Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Similar documents
Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

CUSTOMER/ TWIN ARROWS PROJECT

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX E: Project Need and Description

Interconnection System Impact Study Report Request # GI

APPENDIX F: Project Need and Description

Interconnection Feasibility Study Report GIP-226-FEAS-R3

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PG&E s 2012 Request Window Proposals

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

APPENDIX E: Project Need and Description

MILLIGAN SOLAR PROJECT

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Pacific Gas and Electric Company s 2013 Annual Progress Report

Feasibility Study Report

Interconnection Feasibility Study Report GIP-084-FEAS-R2

100 MW Wind Generation Project

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Appendix D Black Hills Project Summary

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

ABB POWER SYSTEMS CONSULTING

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Generator Interconnection System Impact Study For

Interconnection Feasibility Study Report GIP-369-FEAS-R1

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

INESING srl. MOBILE SUBSTATIONS Energy Solution. Energy Innovation. INESING srl Energy Innovation

North Oregon Coast Area Study. Adam Lint

West Station-West Cañon 115 kv Transmission Project

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Q0044 interconnection at

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Chapter 6 Generator-Voltage System

CHAPTER 4 PROTECTION REQUIREMENTS

Black Hills Project Summary

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Generation Interconnection Facilities Study For

PG&E s 2017 Request Window Proposals CAISO 2017/2018 Transmission Planning Process

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Feasibility Study for the Q MW Solar Project

System Impact Study Report

Interconnection Feasibility Study Report Request # GI

15 Nelson-Marlborough Regional Plan

New Mexico Transmission Expansion Concepts For Wind Resources

APPENDIX XIII PROJECT SPECIFICATIONS AND CONTRACT CAPACITY CALCULATION I. PROJECT SPECIFICATIONS

Customer Substation Manual

Functional Specification Revision History

PSNH INTERCONNECTION REQUEST

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

SWITCHGEAR DIVISION PRODUCT PROFILES

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Falcon-Midway 115 kv Line Uprate Project Report

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

MICHIGAN ELECTRIC UTILITY

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

Feasibility Study for the Q MW Solar Project

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Midway/Monument Area TTC Study

First Applications on AltaLink s Network. Roggero Ciofani, P. Eng. Colin Clark, P. Eng.

7. SERVICES OVER 600 VOLTS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

www. ElectricalPartManuals. com lncoming-6900 through 69,000 volts Outgoing-2400 through 13,800 volts Ratings:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Sub-Regional RTEP Committee PJM South

Interconnection System Impact Study Final Report February 19, 2018

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

15 Nelson-Marlborough Regional Plan

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study Report

Sub Regional RTEP Committee Western Region ATSI

Form G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION

Sub Regional RTEP Committee Mid-Atlantic

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 2 DESCRIPTION OF SERVICE

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Transcription:

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction of a reliability-driven Wheeler Ridge Junction Substation Project in the Kern Division of the PG&E service territory. The project will provide Wheeler Ridge Substation, as well as CDWR pumps, with a more reinforced 230 kv source from Kern PP. A simplified single-line diagram of the existing and proposed project is shown below in Figures 1 and 2. Figure 1: Existing single-line diagram of Wheeler Ridge Junction Substation Project

Figure 2: Proposed single-line diagram of the Wheeler Ridge Junction Substation Project The scope of this project includes: Build a new 230/115 kv transmission substation at Wheeler Ridge Junction (WRJ) o 3 230 kv line terminations (ultimate 6) o 3 115 kv line terminations (ultimate 8) o 2 230/115 kv 420 MVA transformers Convert 15.5 miles of the Wheeler Ridge-Lamont 115 kv line from Wheeler Ridge to tower 011/065 to operate at 230 kv. Terminate at Wheeler Ridge and WRJ stations. Open end Kern-Tevis-Stockdale-Lamont 115 kv line at tower 005/035 and loop Stockdale 115 kv substation. Convert and re-conductor 5 miles of the Kern-Tevis-Stockdale-Lamont 115 kv Line section from Towers 005/035 to 011/065 to 230 kv operation on both sides of double circuit tower line (other side is idle circuit). Terminate both circuits at the WRJ station. Terminate both remaining 115 kv lines to Lamont at WRJ station. Remove Stockdale #2 230 kv Tap from Stockdale substation, and terminate the first newly converted 230 kv circuit. Bypassing Stockdale substation.

