An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

Similar documents
Study of 345 kv Transient Recovery Voltages on the Illinois Power System

6545(Print), ISSN (Online) Volume 4, Issue 2, March April (2013), IAEME & TECHNOLOGY (IJEET)

Investigation of Transient Recovery Voltage Across a Circuit Breaker with Presence of Braking Resistor

Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Mitigation of Transient Recovery Voltage Issues Associated with Transmission Capacitor Banks

MODELLING OF 25 kv ELECTRIC RAILWAY SYSTEM IN EMTP-RV

Evaluation of Torsional Efforts on Thermal Machines Shaft with Gas Turbine resulting of Automatic Reclosing

Pankaj Khali, ABB India Limited Representing :ABB Switzerland limited, September 2016 Generator Circuit-Breakers. Technical Seminar: PLN

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project

EE 741 Over-voltage and Overcurrent. Spring 2014

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Reactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation

New 115 kv Disconnect Switches at Bloomsburg MTS

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Performance Analysis of Transient Stability on a Power System Network

Independent Testing Laboratory for High Voltage Equipment

Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

Analysis of Switching Transient Overvoltages in the Power System of Floating Production Storage and Offloading Vessel

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

Item 1: Contents of the complete training & CV of the lecturer

Comparative Analysis of Integrating WECS with PMSG and DFIG Models connected to Power Grid Pertaining to Different Faults

A study of the power capacity of regenerative inverters in a DC electric railway system

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

A novel synthetic test system for thyristor level in the converter valve of HVDC power transmission

GE TRANQUELLTM Surge Arresters

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Modelling of Hybrid DC Circuit Breaker Based on Phase-Control Thyristors

Generator Interconnection System Impact Study For

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

TRANSMISSION PLANNING CRITERIA

Review paper on Fault analysis and its Limiting Techniques.

3.2. Current Limiting Fuses. Contents

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

IMPACT OF INDUCTION MOTOR LOADS INTO VOLTAGE STABILITY MARGINS OF LARGE SYSTEMS

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

Performance Analysis of 3-Ø Self-Excited Induction Generator with Rectifier Load

Metal-Enclosed Switches. Medium Voltage. Medium Voltage Metal-Enclosed Switches Contents

ABB Switzerland Ltd High Voltage Products PTHG-V / Marta Lacorte Business Development LAM High Current Systems. Generator Circuit- Breaker Systems

Secondaries. arc flash note Introduction. By Mike Lang, engineer and. Services Supervisor

Surge Arresters. UltraSIL Housed VariSTAR Station Class Surge Arresters GENERAL CONSTRUCTION

Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Medium Voltage Metal-Enclosed Switches

Modelling and Simulation of DFIG based wind energy system

ABB POWER SYSTEMS CONSULTING

Enhancement of Transient Stability Using Fault Current Limiter and Thyristor Controlled Braking Resistor

Study of Motoring Operation of In-wheel Switched Reluctance Motor Drives for Electric Vehicles

Vacuum Generator Circuit Breaker - A trend-setting power plant technology

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

R-MAG. Vacuum Circuit Breaker with Magnetic Actuator Mechanism

ECEN 667 Power System Stability Lecture 19: Load Models

Cost Benefit Analysis of Faster Transmission System Protection Systems

Islanding of 24-bus IEEE Reliability Test System

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

Noxon Rapids Reactor Project. Scott Wilson June 9, 2016 Tracy Rolstad

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Dynamic Reactive Power Control for Wind Power Plants

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Influence of Electric Field Distribution along the Line Post and Pin Post Insulator due to Lightning Strike

ELECTRICAL POWER and POWER ELECTRONICS

Targeted Application of STATCOM Technology in the Distribution Zone

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Modeling and Simulation of TSR-based SVC on Voltage Regulation for Three-Bus System

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Modeling of 25 kv Electric Railway System for Power Quality Studies

Implementation SVC and TCSC to Improvement the Efficacy of Diyala Electric Network (132 kv).

New York Science Journal 2017;10(3)

Electric Power System Under-Voltage Load Shedding Protection Can Become a Trap

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

China. Fig. 1 Chain SVG Electrical Diagram

Report No.: MS/E Copy No.: 0 Contents: 140 sheets

Experiences with Wind Power Plants with Low SCR

Power Flow Control through Transmission Line with UPFC to Mitigate Contingency

Study of Fault Currents and Relay Coordination of a Chemical Industry After Integrating with PV Generation and Simulation with a Software.

