The relative site locations are detailed below with the main headquarters circled in blue and the new Fiji Airways Aviation Academy in green.

Similar documents
Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000

Generation Interconnection Facilities Study For

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

TENDER DOCUMENT PART-II

OFF GRID SOLAR PV SYSTEMS

Airports Going SOLAR! Michael Shonka

Phone: Website: CAPABILITY STATEMENT. Energy Efficiency & Sustainability Engineers

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

STREAMLINED SOLAR CHECKLIST Owner Name:

Interconnection System Impact Study Report Request # GI

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Interconnection Process for Generation Systems

Schneider Electric PV Skid. Optimized solar power conversion system tailored to enhance any North American PV power plant

Solar PV Projects PPA Model

BU Power Conversion, 03/2013 ABB solar inverters Product portfolio. ABB Group June 19, 2013 Slide 1

ENERGY STORAGE FOR THE EDGE OF THE GRID

100kW GROUND MOUNTED SOLAR PHOTOVOLTIC POWER PLANT DETAILED PROJECT REPORT AERO SPACE MATERIALS PVT LTD

Should I Get a Solar Array for my House? The Regulations, Available Equipment, and Benefits Steven Johnson

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

100 MW Wind Generation Project

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Solar Photovoltaic (PV) Design Considerations & Issues. By Paul M. Williams, President & CEO

15 Nelson-Marlborough Regional Plan

Solar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings

Solar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd)

Net Metering Program

* Protected from tools and particles greater than 2.5 millimeters * Protected form low pressure water jets from any direction

Compact Energy Storage Module. Modular Systems, EPDS. Product overview

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Net +Plus Connection Code

15 Nelson-Marlborough Regional Plan

Building the Business Case for Energy Storage

Solar PV General Introduction Guide for Electricians

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Merger of the generator interconnection processes of Valley Electric and the ISO;

Example 1MW Solar System for Fosters Yatala

Health & Safety Issues Associated with Solar Photovoltaic (PV)

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Horns Rev 3 & Kriegers Flak Platform Interfaces

SUBSIDY SCHEME FOR GRID CONNCTED AND OFF GRID SOLAR SYSTEMS AT IOCL PETROL PUMPS

Section 6 - Employer s Requirements

REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS. International Competitive Bidding (ICB)

Photovoltaic Solar Plan Review

2016 Photovoltaic Solar System Plan Review List

TERMS AND CONDITIONS

Solar*Rewards Frequently asked questions system size and customer usage

24. SOLAR INCENTIVE PROGRAM II

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone.

Generator Interconnection System Impact Study For

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

New Jersey State Report

Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

17 th Annual Caribbean Energy Conference

Ministry of New and Renewable Energy. Jawaharlal Nehru National Solar Mission (Off-grid and Decentralized Solar Applications)

Guideline on Energy Storage

Bulletin Wiring methods for Solar Photovoltaic Systems Rules, 2-034, , and , Tables 11 and 19

Emerald Reactive Support Alternative Solution Expressions of interest

City of Manhattan Beach Community Development

ASP General Information

Lot 26 WBS 1150 Bill of Quantities

ABB solar inverters Product portfolio

MAKING SOLAR SYSTEMS SMARTER PANEL TO GRID SOLUTIONS FROM A GLOBAL LEADER IN SOLAR TECHNOLOGY

Contents. 1 Introduction. 2. Advisory and Information Systems. 3. Supply. 3.1 Quality of Electric Supply. 3.2 Interference with other Customers

Africa Australia Technology & Infrastructure Conference. John Davidson Executive Director Carnegie Clean Energy

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Your Needs. Our Technology.

Forecast Life-Cycle Cost of solar PV Electrity (LCOE) (RM/ KWhr) VS Future Cost of Electricity from Fossil Fuel (RM/ KWhr)

Renewable Energy Integration: Wind, Solar and Energy Storage

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Get ready for rising energy challenges. This is where xstorage Home can help

GRID CONNECTED 400kWp SOLAR ROOF TOP POWER PLANT NET METERING AT KARNATAKA STATE CRICKET ASSOCIATION M. CHINNASWAMY STADIUM, BENGALURU

MILLIGAN SOLAR PROJECT

Stand-alone Power System (SPS) CASE STUDY APPLICATION PACK

ANNEX B TERMS OF REFERENCE FOR THE DESIGN OF A LOW VOLTAGE POWER NETWORK FOR IMS STATIONS IN WARRAMUNGA, AUSTRALIA

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

Umatilla Electric Cooperative Net Metering Rules

KENYA POWER-MOMBASA BRANCH REPLACEMENT OF AIR-CONDITIONING AND ASSOCIATED WORKS BILLS OF QUANTITIES FOR ELECTRICAL INSTALLATIONS BILL NO

ANNEXURE-I CHECK LIST FOR APPLICATION FORM

Solar Farm Electrical Control Buildings & Substation Build Project

Microgrids for industrial applications. ABB Group June 22, 2016 Slide 1

Pika Energy Island Made in America

Contents. Solar Select TM Frequently Asked Questions

Guidelines for connection of generators:

