52.83 $63.62 2,000-2,999 hours $43.48 $54.99 $66.50 3,000-3,999 hours $44.92 $57.15 $69.38 4,000-4,999 hours $46.36 $59.31 $72.26 5,000-5,999 hours $47.80 $61.48 $75.14 Page 20 of 31

Page 21 of 31 Class II Equipment - Boom Truck, Crusher, EN-324A2-UC2 10/14/2014 $45.14 $57.08 $69.02 H H H H H H H D Y Hoist, Pump 6 inch discharge or larger, side boom tractor, Tractor (pneu-tired other than backhoe or front end loader), Trencher 8 ft. digging capcity and smaller, Vac Truck Class III Equipment - Air Compressors 600 cfm EN-324A2-UC3 10/14/2014 $44.64 $56.33 $68.02 H H H H H H H D Y or larger, Air Compressors 2 or more less than 600 dfm, Boom Truck non-swinging nonpowered type boom, Concrete Breaker selfpropelled or truck mounted, Concrete paver 1 drum 1/2 yd. or larger, Elevator other than passenger, Pump 4 inch to 6 inch discharge, pumpcrete machine, wagon drill, welding machine or generator 2 or more 300 amp or Class IV Equipment - Boiler, Concrete Saw 40 EN-324A2-UC4 10/14/2014 $44.36 $55.91 $67.46 H H H H H H H D Y hp or over, curing machine self propelled, end dumps, extend a boom forklift, farm tractor with attachment, finishing machine concrete, firemen, hydraulic pipe pushing machine, mulching equipment, oiler, pumps up to 4 inch discharge, roller other than asphalt, stump remover, sweeper wayne type, trencher, vibrating compaction equipment self propelled 6 ft. wide or over, water wagon. Page 21 of 31

Page 22 of 31 Painter Painter (8 hours of repaint work performed on PT-22-P 10/28/2015 $43.57 $56.60 $69.63 H H D H D D D D Y Sunday shall be paid time & one half rate) Four 10s allowed Monday-Thursday with Friday makeup day if job down due to weather, holiday or other conditions beyond the control of the employer. Fridays for bad weather or holidays First 6 months $30.54 $37.05 $43.57 Second 6 months $34.45 $42.92 $51.39 Third 6 months $35.75 $44.87 $53.99 Fourth 6 months $37.06 $46.83 $56.61 Fifth 6 months $38.36 $48.79 $59.21 Final 6 months $39.66 $50.73 $61.81 Pipe and Manhole Rehab General Laborer for rehab work or normal TM247 4/17/2015 $28.20 $38.20 H H H H H H H H N cleaning and cctv work-top man, scaffold man, CCTV assistant, jetter-vac assistant Tap cutter/cctv Tech/Grout Equipment TM247-2 4/17/2015 $32.70 $44.95 H H H H H H H H N Operator: unit driver and operator of CCTV; grouting equipment and tap cutting equipment CCTV Technician/Combo Unit Operator: unit TM247-3 4/17/2015 $31.45 $43.07 H H H H H H H H N driver and operator of cctv unit or combo unit in connection with normal cleaning and televising work Boiler Operator: unit driver and operator of TM247-4 4/17/2015 $33.20 $45.70 H H H H H H H H N steam/water heater units and all ancillary equipment associated County: Statewide Page 22 of 31

Page 23 of 31 Combo Unit driver & Jetter-Vac Operator TM247-5 4/17/2015 $33.20 $45.70 H H H H H H H H N Pipe Bursting & Slip-lining Equipment Operator TM247-6 4/17/2015 $34.20 $47.20 H H H H H H H H N Plasterer Plasterer BR9-3-PCC 3/17/2015 $43.33 $55.80 $68.27 H H H H H H H D Y 4 10s allowed M-F 0-749 hours $34.60 $42.71 $50.81 750-1499 hours $35.85 $44.58 $53.31 1500-2249 hours $37.09 $46.44 $55.79 2250-2999 hours $38.34 $48.31 $58.29 3000-3749 hours $39.59 $50.19 $60.79 3750-4499 hours $40.84 $52.07 $63.29 Plasterer PL886 6/26/2014 $42.53 $56.24 $69.94 X X H X X X H D N 1st 6 months $28.82 $35.67 $42.52 2nd 6 months $30.20 $37.74 $45.28 3rd 6 months $31.57 $39.80 $48.02 4th 6 months $34.31 $43.90 $53.50 5th 6 months $35.68 $45.96 $56.24 6th 6 months $37.05 $48.02 $58.98 7th 6 months $39.79 $52.12 $64.46 8th 6 months $41.16 $54.18 $67.20 Page 23 of 31