R-MAG Vacuum Circuit Breaker with Magnetic Actuator Mechanism 15.5 kv - 27 kv; 1200 A A

VariSTAR Type AZE station-class surge arresters for systems through 345 kv IEEE certified

Analysis of Grid Connected Solar Farm in ETAP Software

Chapter 6 Generator-Voltage System

DEPARTMENT OF ELECTRICAL ENGINEERING DIT UNIVERSITY HIGH VOLTAGE ENGINEERING

Impact Analysis of Off-board Charger to Power Quality

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Modelling and Analysis of Thyristor Controlled Series Capacitor using Matlab/Simulink

Prüffeld der Schaltwerke

DISTRIBUTED generation (DG) units, distributed storage

HIGS Highly Integrated Generator Circuit-Breaker Switchgear

GENERAL. CONSTRUCTION External

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014

POWER FACTOR CORRECTION OF FAST DYNAMICS INDUSTRIAL LOADS

Transcription:

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks D. M. Nobre W. L. A. Neves B. A. de Souza Departamento de Engenharia Elétrica - UFPB Av. Aprígio Veloso, 882 Bodocongó 58.109-970, Campina Grande PB Brazil diana@dee.ufpb.br, waneves@dee.ufpb.br, benemar@dee.ufpb.br Abstract - Circuit breakers can fail to interrupt threephase fault currents when power systems have Transient Recovery Voltage (TRV) characteristics, which exceed their ratings. This paper is the outcome of a study for the reevaluation of three 15 kv breakers at the CHESF (Companhia Hidroelétrica do São Francisco) Angelim substation, located in the northeast of Brazil. Digital simulations are carried out with ATP (Alternative Transients Program) to compute the TRV waveforms. Alternative actions are taken to bring circuits within the 15 kv circuit breaker ratings when the parameters of the simulated TRV exceed the breaker ratings. A simple and cheap alternative to reduce TRV peaks is the placement of s across the breaker terminals. Keywords: Circuit Breakers, TRV, Devices, Electromagnetic Transients. I. INTRODUCTION Recently, a study to examine TRV characteristics for medium-voltage circuit breakers was conducted by Swindler et al [1]. It was considered 13.8 kv breakers in an oil refinery in which circuit parameters as originally designed would have exceeded the TRV (Transient Recovery Voltage) ratings. Digital simulations were carried out with the EMTP (Electromagnetic Transients Program) to analyze TRV parameters. Alternatives to bring circuits to within the 13.8 kv circuit breaker ratings were presented. The circuit transient recovery voltage can be modified by the circuit breaker's design or by the use of additional components like opening resistors, surge capacitors, grading resistors or capacitors. The most common adopted solutions are: considering present and 2003 substation configurations. II. METHODOLOGY The TRV to which a circuit breaker is subjected depends on the type of fault, its location and the type of switching circuit. These studies must consider: three-phase ungrounded terminal fault interruption since it is usually the most severe TRV condition, with the highest peak voltage magnitudes across the first opening-pole of the breaker. This type of fault is used as the basis for the breaker rating; the short-line fault since it usually has the highest rate of rise of the recovery voltage. The ATP is used to compute the TRV waveforms and to calculate its parameters [2]. These parameters are compared with the TRV circuit breaker ratings. III. CIRCUIT BREAKER RATINGS In this TRV study, the NBR-7118 Brazilian Standard, which is based in IEC-56 International Standard, 1987, is used [3]. Its purpose is to provide an application guide on the TRV ratings for ac circuit breakers rated above 1000V. For circuit breakers rated 72.5 kv and below, the TRV is defined by the Two Parameter Method in which two TRV envelopes are used to define the TRV maximum value (U c ) and the rate of rise of the recovery voltage (RRRV). Fig. 1 shows TRV envelope for 15 kv circuit breakers. when the TRV peak value is above the breaker rating, the existing breaker is replaced by one of higher voltage class; when the rate of rise of the recovery voltage exceeds the specified value, surge capacitors are used to reduce it. This paper is the outcome of a study for the reevaluation of three 15 kv breakers at the CHESF Angelim substation, located in Pernambuco State, Brazil. TRV parameters are analyzed for bus and line breakers, Fig. 1. Two parameter envelope for circuit breakers rated 72.5 kv.