Energy Savings through Solar Energy for Municipalities

Storage guidance & codes. Martin Cotterell

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

Power Conversion System for ESS 100 kw to 30 MW Bi-directional Inverters

JEA Distributed Generation Policy Effective April 1, 2018

Corporate Brochure. June 2016

Hawk Asgeirsson Manager Power Systems Technologies DTE Energy

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y

Brion Energy Corporation

Transcription:

Page 1 of 8 This is NOT the Expression of Interest Application Form. The Expression of Interest Application Form is a separate document. This information document is provided such that interested firms may understand the possible scope of works and the associated opportunity. PROJECT BACKGROUND Fiji Airways as Fiji s national airline are based at Nadi International Airport. Fiji Airways wish to reduce their carbon footprint and their electrical costs through the installation of solar arrays on the available sites and buildings both within their Nadi headquarters and hanger complex and the new Fiji Aviation Academy building which is to be constructed in Namaka, Nadi. The relative site locations are detailed below with the main headquarters circled in blue and the new Fiji Airways Aviation Academy in green. Both sites are adjacent the airport and located within 1 kilometre of Nadi Bay. Installations therefore need to be mindful of the marine exposure of the site.

Page 2 of 8 EXISTING FACILITIES: NADI HEADQUARTERS The existing Nadi Headquarters and Hanger provides a large area and site for a roof mounted Solar PV installation. MAIN BUILDING The main hanger has three separate roofs with main hanger roof having lower roofs to the western and northern sides.

Page 3 of 8 Extract of existing design drawing section showing the western lower level roof. Fig : Extract of Roof drawing of main Hanger

Page 4 of 8 Level 3 as a north facing roof having its roofing replaced with Trimdeck roof sheeting. The lower level 1 roof is subject to significant shading from the upper hanger roof in the morning. PUMP HOUSE

Page 5 of 8 1.2.3. CUSTOMS BOND The customs bond building has a northern and south facing centrally pitched roof.

Page 6 of 8 EXISTING ELECTRICAL INSTALLATION The power supply to the premises is via 2 x 500kVA Fiji Electricity Authority (FEA) substation transformers connected in parallel. These transformers are housed within a substation building and located adjacent to the carpark area. There is a site main switchboard (SMSB) within the Hangar Building from which all loads are distributed. The mains power to the SMSB is currently backed up by 2 standby generators rated at 181Kva and 400kVA and the loads within the SMSB are separated by two essential Bus Bars with separate Automatic Transfer Switches (ATS) on each bus bar. The generator installation is to be upgraded to 1 MW in the next 12 months. All outgoing low voltage sub main cables to all electrical distribution boards are reticulated from this SMSB via perforated cable trays and cable ladders to all levels. The total forecast peak load 600 kva at the maximum compared to an installed capacity of 1000 kva. Average load is 277kVA based on logging results over two days.

Page 7 of 8 NEW FACILITIES: FIJI AVIATION ACADEMY The new Fiji Aviation Academy building is intended to incorporate solar arrays in its design. The below preliminary roof plan has the likely solar array panel locations nominated on the north facing roofs with each array area being approximately 250m2.. Preliminary roof plan : Fiji Aviation Academy. SCOPE OF WORKS: SOLAR INSTALLATION The work carried out shall comprise the design, supply, installation, testing, commissioning and defects liability and maintenance of the proposed Solar PV installations located at the sites as previously nominated. The respondent shall be responsible for submitting all technical information for their proposed panels, inverters, protection relay, controls system, structural supports and accessories as part of their proposal submission. The documents show the general intent and do not show all equipment and scope required to complete the works.

Page 8 of 8 The work includes but is not limited to the following main elements: Liaison with FEA, Fiji Airways, Airports Fiji Limited and CAAF for the proposed Solar PV installation including pre-approval. Temporary builder s power. Installation of PV panel, inverters, protection relay, control system and all accessories for a fully functioning grid system. Switchboard upgrades, alterations and additions to cater for the Solar PV installations. New metering to cater for Solar PV installation. Cables, installation and termination. Cabling and cable support systems. Roof penetrations and decktite seals on roof penetrations. Earthing. Accessories and appliances. Equipment supports and bracing. Liaison with other trades. Maintenance Manuals. As-Installed Drawings. Training. Maintenance during 12 months defects liability period. Safe Roof access systems for Maintenance Purposes where panels are installed within 3 m of roof edges. The above scope is preliminary and subject to development and change by Fiji Airways. The delivery methodology is as a Supply delivery and training (and potentially operate) solution incorporating the following hold points: 1. Proposal submission 2. Proposal approval 3. Design submissions and preapproval phase. 4. Technical compliance review 5. Site delivery 6. Site acceptance testing 7. Training 8. Acceptance/Handover 9. Operations and Maintenance phase. Proposals from respondents are expected to include the following ownership options: Capital procurement and outright ownership by Fiji Airways. Lease costs per annum. Purchase of power supplied per kw/hr.