Investing in Innovation S&C Electric Company s Advanced Technology Center The Power Affiliates Program 32 nd Annual Review May 20, 2011 University of Illinois at Urbana-Champaign Chris Lettow Manager Product Engineering
Who Is S&C Electric Company? Specialists in electric power switching and protection Headquartered in Chicago, USA Operations in five countries Employee-Owned Annual sales ~ $500+ million USD 2500 employees globally
What is the ATC? A high-power testing laboratory Located in S&C s Chicago, IL industrial campus 2 850MVA generators 1700MVA total Up to 100 ka and up to 230 kv 43,000 Sq Ft facility Environmentally Friendly City of Chicago Green Building Policy LEED Gold Certification Affiliation with NEETRAC
Why Build the ATC? Many reasons but shortening product development time is key Prior to ATC construction, S&C s previous High Power Lab test capability was only 100MVA Required testing at outside laboratories in Vancouver and Holland In addition to the cost of testing, this left development teams little flexibility and required long lag times between test, analyze data, re-design and re-test
Why Build the ATC? Previous High Power Lab provided ability for proof of concept testing only could usually not test any product to full rating Example: 27kV, 12.5kA interrupter could test only as high as 8kV, 7.5kA Lead times at outside laboratories usually very long and often uncertain difficult to factor in to development project schedule
NEETRAC - National Electric Energy Testing Research & Applications Center Affiliated with Georgia Tech College of Engineering Comprised of utilities, manufacturers and educators S&C joined in 2009 NEETRAC shared in funding of the ATC and will use the ATC for its testing programs
G G ATC One-Line S/P S/P CB CB D/Y CB CB D/Y CB Qty (2) 850 MVA Generators 4.5 MVA Variable Speed Drive 80 ka air-blast main breakers 63 ka vacuum aux breakers Controlled Closing Make Switch Qty (6) 220 MVA Transformers TRV Control Load Simulation Components Distribution Line Simulator
Mayor Daley Chicago Groundbreaking
The Beginning
Foundation Preparation
Foundation (basement)
Adding a Main Level Floor
The Steel Goes Up
One-Half of the Building
Shell and then Walls
Some of the LEED Stuff
LEED Efforts (Leadership in Energy & Environmental Design) LEED Gold Certification Green/Energy Star roof Recycling storm water for irrigation High efficiency mercury-free lighting Recycling construction materials and debris Landscaping to shade parking areas Committed to 24% minority and 4% women-owned local business participation Pursuing LEED certification for entire JRCIC 20 buildings 45 acre site
Exterior Skin Goes On
Connecting the Buildings
Coming Together
Starting the Generator Foundations
Looking Down From First Floor
Forming the Generator Foundation
Pouring the Generator Foundation
The Generator Foundation
Installing the Spring Mounts
Two Completed Generator Foundations
Times Two
Mounting Plates Installed
Completed Foundation
Cooling Fans
What About the Generators?
Generator Rotor
Generator Bus - Before
Generator Bus - After
Completed, Rebuilt Bus Assembly
Bus Installation
Bringing in the Transformers
Transformers continued
Just Roll Em In
Transformers Scraped & Primed
Fresh Coat of Paint
Where the Green Roof Will Be Planted
Planting Underway
Pressure-Relief Vents (Top of Roof)
Generator in Storage
Leaving the Warehouse...
More...
So Many Wheels, So Little Time...
In Transit On Ridge Boulevard
Arrival at S&C
Installing the Generators
Gantry Crane
Tight Fit!
Lowering onto Mounting Plate
Overhead of Generator Room
Inside of Stator
Rotors Being Unpacked
Installing the Rotor
Generator Rotor Near Completion
Completed Generator Room
Generators with Final Color Scheme
Close-up
Second Floor of Transformer Room
Bus & Switches Above Transformers
Completed!
Transformer Primary Bus Connection
Inductors Being Installed
Inductors and Bus Bracing
Peak Inductors Control Peak of current in first loop during interrupting testing
Bus Construction Inside the ATC
Basement Bus Work
More Basement
Air Blast Breaker
Make Switch
Enclosure For Roof Bus
Installing the Skin on the Building S&C Green
Windows Coming Together
Exterior Completed!
The Green Roof
Aerial Shot of ATC
ATC Benefits Already Realized ATC opened in January, 2010 Innovation has always been crucial to S&C s success and the ATC has already paid dividends! Within first month of operation, increased testing capabilities of ATC allowed us to perform testing required to expand interrupting rating of an existingo product Several ongoing development projects have been aided by the ability to test, react and re-test quickly without the need for expensive travel and test preparations Engineers more engaged in the testing process - as home lab better understanding of components, lab capabilities and circuit setups
ATC Benefits Soon to be Realized Relationship with NEETRAC offers many benefits, chief among them the ability to obtain 3 rd Party Test Certifications in our own laboratory 3 rd Party, independent certifications to industry standards (IEEE, IEC) becoming required by more and more utilities particularly internationally NEETRAC s involvement allows outside customers to make use of the ATC for their own use with confidentiality ensured Separate control room for NEETRAC/outside customers off limits to S&C personnel