The TRV envelope comprises a two-parameter reference line (two straight line segments) and a delay line of specified value, where: U c is the TRV maximum value, in kv; t 3, time to reach U c, in µs; t d, specified delay time, in µs; u = 1 3U c, in kv; t, time to reach u, in µs. The required 15 kv circuit breaker TRV capabilities at three interrupting current levels for terminal faults are indicated in Table 1. Table 1. 15 kv breaker's capability. Percent of interrupting rating U c (kv) RRRV (kv/µs) 0-30% 27.6 1.97 30% - 60% 27.6 0.95 60% - 100% 25.7 0.38 Fig. 2 shows how to obtain these TRV parameters in practical situations. The RRRV is defined as the slope of the OP line segment. For the interruption process to be successful, the computed curve must be under the twosegment curve leading to calculated TRV parameters within 15 kv breaker ratings. Fig. 3. Angelim configuration Table 2. 230 kv bus equivalent. Sequence 1998-2002 2003-2007 R (Ω) X (Ω) R (Ω) X (Ω) Positive 025 205 023 187 Zero 049 224 029 165 Table 3. Transformer ratings. T 1 T T 1 (1998) 2 (2003) MVA rating 33.3 5 100 positive-sequence impedance (S base = 100 MVA ) (%) 73.15 125.2 13.2 Fig. 2. TRV parameters. IV. CASE STUDY: 13.8 kv CIRCUIT BREAKERS Digital simulations using ATP were made for the Angelim substation. Two configurations were considered: the configuration for the year 1998 up to the year 2002 and the one for the year 2003 up to the year 2007. The Angelim substation diagram is shown in Fig. 3 and its data are summarized in tables 2 to 6. The power system is represented by its 230 kv bus Thévenin equivalent (when performing transient simulations it is recommended that one should represent at least two buses, besides the one in which the breaker to be evaluated is connected) [4]. The 230 kv and 13.8 kv transformer windings are wye connected with grounded neutral. The 69 kv windings are delta connected. Table 4. 69 kv and 13.8 kv load. Voltage Bus 1998-2002 2003-2007 (kv) MW MVAr MW MVAr 69 104 27.4 123 32.3 13.8 3 0 4.2 0 Table 5. Connecting lead parameters. X L Ω/km/phase R Ω/km/phase C nf/km/phase 0.147 0.349 12.35 Table 6. Lead lengths. 230 kv Bus 33.3 MVA Transformer 45m 69 kv Bus - 5 MVA Transformer 30m 5 MVA Transformer - 11T4 Breaker 15m 11T4 Breaker 13.8 kv Bus 3m 13.8 kv Bus - 21Y5 Breaker 5m 13.8 kv Bus - 21Y3 Breaker 10m 13.8 kv Bus - 21Y4 Breaker 2m