Terminate second newly converted 230 kv circuit at Stockdale substation, for a loop arrangement. Re-conductor and upgrade 6 miles of the idle line from Wheeler Ridge Junction towards Magunden substation. Upgrade for 115 kv operation, and terminate at Magunden and WRJ stations. The project will mitigate the thermal overloads and voltage concerns identified in the Wheeler Ridge 230 kv system, specifically in the area of the CDWR pumps, following a Category C1 or C2 contingency due to loss of either the Midway 230kV Bus 1D or Midway 230kV CB642 fault. This project will also mitigate several 115kV concerns in the Kern PP 115kV area. This project is dependent on the Midway #2 230kV Line project that was submitted through the 2013 Request Window and approved during the 2013-2014 CAISO TPP. The ISO estimates that the proposed Wheeler Ridge Junction Project in its entirety will cost between $90 million and $140 million in 2014 dollars. The proposed in-service date of the project is May 2020. The facilities in the Wheeler Ridge Junction substation project that are eligible for competitive solicitation are the 230 kv bus-work and termination equipment, and the 230/115 kv transformers. The 115 kv bus-work and termination equipment and modifications to existing facilities are not eligible for competitive solicitation. For the interconnection of the existing 230kV lines to the Wheeler Ridge Junction substation, the incumbent PTO (PG&E) will be responsible to bring the new transmission line extensions up to a point within 100 feet of the new substation fence. The new line extensions will terminate on a dead end structure(s), to be owned by PG&E. The approved project sponsor will be responsible (and will own and maintain) for the transmission facilities from this last dead end structure(s) extending into and terminating on the high voltage rack. The approved project sponsor, who will be the owner of the 230 kv yard of the substation, will be responsible to own, operate and maintain the protection equipment located within the substation that is designated for the protection of the incoming transmission lines. The approved project sponsor will coordinate with PG&E for the specifications and the details of the associated line protection (e.g. current differential, directional comparison) etc. and will work with PG&E to develop relay logic and detailed relay settings. While the low voltage facilities, 115 kv bus-work and termination equipment are not a part of the scope of the facilities for competitive solicitation, the approved project sponsor will be required to coordinate with PG&E to determine the total amount of acreage required to build the entire facility. Further, the approved project sponsor will be responsible to acquire the station land and necessary environmental permits from the applicable siting agency for both the 230 kv and 115 kv yards, but will need to grant a permanent easement or transfer of ownership of a parcel of land to PG&E for PG&E s portion of the total station equipment. This will ensure that there is adequate property purchased and made available to accommodate the initial and ultimate configurations of both yards. The approved project sponsor will coordinate with PG&E as to how to divide the two yards. The approved project sponsor shall coordinate and negotiate with PG&E on how the low side of each transformer is to be interconnected to the bus in the low

voltage 115 kv yard. PG&E will specify the phase rotation for the termination to the 115 kv bus in the low voltage yard. With respect to protection and control buildings, the approved project sponsor and PG&E will each install, own and maintain separate protection and control buildings for their respective substation yards.

2. Functional Specifications Substation Nominal Phase to Phase Voltage: 230/115kV Initial Bus Configuration (DBDB, BAAH, SBSB, etc.): Breaker and a half (BAAH) Ultimate Bus Configuration (DBDB, BAAH, SBSB, etc.): BAAH Initial Number of 230 kv Lines: 3 Ultimate Number of 230 kv Lines: 6 Initial Number of 230 kv CBs: 8 Ultimate Number of 230 kv CBs: 12 Initial Minimum Bus Ampacity: 3000A Ultimate Bus Ampacity: 3000A Minimum CB Ampacity: 2000A Minimum CB Interrupting Capability: 40 ka Transfer Bus Required (SBSB only): N/A Station Minimum BIL: 900 kv Initial Reactive Power Requirements: None Ultimate Reactive Power Requirements: To be determined Telemetering Requirements: Install necessary equipment, including RTUs to monitor the typical bulk power elements such as MW, MVAr, and phase currents (Amps) at each line and also voltages (kv) at lines and buses and all circuit breaker (CB) status/control, protection relays statuses and alarms. The installed equipment must be capable of transmitting information to the appropriate Control Center. Latest In Service Date: May 2020 Low Profile Required: Subject to local permitting requirements Gas Insulation Required: No Initial Number of Transformers: 2 Ultimate Number of Transformers: 2 Transformer Nominal Low Winding Phase to Phase Voltage: 115 kv Tertiary Winding Required: Yes Nominal Voltage Rating: 13.2 kv Primary Voltage Winding (wye, grounded wye, delta, etc): Grounded Wye Secondary Voltage Winding Grounded Wye_ Tertiary Voltage Winding Corner Grounded Delta Maximum Transformer % IZ: 6.5 % Minimum Transformer %IZ: 5.5% (Impedance of the two are required to match as close as possible for parallel operation) Minimum Transformer OA Rating: 252 MVA Maximum Transformer Load: 420 MVA LTC Required: Yes +/- 10% No Load Taps Required: 5 NLTs with two 2.5% taps above & below nominal voltage of 230 kv