Page 24 of 31 Plumber & Pipefitter Plumber & Pipefitter PL-333-RII 12/29/2009 $51.02 $76.33 $101.64 H H H H H H H D Y Four 10s allowed Monday thru Thursday. Friday not a makeup, considered OT, paid @ time & one-half. Make up day allowed Subdivision of county Plumber, Pipefitter, Welder & HVAC 1st 6 months $32.97 $49.26 $65.54 2nd 6 months $34.61 $51.72 $68.82 3rd 6 months $36.25 $54.18 $72.10 4th 6 months $37.89 $56.64 $75.38 5th 6 months $39.53 $59.10 $78.66 6th 6 months $41.17 $61.56 $81.94 7th 6 months $42.82 $64.03 $85.24 8th 6 months $44.46 $66.49 $88.52 9th 6 months $46.10 $68.95 $91.80 10th 6 months $47.74 $71.41 $95.08 EXCEPT the Townships of Clinton, Macon and Tecumseh. Plumber, Pipefitter, Welder & HVAC PL-190 10/27/2015 $59.60 $82.90 $106.19 H H H H H H H D Y 4 tens can be worked between Monday and Friday 1st Year $39.56 $52.84 $66.11 2nd Year $43.03 $58.04 $73.05 3rd Year $46.49 $63.23 $79.97 4th Year $49.95 $68.42 $86.89 5th Year-1st 6 months $51.68 $71.02 $90.35 5th Year-2nd 6 months $53.41 $73.61 $93.81 Subdivision of county The Townships of Tecumseh, Clinton and Macon ONLY. Page 24 of 31

Page 25 of 31 Roofer Commercial Roofer RO-134 9/8/2005 $36.79 $48.98 $61.16 H H D X D D D D Y Make up day allowed 1st period $24.61 $30.70 $36.80 2nd period $25.82 $32.52 $39.22 3rd period $27.04 $34.35 $41.66 4th period $28.26 $36.18 $44.10 5th period $29.48 $38.01 $46.54 6th period $30.70 $39.84 $48.98 7th period $31.92 $41.67 $51.42 8th period $33.13 $43.48 $53.84 Sewer Relining Class I-Operator of audio visual CCTV system SR-I 11/3/2014 $42.76 $57.75 $72.74 H H H H H H H D N including remote in-ground cutter and other equipment used in conjunction with CCTV Class II-Operator of hot water heaters and SR-II 11/3/2014 $41.23 $55.46 $69.68 H H H H H H H D N circulation system; water jetters; and vacuum and mechanical debris removal systems and those assisting. County: Statewide Page 25 of 31

Page 26 of 31 Sheet Metal Worker Sheet Metal Worker SHM-33 7/5/2013 $55.59 $74.97 $94.35 H H D H D D D D Y 4 ten hour days allowed when scheduled as four consecutive days, Monday thru Friday 1st Year $25.97 $34.47 $42.96 3rd 6 months $39.38 $50.66 $61.93 4th 6 months $40.95 $53.02 $65.07 5th 6 months $42.52 $55.37 $68.21 6th 6 months $44.09 $57.72 $71.35 7th 6 months $45.66 $60.08 $74.49 8th 6 months $47.23 $62.44 $77.63 9th 6 months $48.80 $64.79 $80.77 10th 6 months $50.38 $67.16 $83.93 Sprinkler Fitter Sprinkler Fitter SP 669 9/17/2009 $46.51 $61.99 $77.47 H H H H H H H D Y Make up day allowed Class 1 & 2 $23.44 $31.31 $39.17 Class 3 $29.35 $37.75 $46.15 Class 4 $30.93 $40.12 $49.31 Class 5 $35.50 $45.47 $55.45 Class 6 $37.07 $47.83 $58.59 Class 7 $38.65 $50.20 $61.75 Class 8 $40.22 $52.55 $64.89 Class 9 $41.79 $54.91 $68.03 Class 10 $43.36 $57.27 $71.17 Page 26 of 31

Page 27 of 31 Terrazzo Terrazzo Finisher BR1-TRF 10/17/2014 $43.97 $55.03 $66.08 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $19.04 $25.12 $31.20 Level 2 $20.24 $26.92 $33.60 Level 3 $27.01 $33.96 $40.90 Level 4 $28.47 $36.14 $43.82 Level 5 $29.99 $37.84 $45.70 Level 6 $31.61 $39.86 $48.10 Level 7 $33.30 $41.59 $49.87 Level 8 $34.79 $43.48 $52.17 Terrazzo Worker BR1-TRW 10/17/2014 $49.73 $63.67 $77.60 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $25.14 $32.65 $40.15 Level 2 $28.20 $36.49 $44.78 Level 3 $33.41 $41.97 $50.53 Level 4 $36.15 $45.66 $55.17 Level 5 $38.42 $48.17 $57.92 Level 6 $42.07 $53.56 $65.05 Level 7 $42.74 $54.38 $66.02 Level 8 $43.67 $55.78 $67.88 Page 27 of 31