The bushing and winding capacitances of the transformers were considered to be nearly 3000 pf [5]. The effective capacitances of the circuit breakers were considered to be 600 pf. A. Digital Simulations The circuit breakers to be evaluated are located at the 11T4, 21Y4 and 21Y3 substation positions, according to Fig. 3. For each breaker, using a time step of 1µs, the simulated TRV waveforms are obtained for three-phase ungrounded terminal faults. For the 21Y3 breaker, digital simulations are also performed for short-line fault clearing for 1, 3 and 5 km from the breaker terminals. The effect of the 13.8 kv load on the short-circuit current and on the TRV is taken into account for the following situations: no load, 0.5 MW and full load. The effects of bushing add winding capacitance to ground values of transformers T 1 and T 2 are considered in TRV simulations. AC short-circuit current peak values, I sc, and the maximum allowed circuit breaker currents, I max, are shown in Table 7. Table 7. Short-circuit breaking current levels. Breaker Year I (ka) I max (ka) I (%) sc 11T4 1998 7.39 13.07 2003 9.30 40 16.44 21Y4 1998 7.39 32.66 2003 9.29 16 41.07 21Y3 1998 7.38 32.60 16 2003 9.27 40.98 Three-Phase Faults Fig. 4 shows the TRV waveform for the 11T4 breaker when clearing a three-phase ungrounded terminal fault in present configuration. The TRV peaks and rate of rise calculated for each breaker opening operation are shown in figs. 5 and 6. It is necessary to identify the short-circuit breaking capacity for all breakers to be evaluated. From Table 7 and Table 1, one can see that the interrupting current levels for the 11T4, 21Y4 and 21Y3 breakers are in the range from 0 to 30%, from 30% to 60% and from 30% to 60% of their rated short-circuit current, respectively. For the 11T4 breaker the RRRV values are above the standard ratings for all situations and the TRV peak exceeds the standard ratings in the following situations: no load at 13.8 kv bus, years 1998-2002; up to a 0.5 MW load, year 2003-2007. For the 21Y4 and 21Y3 breakers, The RRRV values exceed the standard ratings up to a 3 MW load for the years 1998-2002 and up to a 4.2 MW load for the years 2003-2007. The TRV peaks exceeds the standard ratings for: no load at 13.8 kv bus, year 1998 to 2002; up to a 4.2 MW load, year 2003 to 2007. sc TRV peak, kv RRRV, kv/µs TRV - Phase A (kv) 40 35 30 25 20 15 10 5 0 3,0 2,5 2,0 1,5 1,0 0,5 0,0 3 2 1 38 40 42 44 46 Time (microseconds) Fig. 4. TRV waveform for the 11T4 breaker. (13.8 kv bus with no load ) 11T4-1998 11T4-2003 21Y4-1998 21Y4-2003 21Y3-1998 21Y3-2003 Circuit Breaker - Year Fig. 5. Three-phase fault TRV peaks. 11T4-1998 11T4-2003 21Y4-1998 21Y4-2003 21Y3-1998 21Y3-2003 Circuit Breaker - Year Short-Line Fault Fig. 6. Three-phase fault TRV rate of rise. Fig. 7 shows the TRV waveform for the 21Y3 breaker when clearing a fault at 1 km from the breaker terminals for 2003 configuration. The calculated TRV parameters are shown in figs. 8 and 9. The parameters for short-line faults are within standard values. The three-phase ungrounded terminal fault at the 13.8 kv bus with no load presented the most severe TRV condition in all simulated cases.

TRT - Phase A (kv) -4.0-8.0-12.0-16.0-2 V. ALTERNATIVE ACTIONS TO REDUCE TRV The placement of s (three or four disks - commercial layout - 62 mm diameter and 23 mm height) across the breaker terminals (Fig. 10) is an alternative to reduce TRV peaks. Figs. 11 and 12 show simulation results for the 11T4 and 21Y4 circuit breakers when clearing a three-phase ungrounded terminal fault (the TRV waveform for the 21Y3 breaker is similar to the one for the 21Y4 breaker). 8.10 8.15 8.20 8.25 8.30 Time (ms) Fig. 7. TRV waveform for short-line fault at 1km from 21Y3 breaker terminals (13.8 kv bus with no load ). 30 25 Circuit breaker Fig. 10. to reduce TRV peaks. TRV peak, kv 20 15 10 3 TRV - without s TRV - with three disks TRV - with four disks 5 0 1km-1998 1km-2003 3 km-1998 3 km-2003 5 km-1998 5 km-2003 Distance from breaker terminals - Year Fig. 8. TRV peaks (short-line fault). TRV - Phase A (kv) 2 1 2,5 RRRV, kv/µs 2,0 1,5 1,0 0,5 3 40 44 48 Time (microseconds) Fig. 11. TRV 11T4 breaker. TRV - without s TRV - with three disks TRV - with four disks 0,0 1 km-1998 1 km-2003 3 km-1998 3 km-2003 5 km-1998 5 km-2003 Distance from breaker terminals - Year Fig. 9. TRV rate of rise (short-line fault). Note in figs. 6 and 9 the reference line values for 21Y3 breaker are different since the AC short-circuit current peak values calculated for interrupting short-line faults are smaller than for three-phase ungrounded terminal faults. Thus, as shown in Fig. 9 and according to Table 1, the 21Y3 breaker TRV capability is at 0-30% level of interrupting rating (1.97 kv/µs). TRV - Phase A (kv) 2 1 40 44 48 Time (microseconds) Fig. 12. TRV 21Y4 breaker.