Page 28 of 31 Tile Tile Finisher BR1-TF 10/17/2014 $43.50 $54.32 $65.14 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $19.04 $25.12 $31.20 Level 2 $20.24 $26.92 $33.60 Level 3 $27.01 $33.96 $40.90 Level 4 $28.47 $36.14 $43.82 Level 5 $29.99 $37.84 $45.70 Level 6 $31.61 $39.86 $48.10 Level 7 $33.30 $41.59 $49.87 Level 8 $34.79 $43.48 $52.17 Tile Layer BR1-TL 10/17/2014 $49.68 $63.59 $77.50 H H D H D D D D Y A 4 ten workweek may be worked Monday thru Thursday or Tuesday thru Friday. Level 1 $25.14 $32.65 $40.15 Level 2 $28.20 $36.49 $44.78 Level 3 $33.41 $41.97 $50.53 Level 4 $36.15 $45.66 $55.17 Level 5 $38.42 $48.17 $57.92 Level 6 $42.07 $53.56 $65.05 Level 7 $42.74 $54.38 $66.02 Level 8 $43.67 $55.78 $67.88 Truck Driver of all trucks of 8 cubic yd capacity or over TM-RB2 8/8/2013 $41.92 $37.85 H H H H H H H H Y Page 28 of 31

Page 29 of 31 of all trucks of 8 cubic yard capacity or less TM-RB2A 8/8/2013 $41.82 $37.70 H H H H H H H H Y (except dump trucks of 8 cubic yard capacity or over, tandem axle trucks, transit mix and semis, euclid type equipment, double bottoms and low boys) on euclid type equipment TM-RB2B 8/8/2013 $41.35 $38.08 H H H H H H H H Y Underground Laborer Open Cut, Class I Construction Laborer LAUC-Z3-1 10/30/2014 $33.61 $43.93 $54.25 X X X X X X X D Y 0-1,000 work hours $29.08 $37.14 $45.19 1,001-2,000 work hours $29.98 $38.49 $46.99 2,001-3,000 work hours $30.89 $39.86 $48.81 3,001-4,000 work hours $32.70 $42.57 $52.43 Underground Laborer Open Cut, Class II Mortar and material mixer, concrete form man, LAUC-Z3-2 10/30/2014 $33.75 $44.14 $54.53 X X X X X X X D Y signal man, well point man, manhole, headwall and catch basin builder, guard rail builders, headwall, seawall, breakwall, dock builder and fence erector. 0-1,000 work hours $29.18 $37.29 $45.39 1,001-2,000 work hours $30.10 $38.67 $47.23 2,001-3,000 work hours $31.01 $40.04 $49.05 3,001-4,000 work hours $32.84 $42.78 $52.71 Page 29 of 31

Page 30 of 31 Underground Laborer Open Cut, Class III Air, gasoline and electric tool operator, vibrator LAUC-Z3-3 10/30/2014 $33.87 $44.32 $54.77 X X X X X X X D Y operator, drillers, pump man, tar kettle operator, bracers, rodder, reinforced steel or mesh man (e.g. wire mesh, steel mats, dowel bars, etc.), cement finisher, welder, pipe jacking and boring man, wagon drill and air track operator and concrete saw operator (under 40 h.p.), windlass and tugger man, and directional boring man. 0-1,000 work hours $29.27 $37.42 $45.57 1,001-2,000 work hous $30.19 $38.80 $47.41 2,001-3,000 work hours $31.11 $40.18 $49.25 3,001-4,000 work hours $32.95 $42.94 $52.93 Underground Laborer Open Cut, Class IV Trench or excavating grade man. LAUC-Z3-4 10/30/2014 $33.92 $44.40 $54.87 X X X X X X X D Y 0-1,000 work hours $29.31 $37.48 $45.65 1,001-2,000 work hours $30.23 $38.86 $47.49 2,001-3,000 work hours $31.15 $40.24 $49.33 3,001-4,000 work hours $33.00 $43.02 $53.03 Underground Laborer Open Cut, Class V Pipe Layer LAUC-Z3-5 10/30/2014 $34.06 $44.61 $55.15 X X X X X X X D Y 0-1,000 work hours $29.41 $37.64 $45.85 1,001-2,000 work hours $30.34 $39.03 $47.71 2,001-3,000 work hours $31.27 $40.42 $49.57 3,001-4,000 work hours $33.13 $43.22 $53.29 Page 30 of 31

Page 31 of 31 Underground Laborer Open Cut, Class VI Grouting man, top man assistant, audio visual LAUC-Z3-6 10/30/2014 $31.36 $40.56 $49.75 X X X X X X X D Y television operations and all other operations in connection with closed circuit television inspection, pipe cleaning and pipe relining work and the installation & repair of water service pipe & appurtenances 0-1,000 work hours $27.39 $34.60 $41.81 1,001-2,000 work hours $28.18 $35.79 $43.39 2,001-3,000 work hours $28.98 $36.99 $44.99 3,001-4,000 work hours $30.57 $39.38 $48.17 Underground Laborer Open Cut, Class VII Restoration laborer, seeding, sodding, planting, LAUC-Z3-7 10/30/2014 $28.51 $36.28 $44.05 X X X X X X X D Y cutting, mulching and topsoil grading and the restoration of property such as replacing mail boxes, wood chips, planter boxes, flagstones etc. 0-1,000 work hours $25.25 $31.40 $37.53 1,001-2,000 work hours $25.90 $32.37 $38.83 2,001-3,000 work hours $26.56 $33.36 $40.15 3,001-4,000 work hours $27.86 $35.31 $42.75 Page 31 of 31