The calculated TRV parameters are shown in tables 8 and 9. If s are used the TRV peaks will be within standard values (Table 1). The simulated absorbed energy curve for a three disk is shown in Fig. 13. After 2ms the energy increase is very small. Table 8. TRV calculated parameters - three disks U c (kv) RRRV (kv/µs) Year 1998 2003 Year Breaker without with without with 11T4 28.07 15.44 2.51 2.14 21Y4 27.92 15.50 1.90 1.72 21Y3 28.17 15.56 1.99 1.72 11T4 33.73 16.86 2.92 2.43 21Y4 33.72 15.60 2.54 1.93 21Y3 33.94 15.67 2.60 1.98 Table 9. TRV calculated parameters - four disks U c (kv) RRRV (kv/µs) without with without with 11T4 28.07 20.49 2.51 2.24 1998 2003 4 Breaker 21Y4 27.92 20.60 1.90 1.83 21Y3 28.17 20.62 1.99 1.84 11T4 33.73 20.64 2.92 2.66 21Y4 33.72 20.72 2.54 2.18 21Y3 33.94 20.81 2.60 2.14 are nearly 0.65mA and 0.18mA, respectively. The used arrester v-i curve was the one for a temperature of 40ºC [7]. The energy absorbed by the blocks in either case is very small. Comparing tables 8 and 9 with Table 1, the TRV rate of rise values are still above the standard ratings. Thus, it is recommended the installation of surge capacitors at the source side breaker terminals. For the 11T4 circuit breaker a 37 nf (four disks) surge capacitor would reduce the RRRV to values within the standard rating in the two configurations. With this surge capacitor, a RRRV reduction of nearly 50% is accomplished for the year 2003-2007 configuration. Similarly, for the 21Y4 and 21Y3 circuit breakers, 159 nf (four disks) surge capacitors would bring the RRRV values to standard rating. The use of four disks to reduce TRV peaks is more appropriate and secure comparing to the use of three disks. The maximum continuous operating voltage (MCOV) of the arrester and its residual voltage are nearly 11.2 and 20 kv, respectively. VI. CONCLUSIONS A study for the reevaluation of 15 kv breakers was performed for the CHESF Angelim substation. The calculated TRV responses were compared to the capabilities of the circuit breakers. In some situations, the TRV exceeded the breaker ratings. From simulation results, it was shown that the placement of s across breaker terminals reduces TRV peaks. Surge capacitors, at the source side, were used to reduce the TRV rate of rise. Although simulations have shown that s placed across the breaker terminals are effective in reducing TRV peaks, it would be interesting to carry out laboratory or field tests for validation purposes. Energy (J) 3 2 1 VII. ACKNOWLEDGMENTS The authors are grateful to the reviewers for their valuable suggestions. The authors would like to thank the Electrical Engineering Department of UFPB for its support and CHESF for the substation data used in this work. The authors also would like to thank M. O. B. C. Melo, F. R. Alves, J. S. Monteiro (CHESF Engineers), and prof. E. G. Costa, D. Sc. (UFPB). Miss D. M. Nobre wishes to acknowledge to Brazilian National Research Council (CNPq) for financial support. 2.0 4.0 6.0 8.0 Time (ms) Fig. 13. Three disk s absorbed energy. At steady-state the rms voltage across the is nearly 8 kv. The maximum continuous operating voltage (MCOV) for the power system is 8.8 kv. The steady-state current peak values to three and four block s VIII. REFERENCES [1] D.L. Swindler, P. Schwartz, P.S. Hamer, S.R. Lambert, "Transient recovery voltage considerations in the application of medium-voltage circuit breakers", IEEE Transaction on Industry Applications, vol. 33, nº. 2, March/April 1997, pp. 383-388.

[2] Leuven EMTP Center, ATP - Alternative Transients Program Rule Book, Belgium, July 1987. [3] NBR-7118 High Voltage Circuit Breaker Brazilian Standards (In Portuguese), Rio de Janeiro, Brazil, 161 p., September 1994. [4] CCON ((North-Northeast Operation Coordinating Committee), Methodology and Criteria for the Analysis of Circuit Breakers Adequacy to Transient Recovery Voltages (In Portuguese), Recife, Brazil,214 p., June 1991. [5] IEEE Application Guide for Transient Recovery Voltage for AC High-Voltage Circuit Breakers Rated on a Symmetrical Current Basis - IEEE C37.011-1994 Standard, New York, NY, June 1995. [6] D.M. Nobre, Transient Recovery Voltage Reevaluation Studies for 15 kv-class Circuit Breakers (In Portuguese), M.Sc. Dissertation. UFPB. Campina Grande, Brazil, 85 p., November 1999. [7] E. G., COSTA, Surge Arrester Performance Analysis (In Portuguese), D.Sc. Thesis. UFPB Campina Grande, Brazil, 177 p., April 1999.